CN107394720A - 变电站内架空软母线长度的简便确定方法 - Google Patents
变电站内架空软母线长度的简便确定方法 Download PDFInfo
- Publication number
- CN107394720A CN107394720A CN201710461018.5A CN201710461018A CN107394720A CN 107394720 A CN107394720 A CN 107394720A CN 201710461018 A CN201710461018 A CN 201710461018A CN 107394720 A CN107394720 A CN 107394720A
- Authority
- CN
- China
- Prior art keywords
- soft bus
- length
- aerial
- transformer station
- insulator chain
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G5/00—Installations of bus-bars
Landscapes
- Testing Relating To Insulation (AREA)
Abstract
本发明公开了一种变电站内架空软母线长度的简便确定方法,解决了变电站内架空软母线长度的准确确定的问题。架空软母线的两侧挂点标高是相同的,且两侧挂点的间距小于80米,两侧挂点所需切割下的架空软母线长度L0的计算公式为:L0=L‑2λ+M1+M2;其中:L为两挂点间的直线距离;λ为架空软母线端部所连接的绝缘子串和金具的总长度;M1为绝缘子串修修长度:M1=N×1(厘米),N为架空软母线端部所连接的绝缘子串的片数;M2为弧垂修正长度。本发明特别适合变电站电气安装工程中使用,达到了简便、快捷、准确的效果,避免了导线的浪费,节约了施工成本。
Description
技术领域
本发明涉及一种架空软母线的长度确定方法,特别涉及一种在施工变电站内架空软母线时确定所需长度的确定方法。
背景技术
在变电站电气安装施工过程中,当施工架空软母线时,首先要确定需要的长度,然后,根据需要的长度从线盘上割取,将割下的软母线安装上绝缘子串和金具后架在相应的挂点上。现有技术都是根据软母线两挂点的直线距离和弧垂的高度进行估算后,来确定需要软母线的长度,经常会发生导线切割长度不偏小的现象,切割下的导线不能使用,造成了材料浪费。
发明内容
本发明提供了一种变电站内架空软母线长度的简便确定方法,解决了变电站内架空软母线长度的准确确定的技术问题。
本发明是通过以下技术方案解决以上技术问题的:
一种变电站内架空软母线长度的简便确定方法,其特征在于,变电站为500kV及以下电压等级变电站,架空软母线的两侧挂点标高是相同的,且两侧挂点的间距小于80米,架空软母线材质为钢芯铝导线,架空软母线是单母线或双分裂软母线,两侧挂点所需切割下的架空软母线长度L0的计算公式为:
L0=L-2λ+M1+M2;
其中:L为两挂点间的直线距离;
λ为架空软母线端部所连接的绝缘子串和金具的总长度;
M1为绝缘子串修修长度:M1=N×1(厘米),N为架空软母线端部所连接的绝缘子串的片数;
M2为弧垂修正长度:当架空软母线是横截面为300厘米及300厘米以下的钢芯铝导线时,M2=F÷6(厘米);当架空软母线是横截面为300厘米以上的钢芯铝导线时,M2=F÷8(厘米),其中F为架空软母线的设计弧垂长度(单位为厘米)。
本发明特别适合变电站电气安装工程中使用,达到了简便、快捷、准确的效果,避免了导线的浪费,节约了施工成本。
附图说明
图1是本发明的变电站内架空软母线结构示意图。
具体实施方式
下面结合附图对本发明进行详细说明:
一种变电站内架空软母线长度的简便确定方法,其特征在于,变电站为500kV及以下电压等级变电站,架空软母线的两侧挂点标高是相同的,且两侧挂点的间距小于80米,架空软母线材质为钢芯铝导线,架空软母线是单母线或双分裂软母线,两侧挂点所需切割下的架空软母线长度L0的计算公式为:
L0=L-2λ+M1+M2;
其中:L为两挂点间的直线距离;
λ为架空软母线端部所连接的绝缘子串和金具的总长度;
M1为绝缘子串修修长度:M1=N×1(厘米),N为架空软母线端部所连接的绝缘子串的片数;如220KV变电站的架空软母线端部连接的绝缘子串为18片,M1为18厘米;
M2为弧垂修正长度:当架空软母线是横截面为300厘米及300厘米以下的钢芯铝导线时,M2=F÷6(厘米);当架空软母线是横截面为300厘米以上的钢芯铝导线时,M2=F÷8(厘米),其中F为架空软母线的设计弧垂长度(单位为厘米);弧垂F 为200厘米的横截面为500平方厘米的LGJ-500导线,M2=F/8=200/8=25厘米。
Claims (1)
1.一种变电站内架空软母线长度的简便确定方法,其特征在于,变电站为500kV及以下电压等级变电站,架空软母线的两侧挂点标高是相同的,且两侧挂点的间距小于80米,架空软母线材质为钢芯铝导线,架空软母线是单母线或双分裂软母线,两侧挂点所需切割下的架空软母线长度L0的计算公式为:
L0=L-2λ+M1+M2;
其中:L为两挂点间的直线距离;
λ为架空软母线端部所连接的绝缘子串和金具的总长度;
M1为绝缘子串修修长度:M1=N×1(厘米),N为架空软母线端部所连接的绝缘子串的片数;
M2为弧垂修正长度:当架空软母线是横截面为300厘米及300厘米以下的钢芯铝导线时,M2=F÷6(厘米);当架空软母线是横截面为300厘米以上的钢芯铝导线时,M2=F÷8(厘米),其中F为架空软母线的设计弧垂长度(单位为厘米)。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710461018.5A CN107394720A (zh) | 2017-06-18 | 2017-06-18 | 变电站内架空软母线长度的简便确定方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710461018.5A CN107394720A (zh) | 2017-06-18 | 2017-06-18 | 变电站内架空软母线长度的简便确定方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107394720A true CN107394720A (zh) | 2017-11-24 |
Family
ID=60333313
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710461018.5A Pending CN107394720A (zh) | 2017-06-18 | 2017-06-18 | 变电站内架空软母线长度的简便确定方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107394720A (zh) |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103594977A (zh) * | 2013-12-04 | 2014-02-19 | 国家电网公司 | 一种软母线架设安装工艺 |
CN103955569A (zh) * | 2014-04-18 | 2014-07-30 | 福州大学 | 一种500kV变电站软导线下料长度数学模型计算方法 |
CN104951603A (zh) * | 2015-06-08 | 2015-09-30 | 福州大学 | 一种基于悬链线的变电站软导线下料长度数值求解方法 |
CN106570239A (zh) * | 2016-10-25 | 2017-04-19 | 中国电力科学研究院 | 软母线下料长度计算方法及装置 |
-
2017
- 2017-06-18 CN CN201710461018.5A patent/CN107394720A/zh active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103594977A (zh) * | 2013-12-04 | 2014-02-19 | 国家电网公司 | 一种软母线架设安装工艺 |
CN103955569A (zh) * | 2014-04-18 | 2014-07-30 | 福州大学 | 一种500kV变电站软导线下料长度数学模型计算方法 |
CN104951603A (zh) * | 2015-06-08 | 2015-09-30 | 福州大学 | 一种基于悬链线的变电站软导线下料长度数值求解方法 |
CN106570239A (zh) * | 2016-10-25 | 2017-04-19 | 中国电力科学研究院 | 软母线下料长度计算方法及装置 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN205178430U (zh) | 一种测温母线槽 | |
CN102280194A (zh) | 一种分割导体结构的交联聚乙烯绝缘电力电缆 | |
CN202058497U (zh) | 一种分割导体结构的交联聚乙烯绝缘电力电缆 | |
CN104952561A (zh) | 10kV输电线路用防雷防冰针式复合绝缘子 | |
CN206619449U (zh) | 一种防污秽的树脂基体绝缘子 | |
CN107394720A (zh) | 变电站内架空软母线长度的简便确定方法 | |
CN201707959U (zh) | 分裂式复合屏蔽绝缘铜、铝管母线 | |
CN203444849U (zh) | 架空绝缘电缆 | |
CN103840276A (zh) | 一种绝缘母线的连接装置 | |
RU185716U1 (ru) | Шинный датчик высокого напряжения | |
CN104314352B (zh) | 复合材料紧凑型输电线路杆塔 | |
CN206877775U (zh) | 一种新型500kv线路型避雷器芯组结构 | |
CN202502203U (zh) | 一种杆塔与绝缘子串覆冰桥接闪络模拟实验装置 | |
CN204732236U (zh) | 10kV输电线路用防雷防冰针式复合绝缘子 | |
CN204614461U (zh) | 一种新型交联聚乙烯绝缘电力电缆 | |
CN204732237U (zh) | 用于10kV输电线路的防雷防冰针式复合绝缘子 | |
CN201319277Y (zh) | 一种防冰闪高压棒形悬式复合绝缘子伞形结构 | |
CN203813047U (zh) | 一种绝缘母线的连接装置 | |
CN202093879U (zh) | 一种分层绝缘绞合导体的电力电缆 | |
CN207781218U (zh) | 一种110kV架空输电线路用架空绝缘电缆 | |
CN203242361U (zh) | 一种聚氯乙烯绝缘软电缆 | |
CN204884720U (zh) | 一种防止上方导体脱冰引起下方导体相间短路的伞状阻冰装置 | |
CN208298582U (zh) | 一种风力发电设备用中压防雷导流预分支电缆 | |
CN206349177U (zh) | 一种可融冰的架空防雷双导体绝缘地线 | |
CN204885498U (zh) | 母线排接地装置 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20171124 |