CN107398697A - A kind of flowmeter cleaning and its automatic hookup wire of adapter - Google Patents

A kind of flowmeter cleaning and its automatic hookup wire of adapter Download PDF

Info

Publication number
CN107398697A
CN107398697A CN201710572924.2A CN201710572924A CN107398697A CN 107398697 A CN107398697 A CN 107398697A CN 201710572924 A CN201710572924 A CN 201710572924A CN 107398697 A CN107398697 A CN 107398697A
Authority
CN
China
Prior art keywords
supply line
adapter
flowmeter
posture correction
correction area
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710572924.2A
Other languages
Chinese (zh)
Other versions
CN107398697B (en
Inventor
王匀
姜鼎
许桢英
邹荣
于超
唐书浩
谭中锐
尹研
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MEZOLEN INSTRUMENT (CHANGZHOU) Co.,Ltd.
Original Assignee
Jiangsu University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu University filed Critical Jiangsu University
Priority to CN201710572924.2A priority Critical patent/CN107398697B/en
Publication of CN107398697A publication Critical patent/CN107398697A/en
Application granted granted Critical
Publication of CN107398697B publication Critical patent/CN107398697B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23PMETAL-WORKING NOT OTHERWISE PROVIDED FOR; COMBINED OPERATIONS; UNIVERSAL MACHINE TOOLS
    • B23P19/00Machines for simply fitting together or separating metal parts or objects, or metal and non-metal parts, whether or not involving some deformation; Tools or devices therefor so far as not provided for in other classes
    • B23P19/001Article feeders for assembling machines
    • B23P19/006Holding or positioning the article in front of the applying tool
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B08CLEANING
    • B08BCLEANING IN GENERAL; PREVENTION OF FOULING IN GENERAL
    • B08B3/00Cleaning by methods involving the use or presence of liquid or steam
    • B08B3/02Cleaning by the force of jets or sprays
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23PMETAL-WORKING NOT OTHERWISE PROVIDED FOR; COMBINED OPERATIONS; UNIVERSAL MACHINE TOOLS
    • B23P19/00Machines for simply fitting together or separating metal parts or objects, or metal and non-metal parts, whether or not involving some deformation; Tools or devices therefor so far as not provided for in other classes
    • B23P19/001Article feeders for assembling machines
    • B23P19/007Picking-up and placing mechanisms

Abstract

The invention provides a kind of cleaning of flowmeter and its automatic hookup wire of adapter, include washing station, screen station, vision-based detection station, assembly station.The washing station is made up of giant, swivel base, spiral guide plate, the screening station is made up of two one-level, two level posture correction conveyer belts, the two level posture correction area is connected with supply line, the vision-based detection station is made up of two conllinear video cameras, it is symmetrical in supply line both sides, the assembly station is made up of two conllinear manipulators, symmetrical in supply line both sides.By washing station, screening station, vision-based detection station, the assembly station set gradually, to realize that flowmeter cleaning and its adapter are installed automatically, flowmeter determination rates are favorably improved, while simplify identity process.

Description

A kind of flowmeter cleaning and its automatic hookup wire of adapter
Technical field
The present invention relates to a kind of cleaning of flowmeter and its automatic hookup wire of adapter, and more particularly to a kind of automatic detection Line and switching device, belong to measurement test and technical field of automation.
Background technology
When carrying out meter proof during special equipment detects research institute, because the interface specification for testing pipeline is limited, and The interface specification of tested flowmeter is varied, in qualification process, is detected flowmeter and the dismounting tested between pipeline very not Just, and because tested flow count number is more, usually require to expend in flowmeter specification and matching for calibrating pipeline specifications A large amount of manpowers and time, it is unfavorable for improving the efficiency of calibrating.Therefore, the present invention is filled by providing a kind of automatic inspection line and switching Put with switching device to solve the above problems.
The content of the invention
The invention provides a kind of flowmeter specification automatic detection and adapter hookup wire, for solving in meter proof Tested flowmeter and cumbersome, the flowmeter specification that dismounts tested between pipeline usually require consumption with matching for calibrating pipeline specifications Take a large amount of manpowers and time, the problems such as being unfavorable for improving calibrating efficiency.
The present invention is achieved through the following technical solutions:
It is characterized in that:Mainly include swivel base, spiral guide plate, hydraulic giant support, giant, video camera, machinery Hand, one-level posture correction area, two level posture correction area, assembling supply line,
Multiple pod apertures are set on the swivel base, and spiral guide plate is located at the top of the swivel base, the height Pressure hydraulic giant is fixed on hydraulic giant support, and above spiral guide plate;The end of the spiral guide plate sets transition slide Alignd with the starting end in contact in one-level posture correction area;
The one-level posture correction area is made up of parallel in the horizontal direction several conveyer belts, is set above transmission tape beginning end Height limit plate is equipped with, is provided between conveyer belt and moves the parallel Horizontal limiting plate in direction;
Two level posture correction area is arranged on the afterbody of one-level correction zone, and two level posture correction area's initiating terminal is rectified with one-level posture The contact alignment of Zheng Qu ends, the two level posture correction area are mainly made up of sideboard, fixed dam, and the two level posture is rectified Positive area is body structure, and its side wall is movable, and bottom plate is fixed, and inside is provided with some vertical embedded wall box at a certain distance Fixed dam, its top can correct area in two level posture and be moved horizontally with wall box away from wall box upper surface 4cm, baffle plate; Sideboard is hinged with box bilateral wall, and pin joint and fixed dam be in same plane, away from fixed dam top 3.5cm, its Two level posture correction area's initiating terminal be in raised configuration, be horizontally distributed in body structure upper strata, its size can block just by The compartment entrance that adjacent two fixed dam is formed, when that will approach assembling supply line, sideboard drops to and fixed dam The position being close to;Described two level posture correction area end bottom is not provided with bottom plate, leads directly to assembling supply line, is easy to flowmeter certainly By sliding to assembling supply line;
Assembling supply line is arranged on the afterbody in two level posture correction area, and the assembling supply line and two level posture correction area are different Face is intersected vertically, and described two video cameras positioned at assembling supply line both sides and are fixed on camera support, the manipulator respectively Positioned at the downstream of video camera, and mounted in the both sides of assembling supply line, adapter goods is additionally provided with positioned in the both sides of assembling supply line Frame, and adapter shelf are located at beside manipulator;The afterbody of the assembling supply line sets supply line steering gear, pigeonholes.
Further, gravity buffering and aligning device are provided with the assembling supply line, the gravity buffering is with aligning Device aligns ring, bearing platform, buffer spring, gauge outfit including conduit and aligns push rod, and bearing platform bottom is filled by several buffer springs On the bottom plate of assembling supply line, gauge outfit aligns push rod and is arranged on the relative side of two adjacent demarcation strips and symmetrically divides Cloth, two conduits align ring and are arranged on two outer side shields of assembling supply line and are symmetrically distributed.
Further, the rounded array arrangement of multiple pod apertures on the swivel base.
Further, the quantity of conveyer belt is three, is driven by motorized pulleys.
Further, spiral guide plate lower surface is parallel with swivel base upper surface and spacing 1cm;Transition slide upper flat Face is parallel with swivel base lower surface, and spacing 1cm.
Further, the rounded array of described giant is evenly distributed on the annular frame of hydraulic giant cradle top.
Further, described transition slide surface covering rubber layer, the drop 30cm at transition slide both ends.
Further, the difference in height between height limit plate and conveyer belt is that h meets D<h<H, wherein, D justifies for flowmeter The diameter of cylindricality gauge outfit, H are the height of flowmeter.
Adapter for described flowmeter specification fast automatic detecting and its adapter hookup wire, it is characterised in that Including upper connection component, lower connector, upper connection component includes about collar, clamping sleeve, spring, rubber sliding sleeve,
The constraint is set on the outside of clamping sleeve;
The clamping sleeve can slide along about collar inner surface, and outer circular top part is provided with connection screw thread;
Circular diameter D1 is slightly less than diameter D2, the D1=0.8D2 of clamping sleeve bottom cylindrical in the rubber sliding sleeve, to ensure to have The sealing of effect, it is arranged between about collar and clamping sleeve, can be along about collar inner surface and clamping sleeve outer surface in the effect of spring Lower slider;
The spring is arranged between clamping sleeve bottom and rubber sliding sleeve circle outer ring.
The beneficial effects of the invention are as follows:
By being disposed with washing station, vision-based detection station, manipulator assembly station and sortation process, come real Existing flowmeter cleaning and its automatic installation of adapter, identity process is simplified while flowmeter determination rates are improved.This Inventive structure is simple, saves substantial amounts of labour.
The flowmeter switching device, mainly there is very high modulus of elasticity this feature using rubber, by clamping sleeve When compressing downwards, rubber sliding sleeve is pressed into the cavity of the lower link element with spherical cavity in advance by spring, then pressed The further slide downward of tight set, the structure of expanding of rubber sliding sleeve is further expanded, it is close to lower connector spherical cavity Inner surface, play a part of sealing.When needing to take out upper connection component, the step of clamping sleeve one need to be only pressed downward, rubber sliding sleeve Less that section of pipe shaft of external diameter in the middle part of clamping sleeve is will slide into, so that the diameter that structure is expanded in rubber sliding sleeve bottom reduces, this When on connection component can conveniently take out.After upper connection component exits lower connector, because spring is in compressive state, by The influence of its elastic force, rubber sliding sleeve are extruded at the smaller tube wall of outside diameter among clamping sleeve, and connection component is extensive on adapter Again to original state.
Brief description of the drawings
Fig. 1 is the schematic diagram of flowmeter of the present invention cleaning and its automatic hookup wire of adapter;
Fig. 2 is the schematic diagram of washing station in the embodiment of the present invention;
Fig. 3 is that two level posture corrects area end schematic diagram in the embodiment of the present invention;
Fig. 4 is that gravity buffering and the flowmeter aligning device schematic diagram in supply line are assembled in the embodiment of the present invention;
Fig. 5 is flowmeter adapter overall structure diagram in the embodiment of the present invention;
Fig. 6 is connecting component structure schematic diagram on flowmeter adapter in the embodiment of the present invention;
Fig. 7 is connecting-piece structure schematic diagram under flowmeter adapter in the embodiment of the present invention.
In figure:
1. swivel base, 2. spiral guide plates, 3. hydraulic giant supports, 4. pod apertures, 5. giants, 6. height limit plates, 7. Horizontal limiting plate, 8. sideboards, 9. fixed dams, 10. video cameras, 11. manipulators, 12. transition slides, 13. one-level appearances State corrects area, and 14. conveyer belts, 15. two level postures correction area, 16. camera supports, 17. adapter shelf, 18. assemble supply lines, 19. supply line steering gear, 20. pigeonholes, 28. times connectors, the 21. outer side shields of assembling supply lines, 22. conduits align ring, 23. Bottom plate, 24. bearing platforms, 25. buffer springs, 26. gauge outfits align push rod, 27. demarcation strips, 28. times connectors, 29. about collars, 30. clamping sleeve, 31. springs, 32. rubber sliding sleeves.
Embodiment
Below in conjunction with the accompanying drawings and specific embodiment the present invention is further illustrated, but protection scope of the present invention is simultaneously Not limited to this.
It is shown in Figure 1, for flowmeter of the present invention cleaning and its automatic hookup wire of adapter, including swivel base 1), spiral guide plate 2, hydraulic giant support 3, pod apertures 4, giant 5, height limit plate 6, Horizontal limiting plate 7, sideboard 8, Fixed dam 9, video camera 10, manipulator 11, transition slide 12, one-level posture correction area 13, conveyer belt 14, the correction of two level posture Area 15, camera support 16, adapter shelf 17, assembling supply line 18, supply line steering gear 19, pigeonholes 20.
As shown in Fig. 2 multiple pod apertures 4 are set on the swivel base 1, multiple 4 rounded array arrangements of pod apertures.Spiral shell Rotation guide plate 2 is located at the top of the swivel base 1, and the giant 5 is fixed on hydraulic giant support 3, and is led positioned at spiral To the top of plate 2;Described 5 rounded array of giant is evenly distributed on the annular frame at the top of hydraulic giant support 3.The spiral shell The end of rotation guide plate 2 sets transition slide 12 and the starting end in contact in one-level posture correction area 13 to align.Described transition is slided Terraced 12 surfaces covering rubber layer, the drop 30cm at the both ends of transition slide 12.The lower surface of spiral guide plate 2 and the upper table of swivel base 1 Face is parallel and spacing 1cm;The upper plane of transition slide 12 is parallel with the lower surface of swivel base 1, and spacing 1cm.
The one-level posture correction area 13 is made up of parallel in the horizontal direction by three motorized pulleys driving conveyer belt 14, Height limit plate 6 is provided with above the initiating terminal of conveyer belt 14, is provided between conveyer belt 14 and moves the parallel level in direction Limiting plate 7.Difference in height between height limit plate 6 and conveyer belt 14 meets D for h<h<H, wherein, D is flowmeter cylinder table The diameter of head, H are the height of flowmeter.
Two level posture correction area 15 is arranged on the afterbody of one-level correction zone 13, the two level posture correction initiating terminal of area 15 and one-level The contact alignment of the posture correction end of area 13, the two level posture correction area 15 are mainly made up of sideboard 8, fixed dam 9, institute It is body structure to state two level posture correction area 15, and its side wall is movable, and bottom plate is fixed, and inside is provided with some vertical at a certain distance The fixed dam 9 of embedded wall box, its top away from wall box upper surface 4cm, baffle plate 9 can two level posture correct area 15 with Wall box moves horizontally;Sideboard 8 is hinged with box bilateral wall, and pin joint is in same plane with fixed dam 9, away from solid Determine the top 3.5cm of baffle plate 9, it is in raised configuration in the two level posture correction initiating terminal of area 15, is horizontally distributed on body structure Layer, its size can block the compartment entrance being made up of adjacent two fixed dam 9 just, when assembling supply line 18 will be approached, Sideboard 8 drops to the position being close to fixed dam 9;The described two level posture correction end bottom of area 15 is not provided with bottom Plate, assembling supply line 18 is led directly to, be easy to flowmeter free skating to drop down onto assembling supply line 18, as shown in Figure 3.
Assembling supply line 18 is arranged on the afterbody in two level posture correction area 15, and the assembling supply line 18 is rectified with two level posture Positive area 15 antarafacial intersects vertically, and described two video cameras 10 positioned at the assembling both sides of supply line 18 and are fixed on camera support 16 respectively On, the manipulator 11 is located at the downstream of video camera 10, and mounted in the both sides of assembling supply line 18, positioned in assembling supply line 18 Both sides be additionally provided with adapter shelf 17, and adapter shelf 17 are located at the side of manipulator 11;The tail of the assembling supply line 18 Portion sets supply line steering gear 19, pigeonholes 20.
As shown in figure 4, be provided with gravity buffering and aligning device in the assembling supply line 18, gravity buffering with it is right Equipment aligns ring 22, bearing platform 24, buffer spring 25, gauge outfit including conduit and aligns push rod 26, and the bottom of bearing platform 24 passes through number On the bottom plate 23 of assembling supply line 18, gauge outfit aligns push rod 26 and is arranged on two adjacent demarcation strips 27 individual buffer spring 25 It is on relative side and symmetrical, two conduits align ring 22 be arranged on assembling supply line two outer side shields 21 on and It is symmetrically distributed.
After tested flowmeter is placed on the centre of swivel base 1, giant 5 start spray water operation, 5 minutes Afterwards, swivel base 1 starts to rotate, and flowmeter is moved to the edge of swivel base 1, and freely fall by the guiding of spiral guide plate 2 Fall on transition slide 12, by the transmission of transition slide 12, flowmeter enters one-level posture correction area 13, is rubbed by contact Wipe, Horizontal limiting plate 7 can be corrected the transmission in area 13 by one-level posture, flowed by crooked flowmeter guiding into vertical state Gauge enters two level posture correction area 15, and flowmeter slides to the sideboard 8 of raised configuration, fallen with rear active baffle 8, Because flowmeter meter overweights pipe shaft, flowmeter is fallen into the compartment being split to form by fixed dam 9 with head-down posture, The flowmeter after posture correction is completed freely to be slipped at two level posture corrects area 15 and assembles the square crossing of supply line 18 Assemble on supply line 18, assemble in supply line 18 and be provided with damping of shocks and aligning device, it is ensured that tested flowmeter will not be slided again It is damaged during falling, the flowmeter after aligning is by assembling the transmission of supply line 18, after reaching vision-based detection station, Video camera 10 detects to the threaded connection hole of flowmeter, and then flowmeter enters the operating area of manipulator 11, manipulator 11 The threaded connection hole dimension information that will be detected according to camera 10, capture in the corresponding region of adapter shelf 17 and meet matching It is required that adapter, be assembled on tested flowmeter, after the completion of assembling, flowmeter when by supply line steering gear 19, Can free skating drop down onto pigeonholes 20, after sorting, you can be directly mounted to the calibrating for being already installed with connector 28 under adapter In system.
If the testing result for occurring two or more station in detection process is different, the feelings of flowmeter interface specification None- identified Condition, alarm 8 send alarm sounds.
After tested flowmeter enters assembling supply line 18, with gauge outfit, the posture of pipe shaft upward, vertical drop arrive down first On bearing platform 24, the bottom of bearing platform 24 is provided with 4 buffer springs 25 in a manner of quadrangular array, can prevent flowmeter due to Severe impact and damage, subsequent gauge outfit aligns push rod 26 and stretched out, and it is right on front and rear adjacent demarcation strip 27 that gauge outfit aligns push rod 26 Title is distributed with two, and rise is identical, gauge outfit can be pushed into the compartment center position being made up of adjacent demarcation strip 27, with rear tube Ring 22 is aligned to stretch out, conduit aligns the both sides of side shield 21 center outside relative assembling supply line of ring 22 and is symmetrically distributed with two, Compartment center position will can be in, but still righting, gravity are carried out to the inclined pipe shaft of the assembling axis normal direction of supply line 18 Buffering and flowmeter aligning device can play a part of clamping tested flowmeter simultaneously, be easy to follow-up vision-based detection and adapter Installation.
As shown in Fig. 5, Fig. 6, Fig. 7, the flowmeter adapter that uses in flowmeter cleaning and its automatic hookup wire of adapter Including:Upper connection component and lower connector 28, upper connection component include about collar 29, clamping sleeve 30, spring 31, rubber sliding sleeve 32。
When clamping sleeve 30 compresses downwards, by spring 31 by can be along the rubber sliding sleeve 32 that about collar 29 and clamping sleeve 30 slide Press-in is carried in the cavity of the lower connector 28 of spherical cavity in advance, then 30 further slide downward of clamping sleeve, due to pressure The bottom cylindrical diameter of tight set 3 is slightly larger than the inner circle of rubber sliding sleeve 32, even if so rubber is slided after clamping sleeve 30 further pushes The structure of expanding of set 32 is further expanded, so that the structure of expanding of the bottom of rubber sliding sleeve 32 is close to the lower spherical cavity of connector 28 Inner surface, play a part of sealing.When needing to take out upper connection component, only clamping sleeve 30 need to be further pressed downward, this When, because rubber sliding sleeve 32 is close to the outer wall of clamping sleeve 30, when clamping sleeve 30 continues to move downward, then rubber sliding sleeve 32 will be sliding Enter at the less pipe shaft of middle part external diameter of clamping sleeve 30, so that the diameter that structure is expanded in the bottom of rubber sliding sleeve 32 reduces, rubber is slided Set 32 will no longer be close to the inner surface of the lower spherical cavity of connector 28, and now upper connection component can conveniently take out.When upper connection After component exits lower connector 28, because spring 31 is in compressive state, influenceed by its elastic force, rubber sliding sleeve 32 is by from pressure Extruded at the smaller tube wall of middle outside diameter of tight set 30, rubber sliding sleeve 32 can be returned to and closely pasted with the bottom outer of clamping sleeve 30 again The original state of conjunction.
The embodiment is preferred embodiment of the invention, but the present invention is not limited to above-mentioned embodiment, not Away from the present invention substantive content in the case of, those skilled in the art can make it is any it is conspicuously improved, replace Or modification belongs to protection scope of the present invention.

Claims (9)

1. a kind of flowmeter cleaning and its automatic hookup wire of adapter, it is characterised in that:Mainly include swivel base (1), spiral Guide plate (2), hydraulic giant support (3), giant (5), video camera (10), manipulator (11), one-level posture correction area (13), two Level posture correction area (15), assembling supply line (18),
Multiple pod apertures (4) are set on the swivel base (1), and spiral guide plate (2) is located at the upper of the swivel base (1) Side, the giant (5) are fixed on hydraulic giant support (3), and above spiral guide plate (2);The spiral guide plate (2) end sets transition slide (12) and the starting end in contact of one-level posture correction area (13) to align;
One-level posture correction area (13) is made up of parallel in the horizontal direction several conveyer belts (14), conveyer belt (14) starting End top is provided with height limit plate (6), is provided between conveyer belt (14) and moves the parallel Horizontal limiting plate in direction (7);
Two level posture correction area (15) is arranged on the afterbody of one-level correction zone (13), two level posture correction area's (15) initiating terminal and one Level posture correction area (13) end contact alignment, two level posture correction area (15) is mainly by sideboard (8), fixed dam (9) form, two level posture correction area (15) is body structure, and its side wall is movable, and bottom plate is fixed, and inside is set at a certain distance The fixed dam (9) of some vertical embedded wall box is equipped with, away from wall box upper surface 4cm, baffle plate (9) can be two at its top Level posture correction area (15) moves horizontally with wall box;Sideboard (8) is hinged with box bilateral wall, and pin joint is kept off with fixed Plate (9) is in same plane, and away from 3.5cm at the top of fixed dam (9), it is in two level posture correction area (15) initiating terminal and risen State, body structure upper strata is horizontally distributed in, its size can block the compartment being made up of adjacent two fixed dam (9) and enter just Mouthful, when that will approach assembling supply line (18), sideboard (8) drops to the position being close to fixed dam (9);Described Two level posture correction area (15) end bottom is not provided with bottom plate, leads directly to assembling supply line (18), is easy to flowmeter free skating to drop down onto Assemble supply line (18);
Assembling supply line (18) is arranged on the afterbody of two level posture correction area (15), the assembling supply line (18) and two level posture Correction area (15) antarafacial intersects vertically, and described two video cameras (10) positioned at assembling supply line (18) both sides and are fixed on phase respectively On machine support (16), the manipulator (11) is located at the downstream of video camera (10), and mounted in the both sides of assembling supply line (18), position In being additionally provided with adapter shelf (17) in the both sides of assembling supply line (18), and adapter shelf (17) be located at by manipulator (11) Side;The afterbody of the assembling supply line (18) sets supply line steering gear (19), pigeonholes (20).
2. flowmeter cleaning according to claim 1 and its automatic hookup wire of adapter, it is characterised in that:The assembling fortune Be provided with gravity buffering and aligning device in defeated line (18), the gravity buffering and aligning device including conduit align ring (22), Bearing platform (24), buffer spring (25), gauge outfit align push rod (26), and bearing platform (24) bottom is filled by several buffer springs (25) On the bottom plate (23) of assembling supply line (18), gauge outfit aligns push rod (26), and to be arranged on two adjacent demarcation strips (27) relative It is on side and symmetrical, two conduits align ring (22) be arranged on assembling supply line two outer side shields (21) on and into It is symmetrical.
3. flowmeter cleaning according to claim 1 and its automatic hookup wire of adapter, it is characterised in that:The rotation bottom Multiple pod apertures (4) rounded array arrangement on disk (1).
4. flowmeter cleaning according to claim 1 and its automatic hookup wire of adapter, it is characterised in that:Conveyer belt (14) Quantity be three, driven by motorized pulleys.
5. flowmeter cleaning according to claim 1 and its automatic hookup wire of adapter, it is characterised in that:Spiral guide plate (2) lower surface is parallel with swivel base (1) upper surface and spacing 1cm;Under transition slide (12) upper plane and swivel base (1) Surface is parallel, and spacing 1cm.
6. flowmeter cleaning according to claim 1 and its automatic hookup wire of adapter, it is characterised in that:Described high pressure Hydraulic giant (5) rounded array is evenly distributed on the annular frame at the top of hydraulic giant support (3).
7. flowmeter cleaning according to claim 1 and its automatic hookup wire of adapter, it is characterised in that:Described transition Slide (12) surface covers rubber layer, the drop 30cm at transition slide (12) both ends.
8. flowmeter cleaning according to claim 1 and its automatic hookup wire of adapter, it is characterised in that:Height limit plate (6) difference in height between conveyer belt (14) is that h meets D<h<H, wherein, D is the diameter of flowmeter cylinder gauge outfit, and H is stream The height of gauge.
9. a kind of adapter of flowmeter specification fast automatic detecting and its adapter hookup wire for described in claim 1, It is characterised in that it includes upper connection component, lower connector (28), upper connection component includes about collar (29), clamping sleeve (30), bullet Spring (31), rubber sliding sleeve (32),
The about collar (29) is arranged on the outside of clamping sleeve (30);
The clamping sleeve (30) can be slided along about collar (29) inner surface, and outer circular top part is provided with connection screw thread;
The interior circular diameter D1 of rubber sliding sleeve (32) is slightly less than diameter D2, the D1=0.8D2 of clamping sleeve bottom cylindrical, to ensure to have The sealing of effect, it is arranged between about collar (12) and clamping sleeve (13), can be along about collar (29) inner surface and clamping sleeve (30) outside Slide under the action of the spring on surface;
The spring (31) is arranged between clamping sleeve (30) bottom and rubber sliding sleeve (32) circular outer ring.
CN201710572924.2A 2017-07-14 2017-07-14 A kind of cleaning of flowmeter and its automatic hookup wire of adapter Active CN107398697B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710572924.2A CN107398697B (en) 2017-07-14 2017-07-14 A kind of cleaning of flowmeter and its automatic hookup wire of adapter

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710572924.2A CN107398697B (en) 2017-07-14 2017-07-14 A kind of cleaning of flowmeter and its automatic hookup wire of adapter

Publications (2)

Publication Number Publication Date
CN107398697A true CN107398697A (en) 2017-11-28
CN107398697B CN107398697B (en) 2019-08-02

Family

ID=60405384

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710572924.2A Active CN107398697B (en) 2017-07-14 2017-07-14 A kind of cleaning of flowmeter and its automatic hookup wire of adapter

Country Status (1)

Country Link
CN (1) CN107398697B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111921919A (en) * 2020-10-15 2020-11-13 郭曼 Bearing steel ball cleaning device
CN112657203A (en) * 2020-12-22 2021-04-16 常州市腾翔机械重工有限公司 Automatic monitoring and intelligent anti-falling slide anti-falling device
CN112919008A (en) * 2021-02-07 2021-06-08 孙羽 Building site steel pipe diameter measurement sorting equipment

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002035704A (en) * 2000-07-25 2002-02-05 Toshiba Corp Substrate washing method and substrate washing apparatus
CN201644429U (en) * 2010-01-06 2010-11-24 山东泽谊自控技术有限公司 Automatic cleaning device of flow meter
CN102107195A (en) * 2009-12-23 2011-06-29 中芯国际集成电路制造(上海)有限公司 Method for cleaning float flowmeter on line and circulating cooling water system
CN203018985U (en) * 2012-11-05 2013-06-26 浙江佳友热能科技设备有限公司 Assembling tool
CN203227980U (en) * 2013-04-03 2013-10-09 中国石油天然气股份有限公司 Flow meter supporting and stabilizing device
CN206241580U (en) * 2016-10-27 2017-06-13 天津银宝山新科技有限公司 Flow meter body and upper shell erecting device

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002035704A (en) * 2000-07-25 2002-02-05 Toshiba Corp Substrate washing method and substrate washing apparatus
CN102107195A (en) * 2009-12-23 2011-06-29 中芯国际集成电路制造(上海)有限公司 Method for cleaning float flowmeter on line and circulating cooling water system
CN201644429U (en) * 2010-01-06 2010-11-24 山东泽谊自控技术有限公司 Automatic cleaning device of flow meter
CN203018985U (en) * 2012-11-05 2013-06-26 浙江佳友热能科技设备有限公司 Assembling tool
CN203227980U (en) * 2013-04-03 2013-10-09 中国石油天然气股份有限公司 Flow meter supporting and stabilizing device
CN206241580U (en) * 2016-10-27 2017-06-13 天津银宝山新科技有限公司 Flow meter body and upper shell erecting device

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111921919A (en) * 2020-10-15 2020-11-13 郭曼 Bearing steel ball cleaning device
CN112657203A (en) * 2020-12-22 2021-04-16 常州市腾翔机械重工有限公司 Automatic monitoring and intelligent anti-falling slide anti-falling device
CN112919008A (en) * 2021-02-07 2021-06-08 孙羽 Building site steel pipe diameter measurement sorting equipment
CN112919008B (en) * 2021-02-07 2022-07-08 日照利伟建设集团有限公司 Building site steel pipe diameter measurement sorting equipment

Also Published As

Publication number Publication date
CN107398697B (en) 2019-08-02

Similar Documents

Publication Publication Date Title
CN107398697A (en) A kind of flowmeter cleaning and its automatic hookup wire of adapter
CN107398724A (en) A kind of sleeve conversion head elastic steel ball automatic assembly equipment
CN104297423A (en) Detection device and detection method
CN109375025A (en) A kind of capacitor element detection system
CN108296740A (en) A kind of rocking bar spring assembling device
CN209014214U (en) A kind of water-cooled machine air-leakage test instrument for battery production
CN208928634U (en) A kind of sorting cigarette equipment
CN207398285U (en) A kind of lithium battery cleaning machine electrode column sealing fixture
CN106310635A (en) Air-compression type tennis ball serving machine with high initial velocity
CN204142647U (en) Based on the on-line detecting system of machine vision
CN204643118U (en) A kind of composite structure pay-off
CN208262215U (en) A kind of rocking bar spring assembling device
CN109378670A (en) Assembly test assembly line and its assembly test method with protective door socket
CN208656954U (en) Vegetable cultivation internet monitor camera device
CN209246956U (en) A kind of Full automatic product full inspection machine
CN209131613U (en) A kind of inner ring automatic detection device
CN107571015A (en) A kind of bearing kludge
CN110712037B (en) Direct drive assembly device
CN210487182U (en) Pipeline leakproofness detection device
CN107309634A (en) Spring spinning machine
CN209266279U (en) Keyboard spare part automatic assembly equipment
CN104240994B (en) A kind of device of automatic assembling microswitch
CN206288644U (en) 3D display transmitting devices
CN207542379U (en) A kind of electronic information transmitting antenna
CN206622339U (en) Intermittently more funnel pipe type Kiwi berry quality sorting devices

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20210202

Address after: 226001 room 1002, Huali building, No.6 Gongnong Road, Chongchuan District, Nantong City, Jiangsu Province

Patentee after: Nantong Ningjing Information Technology Co.,Ltd.

Address before: Zhenjiang City, Jiangsu Province, 212013 Jingkou District Road No. 301

Patentee before: JIANGSU University

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20210805

Address after: 213000 No. 58-1, Yulong Middle Road, Xinbei District, Changzhou City, Jiangsu Province

Patentee after: MEZOLEN INSTRUMENT (CHANGZHOU) Co.,Ltd.

Address before: 226001 room 1002, Huali building, No.6 Gongnong Road, Chongchuan District, Nantong City, Jiangsu Province

Patentee before: Nantong Ningjing Information Technology Co.,Ltd.

TR01 Transfer of patent right
CP02 Change in the address of a patent holder

Address after: 213168 Building 26, No. 9 Caoxi Road, Niutang Town, Wujin District, Changzhou City, Jiangsu Province (Lvjian District)

Patentee after: MEZOLEN INSTRUMENT (CHANGZHOU) Co.,Ltd.

Address before: 213000 No. 58-1, Yulong Middle Road, Xinbei District, Changzhou City, Jiangsu Province

Patentee before: MEZOLEN INSTRUMENT (CHANGZHOU) Co.,Ltd.

CP02 Change in the address of a patent holder