CN107489277A - 一种新型钢‑混梁柱节点施工结构及综合施工方法 - Google Patents
一种新型钢‑混梁柱节点施工结构及综合施工方法 Download PDFInfo
- Publication number
- CN107489277A CN107489277A CN201710766495.2A CN201710766495A CN107489277A CN 107489277 A CN107489277 A CN 107489277A CN 201710766495 A CN201710766495 A CN 201710766495A CN 107489277 A CN107489277 A CN 107489277A
- Authority
- CN
- China
- Prior art keywords
- reinforced concrete
- concrete column
- column
- gusset
- node
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 239000011150 reinforced concrete Substances 0.000 title claims abstract description 72
- 238000010276 construction Methods 0.000 title claims abstract description 33
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 25
- 239000010959 steel Substances 0.000 title claims abstract description 25
- 235000010627 Phaseolus vulgaris Nutrition 0.000 title claims abstract description 14
- 244000046052 Phaseolus vulgaris Species 0.000 title claims abstract description 14
- 210000003205 muscle Anatomy 0.000 claims abstract description 36
- 239000004567 concrete Substances 0.000 claims abstract description 33
- 238000003466 welding Methods 0.000 claims abstract description 17
- 230000003014 reinforcing effect Effects 0.000 claims abstract description 16
- 238000005516 engineering process Methods 0.000 claims abstract description 12
- 230000010354 integration Effects 0.000 claims abstract description 5
- 238000012545 processing Methods 0.000 claims abstract description 5
- 238000000034 method Methods 0.000 claims description 22
- 208000010040 Sprains and Strains Diseases 0.000 claims description 16
- 206010024453 Ligament sprain Diseases 0.000 claims description 11
- 238000005266 casting Methods 0.000 claims description 7
- 238000013461 design Methods 0.000 claims description 3
- 238000004088 simulation Methods 0.000 abstract description 2
- 238000009435 building construction Methods 0.000 abstract 1
- 210000000988 bone and bone Anatomy 0.000 description 4
- 238000005260 corrosion Methods 0.000 description 2
- 238000007689 inspection Methods 0.000 description 2
- 230000002265 prevention Effects 0.000 description 2
- 238000000275 quality assurance Methods 0.000 description 2
- 230000002787 reinforcement Effects 0.000 description 2
- 230000005540 biological transmission Effects 0.000 description 1
- 238000004891 communication Methods 0.000 description 1
- 238000007796 conventional method Methods 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 230000001681 protective effect Effects 0.000 description 1
- 238000010008 shearing Methods 0.000 description 1
- 239000002689 soil Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/18—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
- E04B1/20—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of concrete, e.g. reinforced concrete, or other stonelike material
- E04B1/21—Connections specially adapted therefor
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Mechanical Engineering (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Joining Of Building Structures In Genera (AREA)
Abstract
Description
Claims (4)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201710766495.2A CN107489277B (zh) | 2017-08-30 | 2017-08-30 | 一种新型钢-混梁柱节点施工结构及综合施工方法 |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201710766495.2A CN107489277B (zh) | 2017-08-30 | 2017-08-30 | 一种新型钢-混梁柱节点施工结构及综合施工方法 |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN107489277A true CN107489277A (zh) | 2017-12-19 |
| CN107489277B CN107489277B (zh) | 2024-04-12 |
Family
ID=60646014
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201710766495.2A Active CN107489277B (zh) | 2017-08-30 | 2017-08-30 | 一种新型钢-混梁柱节点施工结构及综合施工方法 |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN107489277B (zh) |
Cited By (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109680809A (zh) * | 2019-02-28 | 2019-04-26 | 清华大学 | 上层钢管柱与下层钢筋混凝土柱的转换节点及施工方法 |
| CN109680811A (zh) * | 2019-03-01 | 2019-04-26 | 中建四局第三建筑工程有限公司 | 一种装配式建筑预制型钢柱节点连接结构及其施工方法 |
| CN111539061A (zh) * | 2020-06-02 | 2020-08-14 | 甘肃省建设监理有限责任公司 | 一种基于bim的梁柱节点钢筋避让结构的钢筋处理方法 |
| CN112095922A (zh) * | 2020-09-02 | 2020-12-18 | 中国建筑第八工程局有限公司 | 钢结构柱 |
| CN113931301A (zh) * | 2021-11-19 | 2022-01-14 | 中建科工集团有限公司 | 劲性柱与钢梁连接节点及其施工方法 |
Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH06212691A (ja) * | 1993-01-18 | 1994-08-02 | Shimizu Corp | 建築物の施工方法 |
| JP2009161974A (ja) * | 2008-01-04 | 2009-07-23 | Takenaka Komuten Co Ltd | 鉄筋コンクリート梁の構築方法 |
| CN105332510A (zh) * | 2015-11-12 | 2016-02-17 | 徐仁贵 | 一种复杂梁柱节点核心区施工方法 |
| CN207314523U (zh) * | 2017-08-30 | 2018-05-04 | 中建四局第一建筑工程有限公司 | 一种新型钢-混梁柱节点施工结构 |
-
2017
- 2017-08-30 CN CN201710766495.2A patent/CN107489277B/zh active Active
Patent Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH06212691A (ja) * | 1993-01-18 | 1994-08-02 | Shimizu Corp | 建築物の施工方法 |
| JP2009161974A (ja) * | 2008-01-04 | 2009-07-23 | Takenaka Komuten Co Ltd | 鉄筋コンクリート梁の構築方法 |
| CN105332510A (zh) * | 2015-11-12 | 2016-02-17 | 徐仁贵 | 一种复杂梁柱节点核心区施工方法 |
| CN207314523U (zh) * | 2017-08-30 | 2018-05-04 | 中建四局第一建筑工程有限公司 | 一种新型钢-混梁柱节点施工结构 |
Cited By (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109680809A (zh) * | 2019-02-28 | 2019-04-26 | 清华大学 | 上层钢管柱与下层钢筋混凝土柱的转换节点及施工方法 |
| CN109680811A (zh) * | 2019-03-01 | 2019-04-26 | 中建四局第三建筑工程有限公司 | 一种装配式建筑预制型钢柱节点连接结构及其施工方法 |
| CN109680811B (zh) * | 2019-03-01 | 2024-05-28 | 中建四局第三建筑工程有限公司 | 一种装配式建筑预制型钢柱节点连接结构及其施工方法 |
| CN111539061A (zh) * | 2020-06-02 | 2020-08-14 | 甘肃省建设监理有限责任公司 | 一种基于bim的梁柱节点钢筋避让结构的钢筋处理方法 |
| CN111539061B (zh) * | 2020-06-02 | 2022-12-13 | 甘肃省建设监理有限责任公司 | 一种基于bim的梁柱节点钢筋避让结构的钢筋处理方法 |
| CN112095922A (zh) * | 2020-09-02 | 2020-12-18 | 中国建筑第八工程局有限公司 | 钢结构柱 |
| CN113931301A (zh) * | 2021-11-19 | 2022-01-14 | 中建科工集团有限公司 | 劲性柱与钢梁连接节点及其施工方法 |
Also Published As
| Publication number | Publication date |
|---|---|
| CN107489277B (zh) | 2024-04-12 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN107489277A (zh) | 一种新型钢‑混梁柱节点施工结构及综合施工方法 | |
| CN104695557B (zh) | 钢结构建筑预埋地脚螺栓一次到位施工方法 | |
| CN103422620B (zh) | 一种预制中空型钢混凝土柱及其拼接结构和拼接方法 | |
| CN207314523U (zh) | 一种新型钢-混梁柱节点施工结构 | |
| CN208486364U (zh) | 框架结构体系 | |
| CN115270278B (zh) | 悬挂倒棱台形混凝土结构bim应用及支模施工工艺方法 | |
| CN107938837A (zh) | 一种钢管混凝土柱与梁主筋连接节点及施工方法 | |
| CN108818919A (zh) | 预制t梁钢筋预绑扎及整体安装的施工方法 | |
| CN103882813A (zh) | 用于桥墩与横系梁同步施工的牛腿托架平台及其搭建方法 | |
| CN107083804A (zh) | 一种墙体构造柱插筋施工方法 | |
| CN203238780U (zh) | 梁柱核心区预制钢筋箍笼 | |
| CN207063515U (zh) | 一种可伸缩铝框模板 | |
| CN211948529U (zh) | 一种多腔体巨柱地脚螺栓群的定位支架 | |
| CN104294920B (zh) | 一种u形钢混凝土组合梁与异形钢管混凝土柱的节点组件及制备方法 | |
| CN104295003A (zh) | 一种构造柱施工方法 | |
| CN206957185U (zh) | 阳角剪力墙套埋螺杆固定悬挑架型钢用连接件 | |
| CN109339223A (zh) | 一种立柱和钢盖梁的连接节点及其施工方法 | |
| CN113216487A (zh) | 一种基于bim技术的叠合板悬挑工字钢施工方法 | |
| CN107299764A (zh) | 一种便于构造柱主筋定位的混凝土装置及施工方法 | |
| CN203799573U (zh) | 实体比例砖混结构房屋结构构造教学模型 | |
| CN105040992B (zh) | 逆作法结构型钢柱倒插式施工方法 | |
| CN206752699U (zh) | 一种钢管混凝土柱连接节点 | |
| CN213477672U (zh) | 一种装配式柱定位灌浆装置 | |
| CN109025059A (zh) | 一种门窗现浇梁浇筑方法 | |
| CN108149866A (zh) | Pc楼梯现浇节点预埋螺栓定位装置及方法 |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| CB02 | Change of applicant information |
Country or region after: China Address after: 510030 room 904, 6th floor, traffic bureau building, 95 Yingbin Avenue, Xinhua Street, Huadu District, Guangzhou City, Guangdong Province Applicant after: China Construction Fourth Engineering Bureau First Construction Co.,Ltd. Applicant after: CHINA CONSTRUCTION FOURTH ENGINEERING DIVISION CORP.,LTD. Address before: 510030 room 904, 6th floor, traffic bureau building, 95 Yingbin Avenue, Xinhua Street, Huadu District, Guangzhou City, Guangdong Province Applicant before: China Construction Fourth Engineering Bureau First Construction Engineering Co.,Ltd. Country or region before: China Applicant before: CHINA CONSTRUCTION FOURTH ENGINEERING DIVISION CORP.,LTD. |
|
| CB02 | Change of applicant information | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant |