CN107301527B - Project evaluation method based on items - Google Patents

Project evaluation method based on items Download PDF

Info

Publication number
CN107301527B
CN107301527B CN201710247252.8A CN201710247252A CN107301527B CN 107301527 B CN107301527 B CN 107301527B CN 201710247252 A CN201710247252 A CN 201710247252A CN 107301527 B CN107301527 B CN 107301527B
Authority
CN
China
Prior art keywords
project
sub
price
item
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710247252.8A
Other languages
Chinese (zh)
Other versions
CN107301527A (en
Inventor
罗杏春
吴培关
瞿国旭
罗余春
杜云梦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kunming University of Science and Technology
Original Assignee
Kunming University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kunming University of Science and Technology filed Critical Kunming University of Science and Technology
Priority to CN201710247252.8A priority Critical patent/CN107301527B/en
Publication of CN107301527A publication Critical patent/CN107301527A/en
Application granted granted Critical
Publication of CN107301527B publication Critical patent/CN107301527B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F16/00Information retrieval; Database structures therefor; File system structures therefor
    • G06F16/20Information retrieval; Database structures therefor; File system structures therefor of structured data, e.g. relational data
    • G06F16/24Querying
    • G06F16/245Query processing
    • G06F16/2458Special types of queries, e.g. statistical queries, fuzzy queries or distributed queries
    • G06F16/2462Approximate or statistical queries

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Strategic Management (AREA)
  • Theoretical Computer Science (AREA)
  • Probability & Statistics with Applications (AREA)
  • General Physics & Mathematics (AREA)
  • Data Mining & Analysis (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Economics (AREA)
  • Marketing (AREA)
  • General Business, Economics & Management (AREA)
  • Tourism & Hospitality (AREA)
  • Quality & Reliability (AREA)
  • Operations Research (AREA)
  • Fuzzy Systems (AREA)
  • Mathematical Physics (AREA)
  • Software Systems (AREA)
  • Computational Linguistics (AREA)
  • Databases & Information Systems (AREA)
  • General Engineering & Computer Science (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

本发明涉及一种既能快速又能精准估价的工程项目分项方法,属于工程项目管理领域。本发明通过对工程项目构成实体材料进行分类分项,分项的“量”和“价”包含了结构部位、工程材料、施工方案、施工管理等全部要素;建立工程项目实体材料分项与工程项目所在地同类已完工工程项目传统分项“量”和“量”对应及“量”和“价”对应的耦合算法和数据库,实现了所在地实体材料分项“价”的自动数理统计和智能数据挖掘;工程项目初步设计概算、施工图预算对“价”的测算值和招投标中标价、结算价、决算价等实际发生值都和“价”的统计值进行对比与验证,实现了“价”在决策阶段的的估算值、设计阶段的测算值和施工阶段的实际值等基本建设全过程的利用与验证,再利用BIM模型自动计算实体(材料)分项的“量”,实现了工程项目快速精准估价。The invention relates to a project sub-item method capable of fast and accurate evaluation, and belongs to the field of project management. The present invention classifies and sub-items the physical materials constituting the engineering project, and the "quantity" and "price" of the sub-items include all elements such as structural parts, engineering materials, construction plans, construction management, etc.; The traditional sub-item "quantity" and "quantity" corresponding to the "quantity" and "quantity" corresponding to the "quantity" and "price" corresponding to the coupling algorithm and database of the similar completed projects in the project location, realize the automatic mathematical statistics and intelligent data of the local physical material sub-item "price" Excavation; the preliminary design estimates of engineering projects and construction drawing budgets compare and verify the estimated value of "price" and the actual value of bidding price, settlement price, final settlement price, etc. with the statistical value of "price" "The use and verification of the whole process of capital construction, such as the estimated value in the decision-making stage, the estimated value in the design stage, and the actual value in the construction stage, etc., and then use the BIM model to automatically calculate the "quantity" of the entity (material) sub-item, and realize the project. Fast and accurate project valuation.

Description

Project evaluation method based on items
Technical Field
The invention relates to an engineering project valuation method based on items, in particular to a method capable of quickly and accurately valuing items based on entity materials forming an engineering project, and belongs to the field of engineering project management.
Background
The division and the sequence of each stage in the whole construction and operation process from decision, design, construction to completion, acceptance, delivery, operation management and maintenance of the engineering project are called as basic construction procedures, the process is determined by objective rules of basic construction (including natural rules and economic rules), is strictly restricted by natural conditions such as geology, hydrology and the like and material technical conditions, and the construction and management are required to be carried out according to the overall design which meets the established requirements and has scientific basis, and generally comprise a decision-making stage (comprising two links of pre-feasibility research and engineering feasibility research), a design stage (comprising three links of preliminary, technical and construction drawing design), a construction stage (comprising links of construction preparation, construction management, completion acceptance inspection and the like) and an operation stage (comprising links of post-evaluation, audit, operation management, maintenance and the like).
At present, the specific methods for investment measurement and cost analysis of engineering projects mainly comprise two methods: and in the decision-making stage, the macroscopic economic indexes are utilized to quickly estimate and design the construction cost of the engineering quantity list in the bidding stage.
The method for quickly estimating the price by using the macroscopic economic indexes in the decision stage is a method for quickly estimating the investment amount of an engineering project by using the statistical values of the similar project macroscopic indexes at the engineering site after the construction scale of the engineering project decision is determined, and although necessary adjustment and correction can be performed on the investment amount according to the engineering attributes of the engineering project when the statistical values of the similar project macroscopic indexes are used, the same engineering project cannot exist at the same time at the engineering site, so that the method is mainly embodied quickly and is difficult to give consideration to accuracy.
The project list and project amount list cost analysis method for bid and bid in the design stage is a method for calculating and analyzing the cost of each calculated sub-project according to the project amount measurement rule of the budget estimate project list or the specification of the project amount list calculation rule after a project has a definite design chart, and then using an applicable quota to analyze the cost and the investment amount of each sub-project of the project.
Because the inclusion, intersection and interleaving relation of the indexes, the components and the contents of 'quantity' and 'price' between the components is very complex, the two methods are difficult to be completely unified and mutually verified, so that the phenomena of decision making over budget, budget over approximate calculation, approximate calculation over estimation and the like are frequently caused, and the investment is out of control.
Disclosure of Invention
The invention aims to solve the technical problem of providing a subentry method capable of quickly estimating and accurately analyzing for investment measurement and cost analysis of a project, and the invention searches main influence factors and coupling mechanisms of quantity and price in the whole process of basic construction of the project from the perspective of entity materials forming a highway project, and provides a subentry method capable of quickly estimating and accurately analyzing for reasonably determining and effectively controlling the cost and investment of the highway project.
The technical scheme adopted by the invention is as follows: a project assessment method based on items comprises the following steps:
classifying and itemizing construction project constitution entity materials according to the principles of physical constitution, homogeneous division and integration and adaptation to the working depth of each stage of a basic construction program, providing expression elements and itemization methods for a building information model-BIM display engineering project, enabling the whole basic construction process of engineering project decision, design, construction and operation and maintenance and all components of construction projects, single projects, unit projects, subsection projects and itemization projects to be applicable, enabling the 'quantity' of itemization to comprise structural parts and elements of construction material constitution project entities, and enabling the 'price' of itemization to comprise all elements of construction schemes, measure projects, auxiliary engineering materials and construction management;
establishing a coupling algorithm and a database corresponding to the project entity material sub-items and the traditional sub-items 'quantity' and the 'quantity' and 'price' of the similar finished project where the project is located, realizing automatic mathematical statistics and intelligent data mining of the sub-items 'price' of the entity material of the location, and obtaining the average value, the highest value and the lowest value of the similar entity material sub-items 'price';
the measured value of 'price' and the actually occurring value in the construction process such as bidding, settlement price and the like in the bidding can be compared and verified according to the approximate calculation of the preliminary design and the budget of the engineering project and the construction drawing design, so that the utilization and verification of the whole basic construction process of the estimated value of 'price' in the decision stage, the measured value in the design stage and the actual value in the construction stage are realized, and the circularly verification and utilization of spiral ascending are formed, and the 'price' is gradually close to the real price in the market;
and (3) automatically calculating the quantity of each entity material item of each stage of the engineering project by using the BIM model, and realizing quick and accurate evaluation of the engineering project and verification of a measured value.
Specifically, the solid material refers to: the combination or composite material of the engineering project entity can be intuitively and automatically calculated and counted in an engineering project building information model-BIM, and the volume, the area, the weight or the number of the engineering project entity can be calculated and counted; the physical composition principle refers to that: carrying out physical subentry according to entity combination or composite materials forming the engineering project, wherein subentry is not combined into new entity material subentry; the principle of homogeneous separation and combination refers to that: the homogeneous property of the same kind of entity materials should be extracted, and the measurement units which are consistent before and after are determined, so that the analysis depth and the management level can be freely combined and separated according to the requirements of different construction costs; the principle that the working depth of each stage of the basic construction program is adapted to is as follows: the basic construction project is estimated, approximated, budgeted, settled and settled in four stages of decision, design, construction and operation, the investment and cost are calculated, the working depth is from macro to micro, and from coarse to fine, the required sub-project method is suitable for the working depth of each stage of the basic construction program, and the requirements of cost analysis and cost management of each stage are met.
Preferably, the average value, the highest value and the lowest value of the entity material sub-item price are used for carrying out comparison and rationality analysis on the preliminary design approximation calculation and the construction drawing budget of the engineering project.
Preferably, the average value, the highest value and the lowest value of the entity material sub-item price are used for comparing and verifying the values of the bidding price, the price in the contract, the settlement price and the settlement price of the project bid.
Preferably, the entity material sub-items are utilized as a project amount list for bidding project projects.
Preferably, the entity material items are used as engineering quantity lists for engineering project management to carry out metering and pricing.
Preferably, the entity material items and the item method thereof are used as the management elements and the management method of the 3D printing of the engineering project.
The invention has the beneficial effects that: the entity material itemization of the invention avoids the complicated relationship of the itemization quantity, the crossing and chaos of the measure engineering quantity and the auxiliary engineering quantity in the construction process, and the like, and makes clear that the 'quantity' of the itemization is only the engineering quantity of the entity material of the engineering project, and other quantities are all contained in the 'price', and the investment value of each stage of the engineering project can be rapidly and accurately calculated by establishing a database for automatic statistics and intelligent data mining through the correspondence of the 'quantity' and the 'price' of the traditional itemization of the finished historical project of the engineering location and the itemization of the itemization method of the invention and the definition of the coupling algorithm to obtain the statistic value and the empirical value of the 'price' of each entity material itemization.
Detailed Description
The present invention will be further described with reference to the following embodiments.
Example 1: a project assessment method based on items comprises the following steps:
classifying and classifying the entity materials of the engineering project according to the principle of 'physical composition, homogeneous separation and combination and adaptation to the working depth of each stage of the basic construction program', for example, the solid materials of the civil engineering project are divided into ten categories of earthwork, masonry, cement concrete, asphalt concrete, mixture, steel, decoration, greening, electromechanics and other materials, and an expression element and a subentry method are provided for a building information model-BIM display engineering project, so that the whole basic construction process of engineering project decision, design, construction and operation and maintenance, and all components of construction projects, single projects, unit projects, subsection projects and subentry projects can be suitable, the 'amount' of the subentry comprises the structural part, the engineering materials form the solid elements of the project, and the 'price' of the subentry comprises all the elements of construction schemes, measure projects, auxiliary engineering materials and construction management;
establishing a coupling algorithm and a database corresponding to the project entity material sub-items and the traditional sub-items 'quantity' and the 'quantity' and 'price' of the similar finished project where the project is located, realizing automatic mathematical statistics and intelligent data mining of the sub-items 'price' of the entity material of the location, and obtaining the average value, the highest value and the lowest value of the similar entity material sub-items 'price';
the measured value of 'price' and the actually occurring value in the construction process such as bidding, settlement price and the like in the bidding can be compared and verified according to the approximate calculation of the preliminary design and the budget of the engineering project and the construction drawing design, so that the utilization and verification of the whole basic construction process of the estimated value of 'price' in the decision stage, the measured value in the design stage and the actual value in the construction stage are realized, and the circularly verification and utilization of spiral ascending are formed, and the 'price' is gradually close to the real price in the market;
and (3) automatically calculating the quantity of each entity material item of each stage of the engineering project by using the BIM model, and realizing quick and accurate evaluation of the engineering project and verification of a measured value.
Specifically, the physical composition principle refers to: carrying out physical subentry according to entity combination or composite materials forming the engineering project, wherein subentry is not combined into new entity material subentry; the principle of homogeneous separation and combination refers to that: the homogeneous property of the same kind of entity materials should be extracted, and the measurement units which are consistent before and after are determined, so that the analysis depth and the management level can be freely combined and separated according to the requirements of different construction costs; the principle that the working depth of each stage of the basic construction program is adapted to is as follows: the basic construction project is estimated, approximated, budgeted, settled and settled in four stages of decision, design, construction and operation, the investment and cost are calculated, the working depth is from macro to micro, and from coarse to fine, the required sub-project method is suitable for the working depth of each stage of the basic construction program, and the requirements of cost analysis and cost management of each stage are met.
Preferably, the average value, the highest value and the lowest value of the entity material sub-item price are used for carrying out comparison and rationality analysis on the preliminary design approximation calculation and the construction drawing budget of the engineering project.
Preferably, the average value, the highest value and the lowest value of the entity material sub-item price are used for comparing and verifying the values of the bidding price, the price in the contract, the settlement price and the settlement price of the project bid.
Preferably, the entity material sub-items are utilized as a project amount list for bidding project projects.
Preferably, the entity material items are used as engineering quantity lists for engineering project management to carry out metering and pricing.
Preferably, the entity material items and the item method thereof are used as the management elements and the management method of the 3D printing of the engineering project.
The invention aims to solve the technical problem of providing a project division method capable of quickly estimating price and accurately analyzing for investment measurement and cost analysis of engineering projects, which is based on the basis of, based on and basic principles of taking solid materials forming civil engineering projects as the project division, namely, the quantity of the project division is only the engineering quantity of the solid materials forming the engineering projects, and is closely related and clearly distinguished from the three elements of ' structural parts, construction methods and composition materials ' of the project division of the traditional project division method, the quantity of the project division method is a real member or a semi-finished product of the engineering projects and contains all contents of the three elements of ' structural parts and composition materials ' of the traditional division, and the measures, engineering quantity and auxiliary engineering quantity contained in the construction processes of the construction methods, the construction schemes and the like are contained in the price ', and the price means that the engineering quantity of the solid materials is completely consumed and comprises the artificial consumption, The comprehensive price of measure engineering quantity and auxiliary engineering quantity contained in related resources of materials, machinery, equipment shift and the like and influence factors thereof, the entity material subentry provides expression elements and subentry expression methods for a building information model-BIM display engineering project, and the independent existence of the entity material subentry is meaningless.
The traditional project division method of the engineering project is to recognize and express the engineering content from three aspects of elements such as structural parts, material composition, construction method and the like, and from the structural view, the engineering project is divided into components such as construction projects, single projects, sub-projects, division projects and the like; the composition of the solid materials of engineering projects, such as civil engineering projects, generally comprises ten types of earthwork, masonry, cement concrete, asphalt concrete, steel, mixtures, decorative materials, greening, electromechanical devices and other materials, and each type can be subdivided into different material elements and specific specifications to form thousands of specific material entities; the construction method of the engineering project mainly comprises two major types of manual construction and mechanical construction, and the specific project has specific construction organization and construction method according to different specific construction conditions and construction factors, such as concrete prefabrication and cast-in-place construction methods. The sub-items in the aspects of metering, pricing, quality inspection and the like are the combination of two or more of the three aspects of structural parts, material composition, construction methods and the like, and the sub-items are divided more and more finely along with the higher and higher requirements on the refinement of project management. The core work of the invention is to find the common and individual characteristics of the entity materials of the engineering project. The method for dividing the entity material into the items is divided according to a physical composition principle, a homogeneous separation and combination principle and a principle of adapting to the working depth of each stage of a basic construction program.
(1) Principle of physical division
The physical items are divided according to the entity combination or composite material forming the engineering project, the items are not combined into new entity material items, for example, the civil engineering project can be divided into ten categories of earth and stone, masonry, cement concrete, asphalt concrete, mixture, steel, decoration, greening, electromechanics and other materials, and the cement concrete and the steel are not combined into reinforced concrete and prestressed concrete.
(2) Principle of homogeneous division and combination
The homogeneous property should be extracted from the same kind of entity (material) items, and the measurement units consistent before and after are determined, so that the analysis depth and the management level can be freely combined and separated according to the different cost.
(3) Principle suitable for working depth of each stage of basic construction program
The basic construction project is estimated, approximated, budgeted, settled and settled from four stages of decision, design, construction and operation, and the investment and cost are calculated, and its working depth is from macro to micro, and from coarse to fine, and said invention is suitable for working depth of every stage of basic construction program, and can meet the requirements of cost analysis and cost management of every stage.
The project division method of the invention carries out physical project division according to the entity materials of the engineering projects, for example, civil engineering projects are divided into ten categories of earthwork, masonry, cement concrete, asphalt concrete, mixture, steel, decoration, greening, electromechanics and other materials, and based on the common and individual contents of the engineering projects at each stage of the basic construction program, the corresponding and containing relations between the entity material divisions and the traditional projects can be obtained; and verifying the rationality and feasibility of the containment relationship between the entity material sub-items and the traditional project table by depending on the finished project data of the project location.
The entity material item avoids the complex relations of the item quantity, the crossing and chaos of the measure engineering quantity and the auxiliary engineering quantity in the construction process, and the like, and the quantity of the item is only the engineering quantity of the entity material of the engineering project, other quantities are contained in the price, and the statistics and the experience value of the price of various entity material items are obtained by establishing a database for automatic statistics and intelligent data mining through the correspondence of the quantity and the price of the traditional item of the finished historical project of the engineering location and the item of the item method of the invention and the definition of a coupling algorithm.
The entity material subentry is a member or semi-finished product subentry table of an engineering project, contains all contents of three elements of 'structural parts, construction methods and composition materials' of the traditional project table subentry, and specifically carries out corresponding containment relationship and coupling algorithm from two aspects of 'quantity' and 'price' to analyze, calculate and count:
(1) the corresponding containing relation between the sub-items of the entity material sub-item table and the sub-objects 'quantities' of the traditional item table is determined according to the sub-object engineering quantity metering rule of the traditional item table, the containing relation between the sub-items of the entity material sub-item table and the sub-objects 'quantities' of the traditional item table is determined, and the sub-objects of some traditional item tables are auxiliary contents for completing the sub-items of the entity material sub-item table, so that the relation of 'quantities' -quantity is not established, but the relation of 'price' -amount is established, and three conditions are mainly adopted: the "amount" of the entity material subentry calculation item "= the" amount "of the traditional project table calculation item; the 'quantity' of the calculation items of the entity material subentry table is inconsistent with the 'quantity' of the calculation items of the traditional subentry table multiplied by conversion coefficients such as units; the amount of the calculation item of the entity material subentry table "= the amount of the decomposition calculation of the calculation item of the traditional project table, the project amount of the composition is supplemented under the calculation item of the project amount list subentry table, and then the calculation items are classified into corresponding entity material calculation items. The "amount" of the calculation item of the physical material itemized table "= the" amount "of the calculation item of the conventional itemized table × the conversion coefficient, and the former case is the conversion coefficient of 1.
(2) The corresponding containing relation between the entity material sub-item and the sub-category price of the traditional project table, the containing relation between the price of each project amount list or the calculation item of the budget estimate project table and the calculation item of the entity material sub-item table is clear according to the project content of the calculation item of the entity material sub-item table, namely the money amount, and the containing relation mainly has two conditions: the price of the subentry of the entity material subentry table is not equal to the price of the calculation item of the traditional item table, and the first two conditions of the corresponding relation of the quantity and quantity are automatically included in the corresponding relation of the price and the amount; the 'price' of the subentry of the entity material subentry table is not equal to the 'price' multiplied by the decomposition coefficient of the traditional subentry table calculation item, if the 'price' of one summary (pre) calculation item is to be decomposed into a plurality of entity material subentry calculation items, a one-to-many corresponding relation is established, and the decomposition coefficient is determined by calculating the to-be-shared entity material subentry table calculation item of the traditional subentry table calculation item.
And then, according to the building information model, namely the 'amount' of the entity materials automatically counted and calculated by the BIM, which is constructed at each stage of the basic construction of the engineering project, the investment value of the engineering project can be quickly and accurately calculated by utilizing the statistical value and the empirical value of the 'price' of each entity material subentry at the site of the engineering project.
The accuracy of rapidly estimating the investment amount of the engineering project decision-making stage by using the subentry method of the invention is greatly improved compared with the traditional method, because: the project sub-expression of the project sub-method of the invention in the decision-making stage is the actual project quantity of the entity materials forming the project, such as earth and stone, masonry, cement concrete, asphalt concrete, mixture, steel, decoration, greening, electromechanics and other materials, etc., which reflects the individual characteristics of the project, and has more fine and accurate expression by one or two macroscopic indexes, such as building area or highway kilometers, etc., compared with the traditional evaluation method, and the measured value does not need to be adjusted according to the concrete project attributes.
The result of real-size cost analysis of project design stage and construction stage can be compared with the entity material statistic value directly, and the reliability of cost analysis result can be ensured.
Furthermore, by using the project grouping method of the invention as a project quantity list for bidding the project and a project quantity list for managing, metering and pricing the project, the common goal of all the participants of the project is to complete the 'quantity' of project entity material items on time according to quality and quantity, the more reasonable division of the risk of all the participants of the project is realized, which is mainly embodied in that the calculation and definition of the 'quantity' of project entity material items are more clear and clear, and the risk of all the participants of the project is contained in the 'price' of project entity material items and is determined by market competition.
Furthermore, the entity material items and the item dividing method thereof are used as the management elements and the management method of the 3D printing of the engineering project.
The core content of the decision-making stage and the design stage of the highway engineering project is the estimation of 'quantity' to 'price', for example, the feasibility study frames 'quantity' macroscopically on the line origin-destination points and main control points of different construction schemes, construction scale and standard argumentation and recommendation, and the preliminary design, technical design and construction drawing design determines 'quantity' and measures and calculates 'price' for the recommended and determined construction schemes; the core contents of the construction phase and the operation phase are the realization and use of the "quantity" and the determination of the "price", for example, the construction bidding is the determination of the "price" of the "quantity" to be implemented, the settlement in the construction management is the execution of the "price" for actually completing the "quantity", and the design change is mostly the change of the "quantity", and is strictly managed. The current typical highway engineering subentry project table mainly comprises a highway engineering project cost composition (total budget amount) project table, a construction quota project table, a budget quota project table, a rough calculation quota project table, an estimation index project table, a budget project table, an estimation project table, a project quantity list, a quality evaluation project table and the like.
The entity material subentry method of the invention divides the entity materials of the highway engineering project into ten categories of earth and stone, masonry, cement concrete, asphalt concrete, mixture, steel, decoration, greening, electromechanics and other materials according to the principles of physical composition principle, homogeneous separation and combination principle, principle of adapting to the working depth of each stage of the basic construction program and the like, and the engineering content and the engineering quantity calculation rule of each subentry are agreed as follows:
(1) calculating engineering quantities of earth and stone according to the solid volumes of road engineering formed by filling and excavating on the original ground line, wherein the engineering quantities comprise roadbed excavation, filling, tunnel excavation, structural foundation pit excavation and the like;
(2) the masonry calculates the engineering quantity according to the entity volume of the engineering project formed by dry-masonry and mortar-masonry blockstones with various mortar marks;
(3) calculating the engineering quantity of the cement concrete according to the concrete marks and the entity volume of the engineering project formed by the cement concrete of the construction method;
(4) calculating the engineering quantity of the asphalt concrete according to the solid volume of the engineering project pavement formed by the asphalt concrete containing the asphalt macadam in various non-oil-stone-separation ratios and construction methods;
(5) calculating the engineering quantity of the mixture according to the entity volume of the engineering project formed by the mixture formed by various independent materials and the construction method, wherein the engineering quantity comprises the mixture of soft foundation treatment, a pavement cushion layer, a base layer and the like;
(6) calculating the engineering quantity of the steel according to the weight of the steel of the engineering project formed by the steel of various types and varieties;
(7) the decoration is marking and beautifying on the solid surface of the engineering project, and is mainly a road marking, a tunnel coating, a ceramic tile and other decorative materials, and the engineering quantity is calculated according to the actual design area of the decoration;
(8) calculating engineering quantity including grass planting, turf, arbor, shrub and the like according to the natural volume of a greening body designed on a highway engineering entity for greening;
(9) calculating the engineering quantity according to the designed comprehensive platform set of the electromechanical equipment;
(10) other materials such as geotechnical materials and other new materials, etc. count the engineering quantity according to the weight of the materials constituting the entity.
Therefore, the project quantity of the entity material sub-items of each single project, unit project and sub-item component can be automatically calculated and counted according to the building information model-BIM in different stages of feasibility research, preliminary design, technical design, construction drawing design, construction settlement, completion settlement and the like in the basic construction stage, and the corresponding containment relationship analysis, calculation and statistics can also be carried out on the finished history projects of the project location from the two aspects of 'quantity' and 'price':
(1) the corresponding containment relationship between the sub-items of the entity material sub-item table and the sub-categories 'quantity' of the traditional project table is as follows:
the containment relationship between the sub-items of the entity material sub-item table and the sub-items 'quantity' of the traditional item table is determined according to the sub-category engineering quantity metering rule of the traditional item table, and the sub-categories of some traditional item tables are the auxiliary contents for completing the sub-items of the entity material sub-item table, so that the relationship of 'quantity' -quantity is not established, but the relationship of 'price' -amount is established, and the method mainly has three conditions:
(ii) the "amount" of the calculation items of the entity Material itemization Table "= the" amount "of the calculation items of the conventional itemization Table"
If the project entity material item of the highway engineering project is ' roadbed excavation ', in a ' project amount list item table ', roadbed excavation is ' = ' earthwork (203-1-1) ' + ' earthwork (203-1-2) ' + ' excavating non-applicable materials (without sludge) (203-1-3) ' + ' excavating sludge (203-1-4) ' + ' clearing landslide body (205-12-1) ' + ' deloading earthwork (205-12-2) ' + ' deloading earthwork (205-12-3) ' (the number in parentheses is the project amount list code, the same below).
② the ' quantity ' of the calculation item of the entity material subentry table (= quantity ' of the calculation item of the traditional item table) × conversion coefficient (such as unit inconsistency)
For example, in the project inventory item table of highway engineering project, the material item of "asphalt concrete" is that "asphalt concrete" = "6 cm (309-1-1-3) thick x 0.06" + "5 cm (309-1-3-2) thick x 0.05" + "3 cm (309-1-4-2) thick x 0.03".
Third, the 'quantity' of the calculation items of the entity material subentry table is not equal to the 'quantity' of the decomposition calculation of the calculation items of the traditional subentry table "
If the calculation items of the single-hole reinforced concrete circular pipe culvert with the inner diameter of 1.0m measured by meters in the highway engineering project are required to complement the construction quantities of cover plate reinforcing steel bars, concrete culvert bodies, cover plates, broken stone cushions, foundation pit excavation and the like according to information such as design charts, engineering ledgers or rated group prices and the like, and then corresponding calculation items of entity materials such as reinforcing steel bars, cement concrete, mixtures, earthwork and the like corresponding to entity material items are classified.
The first and second conditions can be processed uniformly as (1) ("quantity" = quantity "× conversion coefficient of traditional item table calculation item) in the entity material itemizing table calculation item; and thirdly, under the condition, the project amount formed by the project amount list item table is supplemented under the project amount list item table calculation items, and then the project amount list item table is classified into corresponding entity material calculation items of the invention.
(2) The corresponding containing relation between the items of the entity material item table and the sub-category price of the traditional item table is as follows:
according to the ' engineering content ' of the calculation item of the entity material subentry table of the invention, the containing and coupling relation between the calculation item of each engineering quantity list subentry table and the calculation item of the entity material subentry table of the invention, namely the price ' -amount, is clear, and the invention mainly has two conditions:
(ii) the "price" of a subentry of the entity materials subentry "= the" price "of a traditional project table calculation item"
If the project entity material item of the highway engineering project is divided into ' roadbed excavation ' and ' certain project amount list item table ', the ' roadbed excavation ' = ' earthwork (203-1-1) ' + ' earthwork (203-1-2) ' + ' excavating non-applicable materials (not containing sludge) (203-1-3) ' + ' excavating sludge (203-1-4) ' + ' clearing landslide body (205-12-1) ' + ' load reduction earthwork (205-12-2) ' + ' load reduction earthwork (205-12-3) ' + ' borrow (204-3-1) ' + ' abandon party over transport (203-3-1) ', the ' earthwork is filled and excavated on the original ground line according to the agreed project amount calculation rule, and the project amount is calculated according to the volume of the entities which form the highway engineering project and comprise the roadbed excavation (203-1, the earth excavation), the project amount is calculated according to the agreed project amount calculation rule, Fill, tunnel excavation, excavation of structural foundation pit and the like, and the ' abandon square and over transport ' (203-3-1) ' are auxiliary engineering quantities in the construction process, do not form ' quantities ' of the ' material ' subentries of the entity, and correspond to ' price '.
The price of the subentry of the entity material subentry table is not less than the price of the calculation item of the traditional project table multiplied by the decomposition coefficient, and the price of one summary (pre) calculation project calculation item is decomposed into a plurality of entity material subentry calculation items;
if the price of the calculation item of the single-hole reinforced concrete circular pipe culvert with the inner diameter of 1.0m measured by meters in the traditional subentry of the highway engineering project is to be decomposed into the subentry calculation items of solid materials, such as reinforcing steel bars, cement concrete, mixture, earthwork and the like, the group price condition of the calculation item of the traditional project table is inquired, and the decomposition is carried out according to the amount or proportion corresponding to the subentry calculation item of the solid materials.
The first case is that the first and second cases of the corresponding relation of 'quantity' -quantity are automatically included in the corresponding relation of 'price' -amount; and secondly, establishing a one-to-many corresponding relation, and calculating the calculation items of the entity material itemizing table of the calculation items of the traditional item table to determine the decomposition coefficients.
The entity material items avoid the complex relations of the item quantity, the crossing and chaos of the measure engineering quantity and the auxiliary engineering quantity in the construction process, etc., and the quantity of the items is only the engineering quantity of the entity materials constituting the engineering project, other quantities are all contained in the price, and the investment value of each stage of the engineering project can be rapidly and accurately calculated by performing automatic statistics and intelligent data mining on the database established by the traditional items of the finished historical project of the engineering location and the items of the item method of the invention by corresponding the quantity and the price and defining the coupling algorithm.
While the present invention has been described in detail with reference to the specific embodiments thereof, it will be apparent to one skilled in the art that various changes and modifications can be made therein without departing from the spirit and scope thereof.

Claims (5)

1.一种基于分项的工程项目估价方法,其特征在于,包括如下步骤:1. a project appraisal method based on sub-item, is characterized in that, comprises the steps: 按物理构成、同质分合、与基本建设程序各阶段工作深度相适应的原则对工程项目构成实体材料进行分类分项,为建筑信息模型-BIM展示工程项目提供表达要素和分项方法,使工程项目决策、设计、施工和运维的基本建设全过程及建设项目、单项工程、单位工程、分部工程和分项工程全部构件都能适用,分项的“量”包含了结构部位、工程材料构成项目实体的要素,分项的“价”包含了施工方案、措施项目和辅助的工程材料、施工管理的全部要素;所述的实体材料指:构成工程项目实体的组合或复合材料,可以直观地在工程项目建筑信息模型-BIM自动计算统计其体积、面积、重量或个数;According to the principles of physical composition, homogeneous separation and integration, and compatibility with the depth of work in each stage of the capital construction program, the physical materials constituting the project are classified and sub-item, and the expression elements and sub-item methods for the building information model-BIM display project are provided, so that the The entire basic construction process of project decision-making, design, construction and operation and maintenance and all components of construction projects, single projects, unit projects, sub-projects and sub-projects are applicable. The "quantity" of sub-items includes structural parts, engineering Materials constitute the elements of the project entity, and the sub-item "price" includes all elements of the construction plan, measure items, auxiliary engineering materials, and construction management; Intuitively, automatically calculate and count the volume, area, weight or number in the building information model-BIM of the project; 建立工程项目实体材料分项与工程项目所在地同类已完工工程项目传统分项“量”和“量”对应及“量”和“价”对应的耦合算法和数据库,实现所在地实体材料分项“价”的自动数理统计和智能数据挖掘,得到同类实体材料分项“价”的平均值、最高值和最低值的统计值;Establish a coupling algorithm and database corresponding to the “quantity” and “quantity” of the traditional sub-items “quantity” and “quantity” and the “quantity” and “price” of the physical material sub-items of the engineering project and the similar completed engineering projects in the location of the project, so as to realize the “price” of the physical material sub-item of the location. ” automatic mathematical statistics and intelligent data mining, to obtain the statistical value of the average value, the highest value and the lowest value of the sub-item “price” of similar physical materials; 根据工程项目初步设计编制的概算、施工图设计编制的预算对“价”的测算值和招投标中标价、结算价、决算价等施工过程中实际发生值都可以对“价”的统计值进行对比与验证,实现“价”在决策阶段的的估算值、设计阶段的测算值和施工阶段的实际值的基本建设全过程的利用与验证,形成螺旋上升的循环验证与利用,“价”的统计值逐步接近市场真实的价格;According to the estimated budget prepared by the preliminary design of the project and the budget prepared by the construction drawing design, the measured value of the "price" and the actual value of the bidding price, settlement price, final account price and other actual values in the construction process can be calculated on the "price" statistical value. Contrast and verify, realize the utilization and verification of the whole process of capital construction of the estimated value of "price" in the decision-making stage, the estimated value of the design stage and the actual value of the construction stage, forming a spiral upward circular verification and utilization. The statistical value gradually approaches the real price of the market; 利用所述实体材料分项作为招标工程项目的工程量清单;Use the sub-items of the physical materials as the bill of quantities of the bidding project; 利用BIM模型自动计算工程项目各阶段实体材料分项的“量”,实现工程项目估价及与测算值的验证;Use the BIM model to automatically calculate the "quantity" of the physical material sub-items at each stage of the engineering project, and realize the evaluation of the engineering project and the verification of the estimated value; 所述的物理构成原则指:按构成工程项目的实体组合或复合材料进行物理分项,分项间不再组合为新的实体材料分项;所述的同质分合原则指:同类实体材料分项应提炼同质属性,并确定前后一致的计量单位,就不同的造价分析深度和管理层次的需要能分合自如;所述的与基本建设程序各阶段工作深度相适应的原则指:基本建设项目从决策、设计、施工、营运四阶段要进行估算、概算、预算、结算和决算阶段投资和造价的测算,其工作深度是从宏观到微观、由粗到细逐步深入的,所需分项方法与基本建设程序各阶段工作深度相适应,满足各阶段造价分析和造价管理的需要。The said principle of physical composition refers to: carry out physical sub-items according to the physical combination or composite material constituting the project, and the sub-items are no longer combined into new sub-items of sub-items; The sub-items should extract homogeneous attributes, and determine consistent units of measurement, so that they can be divided and combined freely according to the needs of different cost analysis depths and management levels; The construction project needs to be estimated, estimated, budgeted, settled, and finalized from the four stages of decision-making, design, construction, and operation. The investment and cost calculation are carried out. The depth of work is gradually deepened from macro to micro, from coarse to fine. This method is adapted to the depth of work at each stage of the capital construction program, and meets the needs of cost analysis and cost management at each stage. 2.根据权利要求1所述的一种基于分项的工程项目估价方法,其特征在于,利用所述实体材料分项“价”的平均值、最高值和最低值的统计值对工程项目初步设计概算、施工图预算进行对比与合理性分析。2. a kind of engineering project valuation method based on sub-item according to claim 1 is characterized in that, utilizes the statistical value of the average value, the highest value and the lowest value of the sub-item "price" of the solid material to preliminarily evaluate the engineering project. Comparison and rationality analysis of design budget and construction drawing budget. 3.根据权利要求1所述的一种基于分项的工程项目估价方法,其特征在于,利用所述实体材料分项“价”的平均值、最高值和最低值的统计值对工程项目招标的投标报价、合同中标价、结算价和决算价进行对比与验证。3. a kind of project evaluation method based on sub-item according to claim 1 is characterized in that, utilizes the statistical value of the average value, the highest value and the lowest value of the sub-item "price" of the solid material to bid for the construction project Compare and verify the bid price, contract bid price, settlement price and final settlement price. 4.根据权利要求1所述的一种基于分项的工程项目估价方法,其特征在于,利用所述实体材料分项作为工程项目管理的工程量清单进行计量与计价。4 . The method for estimating a project based on a sub-item according to claim 1 , wherein the sub-item of the physical material is used as a bill of quantities for project management to perform measurement and valuation. 5 . 5.根据权利要求1所述的一种基于分项的工程项目估价方法,其特征在于,利用所述实体材料分项及其分项方法作为工程项目3D打印的管理要素和管理方法。5 . The method for estimating a project based on sub-item according to claim 1 , wherein the sub-item of the solid material and the sub-item method thereof are used as the management elements and management method of the 3D printing of the engineering project. 6 .
CN201710247252.8A 2017-04-17 2017-04-17 Project evaluation method based on items Active CN107301527B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710247252.8A CN107301527B (en) 2017-04-17 2017-04-17 Project evaluation method based on items

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710247252.8A CN107301527B (en) 2017-04-17 2017-04-17 Project evaluation method based on items

Publications (2)

Publication Number Publication Date
CN107301527A CN107301527A (en) 2017-10-27
CN107301527B true CN107301527B (en) 2021-01-05

Family

ID=60138020

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710247252.8A Active CN107301527B (en) 2017-04-17 2017-04-17 Project evaluation method based on items

Country Status (1)

Country Link
CN (1) CN107301527B (en)

Families Citing this family (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107977465A (en) * 2017-12-21 2018-05-01 福建省晨曦信息科技股份有限公司 A kind of project cost display methods and terminal
CN108364134B (en) * 2018-02-11 2021-07-23 武汉理工大学 Construction cost management system based on BIM technology
CN108416131B (en) * 2018-02-28 2022-06-17 国泰新点软件股份有限公司 Drawing file display method and device, server and storage medium
CN108984876B (en) * 2018-07-02 2023-09-05 广州盛冠建筑科技有限公司 BIM-based embedded sleeve automatic modeling method and system
CN109272294B (en) * 2018-09-11 2021-07-23 上海宝冶集团有限公司 Quota design method, device, equipment and storage medium for fabricated building
CN109325886A (en) * 2018-09-25 2019-02-12 温州云计划科技有限公司 A method of automatically generating decoration budget and goods matching
CN109472446B (en) * 2018-09-30 2022-03-04 中铁第一勘察设计院集团有限公司 BIM model-based engineering budget estimate planning method
CN109872043A (en) * 2019-01-17 2019-06-11 上海申元工程投资咨询有限公司 A kind of cost process risk management-control method and its system
CN111078750B (en) * 2019-11-29 2023-03-10 深圳市华阳国际工程设计股份有限公司 Data statistical method and device of project model and computer storage medium
CN111210162A (en) * 2020-01-14 2020-05-29 中资锐诚工程项目管理有限公司 BIM-based whole process engineering pricing management method and BIM-based whole process engineering management system
CN111367939B (en) * 2020-03-04 2023-08-22 昆明海巍科技有限公司 Highway engineering project account compiling and managing system, method and computer
CN112785173A (en) * 2021-01-29 2021-05-11 华联世纪工程咨询股份有限公司 Cost whole process management system and method
CN112989459B (en) * 2021-02-22 2023-04-07 上海市城市建设设计研究总院(集团)有限公司 BIM measurement deduction and inspection method based on inventory item

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104537447A (en) * 2015-01-20 2015-04-22 广州赛诺博恩低碳工程研究有限公司 Computing system for construction carbon emission load in construction project
CN105335905A (en) * 2015-11-24 2016-02-17 广州拓欧信息技术有限公司 Building engineering computation and evaluation system and method
CN105844380A (en) * 2016-01-26 2016-08-10 湖北文理学院 BIM-based BIM project element management method and system
CN106022587A (en) * 2016-05-12 2016-10-12 广州络维建筑信息技术咨询有限公司 BIM project progress and cost management system based on earned value theory
CN106095989A (en) * 2016-06-21 2016-11-09 上海市建筑科学研究院(集团)有限公司 A kind of architectural engineering information switching method based on BIM
CN106156343A (en) * 2016-07-21 2016-11-23 中国地质大学(武汉) A kind of deep foundation pit construction Scheme Security evaluation knowledge base and automatic safe reviewing method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104537447A (en) * 2015-01-20 2015-04-22 广州赛诺博恩低碳工程研究有限公司 Computing system for construction carbon emission load in construction project
CN105335905A (en) * 2015-11-24 2016-02-17 广州拓欧信息技术有限公司 Building engineering computation and evaluation system and method
CN105844380A (en) * 2016-01-26 2016-08-10 湖北文理学院 BIM-based BIM project element management method and system
CN106022587A (en) * 2016-05-12 2016-10-12 广州络维建筑信息技术咨询有限公司 BIM project progress and cost management system based on earned value theory
CN106095989A (en) * 2016-06-21 2016-11-09 上海市建筑科学研究院(集团)有限公司 A kind of architectural engineering information switching method based on BIM
CN106156343A (en) * 2016-07-21 2016-11-23 中国地质大学(武汉) A kind of deep foundation pit construction Scheme Security evaluation knowledge base and automatic safe reviewing method

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
《基于BIM的全面造价管理实施构想》;薛守贵;《安徽建筑》;20140820;全文 *
《基于BIM的施工过程管理的应用研究》;刘晓峰;《中国优秀硕士学位论文全文数据库 工程科技Ⅱ辑》;20170415;全文 *
《建设工程造价量与价的思考》;王树军;《中国科技信息》;20140831;全文 *

Also Published As

Publication number Publication date
CN107301527A (en) 2017-10-27

Similar Documents

Publication Publication Date Title
CN107301527B (en) Project evaluation method based on items
Cass et al. Calculation of greenhouse gas emissions for highway construction operations by using a hybrid life-cycle assessment approach: case study for pavement operations
US8260585B2 (en) Computer-implemented land planning system and method designed to generate at least one conceptual fit solution to a user-defined land development problem
CN107967522A (en) A kind of power grid technological transformation overhaul engineering Cost Management System and its control method
CN107977717A (en) A kind of grid maintenance project cost difference automatic adjusting method
CN109409634A (en) A method of the metering of Grid Construction Project project amount is carried out based on project management APP
CN109658131A (en) The method for carrying out cost evaluation based on power grid typical cost data
CN107527185B (en) A Parallel Implementation Method for Compiling and Reviewing Construction Project Cost Documents
CN111210162A (en) BIM-based whole process engineering pricing management method and BIM-based whole process engineering management system
Ahmad et al. The construction solid waste minimization practices among Malaysian contractors
CN117035658A (en) Engineering expense processing method and device
CN113065783A (en) BIM (building information modeling) engineering quantity application method of waste incineration power plant based on BIM technology
CN106934659A (en) Highway engineering material cost difference method of adjustment and system
Guo et al. Predicting the duration of a general contracting industrial project based on the residual modified model
Kerali Economic appraisal of road projects in countries with developing and transition economies
CN117350757A (en) A BIM-based rapid highway cost estimation method and system
CN115760250A (en) Engineering cost compiling method and device, electronic equipment and storage medium
Tsai et al. Developing a comprehensive pavement condition evaluation system for rigid pavements in Georgia
Peng et al. Research on the schemes formulation and optimization method of sponge reconstruction in a highway service area
Chawner Construction Cost Indexes as Influenced by Technological Change and Other Factors
Wang et al. Evaluation of highway maintenance performance using Data Envelopment Analysis (DEA) in Taiwan
Pivetta Development of Software Programs for Performance Related Specifications of Asphalt Concrete Pavements
CN117851412A (en) Highway engineering list compiling method and system based on BIM
Huntsman et al. Highway cost index estimator tool
Buddhavarapu et al. Technical Report Documentation Page 1. Report No.

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant