CN106639396A - Constructional engineering machining workshop with liftable roof - Google Patents

Constructional engineering machining workshop with liftable roof Download PDF

Info

Publication number
CN106639396A
CN106639396A CN201610965048.5A CN201610965048A CN106639396A CN 106639396 A CN106639396 A CN 106639396A CN 201610965048 A CN201610965048 A CN 201610965048A CN 106639396 A CN106639396 A CN 106639396A
Authority
CN
China
Prior art keywords
workshop
top cover
column
architectural engineering
lifted
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610965048.5A
Other languages
Chinese (zh)
Inventor
王铁
殷述学
黄赛帅
彭鹏
张熠
朱海明
刘斌
沈巍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Municipal Engineering Design Insitute Group Co Ltd
Original Assignee
Shanghai Municipal Engineering Design Insitute Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Municipal Engineering Design Insitute Group Co Ltd filed Critical Shanghai Municipal Engineering Design Insitute Group Co Ltd
Priority to CN201610965048.5A priority Critical patent/CN106639396A/en
Publication of CN106639396A publication Critical patent/CN106639396A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H5/00Buildings or groups of buildings for industrial or agricultural purposes
    • E04H5/02Buildings or groups of buildings for industrial purposes, e.g. for power-plants or factories
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/343Structures characterised by movable, separable, or collapsible parts, e.g. for transport
    • E04B1/34336Structures movable as a whole, e.g. mobile home structures
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/343Structures characterised by movable, separable, or collapsible parts, e.g. for transport
    • E04B1/34336Structures movable as a whole, e.g. mobile home structures
    • E04B1/34352Base structures or supporting means therefor
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B7/00Roofs; Roof construction with regard to insulation
    • E04B7/16Roof structures with movable roof parts
    • E04B7/166Roof structures with movable roof parts characterised by a translation movement of the movable roof part, with or without additional movements
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a constructional engineering machining workshop with a liftable roof. The constructional engineering machining workshop comprises a plurality of workshop stand columns, the roof and a lifting device. The bottom ends of the workshop stand columns are connected with workshop bottom beams, and the top ends of the workshop stand columns are connected with workshop top beams. Locking pins are arranged at the appointed height of the tops of the workshop stand columns, and the bottom ends of the workshop stand columns are provided with locking levers. The roof comprises a roof body and a roof support used for connecting the roof body with the workshop stand columns. The roof is locked to the workshop stand columns through the locking pins controlled by the locking levers after being lifted to the appointed height along the workshop stand columns through the lifting device. According to the scheme, the roof is lowered to the ground before windy weather or a typhoon comes and effectively prevented from being damaged by the typhoon; and the roof and a frame are manufactured in sections and assembled in site, can be recycled, and are low in comprehensive cost, more economical and environmentally friendlier, and constructing and dismantling are convenient and flexible.

Description

The architectural engineering job shop of top cover lifting
Technical field
The present invention relates to a kind of architectural engineering job shop for being applied to building engineering construction field, more particularly to a kind of top The architectural engineering job shop of lid lifting.
Background technology
In construction industry field, with the development of society, the standard of safety construction also more and more higher, to workman Personal safety and career safety & health requirement also more and more higher, materials processing canopy has become building engineering construction scene not One of facility that can or lack.At present building-site uses the fixed materials processing canopy built in specified location mostly, There is specific job site using telescopic materials processing canopy, mainly protection, rain-proof, sunshade effect.
Major defect is:
(1) wind-proof performance is poor:What machining shed was generally set up temporarily, mostly more simple, the security performance of structure is poor, Strong wind day, especially typhoon day, need to take more firm measure to be fixed machining shed, if fixation less than Often there is the phenomenon that the top cover of machining shed is blown off by typhoon in position, Jing;
(2) it is revolving not strong:The expense of a fixed machining shed is typically set up at 50,000 yuan or so, wherein, terrace is hard Change, erection of equipment and removal cost are disposable input, machining shed substantially regards waste disposal after removing, it is revolving not By force, waste of material is caused, not enough environmental protection, and integrated cost is also higher.
Therefore, in safety in production, civilized construction standardisation requirements higher and higher today, how to carry out security performance can It is crucial by high, the flexible and convenient to use materials processing canopy of, standardization level.
The content of the invention
In order to solve architectural engineering scene materials processing canopy wind-proof performance it is poor, it is revolving not strong the problems such as, improve machining shed Security reliability, it is ensured that the career safety & health of workman, for the preparation method of job site machining shed, there is provided a kind of top cover The architectural engineering job shop of lifting, the top cover of the job shop can be lifted, with reach more reasonably application and construction place, The purpose that job shop is more solid and reliable, typhoon protection measure is more efficient, integrated cost is relatively low.
To solve above-mentioned technical problem, the present invention provides following technical scheme:
A kind of architectural engineering job shop of top cover lifting, including:Some workshop columns, top cover and lifting device, its In, the bottom of the workshop column is connected with workshop bottom girder, and the top of the workshop column is connected with workshop back timber;The workshop The top specified altitude assignment position of column arranges locking pin, and the bottom of the workshop column arranges locking spanner;The top cover bag Include top cover body and connect the top cover bearing of the top cover body and the workshop column;The lifting device, along the workshop Top cover described in upright lifting is locked in the top cover by the locking spanner control locking pin described to after specified altitude assignment On the column of workshop.
Preferably, in the architectural engineering job shop that above-mentioned top cover is lifted, also including walking girder steel, the walking steel Beam is arranged on the workshop top, and the walking girder steel lower end arranges steel beam rail, first arranged on the walking girder steel electronic Cucurbit, the workshop surrounding arranges roller shutter, by the expansion of the roller shutter so that the workshop forms closing space.
Preferably, in the architectural engineering job shop that above-mentioned top cover is lifted, the top cover is bi-layer tip cap.
Preferably, in the architectural engineering job shop that above-mentioned top cover is lifted, the bi-layer tip cap is made using angle steel Truss.
Preferably, in the architectural engineering job shop that above-mentioned top cover is lifted, also include walking wheel assembly, it is described to walk to take turns total Into being arranged on the position of the workshop bottom girder lower surface correspondence workshop column, it is described walk wheel assembly on rail clamping device is set, The rail clamping device by it is described walk wheel assembly be fixed on sliding rail.
Preferably, in the architectural engineering job shop that above-mentioned top cover is lifted, also including top cover waterproof, the top cover is prevented Water is arranged between the bi-layer tip cap and the workshop column.
Preferably, in the architectural engineering job shop that above-mentioned top cover is lifted, the workshop column adopts H profile steel system Make.
Preferably, in the architectural engineering job shop that above-mentioned top cover is lifted, the bottom and workshop of the workshop column Bottom girder bolt connection, top and the workshop back timber bolt connection of the workshop column.
Preferably, in the architectural engineering job shop that above-mentioned top cover is lifted, the lifting device is chain block, institute The top that chain block is arranged at each workshop column is stated, the top cover is raised to the height specified along the workshop column Degree.
Preferably, in the architectural engineering job shop that above-mentioned top cover is lifted, the lifting device is the second electronic calabash Reed, second electric block is arranged on the workshop back timber, and the top cover is raised into what is specified along the workshop column Highly.
The architectural engineering job shop of the top cover lifting of the present invention adopts liftable top cover, when strong wind day or typhoon day are arrived Before coming, top cover is dropped into ground, be effectively prevented the destruction of typhoon;Top cover, framework sectional making, Assembling is built, is torn open Except convenient, flexible, can repeatedly be used in turn, 100,000 yuan or so of the disposable processing charges of this job shop, if turnover 2 times with On, integrated cost just can be lower than the fixed machining shed set up, more save, it is more environmentally friendly;In addition, the processing cart of the present invention Between, can also realize that surrounding installs roller shutter, internal installation boom hoisting so that whole workshop becomes enclosed top cover lift Job shop, this has just had protection, sunshade, rain-proof, windproof, lifting function concurrently in one, has more met current architectural engineering and apply The Safety standardization at work scene is required;Meanwhile, workshop integrally can slide in orbit, be conducive to the comprehensive profit of construction site With material-conveying vehicle can directly reach processing stand and carry out the handling of material, after the completion of handling, then workshop be moved on into material along track Material processing stand top, reduces the rehandling of material, saves artificial.
Description of the drawings
The front view of the architectural engineering job shop that Fig. 1 is lifted for the top cover of first embodiment of the invention;
The side view of the architectural engineering job shop that Fig. 2 is lifted for the top cover of first embodiment of the invention;
The top view of the architectural engineering job shop that Fig. 3 is lifted for the top cover of first embodiment of the invention;
The front view of the architectural engineering job shop that Fig. 4 is lifted for the top cover of second embodiment of the invention;
The side view of the architectural engineering job shop that Fig. 5 is lifted for the top cover of second embodiment of the invention;
The top view of the architectural engineering job shop that Fig. 6 is lifted for the top cover of second embodiment of the invention;
Fig. 7 is the skeleton structure shaft side figure of the architectural engineering job shop of the top cover lifting of the present invention;
Fig. 8-1 walks wheel assembly front view for the architectural engineering job shop of the top cover lifting of the present invention
Fig. 8-2 walks wheel assembly side view for the architectural engineering job shop of the top cover lifting of the present invention;
In figure:1- top cover bodies, 2- workshops column, 3- workshops bottom girder, 4- wheel sets, 5- sliding rails, 6- rail clamping devices, 7- locking spanners, 8- bottle gouards moved by hands, 8 '-the second electric blocks, 9- top cover waterproofs, 10- top cover bearings, 11- roller shutters, 12- walkings Girder steel, 13- steel beam rails, the electric blocks of 14- first, 15- workshops back timber,
16- locks pin
Specific embodiment
Below in conjunction with the drawings and specific embodiments the architectural engineering job shop that top cover proposed by the present invention is lifted is made into One step is described in detail.According to following explanation and claims, advantages and features of the invention will become apparent from.It should be noted that, Accompanying drawing in the form of simplifying very much and uses non-accurately ratio, only conveniently, lucidly to aid in illustrating the present invention The purpose of embodiment.
Fig. 1 to Fig. 3 is referred to, present embodiment discloses a kind of architectural engineering job shop of top cover lifting, including:It is some Root workshop column 2, bi-layer tip cap and bottle gouard moved by hands 8, wherein, the bottom of the workshop column is connected with workshop bottom girder, the car Between the top of column be connected with workshop back timber;The top specified altitude assignment position of the workshop column 2 arranges locking pin 16, described The bottom of workshop column 2 arranges locking spanner 7;The top cover includes top cover body 1 and connects the top cover body 1 and the car Between column 2 top cover bearing 10;The lifting device, to after specified altitude assignment, passes through along top cover described in the workshop upright lifting The locking spanner 7 control locking pin 16 is locked in the top cover on the workshop column 2.
It is so designed that, before strong wind day or typhoon day arrive, top cover is dropped into ground, is effectively prevented the broken of typhoon It is bad;Top cover, framework sectional making, Assembling is built, removes convenient, flexible, can repeatedly be used in turn, this job shop one 100,000 yuan or so of secondary property processing charges, as long as having enough to meet the need more than 2 times, integrated cost just can be wanted than the fixed machining shed set up It is low, more save, it is more environmentally friendly.
The second embodiment of Fig. 4 to Fig. 6 is referred again to, with differing only in for first embodiment, is lifted in the present embodiment The not described bottle gouard moved by hands 8 of the lifting device of the bi-layer tip cap, but electric block 8 '.
Design of cover is bi-layer tip cap, the safer reliability of energy, it is also possible to be designed as individual layer top cover.
In the above-described embodiments, also including walking girder steel 12, the walking girder steel 12 is arranged on the workshop top, described Walking girder steel 12 lower end arranges steel beam rail 13, and on the walking girder steel 12 the first electric block 14, the workshop surrounding are arranged Roller shutter 11 is set, by the expansion of the roller shutter 11 so that the workshop forms closing space.
Being so designed that can realize that surrounding installs roller shutter 11, internal installation boom hoisting so that whole workshop becomes closing The top cover lift job shop of formula, this has just had protection, sunshade, rain-proof, windproof, lifting function concurrently in one, has more met At present the Safety standardization at building engineering construction scene is required
In the above-described embodiments, the truss that the bi-layer tip cap is made using angle steel.
In the above-described embodiments, also include walking wheel assembly 4, it is described walk wheel assembly 4 be arranged at the lower surface of workshop bottom girder 3 On the position of the correspondence workshop column 2, it is described walk wheel assembly 4 on rail clamping device 6 is set, the rail clamping device 6 by it is described walk wheel it is total It is fixed on sliding rail 5 into 4.
It is so designed that, workshop integrally can slide in orbit, is conducive to the comprehensive utilization of construction site, material-conveying vehicle Processing stand can directly be reached carries out the handling of material, after the completion of handling, then workshop is moved on into materials processing point top along track, The rehandling of material is reduced, is saved artificial.
In the above-described embodiments, also including top cover waterproof 9, the top cover waterproof 9 be arranged at the bi-layer tip cap with it is described Between workshop column 2.
In the above-described embodiments, the workshop column 2 is made using H profile steel.
In the above-described embodiments, the bottom of the workshop column 2 and the bolt connection of workshop bottom girder 3, the workshop column 2 Top and the bolt connection of workshop back timber 15.
It is so designed that, is more convenient dismounting.
In the above-described embodiments, the lifting device is chain block 8, and the chain block 8 is arranged at each described car Between column top, the top cover is raised to the height specified along the workshop column.
In the above-described embodiments, the lifting device is the second electric block 8 ', and second electric block 8 ' is arranged at On the workshop back timber 15, the top cover is raised to the height specified along the workshop column 2.
Fig. 7 is the skeleton structure shaft side figure of the architectural engineering job shop of the top cover lifting of the present invention;
Fig. 8-1 walks wheel assembly front view for the architectural engineering job shop of the top cover lifting of the present invention
Fig. 8-2 walks wheel assembly side view for the architectural engineering job shop of the top cover lifting of the present invention;
The present embodiment also discloses a kind of preparation method of the architectural engineering job shop of top cover lifting as above, bag Include following steps:
Step 1, the bottom of some workshop columns 2 is connected with workshop bottom girder 3, and workshop back timber 15 is stood with the workshop The top connection of post 2;
Step 2, by locking pin 16 the top specified altitude assignment position of workshop column 2 is arranged at, and locking spanner 7 is arranged In the bottom of the workshop column 2;
Step 3, arranges lifting device, top cover is lifted after specified altitude assignment along the workshop column 2, by the locking The control locking pin 16 of spanner 7 is locked in the top cover on the workshop column 2, wherein, the top cover includes top cover body 1 And the top cover bearing 10 of the connection top cover body 1 and the workshop column 2.
In above-mentioned preparation method, also including roller shutter 11 are arranged the step of, walking girder steel 12 is arranged on into workshop top Portion, the lower end of walking girder steel 12 arranges steel beam rail 13, and the first electric block 14 is arranged on the walking girder steel 12, will The roller shutter 11 is arranged at the workshop surrounding, by the way that the roller shutter 11 is launched so that the workshop forms closing space.
In 3 the step of above-mentioned preparation method, the top cover is set into bi-layer tip cap.
In 3 the step of above-mentioned preparation method, the truss that the bi-layer tip cap is made using angle steel.
In above-mentioned preparation method, also including arranging wheel assembly 4 the step of, by it is described walk wheel assembly 4 be arranged at it is described On the position of the lower surface of the workshop bottom girder 3 correspondence workshop column 2, it is described walk wheel assembly 4 on rail clamping device 6, the folder rail are set Device 6 by it is described walk wheel assembly 4 be fixed on sliding rail 5.
In above-mentioned preparation method, also including top cover waterproof 9 are arranged the step of, the top cover waterproof 9 is arranged at described Between bi-layer tip cap and the workshop column 2.
In 1 the step of above-mentioned preparation method, the workshop column 2 is made using H profile steel.
In 1 the step of above-mentioned preparation method, by the bottom of the workshop column 2 and the bolt connection of workshop bottom girder 3, by institute State top and the bolt connection of workshop back timber 15 of workshop column 2.
In 3 the step of above-mentioned preparation method, the lifting device is chain block 8, and the chain block 8 is arranged at often The top of the individual workshop column 2, the top cover is raised to the height specified along the workshop column 2.
In 3 the step of above-mentioned preparation method, the lifting device be the second electric block 8 ', second electric block 8 ' are arranged on the workshop back timber 15, and the top cover is raised to the height specified along the workshop column 2.
Foregoing description is only the description to present pre-ferred embodiments, not to any restriction of the scope of the invention, this Any change, modification that the those of ordinary skill in bright field does according to the disclosure above content, belong to the protection of claims Scope.

Claims (10)

1. the architectural engineering job shop that a kind of top cover is lifted, it is characterised in that include:
Some workshop columns, the bottom of the workshop column is connected with workshop bottom girder, the top and workshop of the workshop column Back timber connects;The top specified altitude assignment position of the workshop column arranges locking pin, and the bottom of the workshop column arranges lock Determine spanner;
The top cover includes top cover body and connects the top cover bearing of the top cover body and the workshop column;
The lifting device, along top cover described in the workshop upright lifting to after specified altitude assignment, by the locking spanner control Locking pin is locked in the top cover on the workshop column.
2. the architectural engineering job shop that top cover as claimed in claim 1 is lifted, it is characterised in that also including walking girder steel, The walking girder steel is arranged on the workshop top, and the walking girder steel lower end arranges steel beam rail, sets on the walking girder steel The first electric block is put, the workshop surrounding arranges roller shutter, by the expansion of the roller shutter so that it is empty that the workshop forms closing Between.
3. the architectural engineering job shop that top cover as claimed in claim 1 is lifted, it is characterised in that the top cover is double-deck top Lid.
4. the architectural engineering job shop that top cover as claimed in claim 3 is lifted, it is characterised in that the bi-layer tip cap is adopted The truss that angle steel makes.
5. the architectural engineering job shop that top cover as claimed in claim 1 is lifted, it is characterised in that also include walking wheel assembly, It is described walk wheel assembly be arranged on the position of the workshop bottom girder lower surface correspondence workshop column, it is described walk wheel assembly on set Put rail clamping device, the rail clamping device by it is described walk wheel assembly be fixed on sliding rail.
6. the architectural engineering job shop that top cover as claimed in claim 3 is lifted, it is characterised in that also including top cover waterproof, The top cover waterproof is arranged between the bi-layer tip cap and the workshop column.
7. the architectural engineering job shop that top cover as claimed in claim 1 is lifted, it is characterised in that the workshop column is adopted H profile steel makes.
8. the architectural engineering job shop that top cover as claimed in claim 1 is lifted, it is characterised in that the bottom of the workshop column End and workshop bottom girder bolt connection, top and the workshop back timber bolt connection of the workshop column.
9. the architectural engineering job shop that top cover as claimed in claim 1 is lifted, it is characterised in that the lifting device is hand Cucurbit is drawn, the chain block is arranged at the top of each workshop column, by the top cover along the workshop column liter To the height specified.
10. the architectural engineering job shop of top cover as claimed in claim 1 lifting, it is characterised in that the lifting device is Second electric block, second electric block is arranged on the workshop back timber, by the top cover along the workshop column It is raised to the height specified.
CN201610965048.5A 2016-10-31 2016-10-31 Constructional engineering machining workshop with liftable roof Pending CN106639396A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610965048.5A CN106639396A (en) 2016-10-31 2016-10-31 Constructional engineering machining workshop with liftable roof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610965048.5A CN106639396A (en) 2016-10-31 2016-10-31 Constructional engineering machining workshop with liftable roof

Publications (1)

Publication Number Publication Date
CN106639396A true CN106639396A (en) 2017-05-10

Family

ID=58820832

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610965048.5A Pending CN106639396A (en) 2016-10-31 2016-10-31 Constructional engineering machining workshop with liftable roof

Country Status (1)

Country Link
CN (1) CN106639396A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106481106A (en) * 2016-10-31 2017-03-08 上海市政工程设计研究总院(集团)有限公司 Slidingtype architectural engineering job shop
CN107503461A (en) * 2017-08-22 2017-12-22 中国核工业华兴建设有限公司 A kind of large span arc-shaped steel roofing to be opened/closed
US10077572B1 (en) * 2017-04-19 2018-09-18 Hmt, Llc Systems and methods for lifting and positioning a roof for installation on a storage tank

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS496749A (en) * 1972-05-04 1974-01-21
SU868017A1 (en) * 1979-03-20 1981-09-30 Тбилисский Филиал Всесоюзного Института По Проектированию Организации Энергетического Строительства "Оргэнергострой" Prefabricated detachable production building
CN201857663U (en) * 2010-08-27 2011-06-08 邓世超 Height-adjustable combination house
CN105124920A (en) * 2015-09-18 2015-12-09 宁波乐歌视讯科技股份有限公司 Lifting workbench
CN105986684A (en) * 2015-02-15 2016-10-05 徐进勇 Mobile type multifunctional component machining workshop
CN106481106A (en) * 2016-10-31 2017-03-08 上海市政工程设计研究总院(集团)有限公司 Slidingtype architectural engineering job shop
CN106593032A (en) * 2016-10-31 2017-04-26 上海市政工程设计研究总院(集团)有限公司 Manufacturing method of sliding type building engineering machining workshop
CN206189928U (en) * 2016-10-31 2017-05-24 上海市政工程设计研究总院(集团)有限公司 Between slidingtype building engineering processing vehicle
CN106930528A (en) * 2016-10-31 2017-07-07 上海市政工程设计研究总院(集团)有限公司 The preparation method of the architectural engineering job shop of top cover lifting
CN206503392U (en) * 2016-10-31 2017-09-19 上海市政工程设计研究总院(集团)有限公司 The architectural engineering job shop of top cover lifting

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS496749A (en) * 1972-05-04 1974-01-21
SU868017A1 (en) * 1979-03-20 1981-09-30 Тбилисский Филиал Всесоюзного Института По Проектированию Организации Энергетического Строительства "Оргэнергострой" Prefabricated detachable production building
CN201857663U (en) * 2010-08-27 2011-06-08 邓世超 Height-adjustable combination house
CN105986684A (en) * 2015-02-15 2016-10-05 徐进勇 Mobile type multifunctional component machining workshop
CN105124920A (en) * 2015-09-18 2015-12-09 宁波乐歌视讯科技股份有限公司 Lifting workbench
CN106481106A (en) * 2016-10-31 2017-03-08 上海市政工程设计研究总院(集团)有限公司 Slidingtype architectural engineering job shop
CN106593032A (en) * 2016-10-31 2017-04-26 上海市政工程设计研究总院(集团)有限公司 Manufacturing method of sliding type building engineering machining workshop
CN206189928U (en) * 2016-10-31 2017-05-24 上海市政工程设计研究总院(集团)有限公司 Between slidingtype building engineering processing vehicle
CN106930528A (en) * 2016-10-31 2017-07-07 上海市政工程设计研究总院(集团)有限公司 The preparation method of the architectural engineering job shop of top cover lifting
CN206503392U (en) * 2016-10-31 2017-09-19 上海市政工程设计研究总院(集团)有限公司 The architectural engineering job shop of top cover lifting

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106481106A (en) * 2016-10-31 2017-03-08 上海市政工程设计研究总院(集团)有限公司 Slidingtype architectural engineering job shop
US10077572B1 (en) * 2017-04-19 2018-09-18 Hmt, Llc Systems and methods for lifting and positioning a roof for installation on a storage tank
CN107503461A (en) * 2017-08-22 2017-12-22 中国核工业华兴建设有限公司 A kind of large span arc-shaped steel roofing to be opened/closed

Similar Documents

Publication Publication Date Title
CN106481106A (en) Slidingtype architectural engineering job shop
CN206503392U (en) The architectural engineering job shop of top cover lifting
CN106639396A (en) Constructional engineering machining workshop with liftable roof
CN109025388B (en) Construction device and construction method of movable expanded openable canopy
CN112267709A (en) Segmented demolition construction method for large-span beam string structure
CN107288352B (en) The transport of the closed shed dormer roof boarding of overlarge area and installation method
CN103899093A (en) Step-by-step hoisting construction method of mega-frame steel truss beam
CN106930528B (en) The production method of the architectural engineering processing workshop of top cover lifting
CN206189928U (en) Between slidingtype building engineering processing vehicle
CN106593032A (en) Manufacturing method of sliding type building engineering machining workshop
CN207700392U (en) A kind of gate periphery wind resisting structure
CN212224698U (en) A instrument formula sunshade weather enclosure for construction
CN104533001A (en) Electric rotary temporary roof for reactor building of nuclear power station
CN1109176C (en) Construction working method for nuclear electric power generation installation
CN210147306U (en) Foldable movable windproof cover for welding penstock
CN204571054U (en) Heat-treatment furnace assembling electric stormproof canopy
CN204098551U (en) A kind of portable workshop
CN106567552A (en) Dynamic closed construction method of subway station using fast folding shelters
CN207686361U (en) A kind of semiclosed reinforcing steel processing shed of packaged type
CN108265830B (en) Multi-station movable construction seat and assembly jacking type building construction method
CN207553605U (en) A kind of sliding architectural engineering processing workshop of head cover integral elevating
CN212897711U (en) A telescopic canopy for grit storage yard
CN107386646A (en) A kind of sliding architectural engineering job shop of top cover integral elevating
CN209352823U (en) A kind of transport support for dry quenching furnace constructing
CN207792528U (en) Open-air automatic rainproof type explosion-proof crane

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination