CN107217855A - A kind of ceramsite concrete light-weight structural wall board construction - Google Patents

A kind of ceramsite concrete light-weight structural wall board construction Download PDF

Info

Publication number
CN107217855A
CN107217855A CN201610162374.2A CN201610162374A CN107217855A CN 107217855 A CN107217855 A CN 107217855A CN 201610162374 A CN201610162374 A CN 201610162374A CN 107217855 A CN107217855 A CN 107217855A
Authority
CN
China
Prior art keywords
pottery
concrete
plate
concrete plate
wall board
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610162374.2A
Other languages
Chinese (zh)
Inventor
汪新
汪一新
何纯波
曹祥彬
倪张江
孙永明
江俊峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wenzhou Innovative New Materials Ltd By Share Ltd
WENZHOU ZHONGCHENG BUILDING GROUP CO Ltd
Original Assignee
Wenzhou Innovative New Materials Ltd By Share Ltd
WENZHOU ZHONGCHENG BUILDING GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wenzhou Innovative New Materials Ltd By Share Ltd, WENZHOU ZHONGCHENG BUILDING GROUP CO Ltd filed Critical Wenzhou Innovative New Materials Ltd By Share Ltd
Priority to CN201610162374.2A priority Critical patent/CN107217855A/en
Publication of CN107217855A publication Critical patent/CN107217855A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C2/00Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels
    • E04C2/02Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by specified materials
    • E04C2/04Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by specified materials of concrete or other stone-like material; of asbestos cement; of cement and other mineral fibres
    • E04C2/044Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by specified materials of concrete or other stone-like material; of asbestos cement; of cement and other mineral fibres of concrete

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Finishing Walls (AREA)

Abstract

High it is an object of the invention to provide a kind of efficiency of construction, load is low, pollution is small and can be prevented effectively from the ceramsite concrete light-weight structural wall board construction of wall crazing.It is characterized in that comprising the following steps:The pottery concrete plate got ready is transported into engineering site by plant produced finished product, sheet material position is determined behind in Fire Hose;Starting point absolute altitude, checks whether pottery concrete plate length and width, thick concrete plate of making pottery with required finished product are consistent;Positioning is punched to the wallboard, wall column, beam of construction;Concrete plate of making pottery is in place, fixed;Check plate and join flatness and perpendicularity with wall column;Plate stitch reinforcement, stickup anti-crack net, carry out processing of plastering afterwards.

Description

A kind of ceramsite concrete light-weight structural wall board construction
Technical field
The present invention relates to a kind of construction, refer in particular to a kind of ceramsite concrete light-weight structural wall board and apply Work engineering method.
Background technology
The traditional way in the casing behind of installation by adhering is fragment of brick masonry panel on wall.With In golden age that construction market has been taken leave of, silver age is stepped into, when construction industry industrial industrialization is The pulsation in generation.We have selected light concrete structural slab to instead of traditional method.And Fire Hose due to Area is larger, it is desirable to which tight, difficulty is higher, representative, thus this engineering method using Fire Hose as Represent.
Equipment box behind light concrete structural slab, thickness is that 30~60mm light concrete panels are to use The New Concrete plate that Ceramsite Concrete is cast, referred to as pottery concrete plate (TTB);(separately there is the thick wood of 15~30mm Fibrous plaster, technological process is close, but is classified as decorative panel, is not discussed in detail).Pottery Concrete plate is produced by factory is unified, and special messenger installs.
The most of production costs of construction of traditional embedded ceramsite concrete light-weight structural wall board compared with Height, cracking hollowing phenomenon takes place frequently, and sound insulation, heat-insulating property are poor.
The content of the invention
High it is an object of the invention to provide a kind of efficiency of construction, load is low, pollution is small and energy It is prevented effectively from the ceramsite concrete light-weight structural wall board construction of wall crazing.
The ceramsite concrete light-weight structural wall board construction, comprises the following steps:
1) the pottery concrete plate got ready, is transported into engineering site by plant produced finished product, in the Fire Hose back of the body Sheet material position is determined afterwards;
2) starting point absolute altitude, check pottery concrete plate length and width, it is thick make pottery with required finished product concrete plate whether phase Symbol;
3) positioning is punched to the wallboard, wall column, beam of construction;Concrete plate of making pottery is in place, fixed;Check plate Join flatness and perpendicularity with wall column;
4) plate stitch reinforcement, stickup anti-crack net, carry out processing of plastering afterwards.
The pottery concrete plate is 30~60 thick, built-in steel wire R φ by core thickness scope 4 200~300mm of@, pottery concrete plate gauge lattice be:Width 700mm, height 1800mm.
Step 3) need to fix the position of steel wire built in pottery concrete plate before, determine pottery concrete plate Block length scantling, control surface flatness and compactness, the laitance of cleaning basic unit, pine before installing Scattered concrete block, debris.
In step 3) in, by design requirement determine pottery concrete plate level start position, it is determined that height and Width position fixing point, ejection control dotted line.
Step 3) in the punching positioning of the wallboard, wall column, beam of construction is referred to:To first make pottery concrete plate Plate determines drawknot node position, then drill pore-forming with wallboard, wall column, beam connecting portion.
Drawknot chain is set in the hole of drill formation, again pottery concrete plate plate is carried out checking thickness afterwards Spend size, positioning and preassembling;Wherein knot chain specification is 220*10*5mm.
Step 3) in pottery concrete plate is in place, fixation refers to:Two people lift pottery concrete plate, up and down, left Right aligned position line, checks that correction perpendicularity, flatness, installation fixation socket chain.
At pottery concrete plate and wallboard, wall column, the link position of girder construction, connecting sewing or small damaged portion Position, after moistening of watering, first with interfacial agents granted full in the handing-over each 200mm in position both sides, then with 1: 3 cement mortar smear one layer, and thick 5mm or so repaves patch reinforcing fibre net, it is ensured that not higher than Pottery concrete board finish, web flattens screed, and mortar layer surface keeps pitted skin.
Beneficial effect of the present invention is:What the ceramsite concrete light-weight structural wall board construction was obtained Making pottery, concrete plate intensity is high, material is light, purposes is wide, volume stability, is adapted to general work civil buildings Structural wall board position after casing, factory is uniformly manufactured, saves manpower, controls the wasting of resources;By force Degree is high, intensity can design mixture proportion as requested, it is lightweight, it is lighter by 25~30% than traditional concrete wall, Purposes is wide, and minimum thickness can be 30mm, can increase thickness in right amount on request, quick for installation; With it is good be incubated, heat-insulated, sound insulation property.It is provided simultaneously with fire prevention, air-tightness is good, waterproof Etc. using functional characteristic.
Embodiment
The ceramsite concrete light-weight structural wall board construction of the present invention is applied to industry and the people With all kinds of installation by adhering dorsal part non bearing structure plates such as structural fire protection case, large-scale distribution box. Comprise the following steps:
The pottery concrete plate got ready is transported into engineering site by plant produced finished product, in Fire Hose behind Determine sheet material position;
Starting point absolute altitude, check pottery concrete plate length and width, it is thick make pottery with required finished product concrete plate whether phase Symbol;
Positioning is punched to the wallboard, wall column, beam of construction;Concrete plate of making pottery is in place, fixed;Check plate Join flatness and perpendicularity with wall column;
Plate stitch reinforcement, stickup anti-crack net, carry out processing of plastering afterwards.
The pottery concrete plate is 30~60 thick, built-in steel wire R φ by core thickness scope 4 200~300mm of@, pottery concrete plate gauge lattice be:Width 700mm, height 1800mm.
Step 3) need to fix the position of steel wire built in pottery concrete plate before, determine pottery concrete plate Block length scantling, control surface flatness and compactness, the laitance of cleaning basic unit, pine before installing Scattered concrete block, debris.
In step 3) in, by design requirement determine pottery concrete plate level start position, it is determined that height and Width position fixing point, ejection control dotted line.
Step 3) in the punching positioning of the wallboard, wall column, beam of construction is referred to:To first make pottery concrete plate Plate determines drawknot node position, then drill pore-forming with wallboard, wall column, beam connecting portion.
Drawknot chain is set in the hole of drill formation, again pottery concrete plate plate is carried out checking thickness afterwards Spend size, positioning and preassembling;Wherein knot chain specification is 220*10*5mm.
Step 3) in pottery concrete plate is in place, fixation refers to:Two people lift pottery concrete plate, up and down, left Right aligned position line, checks that correction perpendicularity, flatness, installation fixation socket chain.
At pottery concrete plate and wallboard, wall column, the link position of girder construction, connecting sewing or small damaged portion Position, after moistening of watering, first with interfacial agents granted full in the handing-over each 200mm in position both sides, then with 1: 3 cement mortar smear one layer, and thick 5mm or so repaves patch reinforcing fibre net, it is ensured that not higher than Pottery concrete board finish, web flattens screed, and mortar layer surface keeps pitted skin.
The characteristics of engineering method of the present invention:Making pottery, concrete plate intensity is high, material is light, purposes is wide, volume It is stable, it is adapted to structural wall board position after general work civil buildings casing, factory is uniformly manufactured, Manpower is saved, the wasting of resources is controlled;Intensity is high, intensity can design mixture proportion as requested, weigh Amount is light, lighter by 25~30% than traditional concrete wall, and purposes is wide, and minimum thickness can be 30mm, can be with Appropriate increase thickness, quick for installation on request;With it is good be incubated, heat-insulated, sound insulation property. It is provided simultaneously with fire prevention, the good, waterproof of air-tightness etc. and uses functional characteristic.
Specifically, the technological principle of engineering method of the present invention is:Pottery concrete plate is according to field requirement Specification purchases the@'s 300 of steel wire R φ 4 in the unified making of factory according to plate thickness (30mm) After light concrete panel, in-site installation, paste anti-crack net in pottery concrete plate surrounding and wall junction and formed Whole building element.
Concrete plate of making pottery is 30~60 thick, built-in steel wire R φ by core thickness scope 4 200~300mm of@.Pottery concrete plate gauge lattice be:Width 700mm, height 1800mm.
Technological process and key points for operation during specific implementation:
In factory according to engineering design requirements, material is chosen, experiment, makes mould, designs concrete Composition and division in a proportion, production pottery concrete plate.Engineering site is transported by plant produced finished product, in Fire Hose behind Sheet material position is determined, whether starting point absolute altitude checks pottery concrete plate length and width, thick and finished product pottery concrete plate Be consistent, positioning → plate, wall column, beam are punched → make pottery concrete plate it is in place → fix → check plate and wall friendship Connect flatness and perpendicularity → plate stitch reinforcement → stickup anti-crack net → completion (hands over next procedure to smear Ash).Product has to comply with《Lightweight aggregate concrete technology code》(JGJ 51-2002) requirement. It should prevent from damaging or damaging in transport.Ceramsite Concrete should be by concrete ratio requirement, with good workability And water-retaining property.Fix the position of built-in steel wire, determine the long scantling of plate.Control surface Flatness and compactness.The laitance of cleaning basic unit, loose concrete block, debris etc. before installing.Should Level starting point position is determined by design requirement, it is determined that height and width position fixing point, ejection Control dotted line.Pottery concrete plate determines drawknot node position, drill pore-forming with wall, post, beam connecting portion.
Pottery concrete plate is carried out according to construction drawing to check thickness, positioning and preassembling.(draw It is 220*10*5 (mm) to tie chain specification.Concrete board wall plate of making pottery installs point 2 people, one group, Two people lift plate, up and down, left and right aligned position line, check correction perpendicularity, flatness, installation It is fixedly connected with chain.At the link position for concrete board wall plate and the structure of making pottery, connecting sewing or small damaged part, After moistening of watering, first with interfacial agents granted full in the handing-over each 200mm in position both sides, then with 1:3 Cement mortar smears one layer, and thick 5mm or so repaves patch reinforcing fibre net, it is ensured that not higher than fill Finish coat, web flattens screed, and mortar layer surface keeps pitted skin, it is ensured that next process Facing decoration, which is plastered, to run smooth.
Pottery concrete plate plate install after and Cement Mortar Used in Capital during should take quarantine measures prevent collision or Loosen.Plaster after completion, chisel must not be picked, metope is beaten.
Required material installation is during construction:
Selected materials are preferably:
Pottery concrete plate is divided into 30~60 thickness by thickness, and wallboard specification is:Width 700, height 1800; Ceramsite Concrete is provided by Commercial Concrete producer by label design mixture proportion list.
Cement:Should be dispatched from the factory using 42.5 grades of slags or Portland cement proves retrial report Announcement, sand:Middle sand, steel wire:R φ 4, reinforcing fibre net, special connection Chain link for chain grate.
Required equipment:Count weight one, weighing apparatus, mortar mixer one, tipping barrow three Platform, spirit level one, two, 5m steel tapes;Hand according to croze, electric drill, hose, Spade, ash bucket, frame stool, line pendant, horizon rule, kit bag, trowel etc. are some.
Construction when quality control be:Concrete plate of making pottery makes must be by engineering design label, size It is required that making, meet label intensity requirement and be defined by strength test report, planar dimension requirement + 8mm, the closely knit+5mm of surfacing.Concrete plate of making pottery is installed must smooth vertical and horizontal, monolithic stability. Surface smoothness is no more than 10mm.Watered the moistening scope of operation, cement before reinforcing mat construction Mortar presses 1:3 proportionings;After the completion of reinforcing mat construction 12mm or so facing decorations should be kept to smear Grey thickness.

Claims (8)

1. a kind of ceramsite concrete light-weight structural wall board construction, it is characterised in that comprise the following steps:
1) the pottery concrete plate got ready, is transported into engineering site by plant produced finished product, in the Fire Hose back of the body Sheet material position is determined afterwards;
2) starting point absolute altitude, check pottery concrete plate length and width, it is thick make pottery with required finished product concrete plate whether phase Symbol;
3) positioning is punched to the wallboard, wall column, beam of construction;Concrete plate of making pottery is in place, fixed;Check plate Join flatness and perpendicularity with wall column;
4) plate stitch reinforcement, stickup anti-crack net, carry out processing of plastering afterwards.
2. ceramsite concrete light-weight structural wall board construction according to claim 1, it is characterised in that: The pottery concrete plate is 30~60 thick, built-in steel wire R φ by core thickness scope 4 200~300mm of@, pottery concrete plate gauge lattice be:Width 700mm, height 1800mm.
3. ceramsite concrete light-weight structural wall board construction according to claim 2, it is characterised in that: Step 3) before need to fix the position of steel wire built in pottery concrete plate, to determine pottery concrete plate long Scantling, control surface flatness and compactness are the laitance of cleaning basic unit before installing, loose Concrete block, debris.
4. ceramsite concrete light-weight structural wall board construction according to claim 1, it is characterised in that: In step 3) in, pottery concrete plate level start position is determined by design requirement, it is determined that height and width Spend position fixing point, ejection control dotted line.
5. the ceramsite concrete light-weight structural wall board construction according to claim 1 or 4, its feature It is:
Step 3) in the punching positioning of the wallboard, wall column, beam of construction is referred to:First will pottery concrete plate plate with Wallboard, wall column, beam connecting portion determine drawknot node position, then drill pore-forming.
6. ceramsite concrete light-weight structural wall board construction according to claim 5, it is characterised in that: Drawknot chain is set in the hole of drill formation, again pottery concrete plate plate is carried out checking thickness afterwards Size, positioning and preassembling;Wherein knot chain specification is 220*10*5mm.
7. ceramsite concrete light-weight structural wall board construction according to claim 5, it is characterised in that: Step 3) in pottery concrete plate is in place, fixation refers to:Two people lift pottery concrete plate, up and down, left and right it is right Positive position line, checks that correction perpendicularity, flatness, installation fixation socket chain.
8. according to ceramsite concrete light-weight structural wall board construction according to any one of claims 1 to 4, It is characterized in that:At pottery concrete plate and wallboard, wall column, the link position of girder construction, connecting sewing Or small damaged part, it is first each on handing-over position both sides with interfacial agents granted full after moistening of watering 200mm, then with 1:3 cement mortar smear one layer, and thick 5mm or so repaves patch and strengthens fine Tie up net, it is ensured that concrete board finish of not higher than making pottery, web flattens screed, mortar layer surface is protected Hold pitted skin.
CN201610162374.2A 2016-03-21 2016-03-21 A kind of ceramsite concrete light-weight structural wall board construction Pending CN107217855A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610162374.2A CN107217855A (en) 2016-03-21 2016-03-21 A kind of ceramsite concrete light-weight structural wall board construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610162374.2A CN107217855A (en) 2016-03-21 2016-03-21 A kind of ceramsite concrete light-weight structural wall board construction

Publications (1)

Publication Number Publication Date
CN107217855A true CN107217855A (en) 2017-09-29

Family

ID=59927790

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610162374.2A Pending CN107217855A (en) 2016-03-21 2016-03-21 A kind of ceramsite concrete light-weight structural wall board construction

Country Status (1)

Country Link
CN (1) CN107217855A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111663787A (en) * 2020-06-03 2020-09-15 南通大学 Construction method for installing RLC (radio Link control) wallboard of inner partition wall

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE19959858A1 (en) * 1999-12-10 2001-06-13 Veit Dennert Kg Baustoffbetr Industrially prefabricated wall element comprises plate like segments with several circumferential pretensioned reinforcement strips around outside and separate from support elements for hanging from crane
CN101586370A (en) * 2008-05-19 2009-11-25 王建荣 Construction method of ceramsite light wallboard
CN104712079A (en) * 2015-03-17 2015-06-17 西安建筑科技大学 Assembled polypropylene fiber sludge ceramsite concrete wall based on rough surface connection and construction method thereof

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE19959858A1 (en) * 1999-12-10 2001-06-13 Veit Dennert Kg Baustoffbetr Industrially prefabricated wall element comprises plate like segments with several circumferential pretensioned reinforcement strips around outside and separate from support elements for hanging from crane
CN101586370A (en) * 2008-05-19 2009-11-25 王建荣 Construction method of ceramsite light wallboard
CN104712079A (en) * 2015-03-17 2015-06-17 西安建筑科技大学 Assembled polypropylene fiber sludge ceramsite concrete wall based on rough surface connection and construction method thereof

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
许士伟等: "陶粒混凝土墙板在某住宅楼工程中的施工应用", 《山西建筑》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111663787A (en) * 2020-06-03 2020-09-15 南通大学 Construction method for installing RLC (radio Link control) wallboard of inner partition wall

Similar Documents

Publication Publication Date Title
CN104358341B (en) Building brickwork and masonry construction method of building brickwork
CN104746772B (en) Ash concrete hollow partition board anti-cracking construction method
CN100513717C (en) Steel structure assisted layered installation and construction method for superhigh PRC partition plate
Kamal Analysis of autoclaved aerated concrete (AAC) blocks with reference to its potential and sustainability
CN104018598A (en) Outer wall structure and construction and installation method
CN102808513B (en) Crack controlling construction method for lightweight wall
US20110219717A1 (en) Lightweight concrete containing aggregates of cement-bonded foamed polystyrene, procedure of making the same and building structures made from this lightweight concrete
CN104074305B (en) A kind of self-heat conserving decoration integrated Multi-function light concrete composite plates and curtain wall
WO2015120794A1 (en) Building component replacing plaster layer with prefabricated panel protection layer
CN203429831U (en) Split-free composite heat insulation template for pouring concrete
CN103835505A (en) Outer wall compound heat preservation board construction method
CN101608503B (en) Method for preventing and controlling cracks of hollow wallboard for building
CN109356319A (en) A kind of one assembly concrete Side fascia of the six directions and its production method
CN107780559A (en) A kind of construction method of heat-insulation and heat-preservation gypsum partition wall
CN202099901U (en) Troweling structure for treatment on junction part of concrete wall column and filler wall
CN102433958A (en) Prefabricated wall board construction member
CN106894538A (en) Filling wall and agent structure concrete integral shaping method
CN105649235A (en) Construction technique for MS dense thin-wall building block filling
CN105275206A (en) A construction method of an external wall of a building
CN205116541U (en) Foaming light aggregate concrete partition plate
CN107217855A (en) A kind of ceramsite concrete light-weight structural wall board construction
WO2018126950A1 (en) Modular stairway
CN102182323A (en) Process for dry laying of autoclaved aerated concrete blocks in low-latitude plateaus
CN108894498A (en) A kind of building filling wall integrated construction technique
CN107246106A (en) A kind of surface cuts shaping haydite concrete prefabricated panel

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: No. 4, building No. 1, No. 2, Jiao Xia Yu Road, pan Qiao street, Ouhai District, Wenzhou, Zhejiang

Applicant after: Wenzhou urban construction group Limited by Share Ltd

Applicant after: Wenzhou Innovative New Materials Limited by Share Ltd.

Address before: 325000, first, second (218-220 rooms), No. 49, Nanhui Road, Louqiao industrial district, Ouhai District, Wenzhou, Zhejiang

Applicant before: Wenzhou Zhongcheng Building Group Co., Ltd.

Applicant before: Wenzhou Innovative New Materials Limited by Share Ltd.

CB02 Change of applicant information
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20170929

WD01 Invention patent application deemed withdrawn after publication