CN106930528B - The production method of the architectural engineering processing workshop of top cover lifting - Google Patents
The production method of the architectural engineering processing workshop of top cover lifting Download PDFInfo
- Publication number
- CN106930528B CN106930528B CN201710083399.8A CN201710083399A CN106930528B CN 106930528 B CN106930528 B CN 106930528B CN 201710083399 A CN201710083399 A CN 201710083399A CN 106930528 B CN106930528 B CN 106930528B
- Authority
- CN
- China
- Prior art keywords
- workshop
- top cover
- column
- architectural engineering
- lifting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
Abstract
The invention discloses a kind of production methods of the architectural engineering processing workshop of top cover lifting, comprising: step 1, the bottom end of several workshop columns is connect with workshop bottom beam, workshop top beam is connect with the top of the workshop column;Step 2, locking pin is set to the top specified altitude assignment position of workshop column, and locking spanner is set to the bottom end of the workshop column;Step 3, lifting device is set, by top cover after the workshop upright lifting to specified altitude assignment, it controls locking pin by the locking spanner top cover is locked on the workshop column, wherein, the top cover includes top cover body and the top cover support for connecting the top cover body and the workshop column.Top cover is dropped to ground, is effectively prevented the destruction of typhoon by the program before strong wind day or typhoon day arrive;Top cover, frame sectional making, on-site assembly build, remove convenient, flexible, can repeatedly be used in turn, and overall cost is low, more save, is more environmentally friendly.
Description
Technical field
The present invention relates to a kind of architectural engineering processing workshop applied to building engineering construction field more particularly to a kind of tops
The production method for covering the architectural engineering processing workshop of lifting.
Background technique
In construction industry field, with the development of society, the standard of safety construction is also higher and higher, to worker
Personal safety and career safety & health requirement it is also higher and higher, material machining shed has become building engineering construction scene not
Can or one of scarce facility.Building-site is mostly using the fixed material machining shed built in designated position at present,
There is specific construction site using telescopic material machining shed, mainly protection, rain-proof, sunshade effect.
Major defect is:
(1) wind-proof performance is poor: what machining shed was generally temporarily set up, mostly more simple, the security performance of structure is poor,
Strong wind day, especially typhoon day need to take machining shed relatively firm measure to be fixed, if fixation less than
The phenomenon that position, the top cover of machining shed is blown off by typhoon frequent occurrence;
(2) revolving not strong: generally to set up the expense of a fixed machining shed at 50,000 yuan or so, wherein terrace is hard
Change, erection of equipment and removal cost are disposable investment, machining shed substantially regards waste disposal after removing, it is revolving not
By force, waste of material is caused, it is not environmentally friendly enough, and also overall cost is also higher.
Therefore, today higher and higher in safety in production, civilized construction standardisation requirements, how to carry out security performance can
It leans on, standardization level is high, material machining shed flexible and convenient to use is crucial.
Summary of the invention
In order to solve the problems such as architectural engineering scene material machining shed wind-proof performance is not poor, revolving strong, machining shed is improved
Security reliability, it is ensured that the career safety & health of worker provides a kind of top cover for the production method of construction site machining shed
The top cover of the production method of the architectural engineering processing workshop of lifting, the processing workshop can be gone up and down, and be answered more reasonablely with reaching
With construction site, the stronger purpose reliable, typhoon protection measure is more efficient, overall cost is relatively low of processing workshop.
In order to solve the above technical problems, the invention provides the following technical scheme:
A kind of production method of the architectural engineering processing workshop of top cover lifting, includes the following steps:
Step 1, the bottom end of several workshop columns is connect with workshop bottom beam, by workshop top beam and the workshop column
Top connection;
Step 2, locking pin is set to the top specified altitude assignment position of workshop column, and locking spanner is set to institute
State the bottom end of workshop column;
Step 3, setting lifting device passes through the locking by top cover after the workshop upright lifting to specified altitude assignment
The top cover is locked on the workshop column by spanner control locking pin, wherein the top cover includes top cover body and company
Connect the top cover support of the top cover body and the workshop column.
It preferably, further include setting roller shutter in the production method of the architectural engineering processing workshop of above-mentioned top cover lifting
Step, by the setting of walking girder steel in the workshop top, steel beam rail is arranged in the walking girder steel lower end, by the first electric block
It is set on the walking girder steel, the roller shutter is set to the workshop surrounding, by the way that the roller shutter to be unfolded, so that described
Workshop forms enclosure space.
Preferably, in the production method of the architectural engineering processing workshop of above-mentioned top cover lifting, in the step 3, by institute
It states top cover and is set as bi-layer tip cap.
Preferably, described in the step 3 in the production method of the architectural engineering processing workshop of above-mentioned top cover lifting
Bi-layer tip cap uses the truss of angle steel production.
It preferably, further include that setting walks wheel always in the production method of the architectural engineering processing workshop of above-mentioned top cover lifting
At the step of, by it is described walk wheel assembly be set to workshop bottom beam lower surface and correspond on the position of the workshop column, it is described
Walk and rail clamping device be set on wheel assembly, the rail clamping device by it is described walk wheel assembly be fixed on sliding rail.
It preferably, further include that setting top cover is anti-in the production method of the architectural engineering processing workshop of above-mentioned top cover lifting
The top cover waterproof is set between the bi-layer tip cap and the workshop column by the step of water.
Preferably, in the production method of the architectural engineering processing workshop of above-mentioned top cover lifting, in the step 1, institute
Workshop column is stated to be made of H profile steel.
It preferably,, will in the step 1 in the production method of the architectural engineering processing workshop of above-mentioned top cover lifting
The bottom end of the workshop column is bolted with workshop bottom beam, and the top of the workshop column is bolted with workshop top beam.
Preferably, in the production method of the architectural engineering processing workshop of above-mentioned top cover lifting, in the step 3, institute
Stating lifting device is chain block, and the chain block is set to the top of each workshop column, by the top cover along
The workshop column is raised to specified height.
Preferably, in the production method of the architectural engineering processing workshop of above-mentioned top cover lifting, in the step 3, institute
Stating lifting device is the second electric block, and second electric block is set on the workshop top beam, by the top cover along
The workshop column is raised to specified height.
The architectural engineering processing workshop of top cover lifting of the invention uses liftable top cover, when strong wind day or typhoon day arrive
Before coming, top cover is dropped into ground, is effectively prevented the destruction of typhoon;Top cover, frame sectional making, on-site assembly are built, are torn open
Except convenient, flexible, can repeatedly be used in turn, 100,000 yuan or so of the disposable processing charges of this processing workshop, if turnover 2 times with
On, overall cost can be lower than the fixed machining shed set up, and more saves, is more environmentally friendly;In addition, processing cart of the invention
Between, surrounding installation roller shutter, internal installation boom hoisting can also be realized, so that entire workshop becomes enclosed top cover lift
Processing workshop, this has just had both protection, sunshade, rain-proof, radix saposhnikoviae, the function of lifting in one, has more met current architectural engineering and apply
The Safety standardization requirement at work scene;Meanwhile workshop can integrally be slided in orbit, be conducive to the comprehensive benefit of construction site
The handling that processing stand carries out material can be directly reached with, material-conveying vehicle, after the completion of handling, then workshop are moved on into material along track
Expect to reduce the rehandling of material above processing stand, save artificial.
Detailed description of the invention
Fig. 1 is the front view for the architectural engineering processing workshop that the top cover of first embodiment of the invention is gone up and down;
Fig. 2 is the side view for the architectural engineering processing workshop that the top cover of first embodiment of the invention is gone up and down;
Fig. 3 is the top view for the architectural engineering processing workshop that the top cover of first embodiment of the invention is gone up and down;
Fig. 4 is the front view for the architectural engineering processing workshop that the top cover of second embodiment of the invention is gone up and down;
Fig. 5 is the side view for the architectural engineering processing workshop that the top cover of second embodiment of the invention is gone up and down;
Fig. 6 is the top view for the architectural engineering processing workshop that the top cover of second embodiment of the invention is gone up and down;
Fig. 7 is the skeleton structure shaft side figure for the architectural engineering processing workshop that top cover of the invention is gone up and down;
The architectural engineering processing workshop that Fig. 8-1 goes up and down for top cover of the invention walks wheel assembly front view
The architectural engineering processing workshop that Fig. 8-2 goes up and down for top cover of the invention walks wheel assembly side view;
In figure: 1- top cover body, the workshop 2- column, the workshop 3- bottom beam, 4- wheel set, 5- sliding rail, 6- rail clamping device,
7- locks spanner, 8- bottle gouard moved by hands, 8 '-the second electric blocks, 9- top cover waterproof, 10- top cover support, 11- roller shutter, 12- walking
Girder steel, 13- steel beam rail, the first electric block of 14-, the workshop 15- top beam,
16- locks pin
Specific embodiment
Below in conjunction with the system for the architectural engineering processing workshop that the drawings and specific embodiments go up and down top cover proposed by the present invention
It is described in further detail as method.According to following explanation and claims, advantages and features of the invention will be become apparent from.It needs
Illustrate, attached drawing is all made of very simplified form and using non-accurate ratio, only to convenient, lucidly auxiliary is said
The purpose of the bright embodiment of the present invention.
It please refers to Fig.1 to Fig.3, present embodiment discloses a kind of architectural engineering processing workshops of top cover lifting, comprising: several
Root workshop column 2, bi-layer tip cap and bottle gouard moved by hands 8, wherein the bottom end of the workshop column is connect with workshop bottom beam, the vehicle
Between the top of column connect with workshop top beam;The top specified altitude assignment position setting locking pin 16 of the workshop column 2, it is described
The bottom end setting locking spanner 7 of workshop column 2;The top cover includes top cover body 1 and the connection top cover body 1 and the vehicle
Between column 2 top cover support 10;The lifting device passes through after top cover to specified altitude assignment described in the workshop upright lifting
The top cover is locked on the workshop column 2 by the control of the locking spanner 7 locking pin 16.
It is designed in this way, before strong wind day or typhoon day arrive, top cover is dropped into ground, be effectively prevented the broken of typhoon
It is bad;Top cover, frame sectional making, on-site assembly build, remove convenient, flexible, can repeatedly be used in turn, this processing workshop one
Secondary 100,000 yuan of property processing charges or so, as long as turnover 2 times or more, overall cost can be than the fixed machining shed set up
It is low, it more saves, is more environmentally friendly.
Referring again to the second embodiment of fig. 4 to fig. 6, the difference with first embodiment is only that, is promoted in the present embodiment
The lifting device of the bi-layer tip cap is not the bottle gouard moved by hands 8, but the second electric block 8 '.
Design of cover is bi-layer tip cap, can be safer reliable, may be designed in single layer top cover.
It in the above-described embodiments, further include walking girder steel 12, the walking girder steel 12 is arranged in the workshop top, described
Steel beam rail 13 is arranged in walking 12 lower end of girder steel, and the first electric block 14, the workshop surrounding is arranged on the walking girder steel 12
Roller shutter 11 is set, by the expansion of the roller shutter 11, so that the workshop forms enclosure space.
It is designed in this way and surrounding installation roller shutter 11, internal installation boom hoisting may be implemented, so that entire workshop becomes to close
The top cover lift processing workshop of formula, this has just had both protection, sunshade, rain-proof, radix saposhnikoviae, the function of lifting in one, has more met
The Safety standardization requirement at building engineering construction scene at present
In the above-described embodiments, the bi-layer tip cap uses the truss of angle steel production.
In the above-described embodiments, further include walking wheel assembly 4, it is described walk wheel assembly 4 be set to 3 lower surface of workshop bottom beam
On the position of the corresponding workshop column 2, it is described walk wheel assembly 4 on rail clamping device 6 is set, the rail clamping device 6 by it is described walk wheel it is total
It is fixed on sliding rail 5 at 4.
It is designed in this way, workshop can integrally be slided in orbit, be conducive to the comprehensive utilization of construction site, material-conveying vehicle
The handling that processing stand carries out material can be directly reached, after the completion of handling, then workshop are moved on to above material processing stand along track,
The rehandling for reducing material saves artificial.
In the above-described embodiments, further include top cover waterproof 9, the top cover waterproof 9 be set to the bi-layer tip cap with it is described
Between workshop column 2.
In the above-described embodiments, the workshop column 2 is made of H profile steel.
In the above-described embodiments, the bottom end of the workshop column 2 is bolted with workshop bottom beam 3, the workshop column 2
Top is bolted with workshop top beam 15.
It is designed in this way, is more convenient disassembly.
In the above-described embodiments, the lifting device is chain block 8, and the chain block 8 is set to each vehicle
Between column top, the top cover is raised to specified height along the workshop column.
In the above-described embodiments, the lifting device is the second electric block 8 ', and second electric block 8 ' is set to
On the workshop top beam 15, the top cover is raised to specified height along the workshop column 2.
Fig. 7 is the skeleton structure shaft side figure for the architectural engineering processing workshop that top cover of the invention is gone up and down;
The architectural engineering processing workshop that Fig. 8-1 goes up and down for top cover of the invention walks wheel assembly front view
The architectural engineering processing workshop that Fig. 8-2 goes up and down for top cover of the invention walks wheel assembly side view;
The present embodiment also discloses a kind of production method of the architectural engineering processing workshop of top cover lifting as described above, packet
Include following steps:
Step 1, the bottom end of several workshop columns 2 is connect with workshop bottom beam 3, workshop top beam 15 and the workshop is stood
The top of column 2 connects;
Step 2, locking pin 16 is set to the top specified altitude assignment position of workshop column 2, and locking spanner 7 is arranged
In the bottom end of the workshop column 2;
Step 3, lifting device is set, top cover is promoted along the workshop column 2 to after specified altitude assignment, the locking is passed through
The top cover is locked on the workshop column 2 by the control locking pin 16 of spanner 7, wherein the top cover includes top cover body 1
And connect the top cover support 10 of the top cover body 1 and the workshop column 2.
In above-mentioned production method, further include the steps that roller shutter 11 is arranged, the setting of walking girder steel 12 is pushed up in the workshop
Portion, 12 lower end of walking girder steel are arranged steel beam rail 13, the first electric block 14 are set on the walking girder steel 12, will
The roller shutter 11 is set to the workshop surrounding, by the way that the roller shutter 11 to be unfolded, so that the workshop forms enclosure space.
In the step 3 of above-mentioned production method, bi-layer tip cap is set by the top cover.
In the step 3 of above-mentioned production method, the bi-layer tip cap uses the truss of angle steel production.
In above-mentioned production method, further include the steps that wheel assembly 4 is walked in setting, by it is described walk wheel assembly 4 be set to it is described
Bottom beam 3 lower surface in workshop corresponds on the position of the workshop column 2, it is described walk wheel assembly 4 on be arranged rail clamping device 6, the folder rail
Device 6 by it is described walk wheel assembly 4 be fixed on sliding rail 5.
In above-mentioned production method, further include the steps that top cover waterproof 9 is arranged, the top cover waterproof 9 is set to described
Between bi-layer tip cap and the workshop column 2.
In the step 1 of above-mentioned production method, the workshop column 2 is made of H profile steel.
In the step 1 of above-mentioned production method, the bottom end of the workshop column 2 is bolted with workshop bottom beam 3, by institute
The top and workshop top beam 15 for stating workshop column 2 are bolted.
In the step 3 of above-mentioned production method, the lifting device is chain block 8, and the chain block 8 is set to often
The top cover is raised to specified height along the workshop column 2 by the top of a workshop column 2.
In the step 3 of above-mentioned production method, the lifting device is the second electric block 8 ', second electric block
8 ' are set on the workshop top beam 15, and the top cover is raised to specified height along the workshop column 2.
Foregoing description is only the description to present pre-ferred embodiments, not to any restriction of the scope of the invention, this hair
Any change, the modification that the those of ordinary skill in bright field does according to the disclosure above content, belong to the protection of claims
Range.
Claims (10)
1. a kind of production method of the architectural engineering processing workshop of top cover lifting, which comprises the steps of:
Step 1, the bottom end of several workshop columns is connect with workshop bottom beam, by the top of workshop top beam and the workshop column
Connection;
Step 2, locking pin is set to the top specified altitude assignment position of workshop column, and locking spanner is set to the vehicle
Between column bottom end;
Step 3, setting lifting device passes through the locking spanner by top cover after the workshop upright lifting to specified altitude assignment
The top cover is locked on the workshop column by control locking pin, wherein the top cover includes top cover body and connection institute
State the top cover support of top cover body and the workshop column.
2. the production method of the architectural engineering processing workshop of top cover lifting as described in claim 1, which is characterized in that further include
The step of roller shutter is set, will walking girder steel setting in the workshop top, the walking girder steel lower end setting steel beam rail, by the
One electric block is set on the walking girder steel, and the roller shutter is set to the workshop surrounding, by by the roller shutter exhibition
It opens, so that the workshop forms enclosure space.
3. the production method of the architectural engineering processing workshop of top cover lifting as described in claim 1, which is characterized in that described
In step 3, the top cover is bi-layer tip cap.
4. the production method of the architectural engineering processing workshop of top cover lifting as claimed in claim 3, which is characterized in that described
In step 3, the bi-layer tip cap is the truss made of angle steel.
5. the production method of the architectural engineering processing workshop of top cover lifting as described in claim 1, which is characterized in that further include
The step of wheel assembly, is walked in setting, by it is described walk wheel assembly be set to the position that workshop bottom beam lower surface corresponds to the workshop column
Set, it is described walk wheel assembly on rail clamping device is set, the rail clamping device by it is described walk wheel assembly be fixed on sliding rail.
6. the production method of the architectural engineering processing workshop of top cover lifting as claimed in claim 3, which is characterized in that further include
The step of top cover waterproof is arranged, the top cover waterproof is set between the bi-layer tip cap and the workshop column.
7. the production method of the architectural engineering processing workshop of top cover lifting as described in claim 1, which is characterized in that described
In step 1, the workshop column is made of H profile steel.
8. the production method of the architectural engineering processing workshop of top cover lifting as described in claim 1, which is characterized in that described
In step 1, the bottom end of the workshop column is bolted with workshop bottom beam, by the top of the workshop column and workshop top beam
It is bolted.
9. the production method of the architectural engineering processing workshop of top cover lifting as described in claim 1, which is characterized in that described
In step 3, the lifting device is chain block, and the chain block is set to the top of each workshop column, by institute
It states top cover and is raised to specified height along the workshop column.
10. the production method of the architectural engineering processing workshop of top cover lifting as described in claim 1, which is characterized in that in institute
It states in step 3, the lifting device is the second electric block, and second electric block is set on the workshop top beam, will
The top cover is raised to specified height along the workshop column.
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2016109746740 | 2016-10-31 | ||
CN201610974674 | 2016-10-31 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106930528A CN106930528A (en) | 2017-07-07 |
CN106930528B true CN106930528B (en) | 2019-07-05 |
Family
ID=59424209
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710083399.8A Active CN106930528B (en) | 2016-10-31 | 2017-02-16 | The production method of the architectural engineering processing workshop of top cover lifting |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106930528B (en) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106639396A (en) * | 2016-10-31 | 2017-05-10 | 上海市政工程设计研究总院(集团)有限公司 | Constructional engineering machining workshop with liftable roof |
CN106481106A (en) * | 2016-10-31 | 2017-03-08 | 上海市政工程设计研究总院(集团)有限公司 | Slidingtype architectural engineering job shop |
Family Cites Families (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3961712A (en) * | 1974-10-31 | 1976-06-08 | International Paper Company | Industrial building structure system |
JPH0821105A (en) * | 1994-07-06 | 1996-01-23 | Maeda Corp | Self-propelling type roof device for all weather construction |
CN203308131U (en) * | 2013-06-20 | 2013-11-27 | 葛洲坝集团第二工程有限公司 | Movable workshop made of arc steel pipe frames |
CN104895356B (en) * | 2015-06-08 | 2017-09-08 | 北京陆桥商检新技术公司 | A kind of closed ceiling of wood fumigation |
CN204876070U (en) * | 2015-08-06 | 2015-12-16 | 杭州众赢科技有限公司 | Liftable formula top cap structure |
-
2017
- 2017-02-16 CN CN201710083399.8A patent/CN106930528B/en active Active
Also Published As
Publication number | Publication date |
---|---|
CN106930528A (en) | 2017-07-07 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106481106A (en) | Slidingtype architectural engineering job shop | |
CN103526949B (en) | A kind of sliding and lifting construction method of attached wall vertical structure | |
US10011979B1 (en) | House having aluminum alloy structure | |
CN106930528B (en) | The production method of the architectural engineering processing workshop of top cover lifting | |
CN204804298U (en) | Building material hoist and mount construction scaffold | |
CN206503392U (en) | The architectural engineering job shop of top cover lifting | |
CN106639396A (en) | Constructional engineering machining workshop with liftable roof | |
CN108049666B (en) | A kind of echelon installation method of super plane multilayer steel truss electronic workshop steel construction | |
CN206189928U (en) | Between slidingtype building engineering processing vehicle | |
CN107288352B (en) | The transport of the closed shed dormer roof boarding of overlarge area and installation method | |
CN106013453B (en) | Long-span Cantilever transfinites structure construction engineering method | |
CN201050200Y (en) | Sentry box possessing rotary wind screen cover | |
CN104533001B (en) | A kind of electronic rotation temporary roof cover for nuclear power plant reactor factory building | |
CN207700068U (en) | A kind of modularization Bridge Pier Construction job platform | |
CN103541300A (en) | Railway concrete continuous beam implemented based on flat-pushing method and construction method thereof | |
CN107461059A (en) | A kind of steel-structure factory building | |
CN205873834U (en) | High empty wagon control box protection casing | |
CN207553605U (en) | A kind of sliding architectural engineering processing workshop of head cover integral elevating | |
CN106593032A (en) | Manufacturing method of sliding type building engineering machining workshop | |
CN207686361U (en) | A kind of semiclosed reinforcing steel processing shed of packaged type | |
CN115095269B (en) | Novel insulating operation platform | |
CN108750135A (en) | A kind of turning type telescopic connecting bridge | |
CN202731321U (en) | Multifunctional movable shack at construction site | |
CN212250138U (en) | Construction operation vehicle in railway tunnel | |
CN207332385U (en) | A kind of steel-structure factory building |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |