CN107292060A - Basement roadway applications method based on BIM technology - Google Patents

Basement roadway applications method based on BIM technology Download PDF

Info

Publication number
CN107292060A
CN107292060A CN201710630567.0A CN201710630567A CN107292060A CN 107292060 A CN107292060 A CN 107292060A CN 201710630567 A CN201710630567 A CN 201710630567A CN 107292060 A CN107292060 A CN 107292060A
Authority
CN
China
Prior art keywords
layer
basement
construction
architectural
parameter
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710630567.0A
Other languages
Chinese (zh)
Inventor
周江峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chengdu Zhi Jian New Architectural Design Consulting Co Ltd
Original Assignee
Chengdu Zhi Jian New Architectural Design Consulting Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chengdu Zhi Jian New Architectural Design Consulting Co Ltd filed Critical Chengdu Zhi Jian New Architectural Design Consulting Co Ltd
Priority to CN201710630567.0A priority Critical patent/CN107292060A/en
Publication of CN107292060A publication Critical patent/CN107292060A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING; COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads

Abstract

The invention discloses a kind of basement roadway applications method based on BIM technology, including following steps:(1) construction scheme, is formulated;(2), based on architectural drawing, three-dimensional modeling is carried out to basic unit, both surface layers;(3), based on construction scheme and architectural drawing, three-dimensional modeling is carried out to the waterproof mortar course being laid on successively in basic unit from top to bottom, polyurethane water-proof paint layer, the concrete layer being laid on successively from top to bottom on surface layer, grout layer;(4), using the dynamic analog in BIM and data analysis, the correlated fitting for obtaining each layer piles up parameter;(5), site operation manufacture is carried out based on piling up parameter and architectural drawing.Present inventive concept is ingenious, and the construction problem of appearance can be had found that it is likely that before construction, and the mode without adjusted in construction carries out site operation, saves the time of construction, reduces rework rate, accelerates project progress.

Description

Basement roadway applications method based on BIM technology
Technical field
The present invention relates to building field, and in particular to a kind of basement roadway applications method based on BIM technology.
Background technology
BIM is the new tool of architecture, engineering science and civil engineering.BIM (Building Information Modeling, abbreviation BIM), it is defined as by being constituted completely with insufficient information to support life cycle management, And the building or architectural engineering information model that can be directly explained by computer applied algorithm.In short, i.e. digital technology support Life cycle management to architectural environment.Existing building construction is aided in using BIM technology, is that the one of construction becomes greatly Gesture.
It is that arrangement and method for construction is carried out according to architectural CAD two-dimentional drawing first mostly when present basement roadway applications Formulate, in the process, the site problems of construction can not be touched at all, such as after progress concrete vibrating is closely knit, to determine The flatness and the gradient on absolute altitude and surface with floating rule, it is necessary to while be struck off while carrying out the check of absolute altitude with spirit level, construction is existing It is complicated and cumbersome.
The content of the invention
It is an object of the invention to a kind of basement roadway applications method of the offer based on BIM technology, this method is made first Determine construction scheme, recycle BIM technology to the basic unit of basement, surface layer and be coated in basic unit, on surface layer each is auxiliary Help layer to carry out three-dimensional modeling, dynamic analog and data analysis are then carried out again, obtain the parameter of piling up in construction simulation, then profit With piling up parameter and architectural drawing carries out site operation.Because BIM technology is simulated using real information, therefore, it is possible to apply Work has found that it is likely that the construction problem of appearance before building, the mode without adjusted in construction carries out site operation, This mode has previewed the dynamic process constructed using the building element in building scheme, also just can appreciate that and is actually applying Produced problem during work, the technical scheme solved the problems, such as can be just provided before not constructing, the time of construction is saved, Reduce rework rate, accelerate project progress.
The present invention is achieved through the following technical solutions:
Basement roadway applications method based on BIM technology, including following steps:
(1), formulate initial construction scheme, in the basic unit of basement from top to bottom successively laying waterproof mortar course, Polyurethane water-proof paint layer, is laid on concrete layer, grout layer on surface layer successively from top to bottom on the surface layer of basement Carry out three-dimensional modeling;
(2), based on architectural drawing, three-dimensional modeling is carried out to basic unit, both surface layers;
(3), based on construction scheme and architectural drawing, to the waterproof mortar being laid on successively from top to bottom in basic unit Layer, polyurethane water-proof paint layer, the concrete layer being laid on successively from top to bottom on surface layer, grout layer carry out three-dimensional modeling;
(4), using the dynamic analog in BIM and data analysis, with the basic unit through three-dimensional modeling, surface layer, waterproof mortar course, The dynamic analog that polyurethane water-proof paint layer, concrete layer, the threedimensional model of grout layer are constructed, obtains the phase of each layer Close fitting piles up parameter;
(5), site operation manufacture is carried out based on piling up parameter and architectural drawing.
The parameter of piling up of the correlated fitting of each layer includes the thickness parameter, gradient coefficient, flatness and resistance to compression of each layer Intensity.
By weight, the component of waterproof mortar is that 1 part of portland cement, average grain diameter are 3mm, are less than 2% containing mud two It is 2-2.5 parts of sand, 0.2-0.5 parts of cationic chloroprene latex, 0.01 part of defoamer, 0.01 part of citric acid, 0.01 part of tartaric acid, appropriate Water.
Concrete layer is cement, the stirring of coarse aggregate, fine aggregate, water is formed.
The particle diameter of coarse aggregate is 5-10 times of fine aggregate particle diameter.
The inventive concept of the present invention is:Construction scheme, base of the recycling BIM technology to basement are formulated first Layer, surface layer and it is coated in basic unit, each auxiliary layer on surface layer and carries out three-dimensional modeling, dynamic analog and number is then carried out again According to analysis, the parameter of piling up in construction simulation is obtained, recycling piles up parameter and architectural drawing carries out site operation.Because BIM Technology is simulated using real information, therefore, it is possible to have found that it is likely that the construction problem of appearance before construction, so that nothing The mode that need to carry out adjusting in construction carries out site operation, and this mode has been previewed to be entered using the building element in building scheme The dynamic process of row construction, also just can appreciate that the produced problem during practice of construction, can just be carried before not constructing Technical scheme for solving problem, saves the time of construction, reduces rework rate, accelerates project progress.
The waterproof mortar that the present invention is used in implementation process can improve waterproof degree.
The present invention compared with prior art, has the following advantages and advantages:
Present inventive concept is ingenious, and the construction problem of appearance can be had found that it is likely that before construction, without carrying out The mode adjusted in construction carries out site operation, and this mode has been previewed is constructed using the building element in building scheme Dynamic process, also just can appreciate that the produced problem during practice of construction, solution can be just provided before not constructing The technical scheme of problem, saves the time of construction, reduces rework rate, accelerates project progress.
Embodiment
For the object, technical solutions and advantages of the present invention are more clearly understood, with reference to embodiment, to present invention work Further to describe in detail, exemplary embodiment and its explanation of the invention is only used for explaining the present invention, is not intended as to this The restriction of invention.
Embodiment 1
Basement roadway applications method based on BIM technology, including following steps:
(1) construction scheme, is formulated, waterproof mortar course, poly- ammonia is laid successively from top to bottom in the basic unit of basement Ester waterproof coating layer, the concrete layer being laid on successively from top to bottom on the surface layer of basement on surface layer, grout layer are carried out Three-dimensional modeling;
(2), based on architectural drawing, three-dimensional modeling is carried out to basic unit, both surface layers;
(3), based on construction scheme and architectural drawing, to the waterproof mortar being laid on successively from top to bottom in basic unit Layer, polyurethane water-proof paint layer, the concrete layer being laid on successively from top to bottom on surface layer, grout layer carry out three-dimensional modeling;
(4), using the dynamic analog in BIM and data analysis, with the basic unit through three-dimensional modeling, surface layer, waterproof mortar course, The dynamic analog that polyurethane water-proof paint layer, concrete layer, the threedimensional model of grout layer are constructed, obtains the phase of each layer Close fitting piles up parameter;
(5), site operation manufacture is carried out based on piling up parameter and architectural drawing.
Embodiment 2
The parameter of piling up of the correlated fitting of each layer includes the thickness parameter, gradient coefficient, flatness and resistance to compression of each layer Intensity.
By weight, the component of waterproof mortar is that 1 part of portland cement, average grain diameter are 3mm, are less than 2% containing mud two It is 2-2.5 parts of sand, 0.2-0.5 parts of cationic chloroprene latex, 0.01 part of defoamer, 0.01 part of citric acid, 0.01 part of tartaric acid, appropriate Water.
Concrete layer is cement, the stirring of coarse aggregate, fine aggregate, water is formed.
The particle diameter of coarse aggregate is 5-10 times of fine aggregate particle diameter.
Above-described embodiment, has been carried out further to the purpose of the present invention, technical scheme and beneficial effect Describe in detail, should be understood that the embodiment that the foregoing is only the present invention, be not intended to limit the present invention Protection domain, within the spirit and principles of the invention, any modification, equivalent substitution and improvements done etc. all should be included Within protection scope of the present invention.

Claims (5)

1. the basement roadway applications method based on BIM technology, it is characterised in that including following steps:
(1) initial construction scheme, is formulated, waterproof mortar course, poly- ammonia is laid successively from top to bottom in the basic unit of basement Ester waterproof coating layer, the concrete layer being laid on successively from top to bottom on the surface layer of basement on surface layer, grout layer are carried out Three-dimensional modeling;
(2), based on architectural drawing, three-dimensional modeling is carried out to basic unit, both surface layers;
(3), based on construction scheme and architectural drawing, to the waterproof mortar course, poly- being laid on successively from top to bottom in basic unit Urethane waterproof coating layer, the concrete layer being laid on successively from top to bottom on surface layer, grout layer carry out three-dimensional modeling;
(4), using the dynamic analog in BIM and data analysis, with the basic unit through three-dimensional modeling, surface layer, waterproof mortar course, poly- ammonia The dynamic analog that ester waterproof coating layer, concrete layer, the threedimensional model of grout layer are constructed, obtains the related plan of each layer That closes piles up parameter;
(5), site operation manufacture is carried out based on piling up parameter and architectural drawing.
2. the basement roadway applications method according to claim 1 based on BIM technology, it is characterised in that each layer The parameter of piling up of correlated fitting includes the thickness parameter, gradient coefficient, flatness and compression strength of each layer.
3. the basement roadway applications method according to claim 1 based on BIM technology, it is characterised in that by weight, The component of waterproof mortar is that 1 part of portland cement, average grain diameter are 3mm, are less than 2% 2-2.5 parts of sand, cation chlorine containing mud two 0.2-0.5 parts of fourth latex, 0.01 part of defoamer, 0.01 part of citric acid, 0.01 part of tartaric acid, appropriate water.
4. the basement roadway applications method according to claim 1 based on BIM technology, it is characterised in that concrete layer Formed for cement, coarse aggregate, fine aggregate, water stirring.
5. the basement roadway applications method according to claim 4 based on BIM technology, it is characterised in that coarse aggregate Particle diameter is 5-10 times of fine aggregate particle diameter.
CN201710630567.0A 2017-07-28 2017-07-28 Basement roadway applications method based on BIM technology Pending CN107292060A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710630567.0A CN107292060A (en) 2017-07-28 2017-07-28 Basement roadway applications method based on BIM technology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710630567.0A CN107292060A (en) 2017-07-28 2017-07-28 Basement roadway applications method based on BIM technology

Publications (1)

Publication Number Publication Date
CN107292060A true CN107292060A (en) 2017-10-24

Family

ID=60103576

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710630567.0A Pending CN107292060A (en) 2017-07-28 2017-07-28 Basement roadway applications method based on BIM technology

Country Status (1)

Country Link
CN (1) CN107292060A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108319479A (en) * 2018-01-29 2018-07-24 蒋成 A kind of BIM extension Enhancement Methods and system based on B/S information systems
CN109760059A (en) * 2019-02-28 2019-05-17 华中科技大学 Mechanical arm fittage planing method and building assembly method based on BIM
CN110342879A (en) * 2019-07-18 2019-10-18 深圳工建科技有限公司 A kind of waterproof mortar and preparation method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1218081A (en) * 1998-10-29 1999-06-02 化学工业部星火化工厂 Organic silicone waterproofing agent and application thereof
CN101220579A (en) * 2008-02-03 2008-07-16 徐培华 Rubber powder modified asphalt macadam bridge surface waterproof layer and construction method
CN101298782A (en) * 2008-06-13 2008-11-05 朱邃科 Method and system for basement engineering water proof and water drain
US9019269B1 (en) * 2011-11-28 2015-04-28 Robert Alan Pogue Interactive rendering of building information model data
CN105781064A (en) * 2016-03-04 2016-07-20 上海宝冶集团有限公司 Floor tile laying construction method based on building information modeling (BIM)
CN105989198A (en) * 2015-01-29 2016-10-05 中交宇科(北京)空间信息技术有限公司 BIM-based (building information modeling based) road parametric auto-modeling method and system

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1218081A (en) * 1998-10-29 1999-06-02 化学工业部星火化工厂 Organic silicone waterproofing agent and application thereof
CN101220579A (en) * 2008-02-03 2008-07-16 徐培华 Rubber powder modified asphalt macadam bridge surface waterproof layer and construction method
CN101298782A (en) * 2008-06-13 2008-11-05 朱邃科 Method and system for basement engineering water proof and water drain
US9019269B1 (en) * 2011-11-28 2015-04-28 Robert Alan Pogue Interactive rendering of building information model data
CN105989198A (en) * 2015-01-29 2016-10-05 中交宇科(北京)空间信息技术有限公司 BIM-based (building information modeling based) road parametric auto-modeling method and system
CN105781064A (en) * 2016-03-04 2016-07-20 上海宝冶集团有限公司 Floor tile laying construction method based on building information modeling (BIM)

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
张长友: "《建筑施工技术》", 31 August 2014 *
赵永任: "《工程项目管理》", 31 August 2016 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108319479A (en) * 2018-01-29 2018-07-24 蒋成 A kind of BIM extension Enhancement Methods and system based on B/S information systems
CN108319479B (en) * 2018-01-29 2019-03-05 蒋成 A kind of BIM extension Enhancement Method and system based on B/S information system
CN109760059A (en) * 2019-02-28 2019-05-17 华中科技大学 Mechanical arm fittage planing method and building assembly method based on BIM
CN109760059B (en) * 2019-02-28 2020-12-08 华中科技大学 Mechanical arm assembly task planning method based on BIM and building assembly method
CN110342879A (en) * 2019-07-18 2019-10-18 深圳工建科技有限公司 A kind of waterproof mortar and preparation method thereof

Similar Documents

Publication Publication Date Title
CN107292060A (en) Basement roadway applications method based on BIM technology
Fortunato et al. Survey and seismic vulnerability assessment of the Baptistery of San Giovanni in Tumba (Italy)
Bednarz et al. Strengthening and long-term monitoring of the structure of an historical church presbytery
CN104458309A (en) Similar material proportion determining method used in physical simulation experiment
CN105089184B (en) Multi-curved concrete hollow modelling wall construction method and rhombic hollow structure formwork
CN107292058A (en) A kind of brickwork method based on BIM technology
CN107354872B (en) A kind of variable cross-section fish-bellied type cast-in-situ box girder concrete faulting of slab ends control structure and construction method
CN107451356A (en) A kind of outer-wall building method based on BIM
CN109555238A (en) The processing method that a kind of aluminum alloy mould plate concrete body exempts from plastering
CN107299762A (en) A kind of concrete pouring procedure based on BIM
CN111946357B (en) Mine method tunnel simulation construction method considering red clay unloading influence
Verstrynge et al. Creep and failure prediction of Diestian ferruginous sandstone: modelling and repair options
Guo et al. Multi-scale peridynamic formulations for chloride diffusion in concrete
CN107451357A (en) A kind of balcony construction method of ground based on BIM
Lee et al. Cast-in-place architectonic concrete in South Korea: Methods and specifications
Lueprasert et al. Tunneling simulation in soft ground using shell elements and grouting layer
Raszczuk et al. Correlation between the cracking pattern of historical structure and soil properties: the case of the church in Kożuchów
Waichita et al. Application of ground spring model in excavation supported by deep cement mixing
CN109083436A (en) A kind of constructing structure method for Historical Block facade rebuilding
CN107292059A (en) A kind of construction method of the terrazzo floor based on BIM
Grillanda et al. Advanced Modeling of a Historical Masonry Umbrella Vault: Settlement Analysis and Crack Tracking via Adaptive NURBS Kinematic Analysis
CN206000096U (en) A kind of cracking resistance and anti-hollowing exempt from block wall structure of plastering
CN107436985A (en) A kind of toilet ground tile paving method based on BIM
CN107436984A (en) A kind of wine cellar construction method based on BIM
Li Architectural design with Autocad

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20171024