CN107386646A CN201710731139.7A CN201710731139A CN107386646A CN 107386646 A CN107386646 A CN 107386646A CN 201710731139 A CN201710731139 A CN 201710731139A CN 107386646 A CN107386646 A CN 107386646A
Authority
CN
China
Prior art keywords
workshop
column
top cover
job shop
fixed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710731139.7A
Other languages
Chinese (zh)
Other versions
CN107386646B (en
Inventor
王铁
殷述学
黄赛帅
彭鹏
张熠
朱海明
刘斌
沈巍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Municipal Engineering Design Insitute Group Co Ltd
Original Assignee
Shanghai Municipal Engineering Design Insitute Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Municipal Engineering Design Insitute Group Co Ltd filed Critical Shanghai Municipal Engineering Design Insitute Group Co Ltd
Priority to CN201710731139.7A priority Critical patent/CN107386646B/en
Publication of CN107386646A publication Critical patent/CN107386646A/en
Application granted granted Critical
Publication of CN107386646B publication Critical patent/CN107386646B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B7/00Roofs; Roof construction with regard to insulation
    • E04B7/16Roof structures with movable roof parts
    • E04B7/166Roof structures with movable roof parts characterised by a translation movement of the movable roof part, with or without additional movements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/162Handles to carry construction blocks
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H1/00Buildings or groups of buildings for dwelling or office purposes; General layout, e.g. modular co-ordination or staggered storeys
    • E04H1/12Small buildings or other erections for limited occupation, erected in the open air or arranged in buildings, e.g. kiosks, waiting shelters for bus stops or for filling stations, roofs for railway platforms, watchmen's huts or dressing cubicles
    • E04H1/1205Small buildings erected in the open air

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The present invention discloses a kind of sliding architectural engineering job shop of top cover integral elevating, it is characterised in that the job shop includes workshop column, and four workshop columns are multisection type workshop column;Bi-layer tip cap, bi-layer tip cap are fixed on the top of four workshop columns by top cover bearing, make the workshop column formation one of bi-layer tip cap, top cover bearing and most the preceding paragraph can be with the entirety of a lifting;Roller shutter, the roller shutter are fixed on four sides of bi-layer tip cap;Wheel set, wheel set are arranged on workshop column bottom so that whole job shop can be fixed on sliding rail on sliding rail slidably after being moved to specified location by rail clamping device.The sliding architectural engineering job shop of the top cover integral elevating of the present invention can slide along track, the top cover of Double-protection can lift, to reach more reasonably application and construction place, the purpose that job shop is more solid and reliable, typhoon protection measure is more efficient, integrated cost is relatively low.

Description

A kind of sliding architectural engineering job shop of top cover integral elevating
Technical field
The present invention relates to a kind of sliding architectural engineering job shop of top cover integral elevating, more particularly to one kind to be applied to Building engineering construction field, integrate protection, sunshade, rain-proof, the top cover integral elevating of windproof, hoisting function Double-protection Sliding architectural engineering job shop.
Background technology
In construction industry field, with the development of society, the standard of safety construction also more and more higher, to worker Personal safety and the requirement of career safety & health also more and more higher, material machining shed have become building engineering construction scene not One of facility that can or lack.Building-site is mostly using the fixed material machining shed built in specified location at present, There is specific job site to use telescopic material machining shed, mainly protection, rain-proof, sunshade effect.
Major defect is:
(1)Can not flexibly it move:Due to using plane fixed and arranged form, it can not move, occupancy fixed venue, material disengaging, Handling can not be settled at one go, it is necessary to rehandling;
(2)Wind-proof performance is poor:What machining shed was generally set up temporarily, mostly more simple, the security performance of structure is poor, strong wind My god, especially typhoon day is, it is necessary to take more firm measure to be fixed machining shed, if fixation is not in place, warp The phenomenon that the top cover of machining shed is blown off by typhoon often occurs;
(3)It is revolving not strong:The expense of a fixed machining shed is typically set up at 50,000 yuan or so, wherein, terrace hardening, set It is disposable input to apply installation and removal cost, and machining shed substantially regards waste disposal after removing, revolving not strong, causes Waste of material, it is not environmentally friendly enough, and also integrated cost is also higher.
Therefore, in safety in production, civilized construction standardisation requirements higher and higher today, how to carry out security performance can Lean on, the material machining shed that standardization level is high, flexible and convenient to use is crucial.
The content of the invention
It is an object of the invention to provide a kind of sliding architectural engineering job shop of top cover integral elevating, solves building The problems such as engineering site material machining shed can not move freely, wind-proof performance is poor, revolving not strong, the safety for improving machining shed can By property, it is ensured that the career safety & health of worker.
To achieve the above object, technical scheme is as follows:A kind of sliding architectural engineering of top cover integral elevating Job shop, it is characterised in that the job shop includes
Four workshop columns, four workshop columns are multisection type workshop column, and multisection type workshop column passes through very heavy The jacking on top and realization of retracting freely are stretched;
Top cover bearing, the upper end of every workshop column are fixed with a top cover bearing;
Bi-layer tip cap, bi-layer tip cap are fixed on the top of four workshop columns by top cover bearing, make bi-layer tip cap, top cover The workshop column of bearing and most the preceding paragraph forms one can be with the entirety of a lifting;
Workshop bottom girder, the workshop bottom girder are arranged between two corresponding workshop columns, the workshop bottom girder and workshop column It is connected by screw bolts;
Steel beam rail, the job shop are provided with two parallel steel beam rails, and the steel beam rail is fixed on top cover bearing On;
Roller shutter, the roller shutter are fixed on four sides of bi-layer tip cap;
Wheel set, wheel set are arranged on workshop column bottom so that whole job shop can be on sliding rail freely Slide, be fixed in after being moved to specified location by rail clamping device on sliding rail.
According to a preferred embodiment of the invention, walking girder steel, the walking steel are provided between two steel beam rails The both ends of beam set the walking roller coordinated with steel beam rail, and the electronic calabash that can be moved along walking girder steel is provided with girder steel of walking Reed.
According to a preferred embodiment of the invention, bi-layer tip cap uses the truss that angle steel makes, and is bound using sandwich color steel plate.
According to a preferred embodiment of the invention, multisection type workshop column is three-stage workshop column, including three sections of cars Between column, respectively first paragraph workshop column, second segment workshop column and the 3rd section of workshop column, three sections of workshop columns it Between be fixed by upstanding studs, when three-stage workshop column is retracted, the first paragraph workshop column retraction second In the column of section workshop, in the 3rd section of workshop column of second segment workshop column retraction, when jack ejects first paragraph workshop column Afterwards, first and second sections of workshop columns are fixed using upstanding studs, after jack ejects second segment workshop column, Second and the 3rd section of workshop column are fixed using upstanding studs.
Another object of the present invention is to the user for the sliding architectural engineering job shop for providing top cover integral elevating Method, before strong wind day or typhoon day arrive, top cover is dropped into ground, effectively prevents the destruction of typhoon.
To achieve these goals, technical scheme is as follows:A kind of sliding building work of top cover integral elevating The application method of journey job shop, it is characterised in that remove upstanding studs, the mode retracted using jack so that second segment In the 3rd section of workshop column of workshop column retraction, in the column of first paragraph workshop column retraction second segment workshop, so that double-deck Top cover drops to extreme lower position;After jack ejects first paragraph workshop column, using upstanding studs by first and second sections of cars Between column be fixed, after jack ejects second segment workshop column, using upstanding studs by second and the 3rd section of workshop Column is fixed, so that bi-layer tip cap rises to highest position.
Another object of the present invention is to the user for the sliding architectural engineering job shop for providing top cover integral elevating Method, workshop can integrally be slided in orbit, be advantageous to the comprehensive utilization of construction site.
To achieve these goals, technical scheme is as follows:A kind of sliding building work of top cover integral elevating The application method of journey job shop, it is characterised in that the job shop only sets the two workshop bottom parallel with sliding rail Beam, passage is avoided so as to be formed between two workshop bottom girders, the application method comprises the following steps:A, by job shop material Material is moved away from processing stand along sliding rail;B, transport vehicle directly reaches the handling that processing stand carries out material;C, after the completion of loading and unloading, then will The job shop is moved on to above material processing stand along sliding rail, is processed operation.
The sliding architectural engineering job shop of the top cover integral elevating of the present invention can enter for different place demands Row is set, and capping bilayer protection is safer reliable, and top cover can be dropped into ground before the arriving of typhoon day fixes, typhoon protection Measure is more effective, than traditional fixed material machining shed using safer, more convenient, more flexible, simultaneously In job shop surrounding installation roller shutter, electric block, walking girder steel, steel beam rail are installed at the top of workshop and make it that whole workshop can Closed, moveable top cover integrally-lifting job shop is become with moment, has protection, sunshade, rain-proof, wind sheltering, lifting concurrently Function in the effect of one, while workshop use segmented assembly formula structure, can repeatedly recycle, more saving, more environmentally friendly, Integrated cost reduces.
The sliding architectural engineering job shop of the top cover integral elevating of the present invention can slide along track, Double-protection Top cover can lift, with reach more reasonably application and construction place, job shop be more solid and reliable, typhoon protection measure more Effectively, the relatively low purpose of integrated cost.The beneficial effects of the invention are as follows:The sliding architectural engineering processing of top cover integral elevating Workshop using Double-protection, can integral elevating top cover, before strong wind day or typhoon day arrive, by top cover together with column Position is preferably minimized, effectively prevents the destruction of typhoon;Meanwhile workshop can integrally be slided in orbit, be advantageous to construction site Comprehensive utilization, material-conveying vehicle can directly reach the handling that processing stand carries out material, after the completion of handling, then by workshop along rail Road is moved on to above material processing stand, reduces the rehandling of material, is saved artificial;Top cover, framework sectional making, live group Dress, build, remove convenient, flexible, can repeatedly be used in turn, 100,000 yuan or so of the disposable processing charges of this job shop, as long as Turnover more than 2 times, integrated cost can is lower than the fixed machining shed set up, and more saves, be more environmentally friendly;It is in addition, of the invention Job shop, surrounding installation roller shutter, internal installation boom hoisting can also be realized so that whole workshop become it is closed, can Mobile top cover integrally-lifting job shop, this has just had protection, sunshade, rain-proof, windproof, lifting function concurrently in one, More meet the Safety standardization requirement at current building engineering construction scene.
Brief description of the drawings
Fig. 1 is the front view of the present invention;
Fig. 2 is the side view of the present invention;
Fig. 3 is the segmentation lifting schematic diagram of the present invention;
Fig. 4 is the skeleton structure shaft side figure of the present invention;
Fig. 5 be the present invention walk wheel figure;
Fig. 6 is Fig. 5 side view.
Figure includes:1st, bi-layer tip cap, 2, workshop column, 3, workshop bottom girder, 4, wheel set, 5, sliding rail, 6, folder Rail device, 7, jack, 8, upstanding studs, 9, electric block, 10, top cover bearing, 11, roller shutter, 12, walking girder steel, 13, girder steel rail Road, 14, main couple, 15, jack truss.
Embodiment
The present invention will be further described below in conjunction with the accompanying drawings.
The sliding architectural engineering job shop of a kind of top cover integral elevating, it is characterised in that the job shop includes
Four workshop columns 2, four workshop columns 2 are made using seamless steel pipe, and four workshop columns 2 are multisection type Workshop column, multisection type workshop column are freely stretched by the jacking and realization of retracting of jack;
Top cover bearing 3, the upper end of every workshop column 2 are fixed with a top cover bearing 10;
Bi-layer tip cap 1, bi-layer tip cap 1 are fixed on the top of four workshop columns 2 by top cover bearing 10, make bi-layer tip cap 1st, the workshop column 2 of top cover bearing 10 and most the preceding paragraph formation one can be with the entirety of a lifting;
Workshop bottom girder 3, the workshop bottom girder 3 are arranged between two corresponding workshop columns 2, and the workshop bottom girder is stood with workshop Post is connected by screw bolts;
Steel beam rail 13, the job shop are provided with two parallel steel beam rails 13, and the steel beam rail 13 is fixed on top On lid bearing 10;
Roller shutter 11, the roller shutter 11 are fixed on four sides of bi-layer tip cap 1;
Wheel set 4, wheel set 4 are arranged on the bottom of workshop column 2 so that whole job shop can be on sliding rail 5 Slidably, it is fixed in after being moved to specified location by rail clamping device 6 on sliding rail 5.
According to a preferred embodiment of the invention, walking girder steel 12, the row are provided between two steel beam rails 13 The both ends for walking girder steel 12 set the walking roller coordinated with steel beam rail 13, and being provided with girder steel 12 of walking can be along walking girder steel 12 Mobile electric block 9.
According to a preferred embodiment of the invention, the truss that bi-layer tip cap 1 is made using angle steel, is sealed using sandwich color steel plate Top.
According to a preferred embodiment of the invention, multisection type workshop column is three-stage workshop column, including three sections of cars Between column, respectively first paragraph workshop column, second segment workshop column and the 3rd section of workshop column, three sections of workshop columns it Between be fixed by upstanding studs 8, when three-stage workshop column is retracted, the first paragraph workshop column retraction second In the column of section workshop, in the 3rd section of workshop column of second segment workshop column retraction, the jack 7 is fixed on the 3rd section of workshop and stood On post, after jack 7 ejects first paragraph workshop column, first and second sections of workshop columns are carried out using upstanding studs 8 It is fixed, after jack 7 ejects second segment workshop column, second and the 3rd section of workshop column are carried out using upstanding studs 8 It is fixed.
It can unload on roller shutter or volume after roller shutter, dismounting upstanding studs, be retracted using jack before the arriving of typhoon day Mode so that in the 3rd section of workshop column of second segment workshop column retraction, first paragraph workshop column retraction second segment workshop is stood In post, so that bi-layer tip cap drops to extreme lower position, top cover is dropped into ground fixes, and can cause typhoon protection measure more Effectively, than traditional fixed material machining shed using safer, more convenient, more flexible.
The segmentation that Fig. 3 is the present invention lifts schematic diagram.As shown in the first step, bi-layer tip cap is located at minimum position, very heavy After top ejects first paragraph workshop column, first and second sections of workshop columns are fixed using upstanding studs, now such as the Two steps illustrate.Then after jack ejects second segment workshop column, using upstanding studs by second and the 3rd section of workshop column It is fixed, so that bi-layer tip cap rises to highest position, now as shown in the 3rd step.In order to ensure its stress more Reliably, danger caused by avoiding when upstanding studs are damaged, jack is not recalled after completing to jack, and upstanding studs divide jointly Stress is carried on a shoulder pole, plays the purpose of double shield.When the hop count using multistage workshop column is more(Such as 10 sections)When, can be according to weather Situation, it is elevated to proper height(Such as 6 ~ 10 sections of height), to be constructed in the case where ensureing safety.
Workshop can integrally be slided in orbit, be advantageous to the comprehensive utilization of construction site, excellent according to one of the present invention Select embodiment, the job shop only sets the two workshop bottom girders parallel with sliding rail, so as to two workshop bottom girders it Between formed avoid passage, when in use, job shop material is moved away from processing stand along sliding rail;Transport vehicle directly reaches processing Point carries out the handling of material;After the completion of handling, then the job shop moved on to above material processing stand along sliding rail, carried out Operation is processed, so as to reduce the rehandling of material, is saved artificial.
Although giving detailed description and explanation to the embodiment of the present invention above, it should be noted that We can carry out various equivalent changes and modification to above-mentioned embodiment according to the conception of the present invention, and its caused function is made , all should be within protection scope of the present invention during with the spirit still covered without departing from specification.

Claims (6)

1. the sliding architectural engineering job shop of a kind of top cover integral elevating, it is characterised in that the job shop includes
Four workshop columns, four workshop columns are multisection type workshop column, and multisection type workshop column passes through very heavy The jacking on top and realization of retracting freely are stretched;
Top cover bearing, the upper end of every workshop column are fixed with a top cover bearing;
Bi-layer tip cap, bi-layer tip cap are fixed on the top of four workshop columns by top cover bearing, make bi-layer tip cap, top cover The workshop column of bearing and most the preceding paragraph forms one can be with the entirety of a lifting;
Workshop bottom girder, the workshop bottom girder are arranged between two corresponding workshop columns, the workshop bottom girder and workshop column It is connected by screw bolts;
Steel beam rail, the job shop are provided with two parallel steel beam rails, and the steel beam rail is fixed on top cover bearing On;
Roller shutter, the roller shutter are fixed on four sides of bi-layer tip cap;
Wheel set, wheel set are arranged on workshop column bottom so that whole job shop can be on sliding rail freely Slide, be fixed in after being moved to specified location by rail clamping device on sliding rail.
A kind of 2. sliding architectural engineering job shop of top cover integral elevating as claimed in claim 1, it is characterised in that institute State and walking girder steel is provided between two steel beam rails, the both ends of the walking girder steel set the walking coordinated with steel beam rail to roll Take turns, the electric block that can be moved along walking girder steel is provided with girder steel of walking.
3. the sliding architectural engineering job shop of a kind of top cover integral elevating as claimed in claim 1, it is characterised in that double Layer top cover uses the truss that angle steel makes, and is bound using sandwich color steel plate.
4. a kind of sliding architectural engineering job shop of top cover integral elevating as claimed in claim 1, it is characterised in that institute It is three-stage workshop column to state multisection type workshop column, including three sections of workshop columns, respectively first paragraph workshop column, second segment Workshop column and the 3rd section of workshop column, it is fixed by upstanding studs between three sections of workshop columns, when described three sections During the retraction of formula workshop column, in the column of the first paragraph workshop column retraction second segment workshop, second segment workshop column retraction the In three sections of workshop columns, after jack ejects first paragraph workshop column, using upstanding studs by first and second sections of workshops Column is fixed, and after jack ejects second segment workshop column, is stood second and the 3rd section of workshop using upstanding studs Post is fixed.
5. a kind of application method of the sliding architectural engineering job shop of top cover integral elevating as claimed in claim 1, its It is characterised by, after unloading roller shutter or the upper roller shutter of volume, removes upstanding studs, the mode retracted using jack so that second segment car Between in the 3rd section of workshop column of column retraction, in the column of first paragraph workshop column retraction second segment workshop, so that double-deck top Lid drops to extreme lower position;After jack ejects first paragraph workshop column, using upstanding studs by first and second sections of workshops Column is fixed, and after jack ejects second segment workshop column, is stood second and the 3rd section of workshop using upstanding studs Post is fixed, so that bi-layer tip cap rises to highest position.
6. a kind of application method of the sliding architectural engineering job shop of top cover integral elevating as claimed in claim 1, its Be characterised by, the job shop only sets the two workshop bottom girders parallel with sliding rail, so as to two workshop bottom girders it Between formed and avoid passage, the application method comprises the following steps:A, job shop material is moved away from processing stand along sliding rail; B, transport vehicle directly reaches the handling that processing stand carries out material;C, after the completion of loading and unloading, then by the job shop along sliding rail Move on to above material processing stand, be processed operation.
CN201710731139.7A 2017-08-23 2017-08-23 Sliding type construction engineering processing workshop with integrally lifting top cover Active CN107386646B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710731139.7A CN107386646B (en) 2017-08-23 2017-08-23 Sliding type construction engineering processing workshop with integrally lifting top cover

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710731139.7A CN107386646B (en) 2017-08-23 2017-08-23 Sliding type construction engineering processing workshop with integrally lifting top cover

Publications (2)

Publication Number Publication Date
CN107386646A true CN107386646A (en) 2017-11-24
CN107386646B CN107386646B (en) 2024-07-05

Family

ID=60346547

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710731139.7A Active CN107386646B (en) 2017-08-23 2017-08-23 Sliding type construction engineering processing workshop with integrally lifting top cover

Country Status (1)

Country Link
CN (1) CN107386646B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111561139A (en) * 2019-11-21 2020-08-21 江苏跃界装配式建筑科技有限公司 Method for constructing roof of fabricated building
CN115680292A (en) * 2022-11-07 2023-02-03 中国一冶集团有限公司 Jacking sliding unloading vehicle for steel structure gallery and mounting method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2113968U (en) * 1992-03-11 1992-08-26 吴审言 Hydraulic jack
US20100327241A1 (en) * 2009-06-25 2010-12-30 Tractive Ab Jacking column for concrete drilling and cutting
CN103089286A (en) * 2013-01-22 2013-05-08 山东科技大学 Driving face self-moving temporary support hydraulic support and support method thereof
CN205398003U (en) * 2016-03-09 2016-07-27 西华大学 Multistage combination formula hoist mechanism
CN205421023U (en) * 2015-12-21 2016-08-03 代森林 Public road bridge roof beam strutting arrangement
CN106481106A (en) * 2016-10-31 2017-03-08 上海市政工程设计研究总院(集团)有限公司 Slidingtype architectural engineering job shop
CN207553605U (en) * 2017-08-23 2018-06-29 上海市政工程设计研究总院(集团)有限公司 A kind of sliding architectural engineering processing workshop of head cover integral elevating

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2113968U (en) * 1992-03-11 1992-08-26 吴审言 Hydraulic jack
US20100327241A1 (en) * 2009-06-25 2010-12-30 Tractive Ab Jacking column for concrete drilling and cutting
CN103089286A (en) * 2013-01-22 2013-05-08 山东科技大学 Driving face self-moving temporary support hydraulic support and support method thereof
CN205421023U (en) * 2015-12-21 2016-08-03 代森林 Public road bridge roof beam strutting arrangement
CN205398003U (en) * 2016-03-09 2016-07-27 西华大学 Multistage combination formula hoist mechanism
CN106481106A (en) * 2016-10-31 2017-03-08 上海市政工程设计研究总院(集团)有限公司 Slidingtype architectural engineering job shop
CN207553605U (en) * 2017-08-23 2018-06-29 上海市政工程设计研究总院(集团)有限公司 A kind of sliding architectural engineering processing workshop of head cover integral elevating

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111561139A (en) * 2019-11-21 2020-08-21 江苏跃界装配式建筑科技有限公司 Method for constructing roof of fabricated building
CN115680292A (en) * 2022-11-07 2023-02-03 中国一冶集团有限公司 Jacking sliding unloading vehicle for steel structure gallery and mounting method
CN115680292B (en) * 2022-11-07 2024-05-17 中国一冶集团有限公司 Steel structure corridor jacking sliding unloading and mounting method

Also Published As

Publication number Publication date
CN107386646B (en) 2024-07-05

Similar Documents

Publication Publication Date Title
CN108265977B (en) Large-span space latticed shell assembly jig frame construction method under complex working condition
CN106481106A (en) Slidingtype architectural engineering job shop
CN104986171B (en) Perforation job platform for railway engineering vehicle
CN107386646A (en) A kind of sliding architectural engineering job shop of top cover integral elevating
CN108798727B (en) Tunnel self-propelled waterproof board cloth hanging steel bar positioning integrated multifunctional trolley and application
WO2020062968A1 (en) Weatherproof steel platform system for integral steel platform formwork construction and method
CN103437563B (en) Mounting method for steel skeleton of large steel structure factory building
CN103481805A (en) Beam transporting vehicle with automatic lifting device
CN103010404B (en) Segmental general assembly method for aluminum alloy superstructure
CN106760561A (en) The assembling method of segmental slipping roof system steel truss
CN206503392U (en) The architectural engineering job shop of top cover lifting
CN106639396A (en) Constructional engineering machining workshop with liftable roof
CN207293987U (en) The railway track construction for possessing support arm Telescopic is hung with just beam is traversing
CN207553605U (en) A kind of sliding architectural engineering processing workshop of head cover integral elevating
CN206189928U (en) Between slidingtype building engineering processing vehicle
CN106930528B (en) The production method of the architectural engineering processing workshop of top cover lifting
CN102913014A (en) Method for realizing three-dimensional parking of trains through rain lifting platform
CN106593032A (en) Manufacturing method of sliding type building engineering machining workshop
CN208455483U (en) A kind of large span composite material-metallic combination truss-type bridges push stringer
CN207686361U (en) Movable semi-closed reinforcing bar processing canopy
CN2890237Y (en) Multifunctional concrete conveying and distributing apparatus
CN207293991U (en) The railway track construction for possessing lifting beam end support function is hung with just beam is traversing
CN210850737U (en) Precast beam quick detach type line production steel form
CN206625635U (en) A kind of multi-storied garage is parked plate anti-shaking device
CN206917297U (en) A kind of large-span steel girder upper air installing system in place

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant