CN107506860A - System and implementation method are realized in lean production plan - Google Patents
System and implementation method are realized in lean production plan Download PDFInfo
- Publication number
- CN107506860A CN107506860A CN201710738387.4A CN201710738387A CN107506860A CN 107506860 A CN107506860 A CN 107506860A CN 201710738387 A CN201710738387 A CN 201710738387A CN 107506860 A CN107506860 A CN 107506860A
- Authority
- CN
- China
- Prior art keywords
- plan
- confirmed
- production
- delivery
- unit
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/04—Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem"
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/08—Logistics, e.g. warehousing, loading or distribution; Inventory or stock management
- G06Q10/087—Inventory or stock management, e.g. order filling, procurement or balancing against orders
Landscapes
- Business, Economics & Management (AREA)
- Engineering & Computer Science (AREA)
- Human Resources & Organizations (AREA)
- Economics (AREA)
- Strategic Management (AREA)
- Entrepreneurship & Innovation (AREA)
- Quality & Reliability (AREA)
- Theoretical Computer Science (AREA)
- Marketing (AREA)
- Operations Research (AREA)
- Development Economics (AREA)
- General Physics & Mathematics (AREA)
- Tourism & Hospitality (AREA)
- Physics & Mathematics (AREA)
- General Business, Economics & Management (AREA)
- Game Theory and Decision Science (AREA)
- Accounting & Taxation (AREA)
- Finance (AREA)
- Educational Administration (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
- General Factory Administration (AREA)
Abstract
Network system realization is realized in a kind of lean production plan, and it comprises the following steps:S1, lean production plan is realized to system division sales order management unit, delivery planning management unit, the detailed administrative unit of delivery plan, production planning management unit, the detailed administrative unit of the production schedule, management of purchasing plan unit, the detailed administrative unit of procurement plan, equipment maintenance and management unit, each component units of data maintenance unit;S2, plan detailed administrative unit, production planning management unit, the detailed administrative unit of the production schedule, management of purchasing plan unit, the detailed administrative unit of procurement plan, equipment maintenance and management unit, data maintenance unit progress functional configuration to sales order management unit, delivery planning management unit, delivery;S3, sales order, delivery plan, the production schedule, procurement plan, plant maintenance, data maintenance management configuration are carried out according to configuration in step S2.
Description
Technical field
The present invention relates to bar codes technique field, system and implementation method are realized in more particularly to a kind of lean production plan.
Background technology
Lean Manufacturing, which contains, timely responds to (Just-in-Time, JIT), bounding theory (Theory of
Constraints, TOC), the concept of lean production and agile manufactruing, while also with the Six Sigma for the purpose of reducing mistake
(Six Sigma) is supplied mutually.Lean Manufacturing is mainly absorbed in the value-added items of client, reduces the discarded object of production and carry
Advocate the method for updating production process.
Another benefit of Lean Manufacturing is that employee can also participate together.Because employee can be in process of production
Present one's view, to improve the process of manufacture, this also helps the enthusiasm and production efficiency for improving employee.
Lean production (Lean Production), it is Massachusetts Institute Technology's numerical digit international automobile meter referred to as " lean "
Draw praise address of the expert of tissue (IMVP) to Japanese Toyota's JIT production planning JIT (Just In Time) mode of production.Essence,
It is i.e. fewer but better, unnecessary production factors are not put into, simply produce the market in urgent need product of necessary amount (under or in reasonable time
The product that procedure is badly in need of);Benefit, i.e., all business activities will have economic benefit beneficial to effectively.Lean Production comes from
Toyota's production system, it is by Massachusetts Institute Technology's tissue 17 national experts, scholars in the world, spent for 5 years, consumption
5,000,000 dollars are provided, exemplified by by auto industry, this starts mass production method and Lean Production JIT typical industry,
Sum up what is come after theorizing.The superiority of Lean Production is not only embodied in manufacturing system, is equally also embodied in
The various aspects such as product development, small enterprises are suited to filling in the gaps in the manufacture by large enterprises of complete sets of equipment, marketing network and management, it is a kind of optimal production of current industrial circle
Organizational framework and mode, it will also turn into the development areas of 21st century standard.
Foremost lean is to lay stress on the seven kinds of wastes reduced from Toyota, lifts overall customer value whereby,
But, which is most preferably to reach this mesh calibration method for, do not come to a conclusion but.Toyota Motor Corporation is from a little company, surely
Step, which increases, turns into automaker the biggest in the world is exactly to focus attention on how to reach this target.
The basic thought of Lean Production can be with short summarizing, i.e.,:Just In Time (JIT), are translated as
Chinese is " when being intended to need, amount on demand, producing required product ".Therefore some managerial experts are also referred to as lean production
Mode is the JIT modes of production, punctuality production mode, unst-in-time manufacuring or the billboard mode of production.
Its core, which is pursued, following two aspects:
First, pursue zero inventory.
Lean production is a kind of pursuit not in stock production, or stock is reached minimum production system, is developed for this
A series of concrete modes including " billboard ", and gradually formed a set of production and operation system to show unique characteristics.
Second, fast reaction is pursued, i.e. the quickly change in reply market.
In order to quickly tackle the change in market, lean production person have developed the layouts such as cell production, fixed variation production
And production programmed method.
Lean Production be around to greatest extent utilize company worker, cooperation manufacturer and assets capability
Synthetic philosophy system.This system requires to form the environment of a solution problem and improvement is updated to problem, it is desirable to each
Link is all that par excellence, and these links have broken traditional functional boundary.
The principal character of Lean Production is shown as:
(1) quality --- find, correct and solve problem;
(2) it is flexible --- small lot, single-piece flow;
(3) time is launched --- the development time is minimized;
(4) product diversification --- shorten production life cycle, reduce scale and benefit influence;
(5) efficiency --- improve productivity ratio, reduce waste;
(6) adaptability --- standard size assembly, coordination;
(7) learn --- constantly improve.
Enterprise ERP applications at present are quite extensive, but traditional ERP software is researched and developed based on MRPII principles, is had
Geneogenous afunction, does not have substantial directive significance to enterprise's production and manufacturing management, plan is inaccurate, workshop still by
In productivity estimation is inaccurate, supplier can not delivery in time, hold up work for lack of material, cause enterprise not produce normally.
Therefore the practical application based on enterprise, with reference to lean production theory, research and development are a set of to solve the problems, such as enterprise practical
Information software is very important, and Lean Manufacturing execution system is wherein critically important part, to solve current institute of enterprise
Problems faced.
Manufacturing execution system (MES) is the tie of Enterprises ' Modern integrated manufacturing system information integration, is to implement Enterprise Agile
Manufacturing strategy and the basic fundamental means for realizing Workshop Production Agility.Manufacturing Executive System MES is in the past 10 years in the world
Develop rapidly, production management technology and real time information system towards shop layer.MES positioning, it is to be in plan layer and scene
Execution level between automated system, mainly responsible Workshop Production Management and scheduling perform.
It is intended to strengthen the perform function of MRP plans, MRP is planned with plant working field control, joined by execution system
System gets up.Here field control includes PLC program controllers, data acquisition unit, bar code, various meterings and detecting instrument, machinery
Hand etc..MES system is provided with necessary interface, and the manufacturer with providing production scene control facility establishes cooperative relationship.World system
Execution system association (MESA) is made to manufacturing execution system (MES) definition:" manufacturing execution system transmission information cause from
Placing an order to the production process between finished goods to optimize.When carrying out, MES uses timely, correct data, carries for production activity
For appropriate guiding, response and report.Change the purpose of fast reaction immediately for condition, be to reduce the work without surcharge
It is dynamic, reach more effective production operation and flow.MES improves the rate of recovery of equipment, on-time-delivery rate, inventory turnover ratio, side
Border contribution, cash flow performance.MES provides the production information needed for two-way communication between enterprise and supplier.”
Lean production plan realizes that system is to carry out lean informatization with software auxiliary enterprises, helps enterprise to realize essence
Prebiotic production.Lean management requires that the Activities of enterprise must all use " lean thinking " (Lean Thinking)." lean is thought
The core of dimension " is exactly to be put into least resource, including manpower, equipment, fund, material, time and space, is createed as more as possible
Value, provide new product for customer and timely service.
The content of the invention
In view of this, the present invention proposes that system and realization side are realized in a kind of lean production plan based on bar codes technique
Method.
Network system realization is realized in a kind of lean production plan, and it comprises the following steps:
S1, lean production plan is realized to system division sales order management unit, delivery planning management unit, delivery meter
Draw detailed administrative unit, production planning management unit, the detailed administrative unit of the production schedule, management of purchasing plan unit, buying meter
Draw detailed administrative unit, equipment maintenance and management unit, each component units of data maintenance unit;
Management of purchasing plan unit includes in the step S1:
" lean production planning system " main window is opened, clicks on menu bar " checking "-" procurement plan ", opens procurement plan
The page;
The procurement plan page is divided into four parts:1 menu, 2 titles, 3 querying conditions, 4 Query Results;
After input inquiry condition, " inquiry " button is clicked;
After the completion of inquiry, chosen in Query Result amount of plan arrange or days column in cell, can perform on demand with
Lower operation;
Number can be used to the automatic plan of distribution of plan chosen, and automatically confirm that and choose plan;
Plan unconfirmed is confirmed, so that subsequent operation can continue to;
The plan that subsequent operation is not done to having confirmed that counter is confirmed;
The procurement plan having confirmed that is chosen, generates procurement request list;
Exit procurement plan;
The detailed administrative unit of procurement plan includes in the step S1:
The cell in amount of plan row is chosen in production schedule inquiry, is clicked on " scheduling/cancellation scheduling ", or double-click days column
Interior cell, into the detailed page of the production schedule;
The detailed page of the production schedule is divided into four parts:1 menu, 2 plan rows, 3 plan row relevant informations;In procurement plan
Detailed page plan row part, following operate is performed on demand:
Preserve amended procurement plan;Editable row include:Delivery date, quantity allotted, confirm quantity;
Plan unconfirmed is confirmed, so that subsequent operation can continue to;
The plan that subsequent operation is not done to having confirmed that counter is confirmed;
The procurement plan having confirmed that is chosen, generates procurement request list;
Refresh page data;
It is detailed to exit procurement plan;
Choose procurement plan row to record, the information such as stock checked in plan row related information section, double-click " it is expected that storage ",
" locked ", " plan used ", i.e., background color be bisque cell, check the material estimated storage, it is locked, plan
Detailed data;
Data maintenance unit includes in the step S1:
Open " lean production planning system ", click on main window left-hand line list item " data maintenance ";
Filesselected type and state in the data maintenance opened on the right side of main window, inquiry button is clicked on, i.e., display is by text
Data content after part type and state packet filter;Query Result is directly changed, save button is clicked on and preserves;
Job order is closed, job order cannot be sent work after closing;The task single file record that needs are closed is chosen, is clicked on
X button is closed;Multiselect is carried out using shift or ctrl keys;
Anti- to close job order, job order can continue to be sent work after instead closing;Choosing needs the anti-task single file note closed
Record, clicks on that anti-X button is counter to close;Multiselect is carried out using shift or ctrl keys;
Job order is deleted, job order will not be reusable in task single dispatch system after deleting.Choose times that needs are deleted
Business single file record, clicks on and deletes button deletion;Having been sent the job order of work cannot be deleted;Use shift or ctrl keys
Carry out multiselect;
Newly-increased job order, increases a line space record row in Query Result, and clicking on save button after input data preserves
Success represents newly-increased job order success;
Export, derived query result generate excel files to the path specified;
S2, detailed administrative unit, the production schedule are planned to sales order management unit, delivery planning management unit, delivery
The detailed administrative unit of administrative unit, the production schedule, management of purchasing plan unit, the detailed administrative unit of procurement plan, plant maintenance
Administrative unit, data maintenance unit carry out functional configuration;
S3, according in step S2 configuration carry out sales order, delivery plan, the production schedule, procurement plan, plant maintenance,
Data maintenance management configuration.
In use lean production method of planning of the present invention,
Sales order management unit includes in the step S1:
For when clicking on main window the left list column " order-newly-increased " item, into the detailed page of sales order;Selling
Sequence information is inputted in the detailed page of order, preserves and audits afterwards;
For when clicking on main window the left list column " order-maintenance " item, the page to be safeguarded into sales order;Operation bag
Closing, anti-closing are included, audits, instead audit, deleting;
During for clicking on main window the left list column " batch imports " item, importing the page into batch and carrying out sales order batch
Measure import operation.
In use lean production method of planning of the present invention, planning management unit bag of being delivered goods in the step S1
Include:
For opening " lean production planning system ", main window left-hand line list item " delivery plan " is clicked on;
The delivery plan page is divided into four parts:1 menu, 2 titles, 3 querying conditions, 4 Query Results;
After input inquiry condition, the display mode needed is selected, clicks " inquiry " button;
After the completion of inquiry, cell in amount of plan row or days column is chosen in Query Result, can be performed on demand such as
Lower operation;
Number can be used to the automatic plan of distribution of plan chosen, and automatically confirm that and choose plan;
Plan unconfirmed is confirmed, so that subsequent operation can continue to;
The plan that subsequent operation is not done to having confirmed that counter is confirmed;
The delivery plan having confirmed that is chosen, generates long purchase plan;
The delivery plan having confirmed that is chosen, generates the production schedule;
Format print delivery plan is played by set;
The delivery plan of print preview form;
The set of design delivery plan printing is drawn squares formula;
Exit delivery plan;
It is additionally operable in schedule window of delivering goods, clicks " file ">" export ", based on the export delivery of Query Result display format
Draw;
The detailed administrative unit of delivery plan includes in the step S1:
For double-clicking the cell in amount of plan row or days column in delivery plan Query Result, it is detailed to open delivery plan
The thin page;
The detailed page of delivery plan is divided into three parts:1 menu, 2 plan rows, 3 plan row relevant informations;
Plan detailed page plan row part in delivery, perform following operate on demand:
Amended delivery plan is preserved, in preceding editable delivery date unconfirmed, quantity allotted and confirms quantity, really
The plan row recognized can not make an amendment again;
The plan that subsequent operation is not done to having confirmed that counter is confirmed;
The delivery plan having confirmed that is chosen, generates long purchase plan;
The delivery plan having confirmed that is chosen, generates the production schedule;
Refresh page data;
Exit the detailed page of delivery plan;
Choose delivery plan row to record, the information such as stock checked in plan row related information section, double-click " it is expected that storage ",
" locked ", " plan used ", i.e., background color be bisque cell, check the material estimated storage, it is locked, plan
Detailed data.
In use lean production method of planning of the present invention,
Production planning management unit includes in the step S1:
Open " lean production planning system ", click on main window left-hand line list item " production schedule ";
The production schedule page is divided into four parts:1 menu, 2 querying conditions, 3 Query Results, 4 graphic analyses;
After input inquiry condition, " inquiry " button is clicked;
After the completion of inquiry, cell in amount of plan row or days column is chosen in Query Result, performs following grasp on demand
Make:
Number can be used to the automatic plan of distribution of plan chosen, and automatically confirm that and choose plan;
Plan unconfirmed is confirmed, so that subsequent operation can continue to;
The plan that subsequent operation is not done to having confirmed that counter is confirmed;
Choose amount of plan column unit lattice to enter the detailed page of the production schedule, carry out scheduling or cancel scheduling operation.Specifically please
Check the detailed page description of the production schedule;
The finished product for having confirmed that simultaneously scheduling is chosen, deploys the production schedule of generation semi-finished product by BOM;
To having produced expansion, but plan not do that the finished product confirmed is counter deploys in semi-finished product;
The production schedule having confirmed that is chosen, generates short-term procurement plan;
The production schedule having confirmed that is chosen, generates production task list;
Exit the production schedule;
Amount of plan is chosen in Query Result, checks graphic analyses;
In schedule window of delivering goods, click " file ">" export ", delivery plan is exported by Query Result display format;
The detailed administrative unit of the production schedule includes in the step S1:
The cell in amount of plan row is chosen in production schedule inquiry, is clicked on " scheduling/cancellation scheduling ", or double-click days column
Interior cell, into the detailed page of the production schedule;
The detailed page of the production schedule is divided into four parts:1 menu, 2 schedules, 3 scheduling results, the related letter of 4 plan rows
Breath;
In the detailed page schedule part of the production schedule, following operate is performed on demand:
Preserve the amended production schedule.Editable row include:Resource, date of manufacture, quantity allotted, confirmation quantity, day
Yield and working time day;
Scheduling mode;
The production schedule is had confirmed that to what is chosen, scheduling is carried out by the daily output, date of manufacture, scheduling mode;
Cancel former scheduling result;
Plan unconfirmed is confirmed, so that subsequent operation can continue to;
The plan that subsequent operation is not done to having confirmed that counter is confirmed;
The production schedule having confirmed that is chosen, generates short-term procurement plan;
The production schedule having confirmed that is chosen, generates production task list;
Replicate the selected line production schedule;
Delete the selected line production schedule;
By the fractionation quantity inputted in selected line one's own profession quantity, the two row production schedules are split into;
The adjustment selected line production schedule puts in order, i.e. scheduling priority;
Refresh page data;
Exit the detailed page of the production schedule;
Choose production schedule row to record, the information such as stock checked in plan row related information section, double-click " it is expected that storage ",
" locked ", " plan used ", i.e., background color be bisque cell, check the material estimated storage, it is locked, plan
Detailed data.
The present invention also provides a kind of lean production plan and realizes system, and it includes such as lower unit:
Lean production planning unit division unit, for lean production plan to be realized into system divides sales order management list
Member, delivery planning management unit, the detailed administrative unit of delivery plan, production planning management unit, the production schedule manage list in detail
Member, management of purchasing plan unit, the detailed administrative unit of procurement plan, equipment maintenance and management unit, each group of data maintenance unit
Into unit;
Management of purchasing plan unit includes in the lean production planning unit division unit:
" lean production planning system " main window is opened, clicks on menu bar " checking "-" procurement plan ", opens procurement plan
The page;
The procurement plan page is divided into four parts:1 menu, 2 titles, 3 querying conditions, 4 Query Results;
After input inquiry condition, " inquiry " button is clicked;
After the completion of inquiry, chosen in Query Result amount of plan arrange or days column in cell, can perform on demand with
Lower operation;
Number can be used to the automatic plan of distribution of plan chosen, and automatically confirm that and choose plan;
Plan unconfirmed is confirmed, so that subsequent operation can continue to;
The plan that subsequent operation is not done to having confirmed that counter is confirmed;
The procurement plan having confirmed that is chosen, generates procurement request list;
Exit procurement plan;
The detailed administrative unit of procurement plan includes in the lean production planning unit division unit:
The cell in amount of plan row is chosen in production schedule inquiry, is clicked on " scheduling/cancellation scheduling ", or double-click days column
Interior cell, into the detailed page of the production schedule;
The detailed page of the production schedule is divided into four parts:1 menu, 2 plan rows, 3 plan row relevant informations;In procurement plan
Detailed page plan row part, following operate is performed on demand:
Preserve amended procurement plan;Editable row include:Delivery date, quantity allotted, confirm quantity;
Plan unconfirmed is confirmed, so that subsequent operation can continue to;
The plan that subsequent operation is not done to having confirmed that counter is confirmed;
The procurement plan having confirmed that is chosen, generates procurement request list;
Refresh page data;
It is detailed to exit procurement plan;
Choose procurement plan row to record, the information such as stock checked in plan row related information section, double-click " it is expected that storage ",
" locked ", " plan used ", i.e., background color be bisque cell, check the material estimated storage, it is locked, plan
Detailed data;
Data maintenance unit includes in the lean production planning unit division unit:
Open " lean production planning system ", click on main window left-hand line list item " data maintenance ";
Filesselected type and state in the data maintenance opened on the right side of main window, inquiry button is clicked on, i.e., display is by text
Data content after part type and state packet filter;Query Result is directly changed, save button is clicked on and preserves;
Job order is closed, job order cannot be sent work after closing;The task single file record that needs are closed is chosen, is clicked on
X button is closed;Multiselect is carried out using shift or ctrl keys;
Anti- to close job order, job order can continue to be sent work after instead closing;Choosing needs the anti-task single file note closed
Record, clicks on that anti-X button is counter to close;Multiselect is carried out using shift or ctrl keys;
Job order is deleted, job order will not be reusable in task single dispatch system after deleting.Choose times that needs are deleted
Business single file record, clicks on and deletes button deletion;Having been sent the job order of work cannot be deleted;Use shift or ctrl keys
Carry out multiselect;
Newly-increased job order, increases a line space record row in Query Result, and clicking on save button after input data preserves
Success represents newly-increased job order success;
Export, derived query result generate excel files to the path specified;
Lean production plan functional configuration unit, for sales order management unit, delivery planning management unit, delivery
Plan detailed administrative unit, production planning management unit, the detailed administrative unit of the production schedule, management of purchasing plan unit, buying
Plan detailed administrative unit, equipment maintenance and management unit, data maintenance unit and carry out functional configuration;
Lean production plan function execution unit, for being configured according in lean production plan functional configuration unit into marketing
Sell order, delivery plan, the production schedule, procurement plan, plant maintenance, data maintenance management configuration.
In system is realized in lean production plan of the present invention,
Sales order management unit includes in the lean production planning unit division unit:
For when clicking on main window the left list column " order-newly-increased " item, into the detailed page of sales order;Selling
Sequence information is inputted in the detailed page of order, preserves and audits afterwards;
For when clicking on main window the left list column " order-maintenance " item, the page to be safeguarded into sales order;Operation bag
Closing, anti-closing are included, audits, instead audit, deleting;
During for clicking on main window the left list column " batch imports " item, importing the page into batch and carrying out sales order batch
Measure import operation.
In system is realized in lean production plan of the present invention, handed in the lean production planning unit division unit
Goods planning management unit includes:
For opening " lean production planning system ", main window left-hand line list item " delivery plan " is clicked on;
The delivery plan page is divided into four parts:1 menu, 2 titles, 3 querying conditions, 4 Query Results;
After input inquiry condition, the display mode needed is selected, clicks " inquiry " button;
After the completion of inquiry, cell in amount of plan row or days column is chosen in Query Result, can be performed on demand such as
Lower operation;
Number can be used to the automatic plan of distribution of plan chosen, and automatically confirm that and choose plan;
Plan unconfirmed is confirmed, so that subsequent operation can continue to;
The plan that subsequent operation is not done to having confirmed that counter is confirmed;
The delivery plan having confirmed that is chosen, generates long purchase plan;
The delivery plan having confirmed that is chosen, generates the production schedule;
Format print delivery plan is played by set;
The delivery plan of print preview form;
The set of design delivery plan printing is drawn squares formula;
Exit delivery plan;
It is additionally operable in schedule window of delivering goods, clicks " file ">" export ", based on the export delivery of Query Result display format
Draw;
The detailed administrative unit of delivery plan includes in the lean production planning unit division unit:
For double-clicking the cell in amount of plan row or days column in delivery plan Query Result, it is detailed to open delivery plan
The thin page;
The detailed page of delivery plan is divided into three parts:1 menu, 2 plan rows, 3 plan row relevant informations;
Plan detailed page plan row part in delivery, perform following operate on demand:
Amended delivery plan is preserved, in preceding editable delivery date unconfirmed, quantity allotted and confirms quantity, really
The plan row recognized can not make an amendment again;
The plan that subsequent operation is not done to having confirmed that counter is confirmed;
The delivery plan having confirmed that is chosen, generates long purchase plan;
The delivery plan having confirmed that is chosen, generates the production schedule;
Refresh page data;
Exit the detailed page of delivery plan;
Choose delivery plan row to record, the information such as stock checked in plan row related information section, double-click " it is expected that storage ",
" locked ", " plan used ", i.e., background color be bisque cell, check the material estimated storage, it is locked, plan
Detailed data.
In system is realized in lean production plan of the present invention,
Production planning management unit includes in the lean production planning unit division unit:
Open " lean production planning system ", click on main window left-hand line list item " production schedule ";
The production schedule page is divided into four parts:1 menu, 2 querying conditions, 3 Query Results, 4 graphic analyses;
After input inquiry condition, " inquiry " button is clicked;
After the completion of inquiry, cell in amount of plan row or days column is chosen in Query Result, performs following grasp on demand
Make:
Number can be used to the automatic plan of distribution of plan chosen, and automatically confirm that and choose plan;
Plan unconfirmed is confirmed, so that subsequent operation can continue to;
The plan that subsequent operation is not done to having confirmed that counter is confirmed;
Choose amount of plan column unit lattice to enter the detailed page of the production schedule, carry out scheduling or cancel scheduling operation.Specifically please
Check the detailed page description of the production schedule;
The finished product for having confirmed that simultaneously scheduling is chosen, deploys the production schedule of generation semi-finished product by BOM;
To having produced expansion, but plan not do that the finished product confirmed is counter deploys in semi-finished product;
The production schedule having confirmed that is chosen, generates short-term procurement plan;
The production schedule having confirmed that is chosen, generates production task list;
Exit the production schedule;
Amount of plan is chosen in Query Result, checks graphic analyses;
In schedule window of delivering goods, click " file ">" export ", delivery plan is exported by Query Result display format;
The detailed administrative unit of the production schedule includes in the lean production planning unit division unit:
The cell in amount of plan row is chosen in production schedule inquiry, is clicked on " scheduling/cancellation scheduling ", or double-click days column
Interior cell, into the detailed page of the production schedule;
The detailed page of the production schedule is divided into four parts:1 menu, 2 schedules, 3 scheduling results, the related letter of 4 plan rows
Breath;
In the detailed page schedule part of the production schedule, following operate is performed on demand:
Preserve the amended production schedule.Editable row include:Resource, date of manufacture, quantity allotted, confirmation quantity, day
Yield and working time day;
Scheduling mode;
The production schedule is had confirmed that to what is chosen, scheduling is carried out by the daily output, date of manufacture, scheduling mode;
Cancel former scheduling result;
Plan unconfirmed is confirmed, so that subsequent operation can continue to;
The plan that subsequent operation is not done to having confirmed that counter is confirmed;
The production schedule having confirmed that is chosen, generates short-term procurement plan;
The production schedule having confirmed that is chosen, generates production task list;
Replicate the selected line production schedule;
Delete the selected line production schedule;
By the fractionation quantity inputted in selected line one's own profession quantity, the two row production schedules are split into;
The adjustment selected line production schedule puts in order, i.e. scheduling priority;
Refresh page data;
Exit the detailed page of the production schedule;
Choose production schedule row to record, the information such as stock checked in plan row related information section, double-click " it is expected that storage ",
" locked ", " plan used ", i.e., background color be bisque cell, check the material estimated storage, it is locked, plan
Detailed data.
System and method is realized in lean production plan provided by the invention, relative to prior art, can be adopted with reference to data
Collect equipment, electronic display and ERP management systems, the value of information is played comprehensive full benefit in enterprise.Belong to IT application in enterprises
High-level application.Under the input of the resources of production such as equivalent devices, personnel, enterprise's rate of capacity utilization, order greatly improved
Ability significantly improves;Data processing time is significantly compressed, and the various production report generation times shift to an earlier date significantly, improve production and hold
The feedback speed of row result, more effectively provide data supporting for company's production and management decision-making;Material tracking and material balance, surpass
Difference alarming and Visual Scene analytical technology, the accuracy of material data is monitored, accomplish to pinpoint the problems in time, timely processing, drop
Low processing loss, improve the quality of production;Integrated by resource optimization, lifting production capacity, improve quality, reduce cost, lifting
Service, enterprise is helped to obtain higher profit and competitiveness.
Brief description of the drawings
Fig. 1 is that system architecture diagram is realized in the lean production plan of the embodiment of the present invention.
Embodiment
The hardware condition of the embodiment of the present invention is as follows:
Bar code printer
Bar code scan equipment
Installation operation system in bar code scan equipment:Windows CE
A kind of following operating system is installed on PC:
Windows 2003
Windows 7
Windows Vista
Windows XP
Windows 2000
The PC for installing software has installed .net framework 2.0
There is administrator right to the PC of software to be installed
Database enables locality connection and long-range connection while uses TCP/IP and named pipes (B)
The embodiment of the present invention provides a kind of lean production plan and realizes network system realization, and it comprises the following steps:
S1, lean production plan is realized to system division sales order management unit, delivery planning management unit, delivery meter
Draw detailed administrative unit, production planning management unit, the detailed administrative unit of the production schedule, management of purchasing plan unit, buying meter
Draw detailed administrative unit, equipment maintenance and management unit, each component units of data maintenance unit;
Management of purchasing plan unit includes in the step S1:
" lean production planning system " main window is opened, clicks on menu bar " checking "-" procurement plan ", opens procurement plan
The page;
The procurement plan page is divided into four parts:1 menu, 2 titles, 3 querying conditions, 4 Query Results;
After input inquiry condition, " inquiry " button is clicked;
After the completion of inquiry, chosen in Query Result amount of plan arrange or days column in cell, can perform on demand with
Lower operation;
Number can be used to the automatic plan of distribution of plan chosen, and automatically confirm that and choose plan;
Plan unconfirmed is confirmed, so that subsequent operation can continue to;
The plan that subsequent operation is not done to having confirmed that counter is confirmed;
The procurement plan having confirmed that is chosen, generates procurement request list;
Exit procurement plan;
The detailed administrative unit of procurement plan includes in the step S1:
The cell in amount of plan row is chosen in production schedule inquiry, is clicked on " scheduling/cancellation scheduling ", or double-click days column
Interior cell, into the detailed page of the production schedule;
The detailed page of the production schedule is divided into four parts:1 menu, 2 plan rows, 3 plan row relevant informations;In procurement plan
Detailed page plan row part, following operate is performed on demand:
Preserve amended procurement plan;Editable row include:Delivery date, quantity allotted, confirm quantity;
Plan unconfirmed is confirmed, so that subsequent operation can continue to;
The plan that subsequent operation is not done to having confirmed that counter is confirmed;
The procurement plan having confirmed that is chosen, generates procurement request list;
Refresh page data;
It is detailed to exit procurement plan;
Choose procurement plan row to record, the information such as stock checked in plan row related information section, double-click " it is expected that storage ",
" locked ", " plan used ", i.e., background color be bisque cell, check the material estimated storage, it is locked, plan
Detailed data;
Data maintenance unit includes in the step S1:
Open " lean production planning system ", click on main window left-hand line list item " data maintenance ";
Filesselected type and state in the data maintenance opened on the right side of main window, inquiry button is clicked on, i.e., display is by text
Data content after part type and state packet filter;Query Result is directly changed, save button is clicked on and preserves;
Job order is closed, job order cannot be sent work after closing;The task single file record that needs are closed is chosen, is clicked on
X button is closed;Multiselect is carried out using shift or ctrl keys;
Anti- to close job order, job order can continue to be sent work after instead closing;Choosing needs the anti-task single file note closed
Record, clicks on that anti-X button is counter to close;Multiselect is carried out using shift or ctrl keys;
Job order is deleted, job order will not be reusable in task single dispatch system after deleting.Choose times that needs are deleted
Business single file record, clicks on and deletes button deletion;Having been sent the job order of work cannot be deleted;Use shift or ctrl keys
Carry out multiselect;
Newly-increased job order, increases a line space record row in Query Result, and clicking on save button after input data preserves
Success represents newly-increased job order success;
Export, derived query result generate excel files to the path specified;
S2, detailed administrative unit, the production schedule are planned to sales order management unit, delivery planning management unit, delivery
The detailed administrative unit of administrative unit, the production schedule, management of purchasing plan unit, the detailed administrative unit of procurement plan, plant maintenance
Administrative unit, data maintenance unit carry out functional configuration;
S3, according in step S2 configuration carry out sales order, delivery plan, the production schedule, procurement plan, plant maintenance,
Data maintenance management configuration.
In use lean production method of planning of the present invention,
Sales order management unit includes in the step S1:
For when clicking on main window the left list column " order-newly-increased " item, into the detailed page of sales order;Selling
Sequence information is inputted in the detailed page of order, preserves and audits afterwards;
For when clicking on main window the left list column " order-maintenance " item, the page to be safeguarded into sales order;Operation bag
Closing, anti-closing are included, audits, instead audit, deleting;
During for clicking on main window the left list column " batch imports " item, importing the page into batch and carrying out sales order batch
Measure import operation.
In use lean production method of planning of the present invention, planning management unit bag of being delivered goods in the step S1
Include:
For opening " lean production planning system ", main window left-hand line list item " delivery plan " is clicked on;
The delivery plan page is divided into four parts:1 menu, 2 titles, 3 querying conditions, 4 Query Results;
After input inquiry condition, the display mode needed is selected, clicks " inquiry " button;
After the completion of inquiry, cell in amount of plan row or days column is chosen in Query Result, can be performed on demand such as
Lower operation;
Number can be used to the automatic plan of distribution of plan chosen, and automatically confirm that and choose plan;
Plan unconfirmed is confirmed, so that subsequent operation can continue to;
The plan that subsequent operation is not done to having confirmed that counter is confirmed;
The delivery plan having confirmed that is chosen, generates long purchase plan;
The delivery plan having confirmed that is chosen, generates the production schedule;
Format print delivery plan is played by set;
The delivery plan of print preview form;
The set of design delivery plan printing is drawn squares formula;
Exit delivery plan;
It is additionally operable in schedule window of delivering goods, clicks " file ">" export ", based on the export delivery of Query Result display format
Draw;
The detailed administrative unit of delivery plan includes in the step S1:
For double-clicking the cell in amount of plan row or days column in delivery plan Query Result, it is detailed to open delivery plan
The thin page;
The detailed page of delivery plan is divided into three parts:1 menu, 2 plan rows, 3 plan row relevant informations;
Plan detailed page plan row part in delivery, perform following operate on demand:
Amended delivery plan is preserved, in preceding editable delivery date unconfirmed, quantity allotted and confirms quantity, really
The plan row recognized can not make an amendment again;
The plan that subsequent operation is not done to having confirmed that counter is confirmed;
The delivery plan having confirmed that is chosen, generates long purchase plan;
The delivery plan having confirmed that is chosen, generates the production schedule;
Refresh page data;
Exit the detailed page of delivery plan;
Choose delivery plan row to record, the information such as stock checked in plan row related information section, double-click " it is expected that storage ",
" locked ", " plan used ", i.e., background color be bisque cell, check the material estimated storage, it is locked, plan
Detailed data.
In use lean production method of planning of the present invention,
Production planning management unit includes in the step S1:
Open " lean production planning system ", click on main window left-hand line list item " production schedule ";
The production schedule page is divided into four parts:1 menu, 2 querying conditions, 3 Query Results, 4 graphic analyses;
After input inquiry condition, " inquiry " button is clicked;
After the completion of inquiry, cell in amount of plan row or days column is chosen in Query Result, performs following grasp on demand
Make:
Number can be used to the automatic plan of distribution of plan chosen, and automatically confirm that and choose plan;
Plan unconfirmed is confirmed, so that subsequent operation can continue to;
The plan that subsequent operation is not done to having confirmed that counter is confirmed;
Choose amount of plan column unit lattice to enter the detailed page of the production schedule, carry out scheduling or cancel scheduling operation.Specifically please
Check the detailed page description of the production schedule;
The finished product for having confirmed that simultaneously scheduling is chosen, deploys the production schedule of generation semi-finished product by BOM;
To having produced expansion, but plan not do that the finished product confirmed is counter deploys in semi-finished product;
The production schedule having confirmed that is chosen, generates short-term procurement plan;
The production schedule having confirmed that is chosen, generates production task list;
Exit the production schedule;
Amount of plan is chosen in Query Result, checks graphic analyses;
In schedule window of delivering goods, click " file ">" export ", delivery plan is exported by Query Result display format;
The detailed administrative unit of the production schedule includes in the step S1:
The cell in amount of plan row is chosen in production schedule inquiry, is clicked on " scheduling/cancellation scheduling ", or double-click days column
Interior cell, into the detailed page of the production schedule;
The detailed page of the production schedule is divided into four parts:1 menu, 2 schedules, 3 scheduling results, the related letter of 4 plan rows
Breath;
In the detailed page schedule part of the production schedule, following operate is performed on demand:
Preserve the amended production schedule.Editable row include:Resource, date of manufacture, quantity allotted, confirmation quantity, day
Yield and working time day;
Scheduling mode;
The production schedule is had confirmed that to what is chosen, scheduling is carried out by the daily output, date of manufacture, scheduling mode;
Cancel former scheduling result;
Plan unconfirmed is confirmed, so that subsequent operation can continue to;
The plan that subsequent operation is not done to having confirmed that counter is confirmed;
The production schedule having confirmed that is chosen, generates short-term procurement plan;
The production schedule having confirmed that is chosen, generates production task list;
Replicate the selected line production schedule;
Delete the selected line production schedule;
By the fractionation quantity inputted in selected line one's own profession quantity, the two row production schedules are split into;
The adjustment selected line production schedule puts in order, i.e. scheduling priority;
Refresh page data;
Exit the detailed page of the production schedule;
Choose production schedule row to record, the information such as stock checked in plan row related information section, double-click " it is expected that storage ",
" locked ", " plan used ", i.e., background color be bisque cell, check the material estimated storage, it is locked, plan
Detailed data.
As shown in figure 1, the present invention also provides a kind of lean production plan and realizes system, it includes such as lower unit:
Lean production planning unit division unit, for lean production plan to be realized into system divides sales order management list
Member, delivery planning management unit, the detailed administrative unit of delivery plan, production planning management unit, the production schedule manage list in detail
Member, management of purchasing plan unit, the detailed administrative unit of procurement plan, equipment maintenance and management unit, each group of data maintenance unit
Into unit;
Management of purchasing plan unit includes in the lean production planning unit division unit:
" lean production planning system " main window is opened, clicks on menu bar " checking "-" procurement plan ", opens procurement plan
The page;
The procurement plan page is divided into four parts:1 menu, 2 titles, 3 querying conditions, 4 Query Results;
After input inquiry condition, " inquiry " button is clicked;
After the completion of inquiry, chosen in Query Result amount of plan arrange or days column in cell, can perform on demand with
Lower operation;
Number can be used to the automatic plan of distribution of plan chosen, and automatically confirm that and choose plan;
Plan unconfirmed is confirmed, so that subsequent operation can continue to;
The plan that subsequent operation is not done to having confirmed that counter is confirmed;
The procurement plan having confirmed that is chosen, generates procurement request list;
Exit procurement plan;
The detailed administrative unit of procurement plan includes in the lean production planning unit division unit:
The cell in amount of plan row is chosen in production schedule inquiry, is clicked on " scheduling/cancellation scheduling ", or double-click days column
Interior cell, into the detailed page of the production schedule;
The detailed page of the production schedule is divided into four parts:1 menu, 2 plan rows, 3 plan row relevant informations;In procurement plan
Detailed page plan row part, following operate is performed on demand:
Preserve amended procurement plan;Editable row include:Delivery date, quantity allotted, confirm quantity;
Plan unconfirmed is confirmed, so that subsequent operation can continue to;
The plan that subsequent operation is not done to having confirmed that counter is confirmed;
The procurement plan having confirmed that is chosen, generates procurement request list;
Refresh page data;
It is detailed to exit procurement plan;
Choose procurement plan row to record, the information such as stock checked in plan row related information section, double-click " it is expected that storage ",
" locked ", " plan used ", i.e., background color be bisque cell, check the material estimated storage, it is locked, plan
Detailed data;
Data maintenance unit includes in the lean production planning unit division unit:
Open " lean production planning system ", click on main window left-hand line list item " data maintenance ";
Filesselected type and state in the data maintenance opened on the right side of main window, inquiry button is clicked on, i.e., display is by text
Data content after part type and state packet filter;Query Result is directly changed, save button is clicked on and preserves;
Job order is closed, job order cannot be sent work after closing;The task single file record that needs are closed is chosen, is clicked on
X button is closed;Multiselect is carried out using shift or ctrl keys;
Anti- to close job order, job order can continue to be sent work after instead closing;Choosing needs the anti-task single file note closed
Record, clicks on that anti-X button is counter to close;Multiselect is carried out using shift or ctrl keys;
Job order is deleted, job order will not be reusable in task single dispatch system after deleting.Choose times that needs are deleted
Business single file record, clicks on and deletes button deletion;Having been sent the job order of work cannot be deleted;Use shift or ctrl keys
Carry out multiselect;
Newly-increased job order, increases a line space record row in Query Result, and clicking on save button after input data preserves
Success represents newly-increased job order success;
Export, derived query result generate excel files to the path specified;
Lean production plan functional configuration unit, for sales order management unit, delivery planning management unit, delivery
Plan detailed administrative unit, production planning management unit, the detailed administrative unit of the production schedule, management of purchasing plan unit, buying
Plan detailed administrative unit, equipment maintenance and management unit, data maintenance unit and carry out functional configuration;
Lean production plan function execution unit, for being configured according in lean production plan functional configuration unit into marketing
Sell order, delivery plan, the production schedule, procurement plan, plant maintenance, data maintenance management configuration.
In system is realized in lean production plan of the present invention,
Sales order management unit includes in the lean production planning unit division unit:
For when clicking on main window the left list column " order-newly-increased " item, into the detailed page of sales order;Selling
Sequence information is inputted in the detailed page of order, preserves and audits afterwards;
For when clicking on main window the left list column " order-maintenance " item, the page to be safeguarded into sales order;Operation bag
Closing, anti-closing are included, audits, instead audit, deleting;
During for clicking on main window the left list column " batch imports " item, importing the page into batch and carrying out sales order batch
Measure import operation.
In system is realized in lean production plan of the present invention, handed in the lean production planning unit division unit
Goods planning management unit includes:
For opening " lean production planning system ", main window left-hand line list item " delivery plan " is clicked on;
The delivery plan page is divided into four parts:1 menu, 2 titles, 3 querying conditions, 4 Query Results;
After input inquiry condition, the display mode needed is selected, clicks " inquiry " button;
After the completion of inquiry, cell in amount of plan row or days column is chosen in Query Result, can be performed on demand such as
Lower operation;
Number can be used to the automatic plan of distribution of plan chosen, and automatically confirm that and choose plan;
Plan unconfirmed is confirmed, so that subsequent operation can continue to;
The plan that subsequent operation is not done to having confirmed that counter is confirmed;
The delivery plan having confirmed that is chosen, generates long purchase plan;
The delivery plan having confirmed that is chosen, generates the production schedule;
Format print delivery plan is played by set;
The delivery plan of print preview form;
The set of design delivery plan printing is drawn squares formula;
Exit delivery plan;
It is additionally operable in schedule window of delivering goods, clicks " file ">" export ", based on the export delivery of Query Result display format
Draw;
The detailed administrative unit of delivery plan includes in the lean production planning unit division unit:
For double-clicking the cell in amount of plan row or days column in delivery plan Query Result, it is detailed to open delivery plan
The thin page;
The detailed page of delivery plan is divided into three parts:1 menu, 2 plan rows, 3 plan row relevant informations;
Plan detailed page plan row part in delivery, perform following operate on demand:
Amended delivery plan is preserved, in preceding editable delivery date unconfirmed, quantity allotted and confirms quantity, really
The plan row recognized can not make an amendment again;
The plan that subsequent operation is not done to having confirmed that counter is confirmed;
The delivery plan having confirmed that is chosen, generates long purchase plan;
The delivery plan having confirmed that is chosen, generates the production schedule;
Refresh page data;
Exit the detailed page of delivery plan;
Choose delivery plan row to record, the information such as stock checked in plan row related information section, double-click " it is expected that storage ",
" locked ", " plan used ", i.e., background color be bisque cell, check the material estimated storage, it is locked, plan
Detailed data.
In system is realized in lean production plan of the present invention,
Production planning management unit includes in the lean production planning unit division unit:
Open " lean production planning system ", click on main window left-hand line list item " production schedule ";
The production schedule page is divided into four parts:1 menu, 2 querying conditions, 3 Query Results, 4 graphic analyses;
After input inquiry condition, " inquiry " button is clicked;
After the completion of inquiry, cell in amount of plan row or days column is chosen in Query Result, performs following grasp on demand
Make:
Number can be used to the automatic plan of distribution of plan chosen, and automatically confirm that and choose plan;
Plan unconfirmed is confirmed, so that subsequent operation can continue to;
The plan that subsequent operation is not done to having confirmed that counter is confirmed;
Choose amount of plan column unit lattice to enter the detailed page of the production schedule, carry out scheduling or cancel scheduling operation.Specifically please
Check the detailed page description of the production schedule;
The finished product for having confirmed that simultaneously scheduling is chosen, deploys the production schedule of generation semi-finished product by BOM;
To having produced expansion, but plan not do that the finished product confirmed is counter deploys in semi-finished product;
The production schedule having confirmed that is chosen, generates short-term procurement plan;
The production schedule having confirmed that is chosen, generates production task list;
Exit the production schedule;
Amount of plan is chosen in Query Result, checks graphic analyses;
In schedule window of delivering goods, click " file ">" export ", delivery plan is exported by Query Result display format;
The detailed administrative unit of the production schedule includes in the lean production planning unit division unit:
The cell in amount of plan row is chosen in production schedule inquiry, is clicked on " scheduling/cancellation scheduling ", or double-click days column
Interior cell, into the detailed page of the production schedule;
The detailed page of the production schedule is divided into four parts:1 menu, 2 schedules, 3 scheduling results, the related letter of 4 plan rows
Breath;
In the detailed page schedule part of the production schedule, following operate is performed on demand:
Preserve the amended production schedule.Editable row include:Resource, date of manufacture, quantity allotted, confirmation quantity, day
Yield and working time day;
Scheduling mode;
The production schedule is had confirmed that to what is chosen, scheduling is carried out by the daily output, date of manufacture, scheduling mode;
Cancel former scheduling result;
Plan unconfirmed is confirmed, so that subsequent operation can continue to;
The plan that subsequent operation is not done to having confirmed that counter is confirmed;
The production schedule having confirmed that is chosen, generates short-term procurement plan;
The production schedule having confirmed that is chosen, generates production task list;
Replicate the selected line production schedule;
Delete the selected line production schedule;
By the fractionation quantity inputted in selected line one's own profession quantity, the two row production schedules are split into;
The adjustment selected line production schedule puts in order, i.e. scheduling priority;
Refresh page data;
Exit the detailed page of the production schedule;
Choose production schedule row to record, the information such as stock checked in plan row related information section, double-click " it is expected that storage ",
" locked ", " plan used ", i.e., background color be bisque cell, check the material estimated storage, it is locked, plan
Detailed data.
System and method is realized in lean production plan provided by the invention, relative to prior art, can be adopted with reference to data
Collect equipment, electronic display and ERP management systems, the value of information is played comprehensive full benefit in enterprise.Belong to IT application in enterprises
High-level application.Under the input of the resources of production such as equivalent devices, personnel, enterprise's rate of capacity utilization, order greatly improved
Ability significantly improves;Data processing time is significantly compressed, and the various production report generation times shift to an earlier date significantly, improve production and hold
The feedback speed of row result, more effectively provide data supporting for company's production and management decision-making;Material tracking and material balance, surpass
Difference alarming and Visual Scene analytical technology, the accuracy of material data is monitored, accomplish to pinpoint the problems in time, timely processing, drop
Low processing loss, improve the quality of production;Integrated by resource optimization, lifting production capacity, improve quality, reduce cost, lifting
Service, enterprise is helped to obtain higher profit and competitiveness.
Hardware, computing device can be directly used with reference to the method or algorithm that the embodiments described herein describes
Software module, or the two combination are implemented.Software module can be placed in random access memory, internal memory, read-only storage, electricity can
Well known in programming ROM, electrically erasable ROM, register, hard disk, moveable magnetic disc, CD-ROM or technical field
In the storage medium of any other forms.
It is understood that for the person of ordinary skill of the art, it can be conceived with the technique according to the invention and done
Go out other various corresponding changes and deformation, and all these changes and deformation should all belong to the protection model of the claims in the present invention
Enclose.
Claims (8)
1. network system realization is realized in a kind of lean production plan, it comprises the following steps:
S1, lean production plan being realized to, system division sales order management unit, delivery planning management unit, delivery plan are detailed
Thin administrative unit, production planning management unit, the detailed administrative unit of the production schedule, management of purchasing plan unit, procurement plan are detailed
Thin administrative unit, equipment maintenance and management unit, each component units of data maintenance unit;
Management of purchasing plan unit includes in the step S1:
" lean production planning system " main window is opened, clicks on menu bar " checking "-" procurement plan ", opens procurement plan page
Face;
The procurement plan page is divided into four parts:1 menu, 2 titles, 3 querying conditions, 4 Query Results;
After input inquiry condition, " inquiry " button is clicked;
After the completion of inquiry, cell in amount of plan row or days column is chosen in Query Result, following behaviour can be performed on demand
Make;
Number can be used to the automatic plan of distribution of plan chosen, and automatically confirm that and choose plan;
Plan unconfirmed is confirmed, so that subsequent operation can continue to;
The plan that subsequent operation is not done to having confirmed that counter is confirmed;
The procurement plan having confirmed that is chosen, generates procurement request list;
Exit procurement plan;
The detailed administrative unit of procurement plan includes in the step S1:
The cell in amount of plan row is chosen in production schedule inquiry, is clicked on " scheduling/cancellation scheduling ", or is double-clicked single in days column
First lattice, into the detailed page of the production schedule;
The detailed page of the production schedule is divided into four parts:1 menu, 2 plan rows, 3 plan row relevant informations;It is detailed in procurement plan
Page plan row part, following operate is performed on demand:
Preserve amended procurement plan;Editable row include:Delivery date, quantity allotted, confirm quantity;
Plan unconfirmed is confirmed, so that subsequent operation can continue to;
The plan that subsequent operation is not done to having confirmed that counter is confirmed;
The procurement plan having confirmed that is chosen, generates procurement request list;
Refresh page data;
It is detailed to exit procurement plan;
Choose procurement plan row to record, the information such as stock are checked in plan row related information section, double-click " it is expected that storage ", "
Locking ", " plan has been used ", i.e., background color is bisque cell, checks that the estimated storage of the material, locked, plan have been used
Detailed data;
Data maintenance unit includes in the step S1:
Open " lean production planning system ", click on main window left-hand line list item " data maintenance ";
Filesselected type and state in the data maintenance opened on the right side of main window, inquiry button is clicked on, i.e. files classes are pressed in display
Data content after type and state packet filter;Query Result is directly changed, save button is clicked on and preserves;
Job order is closed, job order cannot be sent work after closing;The task single file record that needs are closed is chosen, clicks on and closes
Button is closed;Multiselect is carried out using shift or ctrl keys;
Anti- to close job order, job order can continue to be sent work after instead closing;Choosing needs the anti-task single file record closed, point
Hit that anti-X button is counter to close;Multiselect is carried out using shift or ctrl keys;
Job order is deleted, job order will not be reusable in task single dispatch system after deleting.Choose the job order that needs are deleted
Row record, click on and delete button deletion;Having been sent the job order of work cannot be deleted;Carried out using shift or ctrl keys
Multiselect;
Newly-increased job order, increases a line space record row in Query Result, and clicking on save button after input data preserves successfully
Represent newly-increased job order success;
Export, derived query result generate excel files to the path specified;
S2, detailed administrative unit, production planning management are planned to sales order management unit, delivery planning management unit, delivery
The detailed administrative unit of unit, the production schedule, management of purchasing plan unit, the detailed administrative unit of procurement plan, equipment maintenance and management
Unit, data maintenance unit carry out functional configuration;
S3, sales order, delivery plan, the production schedule, procurement plan, plant maintenance, data are carried out according to configuration in step S2
Maintenance management configures.
2. use lean production method of planning as claimed in claim 1, it is characterised in that
Sales order management unit includes in the step S1:
For when clicking on main window the left list column " order-newly-increased " item, into the detailed page of sales order;In sales order
Sequence information is inputted in the detailed page, preserves and audits afterwards;
For when clicking on main window the left list column " order-maintenance " item, the page to be safeguarded into sales order;Operation includes closing
Close, instead close, auditing, anti-examination & verification, deletion;
During for clicking on main window the left list column " batch imports " item, importing page progress sales order batch into batch and leading
Enter operation.
3. use lean production method of planning as claimed in claim 2, it is characterised in that delivery plan pipe in the step S1
Reason unit includes:
For opening " lean production planning system ", main window left-hand line list item " delivery plan " is clicked on;
The delivery plan page is divided into four parts:1 menu, 2 titles, 3 querying conditions, 4 Query Results;
After input inquiry condition, the display mode needed is selected, clicks " inquiry " button;
After the completion of inquiry, cell in amount of plan row or days column is chosen in Query Result, following behaviour can be performed on demand
Make;
Number can be used to the automatic plan of distribution of plan chosen, and automatically confirm that and choose plan;
Plan unconfirmed is confirmed, so that subsequent operation can continue to;
The plan that subsequent operation is not done to having confirmed that counter is confirmed;
The delivery plan having confirmed that is chosen, generates long purchase plan;
The delivery plan having confirmed that is chosen, generates the production schedule;
Format print delivery plan is played by set;
The delivery plan of print preview form;
The set of design delivery plan printing is drawn squares formula;
Exit delivery plan;
It is additionally operable in schedule window of delivering goods, clicks " file ">" export ", delivery plan is exported by Query Result display format;
The detailed administrative unit of delivery plan includes in the step S1:
For double-clicking the cell in amount of plan row or days column in delivery plan Query Result, delivery plan detail page is opened
Face;
The detailed page of delivery plan is divided into three parts:1 menu, 2 plan rows, 3 plan row relevant informations;
Plan detailed page plan row part in delivery, perform following operate on demand:
Amended delivery plan is preserved, in preceding editable delivery date unconfirmed, quantity allotted and quantity is confirmed, has confirmed that
Plan row can not make an amendment again;
The plan that subsequent operation is not done to having confirmed that counter is confirmed;
The delivery plan having confirmed that is chosen, generates long purchase plan;
The delivery plan having confirmed that is chosen, generates the production schedule;
Refresh page data;
Exit the detailed page of delivery plan;
Choose delivery plan row to record, the information such as stock are checked in plan row related information section, double-click " it is expected that storage ", "
Locking ", " plan has been used ", i.e., background color is bisque cell, checks that the estimated storage of the material, locked, plan have been used
Detailed data.
4. use lean production method of planning as claimed in claim 3, it is characterised in that
Production planning management unit includes in the step S1:
Open " lean production planning system ", click on main window left-hand line list item " production schedule ";
The production schedule page is divided into four parts:1 menu, 2 querying conditions, 3 Query Results, 4 graphic analyses;
After input inquiry condition, " inquiry " button is clicked;
After the completion of inquiry, cell in amount of plan row or days column is chosen in Query Result, performs following operate on demand:
Number can be used to the automatic plan of distribution of plan chosen, and automatically confirm that and choose plan;
Plan unconfirmed is confirmed, so that subsequent operation can continue to;
The plan that subsequent operation is not done to having confirmed that counter is confirmed;
Choose amount of plan column unit lattice to enter the detailed page of the production schedule, carry out scheduling or cancel scheduling operation.It please specifically check
The detailed page description of the production schedule;
The finished product for having confirmed that simultaneously scheduling is chosen, deploys the production schedule of generation semi-finished product by BOM;
To having produced expansion, but plan not do that the finished product confirmed is counter deploys in semi-finished product;
The production schedule having confirmed that is chosen, generates short-term procurement plan;
The production schedule having confirmed that is chosen, generates production task list;
Exit the production schedule;
Amount of plan is chosen in Query Result, checks graphic analyses;
In schedule window of delivering goods, click " file ">" export ", delivery plan is exported by Query Result display format;
The detailed administrative unit of the production schedule includes in the step S1:
The cell in amount of plan row is chosen in production schedule inquiry, is clicked on " scheduling/cancellation scheduling ", or is double-clicked single in days column
First lattice, into the detailed page of the production schedule;
The detailed page of the production schedule is divided into four parts:1 menu, 2 schedules, 3 scheduling results, 4 plan row relevant informations;
In the detailed page schedule part of the production schedule, following operate is performed on demand:
Preserve the amended production schedule.Editable row include:Resource, date of manufacture, quantity allotted, confirmation quantity, the daily output
With working time day;
Scheduling mode;
The production schedule is had confirmed that to what is chosen, scheduling is carried out by the daily output, date of manufacture, scheduling mode;
Cancel former scheduling result;
Plan unconfirmed is confirmed, so that subsequent operation can continue to;
The plan that subsequent operation is not done to having confirmed that counter is confirmed;
The production schedule having confirmed that is chosen, generates short-term procurement plan;
The production schedule having confirmed that is chosen, generates production task list;
Replicate the selected line production schedule;
Delete the selected line production schedule;
By the fractionation quantity inputted in selected line one's own profession quantity, the two row production schedules are split into;
The adjustment selected line production schedule puts in order, i.e. scheduling priority;
Refresh page data;
Exit the detailed page of the production schedule;
Choose production schedule row to record, the information such as stock are checked in plan row related information section, double-click " it is expected that storage ", "
Locking ", " plan has been used ", i.e., background color is bisque cell, checks that the estimated storage of the material, locked, plan have been used
Detailed data.
5. system is realized in a kind of lean production plan, it includes such as lower unit:
Lean production planning unit division unit, for by lean production plan realize system division sales order management unit,
Deliver goods planning management unit, delivery plan detailed administrative unit, production planning management unit, the detailed administrative unit of the production schedule,
The each composition of management of purchasing plan unit, the detailed administrative unit of procurement plan, equipment maintenance and management unit, data maintenance unit is single
Member;
Management of purchasing plan unit includes in the lean production planning unit division unit:
" lean production planning system " main window is opened, clicks on menu bar " checking "-" procurement plan ", opens procurement plan page
Face;
The procurement plan page is divided into four parts:1 menu, 2 titles, 3 querying conditions, 4 Query Results;
After input inquiry condition, " inquiry " button is clicked;
After the completion of inquiry, cell in amount of plan row or days column is chosen in Query Result, following behaviour can be performed on demand
Make;
Number can be used to the automatic plan of distribution of plan chosen, and automatically confirm that and choose plan;
Plan unconfirmed is confirmed, so that subsequent operation can continue to;
The plan that subsequent operation is not done to having confirmed that counter is confirmed;
The procurement plan having confirmed that is chosen, generates procurement request list;
Exit procurement plan;
The detailed administrative unit of procurement plan includes in the lean production planning unit division unit:
The cell in amount of plan row is chosen in production schedule inquiry, is clicked on " scheduling/cancellation scheduling ", or is double-clicked single in days column
First lattice, into the detailed page of the production schedule;
The detailed page of the production schedule is divided into four parts:1 menu, 2 plan rows, 3 plan row relevant informations;It is detailed in procurement plan
Page plan row part, following operate is performed on demand:
Preserve amended procurement plan;Editable row include:Delivery date, quantity allotted, confirm quantity;
Plan unconfirmed is confirmed, so that subsequent operation can continue to;
The plan that subsequent operation is not done to having confirmed that counter is confirmed;
The procurement plan having confirmed that is chosen, generates procurement request list;
Refresh page data;
It is detailed to exit procurement plan;
Choose procurement plan row to record, the information such as stock are checked in plan row related information section, double-click " it is expected that storage ", "
Locking ", " plan has been used ", i.e., background color is bisque cell, checks that the estimated storage of the material, locked, plan have been used
Detailed data;
Data maintenance unit includes in the lean production planning unit division unit:
Open " lean production planning system ", click on main window left-hand line list item " data maintenance ";
Filesselected type and state in the data maintenance opened on the right side of main window, inquiry button is clicked on, i.e. files classes are pressed in display
Data content after type and state packet filter;Query Result is directly changed, save button is clicked on and preserves;
Job order is closed, job order cannot be sent work after closing;The task single file record that needs are closed is chosen, clicks on and closes
Button is closed;Multiselect is carried out using shift or ctrl keys;
Anti- to close job order, job order can continue to be sent work after instead closing;Choosing needs the anti-task single file record closed, point
Hit that anti-X button is counter to close;Multiselect is carried out using shift or ctrl keys;
Job order is deleted, job order will not be reusable in task single dispatch system after deleting.Choose the job order that needs are deleted
Row record, click on and delete button deletion;Having been sent the job order of work cannot be deleted;Carried out using shift or ctrl keys
Multiselect;
Newly-increased job order, increases a line space record row in Query Result, and clicking on save button after input data preserves successfully
Represent newly-increased job order success;
Export, derived query result generate excel files to the path specified;
Lean production plan functional configuration unit, for planning to sales order management unit, delivery planning management unit, delivery
Detailed administrative unit, production planning management unit, the detailed administrative unit of the production schedule, management of purchasing plan unit, procurement plan
Detailed administrative unit, equipment maintenance and management unit, data maintenance unit carry out functional configuration;
Lean production plan function execution unit, ordered for carrying out sale according to configuration in lean production plan functional configuration unit
Single, delivery plan, the production schedule, procurement plan, plant maintenance, data maintenance management configuration.
6. system is realized in lean production plan as claimed in claim 5, it is characterised in that
Sales order management unit includes in the lean production planning unit division unit:
For when clicking on main window the left list column " order-newly-increased " item, into the detailed page of sales order;In sales order
Sequence information is inputted in the detailed page, preserves and audits afterwards;
For when clicking on main window the left list column " order-maintenance " item, the page to be safeguarded into sales order;Operation includes closing
Close, instead close, auditing, anti-examination & verification, deletion;
During for clicking on main window the left list column " batch imports " item, importing page progress sales order batch into batch and leading
Enter operation.
7. system is realized in lean production plan as claimed in claim 6, it is characterised in that the lean production planning unit is drawn
Planning management unit of being delivered goods in subdivision includes:
For opening " lean production planning system ", main window left-hand line list item " delivery plan " is clicked on;
The delivery plan page is divided into four parts:1 menu, 2 titles, 3 querying conditions, 4 Query Results;
After input inquiry condition, the display mode needed is selected, clicks " inquiry " button;
After the completion of inquiry, cell in amount of plan row or days column is chosen in Query Result, following behaviour can be performed on demand
Make;
Number can be used to the automatic plan of distribution of plan chosen, and automatically confirm that and choose plan;
Plan unconfirmed is confirmed, so that subsequent operation can continue to;
The plan that subsequent operation is not done to having confirmed that counter is confirmed;
The delivery plan having confirmed that is chosen, generates long purchase plan;
The delivery plan having confirmed that is chosen, generates the production schedule;
Format print delivery plan is played by set;
The delivery plan of print preview form;
The set of design delivery plan printing is drawn squares formula;
Exit delivery plan;
It is additionally operable in schedule window of delivering goods, clicks " file ">" export ", delivery plan is exported by Query Result display format;
The detailed administrative unit of delivery plan includes in the lean production planning unit division unit:
For double-clicking the cell in amount of plan row or days column in delivery plan Query Result, delivery plan detail page is opened
Face;
The detailed page of delivery plan is divided into three parts:1 menu, 2 plan rows, 3 plan row relevant informations;
Plan detailed page plan row part in delivery, perform following operate on demand:
Amended delivery plan is preserved, in preceding editable delivery date unconfirmed, quantity allotted and quantity is confirmed, has confirmed that
Plan row can not make an amendment again;
The plan that subsequent operation is not done to having confirmed that counter is confirmed;
The delivery plan having confirmed that is chosen, generates long purchase plan;
The delivery plan having confirmed that is chosen, generates the production schedule;
Refresh page data;
Exit the detailed page of delivery plan;
Choose delivery plan row to record, the information such as stock are checked in plan row related information section, double-click " it is expected that storage ", "
Locking ", " plan has been used ", i.e., background color is bisque cell, checks that the estimated storage of the material, locked, plan have been used
Detailed data.
8. system is realized in lean production plan as claimed in claim 7, it is characterised in that
Production planning management unit includes in the lean production planning unit division unit:
Open " lean production planning system ", click on main window left-hand line list item " production schedule ";
The production schedule page is divided into four parts:1 menu, 2 querying conditions, 3 Query Results, 4 graphic analyses;
After input inquiry condition, " inquiry " button is clicked;
After the completion of inquiry, cell in amount of plan row or days column is chosen in Query Result, performs following operate on demand:
Number can be used to the automatic plan of distribution of plan chosen, and automatically confirm that and choose plan;
Plan unconfirmed is confirmed, so that subsequent operation can continue to;
The plan that subsequent operation is not done to having confirmed that counter is confirmed;
Choose amount of plan column unit lattice to enter the detailed page of the production schedule, carry out scheduling or cancel scheduling operation.It please specifically check
The detailed page description of the production schedule;
The finished product for having confirmed that simultaneously scheduling is chosen, deploys the production schedule of generation semi-finished product by BOM;
To having produced expansion, but plan not do that the finished product confirmed is counter deploys in semi-finished product;
The production schedule having confirmed that is chosen, generates short-term procurement plan;
The production schedule having confirmed that is chosen, generates production task list;
Exit the production schedule;
Amount of plan is chosen in Query Result, checks graphic analyses;
In schedule window of delivering goods, click " file ">" export ", delivery plan is exported by Query Result display format;
The detailed administrative unit of the production schedule includes in the lean production planning unit division unit:
The cell in amount of plan row is chosen in production schedule inquiry, is clicked on " scheduling/cancellation scheduling ", or is double-clicked single in days column
First lattice, into the detailed page of the production schedule;
The detailed page of the production schedule is divided into four parts:1 menu, 2 schedules, 3 scheduling results, 4 plan row relevant informations;
In the detailed page schedule part of the production schedule, following operate is performed on demand:
Preserve the amended production schedule.Editable row include:Resource, date of manufacture, quantity allotted, confirmation quantity, the daily output
With working time day;
Scheduling mode;
The production schedule is had confirmed that to what is chosen, scheduling is carried out by the daily output, date of manufacture, scheduling mode;
Cancel former scheduling result;
Plan unconfirmed is confirmed, so that subsequent operation can continue to;
The plan that subsequent operation is not done to having confirmed that counter is confirmed;
The production schedule having confirmed that is chosen, generates short-term procurement plan;
The production schedule having confirmed that is chosen, generates production task list;
Replicate the selected line production schedule;
Delete the selected line production schedule;
By the fractionation quantity inputted in selected line one's own profession quantity, the two row production schedules are split into;
The adjustment selected line production schedule puts in order, i.e. scheduling priority;
Refresh page data;
Exit the detailed page of the production schedule;
Choose production schedule row to record, the information such as stock are checked in plan row related information section, double-click " it is expected that storage ", "
Locking ", " plan has been used ", i.e., background color is bisque cell, checks that the estimated storage of the material, locked, plan have been used
Detailed data.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710738387.4A CN107506860A (en) | 2017-08-25 | 2017-08-25 | System and implementation method are realized in lean production plan |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710738387.4A CN107506860A (en) | 2017-08-25 | 2017-08-25 | System and implementation method are realized in lean production plan |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107506860A true CN107506860A (en) | 2017-12-22 |
Family
ID=60692956
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710738387.4A Pending CN107506860A (en) | 2017-08-25 | 2017-08-25 | System and implementation method are realized in lean production plan |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107506860A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108491939A (en) * | 2018-03-28 | 2018-09-04 | 青岛河澄知识产权有限公司 | A kind of Transit Equipment Intelligent Maintenance management method |
CN108764629A (en) * | 2018-04-21 | 2018-11-06 | 广东韶钢工程技术有限公司 | A kind of production management system |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101026647A (en) * | 2007-04-09 | 2007-08-29 | 中国网络通信集团公司 | Telecommunication income check dynamic hierarchical management system and method |
CN102214331A (en) * | 2011-05-30 | 2011-10-12 | 林大统 | ERP (enterprise resource planning)-based contract reviewing method |
US20110251865A1 (en) * | 2008-11-28 | 2011-10-13 | Nulogy Corporation | System, method, and computer program for manufacturing estimation production assembly and inventory management |
CN106779592A (en) * | 2016-12-02 | 2017-05-31 | 林冠良 | A kind of improving production management banner system and application process |
-
2017
- 2017-08-25 CN CN201710738387.4A patent/CN107506860A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101026647A (en) * | 2007-04-09 | 2007-08-29 | 中国网络通信集团公司 | Telecommunication income check dynamic hierarchical management system and method |
US20110251865A1 (en) * | 2008-11-28 | 2011-10-13 | Nulogy Corporation | System, method, and computer program for manufacturing estimation production assembly and inventory management |
CN102214331A (en) * | 2011-05-30 | 2011-10-12 | 林大统 | ERP (enterprise resource planning)-based contract reviewing method |
CN106779592A (en) * | 2016-12-02 | 2017-05-31 | 林冠良 | A kind of improving production management banner system and application process |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108491939A (en) * | 2018-03-28 | 2018-09-04 | 青岛河澄知识产权有限公司 | A kind of Transit Equipment Intelligent Maintenance management method |
CN108764629A (en) * | 2018-04-21 | 2018-11-06 | 广东韶钢工程技术有限公司 | A kind of production management system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107831750B (en) | IMES intelligent manufacturing execution system | |
Sullivan et al. | Equipment replacement decisions and lean manufacturing | |
Riezebos et al. | Lean production and information technology: connection or contradiction? | |
Samaranayake | Business process integration, automation, and optimization in ERP: Integrated approach using enhanced process models | |
US20050278227A1 (en) | Systems and methods of managing price modeling data through closed-loop analytics | |
CN107563627A (en) | Workshop MES management methods and system based on bar codes technique | |
CN101833711A (en) | Method for planning enterprise resources | |
WO2005119547A2 (en) | System and method for organizing price modeling data using hierarchically organized portfolios | |
Wu | Manufacturing and supply systems management: a unified framework of systems design and operation | |
CN109978497A (en) | A kind of business administration office platform system based on cloud ERP management | |
CN111091352A (en) | High-end equipment manufacturing process data management system | |
CN108764629A (en) | A kind of production management system | |
Avvaru et al. | Integration of PLM, MES and ERP systems to optimize the engineering, production and business | |
CN110032154A (en) | A kind of production control method and system of be pilot | |
CN107506860A (en) | System and implementation method are realized in lean production plan | |
CN107704989A (en) | Use Lean Manufacturing management system and method | |
Lin et al. | [Retracted] Supply Chain Management System for Automobile Manufacturing Enterprises Based on SAP | |
Zancul | PLM reference model: a preliminary proposal for reference model evolution | |
Espino-Sanchez et al. | Increased inventory turnover through a Lean Warehousing management model in SMEs suppliers to the food industry | |
Ostic et al. | An introduction to enterprise modeling and simulation | |
Behúnová et al. | An Effective Tool for Increasing the Company’s Production Process–Application of Innovative Planning Methods | |
Rahmadi | Industry 4.0 Readiness for the Circular Economy: Transition Trends and Readiness of Indonesia’s Textile and Electronics Sectors | |
CN107562490A (en) | Lean manufacturing management system and method | |
Gil-Goyzueta et al. | Process Improvement Proposal Storage to Increase the Service Level Using Lean Warehousing in Commerce Companies | |
Rokicki et al. | Integrated IT systems in logistics company management |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20171222 |
|
RJ01 | Rejection of invention patent application after publication |