CN107558776A - The prefabricated component of flange is provided with six direction to be assembled into multi-storied garage in a whole night - Google Patents

The prefabricated component of flange is provided with six direction to be assembled into multi-storied garage in a whole night Download PDF

Info

Publication number
CN107558776A
CN107558776A CN201710808967.6A CN201710808967A CN107558776A CN 107558776 A CN107558776 A CN 107558776A CN 201710808967 A CN201710808967 A CN 201710808967A CN 107558776 A CN107558776 A CN 107558776A
Authority
CN
China
Prior art keywords
prefabricated
flange
storied garage
prefabricated component
whole night
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710808967.6A
Other languages
Chinese (zh)
Other versions
CN107558776B (en
Inventor
汤刚健
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201710808967.6A priority Critical patent/CN107558776B/en
Publication of CN107558776A publication Critical patent/CN107558776A/en
Application granted granted Critical
Publication of CN107558776B publication Critical patent/CN107558776B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Floor Finish (AREA)

Abstract

The present invention is a kind of brand-new multi-storied garage assembly method,It includes flooring,Spandrel girder,Column,Basic integral preform,Prefabricated component is in A,B,C,D,E,F all around six direction face prefabricated flanges up and down,All prefabricated components are all connected by bolt and nut,Multi-storied garage is assembled with such prefabricated component,Upper and lower track,Elevator,A whole night is with regard to that can build up,Multi-storied garage as needed can be in roof,The upper green plants of side wall plantation,The present invention is solved in the big city of prosperity,For example multi-storied garage is made in hospital road surface parking lot into,The multi-storied garage time is built with conventional method to grow,Social traffic jam can be caused,The present invention can be in a whole night with regard to that can build up multi-storied garage,Avoid urban traffic blocking,The present invention is provided with automobile runway up and down in addition,Therefore it is more much lower than intelligent three-dimensional garage cost and later maintenance cost,Therefore the present invention will create bigger economic benefit and social benefit.

Description

The prefabricated component of flange is provided with six direction to be assembled into multi-storied garage in a whole night
Technical field
Assembled architecture.
Background technology
Make multi-storied garage into the big city of prosperity, such as hospital road surface parking lot, multi-storied garage is built with conventional method Time is grown, and can cause social traffic Severe blockage.
The content of the invention
The prefabricated component of flange is provided with six direction to be assembled into multi-storied garage in a whole night.
The prefabricated component of flange is provided with six direction can be assembled into multi-storied garage in a whole night, and 10(Flooring)、4(Load-bearing Beam)、6(Column)Integral preform, prefabricated component is in A, B, C, D, E, F all around six direction face prefabricated flange up and down, and 12(Base Plinth)As needed can be with 10(Flooring)、4(Spandrel girder)、6(Column)Integral preform, all prefabricated components of multi-storied garage are complete Portion is connected by bolt and nut, is not only multi-storied garage, and such prefabricated component is also applied for assembling other buildings.
The prefabricated component of flange is provided with six direction to be assembled into multi-storied garage in a whole night, it is characterized in that 4(Spandrel girder)、 6(Column)、12(Basis)13(Fixing hole)Increase and decrease as needed with the number of six direction face flange it is prefabricated, 14(Water pipe and electricity Source string holes)、15(Alignment pin)、8(Railing pedestal)、24(Planting is blue)、20(Dilatation joint)、21(Railing)Increase and decrease as needed It is prefabricated, 19,23(Upper and lower track)、22(Elevator)Increase and decrease as needed it is prefabricated, with such prefabricated component assemble multi-storied garage, one evening On with regard to that can build up, multi-storied garage as needed can be 25(Roof), side wall 24(Planting is blue)Green plants in plantation.
The prefabricated component of flange is provided with six direction to be assembled into multi-storied garage in a whole night, it is characterized in that E faces 7(Flange) Provided with 9(Positioning hole), F faces 5(Flange)Provided with 15(Alignment pin).
The prefabricated component of flange is provided with six direction to be assembled into multi-storied garage in a whole night, it is characterized in that 1(Flange)It is Flange all around, section h is by two outward openings, and base is relative, is made up of the channel-section steel of mutual distance, and channel-section steel is by the He of base 2 Two side 1-1,1-3 compositions, two 1-1 of side(Side)It is welded by steel plate, and provided with 3(Screw via), it is another Two 1-2 of side(Side)With 16(Prefabricated component steel reinforcement cage)It is welded, 2(Reinforcement)It is welded in channel-section steel, 18(Bolt spiral shell It is female)For connecting two prefabricated components, 1(Flange)Concave side is prefabricated 17(Floor side), 11(Flange)It is basic flange, section M is a channel-section steel, and channel-section steel is made up of base 11-2 and two sides 11-1,11-3, side 11-1(Side)Provided with 3(Screw mistake Hole)Opposite side 11-3(Side)With 16(Prefabricated component steel reinforcement cage)It is welded, and it is prefabricated 17(Floor side), 2(Reinforcement) It is welded in channel-section steel, 18(Bolt and nut)For connecting two prefabricated components.
Fig. 1, it is without basic prefabricated component sketch.
Fig. 2, it is the prefabricated component sketch with basis.
Fig. 3, it is prefabricated component sketch.
Fig. 4, it is prefabricated flange profile.
Fig. 5, be assembling after multi-storied garage sketch.
Fig. 6, it is the multi-storied garage sketch with green plants after assembling.
The invention will be further described below in conjunction with the accompanying drawings, and the prefabricated component that flange is provided with six direction can be in a whole night It is assembled into multi-storied garage.Accompanying drawing 2,10(Flooring)、4(Spandrel girder)、6(Column)、12(Basis)Integral preform, prefabricated component A, B, C, D, E, F all around six direction face prefabricated flange up and down, 4(Spandrel girder)、6(Column)、12(Basis)13(Fixing hole)With The number of six direction face flange increases and decreases prefabricated as needed, and all prefabricated components of multi-storied garage are all connected by bolt and nut Connect, be not only multi-storied garage, be also applied for assembling other buildings, accompanying drawing 1,10 with such prefabricated component(Flooring)、4(Load-bearing Beam)、6(Column), integral preform, prefabricated component is in A, B, C, D, E, F all around six direction face prefabricated flange up and down, 10(Building Face)、4(Spandrel girder)、6(Column)And six direction face flange increases and decreases prefabricated, accompanying drawing 3 as needed, prefabricated component is provided with 14(Water Pipe and power supply string holes)、15(Alignment pin), accompanying drawing 5,8(Railing pedestal)、24(Planting is blue)、20(Dilatation joint)、21(Railing) Increase and decrease as needed it is prefabricated, 19,23(Upper and lower track)、22(Elevator)Increase and decrease as needed it is prefabricated, with such prefabricated component assemble Multi-storied garage, a whole night, accompanying drawing 6, multi-storied garage as needed can be 25 with regard to that can build up(Roof), side wall 24(Planting is blue) Green plants in plantation, accompanying drawing 1, accompanying drawing 3, E faces 7(Flange)Provided with 9(Positioning hole), F faces 5(Flange)Provided with 15(Alignment pin), Accompanying drawing 4,1(Flange)It is all around flange, for section h by two outward openings, base is relative, there is the channel-section steel group of mutual distance Into channel-section steel is made up of base 2 and two sides 1-1,1-3, two 1-1 of side(Side)It is welded by steel plate, and provided with 3 (Screw via), two 1-2 of opposite side(Side)With 16(Prefabricated component steel reinforcement cage)It is welded, 2(Reinforcement)It is welded on groove In steel, 18(Bolt and nut)For connecting two prefabricated components, 1(Flange)Concave side is prefabricated 17(Floor side), 11(Flange) It is basic flange, section m is a channel-section steel, and channel-section steel is made up of base 11-2 and two sides 11-1,11-3, side 11-1(Side Side)Provided with 3(Screw via)Opposite side 11-3(Side)With 16(Prefabricated component steel reinforcement cage)It is welded, and it is prefabricated 17(Floor Side), 2(Reinforcement)It is welded in channel-section steel, 18(Bolt and nut)For connecting two prefabricated components.

Claims (4)

1. the prefabricated component of flange is provided with six direction can be assembled into multi-storied garage in a whole night, and 10(Flooring)、4(Spandrel girder)、6 (Column)Integral preform, prefabricated component is in A, B, C, D, E, F all around six direction face prefabricated flange up and down, and 12(Basis)According to Needing can be with 10(Flooring)、4(Spandrel girder)、6(Column)Integral preform, all prefabricated components of multi-storied garage all pass through spiral shell Bolt nut connects, and is not only multi-storied garage, such prefabricated component is also applied for assembling other buildings.
2. according to the requirement of right 1, the prefabricated component of flange is provided with six direction to be assembled into multi-storied garage in a whole night, It is characterized in that 4(Spandrel girder)、6(Column)、12(Basis)13(Fixing hole)With how much increasings as needed of six direction face flange Subtract it is prefabricated, 14(Water pipe and power supply string holes)、15(Alignment pin)、8(Railing pedestal)、24(Planting is blue)、20(Dilatation joint)、21 (Railing)Increase and decrease as needed it is prefabricated, 19,23(Upper and lower track)、22(Elevator)Increase and decrease as needed it is prefabricated, with such prefabricated Part assembling multi-storied garage, a whole night, multi-storied garage as needed can be 25 with regard to that can build up(Roof), side wall 24(Planting is blue) Green plants in plantation.
3. according to the requirement of right 1, the prefabricated component of flange is provided with six direction to be assembled into multi-storied garage in a whole night, It is characterized in that E faces 7(Flange)Provided with 9(Positioning hole), F faces 5(Flange)Provided with 15(Alignment pin).
4. according to the requirement of right 1, the prefabricated component of flange is provided with six direction to be assembled into multi-storied garage in a whole night, It is characterized in that 1(Flange)It is all around flange, for section h by two outward openings, base is relative, there is the channel-section steel group of mutual distance Into channel-section steel is made up of base 2 and two sides 1-1,1-3, two 1-1 of side(Side)It is welded by steel plate, and provided with 3 (Screw via), two 1-2 of opposite side(Side)With 16(Prefabricated component steel reinforcement cage)It is welded, 2(Reinforcement)It is welded on groove In steel, 18(Bolt and nut)For connecting two prefabricated components, 1(Flange)Concave side is prefabricated 17(Floor side), 11(Flange) It is basic flange, section m is a channel-section steel, and channel-section steel is made up of base 11-2 and two sides 11-1,11-3, side 11-1(Side Side)Provided with 3(Screw via)Opposite side 11-3(Side)With 16(Prefabricated component steel reinforcement cage)It is welded, and it is prefabricated 17(Floor Side), 2(Reinforcement)It is welded in channel-section steel, 18(Bolt and nut)For connecting two prefabricated components.
CN201710808967.6A 2017-09-09 2017-09-09 The prefabricated component of flange is equipped in six direction to be assembled into stereo garage in a whole night Active CN107558776B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710808967.6A CN107558776B (en) 2017-09-09 2017-09-09 The prefabricated component of flange is equipped in six direction to be assembled into stereo garage in a whole night

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710808967.6A CN107558776B (en) 2017-09-09 2017-09-09 The prefabricated component of flange is equipped in six direction to be assembled into stereo garage in a whole night

Publications (2)

Publication Number Publication Date
CN107558776A true CN107558776A (en) 2018-01-09
CN107558776B CN107558776B (en) 2018-06-15

Family

ID=60980430

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710808967.6A Active CN107558776B (en) 2017-09-09 2017-09-09 The prefabricated component of flange is equipped in six direction to be assembled into stereo garage in a whole night

Country Status (1)

Country Link
CN (1) CN107558776B (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008190319A (en) * 2008-05-09 2008-08-21 Jfe Engineering Kk Floor structure of multistory parking garage
CN101408074A (en) * 2008-06-28 2009-04-15 杭州德萨机械技术开发有限公司 Convenient, flexible and assembled intelligent parking garage
CN103276929A (en) * 2013-06-14 2013-09-04 夏健鸣 Small three-dimensional garage
CN203729631U (en) * 2014-01-15 2014-07-23 杭州通识停车设备有限公司 Roadside parking rack
CN105257034A (en) * 2015-09-09 2016-01-20 重庆杰渝建筑机械有限公司 Method of building garage
CN105862900A (en) * 2016-05-25 2016-08-17 山东大学 Assembled type garage structure system based on precast piles and method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008190319A (en) * 2008-05-09 2008-08-21 Jfe Engineering Kk Floor structure of multistory parking garage
CN101408074A (en) * 2008-06-28 2009-04-15 杭州德萨机械技术开发有限公司 Convenient, flexible and assembled intelligent parking garage
CN103276929A (en) * 2013-06-14 2013-09-04 夏健鸣 Small three-dimensional garage
CN203729631U (en) * 2014-01-15 2014-07-23 杭州通识停车设备有限公司 Roadside parking rack
CN105257034A (en) * 2015-09-09 2016-01-20 重庆杰渝建筑机械有限公司 Method of building garage
CN105862900A (en) * 2016-05-25 2016-08-17 山东大学 Assembled type garage structure system based on precast piles and method

Also Published As

Publication number Publication date
CN107558776B (en) 2018-06-15

Similar Documents

Publication Publication Date Title
US8402706B2 (en) Pillar part for modular construction
CN102444204B (en) Support beam structure capable of extending span and reducing height of ceiling structure and installing method thereof
CN106149880A (en) Use the assembling room of new architecture
CN104499413A (en) Modularized steel die and concrete combined arch bridge and suspending construction method of suspension cable thereof
CN105189887A (en) Stair modules which cooperate to form a temporary stair case
CN104912099A (en) Fabricated precast concrete box culvert
ES2333636B1 (en) PRE-MANUFACTURED SEMIRRESISTENT MODULE FOR CONSTRUCTION AND PROCEDURE ASSEMBLY ON THE WORK OF THE SAME.
EP0038800B1 (en) Skeleton-frame system for the erection of building constructions
CN103147532A (en) Double-layer dome structure of space made of bamboo
CN104878867A (en) Ceiling joist and double-layer construction platform integrated structure and manufacturing method thereof
CN106193402B (en) Girder truss integrated form flooring module and its installation method
CN107905385A (en) The assembled arthitecutral structure and method of construction that steel construction is combined with concrete structure
WO2009122562A1 (en) Constructing method of building
CN103814179A (en) Three dimensional upwardly convex frame and method of constructing same
CN202831672U (en) Detachable movable building with outer frame type composite frame structure
CN107558776A (en) The prefabricated component of flange is provided with six direction to be assembled into multi-storied garage in a whole night
US3618277A (en) Hyperboloid buildings
CN202990497U (en) Modular parking lot
CN107558608B (en) Lattice steel frame connecting node and construction method
CN206299015U (en) Assembled composite floor
CN111663818A (en) Intensive garage developed by utilizing urban road underground space
CN216787447U (en) Standardized building unit and prefabricated building
CN107905465A (en) One species wood twin beams stringer type stairway structure and preparation method thereof
NL1043999B1 (en) Aluminium frame building, build element and method therefor
KR101610249B1 (en) Eco-friendly construction methods of buildings and parking Housing

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant