CN107327028A - 曲面主结构与次结构连接施工方法 - Google Patents

曲面主结构与次结构连接施工方法 Download PDF

Info

Publication number
CN107327028A
CN107327028A CN201610273033.2A CN201610273033A CN107327028A CN 107327028 A CN107327028 A CN 107327028A CN 201610273033 A CN201610273033 A CN 201610273033A CN 107327028 A CN107327028 A CN 107327028A
Authority
CN
China
Prior art keywords
curved surface
connecting plate
main structure
time
plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610273033.2A
Other languages
English (en)
Other versions
CN107327028B (zh
Inventor
潘润军
沈勤
吴华忠
张文
白文化
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Baoye construction decoration Co. Ltd
Original Assignee
Shanghai Baoye Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Baoye Group Corp Ltd filed Critical Shanghai Baoye Group Corp Ltd
Priority to CN201610273033.2A priority Critical patent/CN107327028B/zh
Publication of CN107327028A publication Critical patent/CN107327028A/zh
Application granted granted Critical
Publication of CN107327028B publication Critical patent/CN107327028B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/38Connections for building structures in general

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Joining Of Building Structures In Genera (AREA)

Abstract

本发明涉及曲面弧形结构施工。一种曲面主结构与次结构连接施工方法,它包括:连接件加工步骤;包括焊接在主结构上的连接板和同连接板连接的T形板;连接板的底部加工成和曲面主结构的弧度匹配便于两者焊接连接,其中部开设呈横向圆弧状的长腰形孔,而T形板的腹板上开纵向长腰形孔;曲面定位焊接步骤;高度及角度调整步骤:依据次结构弧度、角度,调整“T”型板高度和角度;螺栓紧固步骤:螺栓连接步骤是整个曲面连接板安装最后的工序,连接板与主结构焊接,T形板根据次结构形状完全接触后用螺栓通过腹板上的长腰形孔及连接板上的圆弧状长腰形孔连接固定。本发明解决主结构与次结构误差而导致不能有效连接的问题,加工方便,节省工期,安装简单。

Description

曲面主结构与次结构连接施工方法
技术领域
本发明涉及曲面弧形结构施工,尤其涉及一种曲面主结构与次结构连接时调整误差的方法。
背景技术
现代许多建设项目外形奇特,且大多形状都是以钢结构为基础。对建筑物、构筑物表面装饰时,钢结构上连接次结构,再用次结构连接外部装饰材料。钢结构在工厂加工、折弯到施工现场焊接吊装,每个步骤都会存在误差。次结构在工厂加工折弯也会存在误差。当两者在施工现场连接时,存在的误差不能用固定尺寸连接板有效连接。在此情况下,修改主结构与次结构不仅增大工程成本还影响工程工期。
发明内容
本发明旨在解决上述缺陷,提供一种曲面主结构与次结构连接施工方法。本发明解决主结构与次结构误差而导致不能有效连接的问题,而且加工方便,节省工期,安装简单。
为解决上述问题一种曲面主结构与次结构连接施工方法,它包括下列步骤:
连接件加工步骤;包括焊接在主结构上的连接板和同连接板连接的T形板;连接板的底部加工成和曲面主结构的弧度匹配便于两者焊接连接,其中部开设呈横向圆弧状的长腰形孔,而T形板的腹板上开纵向长腰形孔;
曲面定位焊接步骤;
曲面定位步骤主要根据次结构与主结构位置关系,对连接板与主结构进行焊接,并按照间隔依次对中间转接定位焊接;
高度及角度调整步骤:
依据次结构弧度、角度,调整“T”型板高度和角度;
螺栓紧固步骤:
螺栓连接步骤是整个曲面连接板安装最后的工序,连接板与主结构焊接,T形板根据次结构形状完全接触后用螺栓通过腹板上的长腰形孔及连接板上的圆弧状长腰形孔连接固定。
所述的调整曲面钢结构与次结构误差的施工方法,连接板定位要准确,与主结构焊接全焊透,并对焊点抽样采用超声波探伤进行内部缺陷检查,并检验焊缝饱满。
所述的调整曲面钢结构与次结构误差的施工方法,连接板焊接完成后,以螺栓为转轴,将“T”型板与次结构构件完全接触;并对螺栓终拧,终拧完成后,丝扣要超出螺母3~5个丝扣。
本发明利用可调连接板的弧形长腰形孔来调节,成功解决了曲面钢结构上主结构与次结构有效连接问题,杜绝因误差导致的返工。本发明采用的连接板加工方便,安装简单,较修改主、次结构节省工期。
附图说明
下面结合附图对本发明做进一步说明:
图1为发明示意图;
图2是本发明的主视图。
具体实施方式
请参见图1和图2,一种曲面主结构与次结构连接施工方法,它包括下列步骤:
连接件加工步骤;包括焊接在主结构4上的连接板1和同连接板连接的T形板2;连接板的底部加工成和曲面主结构的弧度匹配便于两者焊接连接,其中部开设呈横向圆弧状的长腰形孔,而T形板的腹板上开纵向长腰形孔;
曲面定位焊接步骤;
曲面定位步骤主要根据次结构与主结构位置关系,对连接板与主结构进行焊接,并按照间隔依次对中间转接定位焊接;
高度及角度调整步骤:
依据次结构弧度、角度,调整“T”型板高度和角度;
螺栓紧固步骤:
螺栓连接步骤是整个曲面连接板安装最后的工序,连接板与主结构焊接,T形板根据次结构形状完全接触后用螺栓3通过腹板上的长腰形孔及连接板上的圆弧状长腰形孔连接固定。
所述的调整曲面钢结构与次结构误差的施工方法,连接板定位要准确,与主结构焊接全焊透,并对焊点抽样采用超声波探伤进行内部缺陷检查,并检验焊缝饱满。
所述的调整曲面钢结构与次结构误差的施工方法,连接板焊接完成后,以螺栓为转轴,将“T”型板与次结构构件完全接触;并对螺栓终拧,终拧完成后,丝扣要超出螺母3~5个丝扣。

Claims (3)

1.一种曲面主结构与次结构连接施工方法,其特征在于,它包括下列步骤:
连接件加工步骤;包括焊接在主结构上的连接板和同连接板连接的T形板;连接板的底部加工成和曲面主结构的弧度匹配便于两者焊接连接,其中部开设呈横向圆弧状的长腰形孔,而T形板的腹板上开纵向长腰形孔;
曲面定位焊接步骤;
曲面定位步骤主要根据次结构与主结构位置关系,对连接板1与主结构进行焊接,并按照间隔依次对中间转接定位焊接;
高度及角度调整步骤:
依据次结构弧度、角度,调整“T”型板高度和角度;
螺栓紧固步骤:
螺栓连接步骤是整个曲面连接板安装最后的工序,连接板与主结构焊接,T形板根据次结构形状完全接触后用螺栓通过腹板上的长腰形孔及连接板上的圆弧状长腰形孔连接固定。
2.根据权利要求1所述的调整曲面钢结构与次结构误差的施工方法其特征在于,连接板定位要准确,与主结构焊接全焊透,并对焊点抽样采用超声波探伤进行内部缺陷检查,并检验焊缝饱满。
3.根据权利要求1所述的调整曲面钢结构与次结构误差的施工方法其特征在于,连接板焊接完成后,以螺栓为转轴,将“T”型板与次结构构件完全接触;并对螺栓终拧,终拧完成后,丝扣要超出螺母3~5个丝扣。
CN201610273033.2A 2016-04-28 2016-04-28 曲面主结构与次结构连接施工方法 Active CN107327028B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610273033.2A CN107327028B (zh) 2016-04-28 2016-04-28 曲面主结构与次结构连接施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610273033.2A CN107327028B (zh) 2016-04-28 2016-04-28 曲面主结构与次结构连接施工方法

Publications (2)

Publication Number Publication Date
CN107327028A true CN107327028A (zh) 2017-11-07
CN107327028B CN107327028B (zh) 2019-04-26

Family

ID=60193136

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610273033.2A Active CN107327028B (zh) 2016-04-28 2016-04-28 曲面主结构与次结构连接施工方法

Country Status (1)

Country Link
CN (1) CN107327028B (zh)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110460066A (zh) * 2019-08-30 2019-11-15 常州博瑞电力自动化设备有限公司 一种箱式配网串联补偿装置

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1113184A (ja) * 1997-06-26 1999-01-19 Onoda Autoclaved Light Weight Concrete Co Ltd Alcパネルの位置調整方法および位置調整機構を備えたalcパネルの取付構造
CN102535642A (zh) * 2011-12-29 2012-07-04 东南大学 空间自由曲面网壳钢结构的装配式节点及其装配方法
CN103362207A (zh) * 2013-07-22 2013-10-23 江苏文汇钢业工程有限公司 钢构件高空预拼装结构
CN204098236U (zh) * 2014-08-21 2015-01-14 中冶东方工程技术有限公司秦皇岛研究设计院 一种用于钢结构的双向水平滑动的竖向支承结构
CN104295000A (zh) * 2014-08-27 2015-01-21 浙江精工钢结构集团有限公司 一种钢结构建筑的双向弯曲类椭圆结构及其制作方法

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1113184A (ja) * 1997-06-26 1999-01-19 Onoda Autoclaved Light Weight Concrete Co Ltd Alcパネルの位置調整方法および位置調整機構を備えたalcパネルの取付構造
CN102535642A (zh) * 2011-12-29 2012-07-04 东南大学 空间自由曲面网壳钢结构的装配式节点及其装配方法
CN103362207A (zh) * 2013-07-22 2013-10-23 江苏文汇钢业工程有限公司 钢构件高空预拼装结构
CN204098236U (zh) * 2014-08-21 2015-01-14 中冶东方工程技术有限公司秦皇岛研究设计院 一种用于钢结构的双向水平滑动的竖向支承结构
CN104295000A (zh) * 2014-08-27 2015-01-21 浙江精工钢结构集团有限公司 一种钢结构建筑的双向弯曲类椭圆结构及其制作方法

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110460066A (zh) * 2019-08-30 2019-11-15 常州博瑞电力自动化设备有限公司 一种箱式配网串联补偿装置

Also Published As

Publication number Publication date
CN107327028B (zh) 2019-04-26

Similar Documents

Publication Publication Date Title
CN205393883U (zh) 一种h型钢组装卡具
CN104652422B (zh) 用于桩基钢筋笼钢筋连接的装置及方法
CN206277093U (zh) 钢筋笼接长定位套筒
CN106400957A (zh) 一种全预制装配式梁柱节点
CN211257341U (zh) 一种圆钢管混凝土柱与工字形钢梁的刚性加强连接节点
CN206844322U (zh) 一种钢管柱和h型钢梁的刚接节点
CN104358320B (zh) 一种全预制装配式梁柱节点
CN105804387A (zh) 一种连墙件及其安拆方法
CN107327028A (zh) 曲面主结构与次结构连接施工方法
CN111001976A (zh) 用于大管径薄壁管道的对口装置及其使用方法
CN205100375U (zh) 一种预制装配式梁柱节点
CN205778937U (zh) 一种精确定位初期支护钢拱架单元与连接钢板的辅助装置
CN106392433B (zh) 钢筋连接定位辅助装置
CN104196023B (zh) 一种带机械连接装置的混凝土预制管桩桩尖的使用方法
CN207746578U (zh) 钢桥板梁翼缘板与腹板焊接反变形结构
CN205421562U (zh) 一种h型悬臂钢梁柱拼接结构
CN209762546U (zh) 一种管道异型套筒
US10100489B2 (en) Structural connectors for dragline boom and mast tubular clusters and methods for repair, reinforcement and life extension of dragline booms and masts
CN207176935U (zh) 一种在弱轴方向上梁柱的半刚性节点螺栓连接结构
CN108867890A (zh) 连接处带刚性模板支架的梁柱整体预制节点及其施工方法
CN204343454U (zh) 一种用轴向十字形圆环插板对接钢管的对接件
CN216765861U (zh) 一种用于管桩快速对接的辅助装置
CN108044251B (zh) 一种十字焊缝贴玻璃纤维布的焊接方法
CN205677073U (zh) 一种全栓接装配式梁柱节点
CN209369185U (zh) 多向钢筋连接装置

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20190415

Address after: 2010 900 Luodian Development Zone, Baoshan District, Shanghai (No. 102 A-150, Shiyi Road)

Applicant after: Shanghai Baoye construction decoration Co. Ltd

Address before: No. 2457 Fuyuan Road, Baoshan District, Shanghai, 2004

Applicant before: Shanghai Baoye Group Corp., Ltd.