CN107451357A - A kind of balcony construction method of ground based on BIM - Google Patents

A kind of balcony construction method of ground based on BIM Download PDF

Info

Publication number
CN107451357A
CN107451357A CN201710630543.5A CN201710630543A CN107451357A CN 107451357 A CN107451357 A CN 107451357A CN 201710630543 A CN201710630543 A CN 201710630543A CN 107451357 A CN107451357 A CN 107451357A
Authority
CN
China
Prior art keywords
construction
bim
ground
gradient
waterproof
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710630543.5A
Other languages
Chinese (zh)
Inventor
周江峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chengdu Zhi Jian New Architectural Design Consulting Co Ltd
Original Assignee
Chengdu Zhi Jian New Architectural Design Consulting Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chengdu Zhi Jian New Architectural Design Consulting Co Ltd filed Critical Chengdu Zhi Jian New Architectural Design Consulting Co Ltd
Priority to CN201710630543.5A priority Critical patent/CN107451357A/en
Publication of CN107451357A publication Critical patent/CN107451357A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F15/00Flooring
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F15/00Flooring
    • E04F15/18Separately-laid insulating layers; Other additional insulating measures; Floating floors
    • E04F15/182Underlayers coated with adhesive or mortar to receive the flooring
    • E04F15/183Underlayers coated with adhesive or mortar to receive the flooring for areas prone to frost damage, e.g. for balconies or terraces
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/20Design optimisation, verification or simulation
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F2290/00Specially adapted covering, lining or flooring elements not otherwise provided for
    • E04F2290/04Specially adapted covering, lining or flooring elements not otherwise provided for for insulation or surface protection, e.g. against noise, impact or fire

Abstract

The invention discloses a kind of balcony construction method of ground based on BIM, including following steps:(1), based on construction drawing, threedimensional model is established;(2), the dynamic analog based on BIM, the dynamic analog of waterproof construction and the dynamic analog of tile work construction are carried out;(3), beneficial to the Gradient of draining during acquisition waterproof construction;Obtain tile work construction when beneficial to draining Gradient and obtain the gradient difference data between lastrow floor tile and next line floor tile;(4) data and construction drawing, obtained based on step (3), carry out the construction on balcony ground.The related data that the present invention is obtained by BIM, has positive booster action for site operation, the preferred plan of draining has just been obtained before construction, avoids the deviation for the influence draining parameter being likely to occur in construction.

Description

A kind of balcony construction method of ground based on BIM
Technical field
The present invention relates to building field, and in particular to a kind of balcony construction method of ground based on BIM.
Background technology
BIM is the new tool of architecture, engineering science and civil engineering.BIM (Building Information Modeling, abbreviation BIM), it is defined as by being formed completely with insufficient information to support life cycle management, And can be by building or architectural engineering information model that computer applied algorithm is directly explained.In short, i.e. digital technology support Life cycle management to architectural environment.Existing building construction is aided in using BIM technology, is that the one of construction becomes greatly Gesture.
The meeting that existing balcony ground construction has just has CAD two dimension drawings to be constructed, but more be then according to skill The experience of art work is constructed, and these modes can only all pinpoint the problems when side is constructed and solve the problems, such as, it is impossible to improves construction Efficiency.
The content of the invention
It is an object of the invention to provide a kind of balcony construction method of ground based on BIM, present invention BIM technology is to applying Associated components during work carry out three-dimensional modeling, then carry out dynamic analog and data analysis again, obtain in construction simulation Beneficial to the Gradient of draining during waterproof construction;Obtain tile work construction when beneficial to draining Gradient and obtain lastrow floor tile Gradient difference data between next line floor tile, data and architectural drawing, arrangement and method for construction is recycled to carry out site operation.The present invention The related data obtained by BIM, has positive booster action for site operation, draining has just been obtained before construction Preferred plan, avoid construction in be likely to occur influence draining parameter deviation.
The present invention is achieved through the following technical solutions:
A kind of balcony construction method of ground based on BIM, including following steps:
(1), based on construction drawing, ground, waterproof layer, cement layer, floor tile, the threedimensional model of floor drain are established;
(2), the dynamic analog based on BIM, with the ground through three-dimensional modeling, waterproof layer, floor drain, the dynamic of waterproof construction is carried out Morphotype is intended, then the dynamic analog of tile work construction is carried out with cement layer, floor tile, i.e. cement layer is laid on waterproof layer, floor tile arrangement It is laid on into multirow on cement layer, when waterproof construction and tile work are constructed, is required to carry out the slope on ground to the face between floor drain Degree arrangement;
(3), beneficial to the Gradient of draining during acquisition waterproof construction;Obtain when tile work is constructed beneficial to the Gradient of draining And obtain the gradient difference data between lastrow floor tile and next line floor tile;
(4) data and construction drawing, obtained based on step (3), carry out the construction on balcony ground.
During waterproof construction, gradient 3-5%.
, it is necessary to coat primer during waterproof construction, primer is the mixture of the material of polyurethane first and second and dimethylbenzene, polyurethane first and second The mass ratio of material and dimethylbenzene is 1:2.
Dry solidification 4h-6h after primer coating.
The present invention compared with prior art, has the following advantages and advantages:
The related data that the present invention is obtained by BIM, has positive booster action for site operation, before construction The preferred plan of draining has just been obtained, has avoided the deviation for the influence draining parameter being likely to occur in construction.
Embodiment
For the object, technical solutions and advantages of the present invention are more clearly understood, with reference to embodiment, the present invention is made Further to describe in detail, exemplary embodiment of the invention and its explanation are only used for explaining the present invention, are not intended as to this The restriction of invention.
Embodiment 1
A kind of balcony construction method of ground based on BIM, including following steps:
(1), based on construction drawing, ground, waterproof layer, cement layer, floor tile, the threedimensional model of floor drain are established;
(2), the dynamic analog based on BIM, with the ground through three-dimensional modeling, waterproof layer, floor drain, the dynamic of waterproof construction is carried out Morphotype is intended, then the dynamic analog of tile work construction is carried out with cement layer, floor tile, i.e. cement layer is laid on waterproof layer, floor tile arrangement It is laid on into multirow on cement layer, when waterproof construction and tile work are constructed, is required to carry out the slope on ground to the face between floor drain Degree arrangement;
(3), beneficial to the Gradient of draining during acquisition waterproof construction;Obtain when tile work is constructed beneficial to the Gradient of draining And obtain the gradient difference data between lastrow floor tile and next line floor tile;
(4) data and construction drawing, obtained based on step (3), carry out the construction on balcony ground.
Embodiment 2
During waterproof construction, gradient 3-5%.
, it is necessary to coat primer during waterproof construction, primer is the mixture of the material of polyurethane first and second and dimethylbenzene, polyurethane first and second The mass ratio of material and dimethylbenzene is 1:2.
Dry solidification 4h-6h after primer coating.
Above-described embodiment, the purpose of the present invention, technical scheme and beneficial effect are carried out further Describe in detail, should be understood that the embodiment that the foregoing is only the present invention, be not intended to limit the present invention Protection domain, within the spirit and principles of the invention, any modification, equivalent substitution and improvements done etc., all should include Within protection scope of the present invention.

Claims (4)

1. a kind of balcony construction method of ground based on BIM, it is characterised in that including following steps:
(1), based on construction drawing, ground, waterproof layer, cement layer, floor tile, the threedimensional model of floor drain are established;
(2), the dynamic analog based on BIM, with the ground through three-dimensional modeling, waterproof layer, floor drain, the dynamic analog of waterproof construction is carried out Intend, then the dynamic analog of tile work construction is carried out with cement layer, floor tile, be i.e. cement layer is laid on waterproof layer, and floor tile is arranged in more Row is laid on cement layer, when waterproof construction and tile work are constructed, is required to carry out the gradient row on ground to the face between floor drain Row;
(3), beneficial to the Gradient of draining during acquisition waterproof construction;Obtain tile work construction when beneficial to draining Gradient and obtain Obtain the gradient difference data between lastrow floor tile and next line floor tile;
(4) data and construction drawing, obtained based on step (3), carry out the construction on balcony ground.
2. the balcony construction method of ground according to claim 1 based on BIM, it is characterised in that during waterproof construction, the gradient For 3-5%.
3. the balcony construction method of ground according to claim 1 based on BIM, it is characterised in that during waterproof construction, it is necessary to Coat primer, primer is the mixture of the material of polyurethane first and second and dimethylbenzene, and the mass ratio of the material of polyurethane first and second and dimethylbenzene is 1: 2。
4. the balcony construction method of ground according to claim 3 based on BIM, it is characterised in that dried after primer coating Solidify 4h-6h.
CN201710630543.5A 2017-07-28 2017-07-28 A kind of balcony construction method of ground based on BIM Pending CN107451357A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710630543.5A CN107451357A (en) 2017-07-28 2017-07-28 A kind of balcony construction method of ground based on BIM

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710630543.5A CN107451357A (en) 2017-07-28 2017-07-28 A kind of balcony construction method of ground based on BIM

Publications (1)

Publication Number Publication Date
CN107451357A true CN107451357A (en) 2017-12-08

Family

ID=60489562

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710630543.5A Pending CN107451357A (en) 2017-07-28 2017-07-28 A kind of balcony construction method of ground based on BIM

Country Status (1)

Country Link
CN (1) CN107451357A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110206313A (en) * 2019-06-20 2019-09-06 浙江华汇装饰工程股份有限公司 A kind of construction method of the mixed paving of flooring plate dry method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1072435A (en) * 1992-08-27 1993-05-26 化学工业部海洋涂料研究所 Building water-proof paint
CN101191364A (en) * 2006-11-28 2008-06-04 贵阳铝镁设计研究院 Planting zoology roofing for topping laying floor brick
CN101949207A (en) * 2010-09-10 2011-01-19 中建七局第四建筑有限公司 Method for constructing subsided rest room
US20130013265A1 (en) * 2011-07-07 2013-01-10 Autodesk, Inc. Direct manipulation of composite terrain objects with intuitive user interaction
CN105781064A (en) * 2016-03-04 2016-07-20 上海宝冶集团有限公司 Floor tile laying construction method based on building information modeling (BIM)
CN206158102U (en) * 2016-10-31 2017-05-10 浙江铭品装饰工程有限公司 Balcony construction site layout structure
CN106886654A (en) * 2017-03-14 2017-06-23 中国建筑第八工程局有限公司 A kind of row's of building by laying bricks or stones brick method based on BIM technology

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1072435A (en) * 1992-08-27 1993-05-26 化学工业部海洋涂料研究所 Building water-proof paint
CN101191364A (en) * 2006-11-28 2008-06-04 贵阳铝镁设计研究院 Planting zoology roofing for topping laying floor brick
CN101949207A (en) * 2010-09-10 2011-01-19 中建七局第四建筑有限公司 Method for constructing subsided rest room
US20130013265A1 (en) * 2011-07-07 2013-01-10 Autodesk, Inc. Direct manipulation of composite terrain objects with intuitive user interaction
CN105781064A (en) * 2016-03-04 2016-07-20 上海宝冶集团有限公司 Floor tile laying construction method based on building information modeling (BIM)
CN206158102U (en) * 2016-10-31 2017-05-10 浙江铭品装饰工程有限公司 Balcony construction site layout structure
CN106886654A (en) * 2017-03-14 2017-06-23 中国建筑第八工程局有限公司 A kind of row's of building by laying bricks or stones brick method based on BIM technology

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
张道真: "《建筑防水》", 31 August 2014 *
花草游戏编辑部: "《庭院屋顶种花与景观设计》", 30 November 2010 *
赵永任: "《工程项目管理》", 31 August 2016 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110206313A (en) * 2019-06-20 2019-09-06 浙江华汇装饰工程股份有限公司 A kind of construction method of the mixed paving of flooring plate dry method

Similar Documents

Publication Publication Date Title
Xu et al. Digital reproduction of historical building ornamental components: From 3D scanning to 3D printing
CN104850709B (en) Building decoration engineering construction three-dimensional simulation method
Bednarz et al. Strengthening and long-term monitoring of the structure of an historical church presbytery
CN105781064A (en) Floor tile laying construction method based on building information modeling (BIM)
CN107299762A (en) A kind of concrete pouring procedure based on BIM
CN105678006A (en) Method for drawing foundation pit excavation drawing
CN111177824A (en) Aluminum alloy formwork construction method based on BIM technology
CN107451357A (en) A kind of balcony construction method of ground based on BIM
CN107451358A (en) A kind of building method of the curved wall based on BIM
CN107292060A (en) Basement roadway applications method based on BIM technology
CN111456279A (en) Brick wall building method and device, computer equipment and storage medium
CN107292058A (en) A kind of brickwork method based on BIM technology
CN103774696A (en) Construction process of cement-based permeable-crystallization type waterproof material
Jesus et al. The potential of 3D printing in building pathology: rehabilitation of cultural heritage
CN111324922B (en) Method, device, computer equipment and storage medium for generating floor tile model
CN107436984A (en) A kind of wine cellar construction method based on BIM
CN107451356A (en) A kind of outer-wall building method based on BIM
CN113129427A (en) Building model processing method and device, computer equipment and readable storage medium
CN107436985A (en) A kind of toilet ground tile paving method based on BIM
CN108265746A (en) A kind of method of back-grouting in Equipment Foundations work progress
CN111524225B (en) Construction method of manual hole digging cast-in-place pile based on BIM technology
CN104058694B (en) A kind of concrete material for pavement patching and constructional method thereof
CN107313518A (en) A kind of toilet warterproof technique based on BIM
KR102191532B1 (en) Liquid waterproof agent and constructing method for waterproof by using the same
CN207281759U (en) A kind of masonry project application system based on BIM

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20171208

RJ01 Rejection of invention patent application after publication