CN107591758B - 一种适应锥筒风塔的风电母线安装方法 - Google Patents

一种适应锥筒风塔的风电母线安装方法 Download PDF

Info

Publication number
CN107591758B
CN107591758B CN201710863110.4A CN201710863110A CN107591758B CN 107591758 B CN107591758 B CN 107591758B CN 201710863110 A CN201710863110 A CN 201710863110A CN 107591758 B CN107591758 B CN 107591758B
Authority
CN
China
Prior art keywords
supporting
power bus
wind power
supporting column
wind
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710863110.4A
Other languages
English (en)
Other versions
CN107591758A (zh
Inventor
殷浩翔
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Haoxiang Electric Group Co ltd
Original Assignee
Haoxiang Electric Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Haoxiang Electric Group Co ltd filed Critical Haoxiang Electric Group Co ltd
Priority to CN201710863110.4A priority Critical patent/CN107591758B/zh
Publication of CN107591758A publication Critical patent/CN107591758A/zh
Application granted granted Critical
Publication of CN107591758B publication Critical patent/CN107591758B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/72Wind turbines with rotation axis in wind direction

Landscapes

  • Wind Motors (AREA)

Abstract

本发明适应锥筒风塔的风电母线安装方法,风电母线安装板通过支撑柱安装在风塔内壁支撑板上,自风塔顶部至风塔底部的支撑柱长度依次增加,以适应锥形风塔的锥度,使得风电母线保持中心垂直度,风电母线受力均匀,减了小风电母线运行时的振动,系统运行稳定性好,安全系数高。

Description

一种适应锥筒风塔的风电母线安装方法
技术领域
本发明涉及一种适应锥筒风塔的风电母线安装方法。
背景技术
风能资源蕴含量巨大,风力发电行业技术的迅猛发展及广阔前景对母线槽产品带来了巨大的市场需求,风电母线槽产品为风力发电机组必不可少的供电系统,现有风力发电系统中的母线槽产品一般通过安装结构固定安装于相当于高层建筑的风塔中,而风塔一般具有上小下大的锥体形状,以适应高强风力作用于风扇发电的同时对风塔主体造成的摇摆、剪切、振动等破坏性反作用力,风电母线安装于风塔主体内部时需适应风塔上小下大的锥体形状,同时风电母线也不能倾斜安装,防止风电母线受力不均匀,影响风电母线系统运行稳定性,造成安全隐患。
发明内容
本发明所要解决的技术问题是,提供一种能够适应风塔主体上小下大的锥体形状,保持风电母线垂直度,适应锥筒风塔的风电母线安装方法。
本发明适应锥筒风塔的风电母线安装方法,包括以下步骤:
第一步,测量风塔顶部风扇主轴至底部控制柜顶部垂直距离,根据垂直距离计算分段母线段数N,每段风电母线标称长度为6m,余数分别设置为两端始端母线、终端连接电缆连接距离;
第二步,每段母线均匀设置两个支撑点,支撑点总数为2N,计算各支撑点至风塔锥筒顶部距离;
第三步,塔顶第一支撑点位置安装支撑板,支撑板通过第一支撑柱固定连接在风电母线的第一安装板上;
第四步,塔顶第二支撑点位置安装支撑板,支撑板通过第二支撑柱固定连接在风电母线第二安装板上,第二支撑柱长度大于第一支撑柱,第二支撑柱与第一支撑柱长度差为A;
第五步,安装第三支撑点的支撑板,并通过第三支撑柱固定连接在风电母线第三安装板上,第三支撑柱长度大于第二支撑柱,第三支撑柱与第二支撑柱长度差也为A;
第六步,依次类推,重复安装第四支撑点至第2N支撑点的支撑板,并分别通过第四支撑柱至第2N支撑柱固定连接在风电母线第四安装板至第2N安装板上,第2N支撑柱长度大于第(2N-1)支撑柱,第2N支撑柱与第(2N-1)支撑柱长度差也为A;
所述第四步至第六步中的A值通过经伟仪测量确定;
所述第四步至第六步中的A值根据风塔锥度通过余弦定理计算确定;
所述安装板通过减震器与风电母线连接。
本发明适应锥筒风塔的风电母线安装方法,风电母线安装板通过支撑柱安装在风塔内壁支撑板上,自风塔顶部至风塔底部的支撑柱长度依次增加,以适应锥形风塔的锥度,使得风电母线保持中心垂直度,风电母线受力均匀,减了小风电母线运行时的振动,系统运行稳定性好,安全系数高。
具体实施方式
一种适应锥筒风塔的风电母线安装方法,包括以下步骤:
第一步,测量风塔顶部风扇主轴至底部控制柜顶部垂直距离,根据垂直距离计算分段母线段数N,每段风电母线标称长度为6m,余数分别设置为两端始端母线、终端连接电缆连接距离;
第二步,每段母线均匀设置两个支撑点,支撑点总数为2N,计算各支撑点至风塔锥筒顶部距离;
第三步,塔顶第一支撑点位置安装支撑板,支撑板通过第一支撑柱固定连接在风电母线的第一安装板上;
第四步,塔顶第二支撑点位置安装支撑板,支撑板通过第二支撑柱固定连接在风电母线第二安装板上,第二支撑柱长度大于第一支撑柱,第二支撑柱与第一支撑柱长度差为A;
第五步,安装第三支撑点的支撑板,并通过第三支撑柱固定连接在风电母线第三安装板上,第三支撑柱长度大于第二支撑柱,第三支撑柱与第二支撑柱长度差也为A;
第六步,依次类推,重复安装第四支撑点至第2N支撑点的支撑板,并分别通过第四支撑柱至第2N支撑柱固定连接在风电母线第四安装板至第2N安装板上,第2N支撑柱长度大于第(2N-1)支撑柱,第2N支撑柱与第(2N-1)支撑柱长度差也为A;
所述第四步至第六步中的A值通过经伟仪测量确定;
所述第四步至第六步中的A值根据风塔锥度通过余弦定理计算确定;
所述安装板通过减震器与风电母线连接。
本发明适应锥筒风塔的风电母线安装方法,风电母线安装板通过支撑柱安装在风塔内壁支撑板上,自风塔顶部至风塔底部的支撑柱长度依次增加,以适应锥形风塔的锥度,使得风电母线保持中心垂直度,风电母线受力均匀,减了小风电母线运行时的振动,系统运行稳定性好,安全系数高。

Claims (4)

1.一种适应锥筒风塔的风电母线安装方法,包括以下步骤:
第一步,测量风塔顶部风扇主轴至底部控制柜顶部垂直距离,根据垂直距离计算分段母线段数N,每段风电母线标称长度为6m,余数分别设置为两端始端母线、终端连接电缆连接距离;
第二步,每段母线均匀设置两个支撑点,支撑点总数为2N,计算各支撑点至风塔锥筒顶部距离;
第三步,塔顶第一支撑点位置安装支撑板,支撑板通过第一支撑柱固定连接在风电母线的第一安装板上;
第四步,塔顶第二支撑点位置安装支撑板,支撑板通过第二支撑柱固定连接在风电母线第二安装板上,第二支撑柱长度大于第一支撑柱,第二支撑柱与第一支撑柱长度差为A;
第五步,安装第三支撑点的支撑板,并通过第三支撑柱固定连接在风电母线第三安装板上,第三支撑柱长度大于第二支撑柱,第三支撑柱与第二支撑柱长度差也为A;
第六步,依次类推,重复安装第四支撑点至第2N支撑点的支撑板,并分别通过第四支撑柱至第2N支撑柱固定连接在风电母线第四安装板至第2N安装板上,第2N支撑柱长度大于第(2N-1)支撑柱,第2N支撑柱与第(2N-1)支撑柱长度差也为A。
2.根据权利要求1所述适应锥筒风塔的风电母线安装方法,其特征在于:所述第四步至第六步中的A值通过经伟仪测量确定。
3.根据权利要求1所述适应锥筒风塔的风电母线安装方法,其特征在于:所述第四步至第六步中的A值根据风塔锥度通过余弦定理计算确定。
4.根据权利要求1所述适应锥筒风塔的风电母线安装方法,其特征在于:所述安装板通过减震器与风电母线连接。
CN201710863110.4A 2017-09-22 2017-09-22 一种适应锥筒风塔的风电母线安装方法 Active CN107591758B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710863110.4A CN107591758B (zh) 2017-09-22 2017-09-22 一种适应锥筒风塔的风电母线安装方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710863110.4A CN107591758B (zh) 2017-09-22 2017-09-22 一种适应锥筒风塔的风电母线安装方法

Publications (2)

Publication Number Publication Date
CN107591758A CN107591758A (zh) 2018-01-16
CN107591758B true CN107591758B (zh) 2023-07-28

Family

ID=61047601

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710863110.4A Active CN107591758B (zh) 2017-09-22 2017-09-22 一种适应锥筒风塔的风电母线安装方法

Country Status (1)

Country Link
CN (1) CN107591758B (zh)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3647937A (en) * 1970-10-02 1972-03-07 Square D Co Weatherproof bus duct joint structure having selectively removable parts
CN104009432A (zh) * 2014-05-13 2014-08-27 镇江西门子母线有限公司 一种风能导电轨安装支架

Family Cites Families (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201134653Y (zh) * 2007-12-19 2008-10-15 中国电力科学研究院 一种试验线段管母线连接金具
CN201256250Y (zh) * 2008-08-21 2009-06-10 刘仕洪 节能电器开关柜
CN201813126U (zh) * 2010-06-22 2011-04-27 唐伟 一种防爆的风能母线槽
CN102797643B (zh) * 2012-07-31 2015-10-28 同济大学 一种风力发电塔装置
CN203056495U (zh) * 2013-01-07 2013-07-10 沈阳锦宏电力科技有限公司 一种风电铝管母线结构
ITBS20130041U1 (it) * 2013-09-17 2015-03-18 Orlando Lozzi Rotore eolico auto avviante ad asse verticale, funzionante ad effetto schiera con numerose pale costituite ognuna da tre profili aerodinamici
DE102014105228A1 (de) * 2014-04-11 2015-10-15 Paul Vahle Gmbh & Co. Kg Positionierbereich für eine Trasse zum vertikalen Einführen von Stromabnehmerkontakten in die Stromschienen der Trasse
CN205752997U (zh) * 2015-11-25 2016-11-30 中国能源建设集团浙江省电力设计院有限公司 基于垂直排列导线的变电构架
CN205882617U (zh) * 2016-07-15 2017-01-11 马鞍山纽盟知识产权管理服务有限公司 一种母线槽支架
CN205811293U (zh) * 2016-07-25 2016-12-14 国网浙江省电力公司经济技术研究院 单柱双母线背靠背垂直布置结构
CN106089595B (zh) * 2016-08-05 2019-02-12 国网山东省电力公司龙口市供电公司 一种风塔电力输送装置
CN106374406A (zh) * 2016-09-29 2017-02-01 易升伟 一种母线槽

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3647937A (en) * 1970-10-02 1972-03-07 Square D Co Weatherproof bus duct joint structure having selectively removable parts
CN104009432A (zh) * 2014-05-13 2014-08-27 镇江西门子母线有限公司 一种风能导电轨安装支架

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
石门坎水电站双曲拱坝施工测量;穆国锋;辛晓涛;张韶华;;云南水力发电;第27卷(第06期);第152-156页\n *

Also Published As

Publication number Publication date
CN107591758A (zh) 2018-01-16

Similar Documents

Publication Publication Date Title
WO2015149411A1 (zh) 覆冰导线脱冰跳跃仿真测试方法
CN106006404A (zh) 一种超高层外挂动臂塔吊爬升支撑装置
CN107591758B (zh) 一种适应锥筒风塔的风电母线安装方法
CN110688803B (zh) 一种输电塔八地脚螺栓四区隔塔脚板厚度计算方法
CN107143463B (zh) 一种控制风力机叶片挥舞的空间拉索系统及优化方法
CN203406500U (zh) 无晕避雷针
CN103624537A (zh) 用于设备安装的调平方法和调平器
CN104533131B (zh) 一种用于特高压±800kV工程的拉线塔的设计方法
CN203039311U (zh) 风力发电用抗震母线槽系统
CN110826211B (zh) 非均布平均风作用下输电线路风荷载的确定方法
CN210536240U (zh) 一种穿墙套管安装结构
CN108242791B (zh) 一种风电母线安装方法
CN113642221A (zh) 一种根据高差、档距确定高风险杆塔体系的方法
CN102134959A (zh) 支撑面积可调式梯脚稳固器
CN203066490U (zh) 钢结构桁架的限位装置
Srikanth et al. Dynamic analysis of transmission line towers
CN104832380A (zh) 用于风电塔筒的防变形支撑架
CN205857227U (zh) 一种风力发电塔空心基础支架
CN206618794U (zh) 一种光纤电流互感器安装支架结构
CN203923920U (zh) 一种钢箱梁分段制造用h型钢可调节胎具
CN201943563U (zh) 伸缩式梯脚稳固器
CN204495538U (zh) 风洞试验模型的一种测力装置
CN210350378U (zh) 一种gis主母线加固装置
CN203765281U (zh) 一种兆瓦级双馈风力发电机组发电机对中专用装置
CN204175175U (zh) 线路塔用电缆检修梯

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant