CN107208384A - Sports ground is constructed - Google Patents
Sports ground is constructed Download PDFInfo
- Publication number
- CN107208384A CN107208384A CN201480084557.6A CN201480084557A CN107208384A CN 107208384 A CN107208384 A CN 107208384A CN 201480084557 A CN201480084557 A CN 201480084557A CN 107208384 A CN107208384 A CN 107208384A
- Authority
- CN
- China
- Prior art keywords
- water
- sports ground
- cloth
- moisture layer
- substrate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 147
- 239000004744 fabric Substances 0.000 claims abstract description 77
- 239000000758 substrate Substances 0.000 claims abstract description 49
- 238000009826 distribution Methods 0.000 claims abstract description 14
- 230000033001 locomotion Effects 0.000 claims abstract description 12
- 238000001816 cooling Methods 0.000 claims abstract description 7
- 238000000034 method Methods 0.000 claims description 43
- 239000002689 soil Substances 0.000 claims description 25
- 230000006641 stabilisation Effects 0.000 claims description 15
- 238000011105 stabilization Methods 0.000 claims description 15
- 239000004033 plastic Substances 0.000 claims description 11
- 229920003023 plastic Polymers 0.000 claims description 11
- 239000000853 adhesive Substances 0.000 claims description 10
- 230000001070 adhesive effect Effects 0.000 claims description 10
- 230000006835 compression Effects 0.000 claims description 10
- 238000007906 compression Methods 0.000 claims description 10
- 239000011248 coating agent Substances 0.000 claims description 8
- 238000000576 coating method Methods 0.000 claims description 8
- 239000012530 fluid Substances 0.000 claims description 6
- 239000000126 substance Substances 0.000 claims description 6
- 238000004064 recycling Methods 0.000 claims description 5
- 238000011065 in-situ storage Methods 0.000 claims description 3
- 238000007711 solidification Methods 0.000 claims description 2
- 230000008023 solidification Effects 0.000 claims description 2
- 239000013536 elastomeric material Substances 0.000 claims 1
- 230000010006 flight Effects 0.000 claims 1
- 238000010276 construction Methods 0.000 abstract description 16
- 108091006146 Channels Proteins 0.000 description 27
- 239000000463 material Substances 0.000 description 19
- 238000003860 storage Methods 0.000 description 13
- 239000002245 particle Substances 0.000 description 12
- 239000011435 rock Substances 0.000 description 12
- 238000005516 engineering process Methods 0.000 description 9
- 244000025254 Cannabis sativa Species 0.000 description 8
- 239000000945 filler Substances 0.000 description 8
- 239000004568 cement Substances 0.000 description 7
- 230000008569 process Effects 0.000 description 7
- 238000012360 testing method Methods 0.000 description 7
- 235000008733 Citrus aurantifolia Nutrition 0.000 description 6
- 235000011941 Tilia x europaea Nutrition 0.000 description 6
- 239000004567 concrete Substances 0.000 description 6
- 238000013461 design Methods 0.000 description 6
- 230000000694 effects Effects 0.000 description 6
- 239000004571 lime Substances 0.000 description 6
- 238000009411 base construction Methods 0.000 description 5
- 230000008859 change Effects 0.000 description 5
- 229920001971 elastomer Polymers 0.000 description 5
- 230000002262 irrigation Effects 0.000 description 5
- 238000003973 irrigation Methods 0.000 description 5
- 239000000203 mixture Substances 0.000 description 5
- 239000004575 stone Substances 0.000 description 5
- ODINCKMPIJJUCX-UHFFFAOYSA-N Calcium oxide Chemical compound [Ca]=O ODINCKMPIJJUCX-UHFFFAOYSA-N 0.000 description 4
- 230000015572 biosynthetic process Effects 0.000 description 4
- 230000006378 damage Effects 0.000 description 4
- 238000013016 damping Methods 0.000 description 4
- 238000009434 installation Methods 0.000 description 4
- 239000004576 sand Substances 0.000 description 4
- 102000010637 Aquaporins Human genes 0.000 description 3
- 230000008901 benefit Effects 0.000 description 3
- 239000004927 clay Substances 0.000 description 3
- 238000011156 evaluation Methods 0.000 description 3
- 238000004519 manufacturing process Methods 0.000 description 3
- 238000002156 mixing Methods 0.000 description 3
- 238000012986 modification Methods 0.000 description 3
- 230000004048 modification Effects 0.000 description 3
- 239000004814 polyurethane Substances 0.000 description 3
- 239000002352 surface water Substances 0.000 description 3
- 108010063290 Aquaporins Proteins 0.000 description 2
- 241000196324 Embryophyta Species 0.000 description 2
- 241001465754 Metazoa Species 0.000 description 2
- 238000004220 aggregation Methods 0.000 description 2
- 230000002776 aggregation Effects 0.000 description 2
- 235000012255 calcium oxide Nutrition 0.000 description 2
- 239000000292 calcium oxide Substances 0.000 description 2
- 239000003153 chemical reaction reagent Substances 0.000 description 2
- 230000001419 dependent effect Effects 0.000 description 2
- 239000004746 geotextile Substances 0.000 description 2
- 239000003673 groundwater Substances 0.000 description 2
- 230000007774 longterm Effects 0.000 description 2
- 244000005700 microbiome Species 0.000 description 2
- 238000005325 percolation Methods 0.000 description 2
- 230000035699 permeability Effects 0.000 description 2
- 229920000642 polymer Polymers 0.000 description 2
- 229920002635 polyurethane Polymers 0.000 description 2
- 238000004321 preservation Methods 0.000 description 2
- 239000002994 raw material Substances 0.000 description 2
- 238000011084 recovery Methods 0.000 description 2
- 230000008929 regeneration Effects 0.000 description 2
- 238000011069 regeneration method Methods 0.000 description 2
- 229920005989 resin Polymers 0.000 description 2
- 239000011347 resin Substances 0.000 description 2
- 239000007921 spray Substances 0.000 description 2
- 239000002699 waste material Substances 0.000 description 2
- 241000195493 Cryptophyta Species 0.000 description 1
- 102000004190 Enzymes Human genes 0.000 description 1
- 108090000790 Enzymes Proteins 0.000 description 1
- 238000006424 Flood reaction Methods 0.000 description 1
- 238000004458 analytical method Methods 0.000 description 1
- 239000010426 asphalt Substances 0.000 description 1
- 239000011230 binding agent Substances 0.000 description 1
- 230000000903 blocking effect Effects 0.000 description 1
- 239000011449 brick Substances 0.000 description 1
- 230000003139 buffering effect Effects 0.000 description 1
- 239000004566 building material Substances 0.000 description 1
- 230000002520 cambial effect Effects 0.000 description 1
- 238000006243 chemical reaction Methods 0.000 description 1
- CRQQGFGUEAVUIL-UHFFFAOYSA-N chlorothalonil Chemical compound ClC1=C(Cl)C(C#N)=C(Cl)C(C#N)=C1Cl CRQQGFGUEAVUIL-UHFFFAOYSA-N 0.000 description 1
- 238000004140 cleaning Methods 0.000 description 1
- 238000005056 compaction Methods 0.000 description 1
- 150000001875 compounds Chemical class 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 230000001627 detrimental effect Effects 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 230000018109 developmental process Effects 0.000 description 1
- 238000007599 discharging Methods 0.000 description 1
- 230000002500 effect on skin Effects 0.000 description 1
- 239000003623 enhancer Substances 0.000 description 1
- 230000007613 environmental effect Effects 0.000 description 1
- 238000000605 extraction Methods 0.000 description 1
- 239000000835 fiber Substances 0.000 description 1
- 239000003292 glue Substances 0.000 description 1
- 239000008187 granular material Substances 0.000 description 1
- 230000009545 invasion Effects 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 239000011159 matrix material Substances 0.000 description 1
- 238000005259 measurement Methods 0.000 description 1
- 238000002844 melting Methods 0.000 description 1
- 230000008018 melting Effects 0.000 description 1
- 238000012544 monitoring process Methods 0.000 description 1
- 239000011368 organic material Substances 0.000 description 1
- 238000005453 pelletization Methods 0.000 description 1
- 230000002093 peripheral effect Effects 0.000 description 1
- 239000011295 pitch Substances 0.000 description 1
- 229920000098 polyolefin Polymers 0.000 description 1
- 239000011148 porous material Substances 0.000 description 1
- 239000000843 powder Substances 0.000 description 1
- 238000002360 preparation method Methods 0.000 description 1
- 238000012545 processing Methods 0.000 description 1
- 230000008439 repair process Effects 0.000 description 1
- 230000000717 retained effect Effects 0.000 description 1
- 238000009666 routine test Methods 0.000 description 1
- 150000003839 salts Chemical class 0.000 description 1
- 238000007873 sieving Methods 0.000 description 1
- 238000002791 soaking Methods 0.000 description 1
- 241000894007 species Species 0.000 description 1
- 239000003381 stabilizer Substances 0.000 description 1
- 238000010561 standard procedure Methods 0.000 description 1
- 230000003068 static effect Effects 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
- 239000004094 surface-active agent Substances 0.000 description 1
- 238000003786 synthesis reaction Methods 0.000 description 1
- 238000010792 warming Methods 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C13/00—Pavings or foundations specially adapted for playgrounds or sports grounds; Drainage, irrigation or heating of sports grounds
- E01C13/08—Surfaces simulating grass ; Grass-grown sports grounds
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C13/00—Pavings or foundations specially adapted for playgrounds or sports grounds; Drainage, irrigation or heating of sports grounds
- E01C13/02—Foundations, e.g. with drainage or heating arrangements
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C23/00—Auxiliary devices or arrangements for constructing, repairing, reconditioning, or taking-up road or like surfaces
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C2201/00—Paving elements
- E01C2201/20—Drainage details
- E01C2201/202—Horizontal drainage channels
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Road Paving Structures (AREA)
Abstract
Sports ground has stable, impermeable substrate, is located at the moisture layer of cloth in substrate and the synthetic turf on moisture layer of cloth.Embankment limits the periphery of sports ground and the height of at least synthetic turf is extended to from substrate.Drainage channel is provided, it has entrance at the height to be connected with moisture layer of cloth, and to allow the water to enter drainage channel from water distribution laminar flow, vice versa.As the result of the construction, receiving area is formed with, it is limited by the embankment and substrate of surround movement.Water can be stored in the receiving area in moisture layer of cloth, so as to make water fade and cooling sports ground.
Description
Technical field
The present invention relates to sports ground, the particularly artificial sports field including artificial turf.The invention further relates to this
The building method and its water management of sports ground and cooling.
Background technology
Known various artificial and half artificial sports field's system.Half artificial court is usually directed to is incorporated into soil by artificial blade of grass
In base, conventional turf grass growth is allowed in the soil base.Other soil base and its draining are set can be with conventional natural grass
The similar appropriate growth to ensure natural grass in court.
Complete people pelletizing is from the Astroturf of the first generationTMFourth-generation system till now, it attempts will be natural
The functional and characteristic of turf is all bound in single product.In artificial court is laid, a primary demand is thereon
It is capable of the appropriate base of laying technology layer.The a big chunk for the overall cost newly installed can be to prepare base.This should be carried
The stabilization and draining level of guarantee are provided with, despite the fact that being that following earth's surface can have very big with the difference in touchdown point or area
It is different.
Another feature of artificial sports field is to be difficult to handle high temperature (such as in the presence of bright sunlight).The table of sports ground
Face temperature can be substantially increased during daytime, so as to change the characteristic of technology layer, even send niff.At these
Ratio grand sports meet under part is affected.Other sports grounds may require that irrigation before match can start.In all situations, water pipe
Reason be designer must design sports ground when the key problem to be taken into account.
Term " water management " refers to four main aspects, and these aspects are:Draining, is irrigated, storage and decay
(attenuation)。
Draining may be defined as draining into water into the EXIT POINT constructed away from sports ground from court region.Excessive water or surface
Waterflooding will have detrimental effect to games results, and can cause the movement of filler material.
Irrigation may be defined as that water is sent on turf surface by the system of pump, Pop-up water sprinkler and water cannon.Will
The purpose that water adds to surface can be a part for the match characteristic as surface, or to cool down turf surface.In sweltering heat
Sunlight conditions in, artificial grass turf system can be warming up to surface become it is uncomfortable and consumption sportsman energy degree.
Storage, which may be defined as providing, accommodates equipment, and the receiving equipment allows to discharge with used in such as court from court
Water in irrigation enters.It can be in the cistern of underground or the reservoir of ground.Storage is also connected with water fade.
Decay may be defined as interim in the reservoir of surface water in the appropriate cistern less than ground level or on the ground
Storage.The cistern or reservoir need with enough sizes to be contained in the runoff being computed of rainfall peak period.Then storage
The water deposited can gradually be released into the drainage system or water channel of combination in a controlled manner, so as to effectively reduce waterflooding
Risk.
Drainage system
The conventional drainage methodology of artificial grass turf system is based on two main methods.First is vertical process, another
It is then horizontal process.
Vertical process:There are many modifications and system under the title of vertical drainage, but general principle keeps constant, that is, is located at
The matrix or pattern of the antipriming pipe of the interconnection of porous ground mass construction bottom.Porous base tectonic sieving is into removing from superincumbent
The water that artificial grass turf system is permeated by the upper strata of porous stone base.Water is taken away playing area and made it into by these pipes
Annular main land drainage or similar drainage control system.
These courts can have the profile for helping water movement;This is referred to as slope or descending.The slope on ionized motion surface
There are various designs with descending, for example:Plus top formula, enclosed, and tilting etc..Angle downwards are intended to 0.4%
And between 1%.Porous ground mass it is a key issue that because the rock compaction amount that can be realized is limited, it is therefore desirable to porous ground mass
With minimum construction depth.The target of any base configuration is to reach to ensure that structure has appropriate structural intergrity and carrying
The a certain test value of ability.For example, a kind of industry standard methods for measuring these values are referred to as Californian Bearing
(CBR is always according to BS 1377-2 by Ratio:1990 define), it represents with percent value.For sports ground, after mounting
Standard target CBR values minimum 30%.In order to realize the value, bigger depth is must take into consideration for porous base construction.This be because
Include interstitial space for porous stone construction, so that water passes through structure.As a result, compared with equal non-porous base construction,
The bulk strength of the structure is not high, and rock has bigger mobility.
Presence of the water in porous stone construction also promotes the further stability of destruction stratum (formation) and causes ground
Layer is easily by frost heave.In order to solve these problems, according to local geology and weather conditions, porous ground mass generally has 300mm's
Minimum-depth.
Another problem is that needing the expensive rock type particularly matched somebody with somebody through level to produce porous basic unit.The rock comes freely
The raw material of truck transport.For 7500m2Standard multi-well court construction and 300mm minimum rock depth, it would be desirable to
2475m3Or 4200 tonnes of rock.20 tonnes can be delivered in view of the truck of standard, this will require about 200 truck loads.
In addition, in addition it is also necessary to the number of truck of extra 200 truck load come remove the subsoil both deposited so that its reset or landfill waste.
Not only cost is high but also effect on environment is also very big for the demand of this use of raw material and 400 times truck strokes.
Horizontal process:Described above, vertical drainage method is dependent on porous base construction is created, and the porous base, which is constructed, to be caused
Water is lower to following sports ground drainage with oozing by porous stone step.Horizontal process uses the limited or non-porous rock of porosity
Stone base is constructed, and does not have sports ground drainage below.General principle is the surface that water flows through artificial turf, flows through filler, and
Flow into some cases in damping mat substrate, the damping mat substrate causes water flatly to be flowed on rock base construction
It is dynamic.In being had a system and method which, court is designed to slope or descending (described above) ensure appropriate water
Stream.The water on outflow sports ground surface is then collected by the rhone or drainpipe installed around turf device periphery.These pipes
There is slope or descending water is moved into main land drainage or similar drainage control system for itself.
Such system is that possible reduce base configuration depth relative to the benefit that porous base is constructed, because these stratum are not
Need interstitial space and thus, it is possible to be compacted.The rock type can have wider particle size, so as to reduce extraction
Rock cost.It is also possible to regeneration aggregate is used in this base configuration form, such as regeneration brick, concrete, pitch
The aggregate of production.Because these surfaces are non-porous or porosity is limited, water is to the structure of basic unit almost without shadow
Ring and therefore limit frost heave and unstable effect.In some cases, it may be desirable to which impermeable lining is installed at the top of rock layers
Pad.Discharged in order that obtaining water from surface, will require that court has descending or slope.The slope can be in a direction or multiple
Constructed in a variety of ways on direction.The construction on this slope needs the technology of court builder, and influences the turf of completion
The ball operation conditions on surface.Further it is necessary to which mounting layer is to make water freely under the shifting of slope between turf and base configuration
To the drainage on periphery.The layer can be by certain form of beam and/or geotextile (geo-technical fabric)
To provide.
A kind of horizontal drainage method for sports ground proposes that it is using in impermeable table in WO2012138216
Porous ground (sub-grade) layer laid on face builds the edge that water is delivered to court by (course), the edge energy in court
It is enough to drain water by conventional drainage.Also propose use ground layer build as receiving area (containment), for example to
Competition Surface is recirculated to, as described below.
Irrigate
The irrigation system of standard depends on the water supplied from total pipeline, and it is pumped on court or around court
Water cannon or Pop-up water sprinkler.In some cases, the water collected from court drainage system is piped into storage to set
In standby and it is recycled back to by water cannon or Pop-up water sprinkler on court.Filter plant is also needed in this case.Water
Use as a part for turf system performance or be used as cooling during hot weather.For full-scale hockey
, 12000 to 18000 liters are may require that before match to soak the court.
All these methods depend on identical general principle, wherein water is applied to the top of turf system and water gradually
Discharged from turf structure.Water can not during indwelling is any on the spot or the long-term time limit, therefore its in terms of performance or cooling to grass
The influence of dermal system has limited short run effect.Because most of artificial turf fibres and filler are not inhaled nearly or completely
Performance is received, so water flows away simply by turf system.The method that water is applied by water cannon or water sprinkler be it is very poorly efficient,
Because the water applied much all just loses as steam before reaching the surface, and the accuracy that water cloth is put also is difficult to control
System.The cost of such system is also high, and is also had an impact to finance and environment using the water supplied directly from total pipeline.
Water is stored
If the requirement or legal obligation to engineering be reuse from court drainage system collect water, or if this
Water cannot directly enter the drainage system of locality, then the storage cistern or reservoir of ground or underground can be constructed near court.As above
Described, some designs will make it that the water collected is filled on the Competition Surface for field of returning serve.The cost for installing storage cistern or reservoir is high, and
And be must be arranged at around the region in court beside such construction.In many situations, solution is to dig huge hole and cover
Hide storage cistern.Additionally have problems that the water of preservation by microorganism and algae pollution.This can be eliminated to the water process
The invasion of sample, it is noted that monitoring and handling the water of the preservation.
Extreme at another, in the region of sinking rainfall, sustainable water storage or rainwater-collecting are the known habits of one kind
Used way.These methods include ground and roof collection, underground dykes and dams and the recharge of ground water.
Decay
Separate flow system system (SUDS) or low influence drainage system (LID) are a development concepts, and it is relevant
The decision-making of draining includes long-term environment and social factor.It considers the quality and quantity and surface water of runoff in city
Comfortable value in environment.Many existing sewerage systems, which can cause, to flood, pollutes or the problem of welding, not
It is proved to be sustainable.
Region more than building needs draining to remove surface water.Generally this is completed with underground piping system, described
Underground piping system is designed based on quantity, i.e., local flood is prevented by being as soon as possible transported away water.But, flow naturally
The change of pattern can result in the problem of catchmenting elsewhere.In addition, such as water in terms of also largely ignoring amenities
The facility of source, community's equipment, beautification of landscape possibility and various wild animals and plants habitats.
SUDS systems are designed to during torrential rain event and played afterwards aggregation, storage and the work for gradually discharging rainwater
With.Existing various types of city systems;From percolation well, multiple basements to open storage reservoir etc., all of which is set
Counting into ensures that the rainwater from non-porous surface such as road, roof and the aggregation of parking of automobile place is directed, stored, and then slow
Slowly discharged with controlled manageable flow velocity into drainage system.
The major defect of these systems is the fact that they need the city position for building shortage in.Due to sand, glue
The permeability formation at leisure such as native and thin dirt, so dependent on to preserve water and then make water slowly by ground seepage flow
System of the percolation well or level of dissipation with petrographic province is also easy to silt up.
The content of the invention
Sports ground is provided according to the present invention, it includes:Stable, impermeable substrate;It is located at the moisture layer of cloth in substrate;
Synthetic turf on moisture layer of cloth;Embankment, it limits the periphery of sports ground and extends at least synthetic turf from substrate
Height;And drainage channel, it has entrance at the height to be connected with moisture layer of cloth, so that water can be from water
Distribution layer flows into drainage channel, and vice versa.As the result of the construction, be formed with receiving area, its by surround movement dike
Bank and substrate are limited.Water can be stored in the receiving area in moisture layer of cloth.Because entrance and drainage channel are relative to water
The position of distribution layer, if so water level in drainage channel is less than the water level of moisture layer of cloth, enabling to water from receiving
Area flows into drainage channel.Or, if the water level in drainage channel is higher than the water level of moisture layer of cloth, water is enabled to from row
Aquaporin, which is flowed into, accommodates area.Therefore general-purpose system can be formed by accommodating area and drainage channel, and water is had no chance between both
Infilter or ooze out.In this context, although referring to entrance, it will be understood that water can flow through them in the two directions.Also not
Excluding water can be flowed into receiving area by one group of opening, and flow to drainage channel from area is accommodated by second group of opening.
Below, the sports ground of reference is intended to include any region of artificial turf, including but not limited to court, Game Zone
Domain, playing area etc..Preferably, the moving region competed and run in people thereon is present invention can be suitably applied to, but is not excluded for
The present invention could be applicable to animal movement or motor sport.In addition, artificial turf is not intended to the turf to any special species
(including turf with artificial filler, sand or without filler) is limited.
Embankment can be the stable, vertical edge of impermeable substrate.Or, embankment may be based on the only of this purpose installation
Vertical kerbstone.In one configuration, embankment may include the multiple kerbstone elements linked together, such as concrete curb.
Bank height should extend on the top of moisture layer of cloth, and wherein at least part turf is in area is accommodated.In an embodiment
In, embankment may extend to the whole height of turf, so that water level can rise to floods sports ground completely.Although concrete road
Edge is easily obtained and cheaply, but the fact that its upright whole height to turf can be produced and can be tripped the obstacle of sportsman.Dike
Bank can also be inclined upward to the height of turf from moisture layer of cloth, and can be by being surround on the ground of higher level height.Embankment
Top can be also circular or any other easily shape.As the confession alternative materials of concrete, embankment can be by plastic material such as
The plastics of recycling are made, and can be at least partly flexible to prevent player injuries.
Drainage channel can be in any position, so that it can be connected by entrance with moisture layer of cloth.Most preferred
In embodiment, drainage channel surround movement and with moisture layer of cloth in same level height.In further embodiment,
Drainage channel can be formed integrally with embankment.In one configuration, embankment may include to fit together to limit drainpipe
The hollow kerbstone element in road.
According to a preferred embodiment, sports ground may include water management equipment, and it is logical in draining that it is arranged to control water
Height in road.In this way it is possible to determine whether water from water distribution laminar flow enter drainage channel in or vice versa.It is any
To control the suitably-arranged of the water in drainage channel all to can be used, including pump, valve, buffering cistern etc..In an implementation
In scheme, the outlet of drainage channel may be connected to water management equipment, but emphasize again that the construction may be such that in the two directions
Flow through the outlet.
In order to provide the suitable control to the water level in area is accommodated, drainage channel can prolong below moisture layer of cloth and above
Stretch.In one configuration, water management equipment, which can have to overflow, is arranged to ensure that excessive water is unable to brimmed over its banks.This is in filler
Can be important in the case of being located in artificial turf, otherwise filler can be flushed away.
Stable, impermeable substrate can construct to realize the stabilization needed for target motion in any suitable manner
Property.Especially, the source that aggregate used can be from primary source or recycling, and it has of the 20mm to powder
Particle size.The aggregate that cement and/or similar reagents can be used to be included, so as to increase intensity, non-porous porosity and compacting value.
According to the importance of the present invention, stable, impermeable substrate may include stable soil base in situ.Soil
Stabilization technology is known generally in various backgrounds, but due to the non-porous property of the technology, soil stabilization is not in people
Used in the construction for making turf court.The combination and that the existing soil in original place can be used to represent is main in construction engineering
Cost and environmental protection and saving, are used to because need not excavate and remove material on-site or be transported to new graded material
Build the place of court ground.
In one embodiment, by soil stabilization at least 100mm depth, optionally to the depth for being more than 200mm,
And in preferred embodiments to about 300mm.As discussed above, the carrier of ideals ability of the base configuration of completion can be
CBR 30%.Depending on existing subsoil type and CBR values, in order to be sufficiently accurate it may be desired to which some subsoil are modified (i.e. less than base configuration).For example
With 4.5%CBR values or less than the value subsoil can need it is lime modified, and 5%CBR or higher than the value subsoil need not this
The modification of sample.15% CBR can be enough in some construction engineerings.
The stable soil base in original position can be through lime modified.Lime modified method is included a small amount of adhesive (quick lime)
Added to material of main part significantly to reduce moisture, thus by wet/inappropriate material be changed into 5%CBR can
With and the building material that can be compacted.Additionally or alternatively, it may include capping substitutable layer or base substitutable layer, wherein will be viscous
Mixture (quick lime and cement) and the water of addition are concomitantly introduced into material of main part.Then it can be compacted and repair the material, so as to stay
There is down required CBR layer.Although the preferable stabilization technology based on lime and cement, technical staff will fully realize
To other soil stabilization technologies according to local edaphic condition and in locality obtained by stabilizing agent and it is applicable.This
The reagent of sample may include enzyme, surfactant, natural and synthesis polymer, resin, salt and fiber enhancer.
In certain embodiments, stable, impermeable substrate may include impermeability film or coating.The film may include
Geotextile is padded.Suitable coating includes pitch, polymer, resin and cement.This is not to ooze in itself in base
Can especially it be applicable in the case of thoroughly.
According to embodiment, moisture layer of cloth has the depth between 10mm and 100mm, optionally about 40mm.For moisture
The total depth of layer of cloth selection may depend on factor quantity.Generally, moisture layer of cloth is deeper, then the receiving area below artificial turf
Volume is bigger and also will be bigger based on draining purpose flow area.
If sports ground is configured without the upside of the moisture layer of cloth between the gradient or runoff, T-ground and at court edge
Moisture layer of cloth downside between the effectively usable gradient by depending on the distance between the two places and moisture layer of cloth
Thickness.For the distance from Central Line to embankment is about 35m football pitch, about 100mm depth can provide improved row
Water.For less sports ground, smaller depth can be appropriate.It will also be appreciated that larger depth can also provide larger
Total receiving area, but it can also result in construction needs large volume of material.
According to the important advantage of the present invention, sports ground can be formed as being entirely horizontal.It will be understood that embankment is typically complete
It is complete horizontal, because its top edge will limit the limit that water can rise without brimmed over its banks dam.In addition, moisture layer of cloth
Upper surface also can basic horizontal.In this case, level is intended to indicate that its surface does not have obvious runoff.It is to be appreciated that
It is that its abswolute level and the uniformity depends greatly on the accuracy and careful property of placement.In an embodiment
In, the gradient that the upper surface of moisture layer of cloth has can be not more than 1/100 and optionally less than 1/300.Also may be used on 3 meters of straight flanges
It is shown as without the height change for being more than 10mm.
Substrate can also basic horizontal.In this case, the thickness of moisture layer of cloth can be constant on whole sports ground
's.It is much easier that manufacture level substrate ratio accurately provides desired slope in one or more directions.It also simplify with
The laying of lower moisture layer of cloth can use prefabricated elements formation distribution layer so that its level.
In a preferred embodiment of the invention, moisture layer of cloth includes the plastic grain and adhesive recycled.
Such construction is described (its content is by quoting overall be incorporated herein) in WO2012/138216, and can
Come easily to apply the construction using the special installation apparatus in sports ground and runway device.It is preferred that particle size can be with
For 0.5 to 20mm, although the particle in the range of 3mm to 8mm has provided good result.Also it is not excluded for using thin
Piece, rod, ball and elongated extrudate.Adhesive can apply to used in particle and suitable for intended applications and position
Any adhesive.It is preferred that adhesive include pitch, polyurethane or polyolefin-based adhesive, and they can in terms of particle,
Between 5 weight % and 40 weight %, preferably to exist between 15% and 25%, and in one embodiment with about 20%
In the presence of.Moisture layer of cloth can also be according to described in EP1603725 method formed, which part melting waste plastic particles welded
It is connected together to form porous layer.This method can be particularly suitable for use in preformed layer, although be not excluded for its can also original position use.
Moisture layer of cloth can also include other components, particularly other particles.Especially, rubber or rock particles can be with
Up to 50 weight %, even up to 70 weight % are included in final mixture, to adjust the technical performance of this layer.In addition,
Moisture layer of cloth can include multiple sublayers (sub-layer) with different performance.This can in particular moisture layer of cloth be most
Top is used as the performance layer with required damping and energy recovery value.
According to the present invention, moisture layer of cloth can be configured to have between 20% and 70%, optionally about 45% space
Rate.For 7500m2The court of mean size and for pore volume for 45% moisture layer of cloth for, 40mm thickness degree is suitable
In 18 liters every square metre or the moisture storage capacity in 135000 liters of whole court, it does not include the overhead provision of drainage channel.Voidage
It can be adjusted by following:Change the size and dimension of cambial particle or particle and change the application in preparation process
Pressure.Moisture layer of cloth can have in 300Kg/m3And 700Kg/m3Between, preferably in 400Kg/m3And 600Kg/m3Between,
Most preferably from about 500Kg/m3Specific density.
Moisture layer of cloth can be set to the engineering property according to target motion or the intensity and modulus of activity.This will also take
Certainly in above-mentioned synthetic turf and the property of any other performance layer.In certain embodiments, moisture layer of cloth will have effective
Rigidity, wherein providing main damping by the performance layer on moisture layer of cloth for sportsman.According to one of the present invention
Embodiment, the Young's modulus under compression of moisture layer of cloth can be more than 0.1MPa, alternatively more than 1MPa, and one
2MPa can be more than in individual embodiment.Generally, Young's modulus under compression will be less than 50MPa, alternatively be less than
10MPa, and it is less than 5MPa in one embodiment.In other embodiments, sports ground can also include being arranged on moisture
Elastic layer between layer of cloth and synthetic turf.
The invention further relates to the method for tectonic movement, it includes:Stable, impermeable substrate is provided;Above carried in substrate
Water supply distribution layer;Synthetic turf is installed on moisture layer of cloth;Form embankment, the embankment limit the periphery of sports ground and from
Substrate extends to the height of at least synthetic turf;And the drainage channel connected with moisture layer of cloth is provided, so that water energy
Enough to enter drainage channel from water distribution laminar flow, vice versa.
Substrate can meet stability and the existing substrate of tonicity requirements.This substrate can include brown area
Place, it includes concrete and asphalt surface.Or, substrate can pass through any routine side using the material for being input to place
Method is such as formed in the soil stabilization of above-described existing on-site soil.The stability of substrate can be at least
CBR 15%, if can preferably proceed at least 100mm depth using the soil stabilization of existing soil come stabilization
Degree.
According to further aspect, the present invention, which can be included on stable base, provides impermeability film or coating with true
Permeability needed for protecting.It will be understood that the absolute impermeability of substrate can be non-key, and it is used for the purpose of avoiding water
Oozed out from area is accommodated.In some cases, such as roof arena, absolute impermeability can be required.
Laying in situ can be included in one embodiment there is provided the method for moisture layer of cloth as also described above and include recovery
The plastic grain and the semi-fluid substance of adhesive utilized, makes semi-fluid substance levelling, and cause semi-fluid substance solidification with shape
Into Rigid Porous layer.This method can use the conventional laydown machine of the type for road or moving surface to carry out.
It can include with pre-formed many of the plastic grain by recycling there is provided moisture layer of cloth in an alternate embodiment
Orifice plate lays substrate.The plate can be made in controlled technique outside place, wherein the performance carefully determined can be realized
Feature.The plate can be provided with blocking element and can also adhere to or be otherwise fixedly secured to substrate.
In one embodiment, forming the method for embankment can include installing hollow kerbstone, make its end-to-end company
Connect to form complete drainage channel.It is also contemplated that can install the drainage channel of continuous length to form dike around sports ground
Bank.
The invention further relates to cool down the method for sports ground, the sports ground is included in the porous water in impermeability receiving area
Synthetic turf on distribution layer, methods described, which is included in the whole region of sports ground, will accommodate area with water and fill to being enough to soak
No the depth of at least part synthetic turf, does not then discharge water from area is accommodated.Water can be discharged partly, and reaching to use
Sports ground and the level for possessing water in receiving area simultaneously.Or, water can be fully drained., can be with by soaking sports ground
Match characteristic is improved, and additionally is able to carry out direct evaporating-cooling court.
In preferred embodiments, turf can from following wetted, the water level wherein in moisture layer of cloth rise until
Turf is partially or completely submerged.Additional wicking device can be included in moisture layer of cloth or divot in or at them it
Between, to promote to deliver water into surface.The irrigation carried out by this way from below avoids using spray thrower and nozzle, these sprays
Drench device and nozzle generally only part effectively and need will be higher than groundwater condition microorganism cleaning level.Can by
The entrance connected between moisture layer of cloth and drainage channel introduces and removed water.
The invention further relates to the method for making water decay in sports ground, the sports ground is included in impermeability and accommodated in area
Porous moisture layer of cloth on synthetic turf, methods described, which is included in the Pluvial, rainfall and almost not to be had accommodating to collect in area
Rain controls the discharge from area is accommodated during not raining.Collected water can be the rain fallen on sports ground, but may be used also
To be the water fallen on peripheral region, can by the drainage channel that is connected with moisture layer of cloth by the water supply to accommodating area.
Brief description of the drawings
By reference to the following drawings of multiple exemplaries, it is to be understood that the features and advantages of the present invention, wherein:
Fig. 1 shows the sectional view of a part for the sports ground according to the present invention;And
Fig. 2 is showing along line II-II through the cross section of Fig. 1 sports ground, and it shows water management system.
Embodiment
Embodiment
Fig. 1 shows the schematic section of a part for sports ground 1 according to embodiments of the present invention.Sports ground 1 includes three
Main layer, i.e. substrate 2, moisture layer of cloth 4 and synthetic turf 6.It is overall to be surrounded by embankment 8.
Substrate 2 is the soil stabilization layer that depth is 300mm, as will be described below.Substrate 2 is natural soil layer below
10, it is existed in behind embankment 8.Bituminous coating 12 is provided with the upper surface of substrate 2, it can seal base impermeablely
Go directly embankment 8 at bottom 2.
Moisture layer of cloth 4 is the thick layers of 40mm, and there are 50 weight % of the plastic grain recycled and rubber grain to mix for it
Compound, the mixture and polyurethane binder of the 14 weight % presence with total are combined together.The layer of gained has about
45% voidage.
Artificial turf 6 is the third generation turf of earliest flocking, and it has 60mm suede height and with Total Turf
60XQ is from Tiger TurfTMThe rubber and sand filler of acquisition.
Embankment 8 is formed by the hollow kerbstone 14 of interlocking provided with drainage channel 16 and entrance 18.Kerbstone 14 has 600mm
Depth, and entrance 18 is the groove that multiple length are 50mm, and it is extended to below the top of embankment 8 at 100mm.Kerbstone 14
It is arranged in concrete haunch of arch 20, and it is sealed against one another by clay pearl 22.Substrate 2 and embankment 8 are formed together with drainage channel 16
Area 24 is accommodated, the receiving area 24 is largely impermeability and can keep water for quite a long time.Draining
Passage 16 is connected to water management equipment 26, and the water management equipment 26 controls flowing in and out from receiving area 24.
The line II-II that Fig. 2 is showing along in Fig. 1 passes through the cross section of sports ground 1, and it shows substrate 2, moisture layer of cloth 4, people
Make lawn layer 6 and kerbstone 14.Fig. 2 also show water management equipment 26, and the water management equipment 26 includes room 28, and it, which is connected to, comes
From the outlet 30 of drainage channel 16.It will be understood that, although showing single outlet 30, the periphery around sports ground 1 may have
Multiple such outlets 30, it is connected to room 28 by annular drainage etc..Room 28 is also connected to heavy rain by valve stream door 32 and arranged
Water system 34.In addition, feed pipe 36 is attached to the top side of room 28.In the embodiment shown, the feed pipe 36 passes through stop cock
38 are connected to total pipeline or another water source (such as recirculated water).It will be understood that, feed pipe 36 may be coupled to any suitable water source
(such as recirculated water), and pump installation rather than stop cock can be provided.Controller 40 ensures control valve stream door 32 and stopped
Cock 38, they can be automatically or manually controlled.
Install
The installation of sports ground 1 from place by going the existing top layer of screefing and organic material to carry out first.Then divide
Subsoil 10 is analysed with the soil stabilization methods needed for determination.In the embodiment shown, soil is heavier clay.In order that this
Antecedent soil moisture and granulating, it is mixed with the lime of doses to 300mm depth.This method uses Wirtgen
The integrated blenders of WR2500SK are carried out, to ensure that mixed layer is consistent on mixing quality and layer depth.First
After phase process, then the region is rolled by laser flattening bulldozer leveling with 20 tons of rollers.Then by the region indwelling
Overnight, so that occurring the chemical reaction between lime and soil.
In the second stage of soil stabilization, cement and water are introduced with the amount determined by analysis, material is bonded to produce waterpower
Material.Reuse the precise volume of Wirtgen blenders, the wherein water needed for the apparatus control and cement.From the tank in machine
Cement is conveyed, while supplying water from the supply (browser) before machine.Again by the depth of soil treatment to 300mm.
During this, the sample of routine test mixing material, to check whether the material shows as expected.It is mixed in soil
Afterwards, laser flattening bulldozer again by material be classified and leveling to relative to 3 meters of straight flanges+- 10mm superficial tolerance, and 20 tons
Roller is compacted the surface.After completion, in order to seal the completion surface of substrate 2, bituminous coating 12 is sprayed to it.
After 3 days, the surface of substrate 2 has following result in the CBR of 4 position measurements:
Position 1-64%
Position 2-30.8%
Position 3-30.1%
Position 4-37%
After processing 4-7 days, substrate 2 is particularly stable, carries jumbo, have no effect the vehicle that can pass through.
The CBR levels of whole surface evaluation are about 60%.
In order to install kerbstone 14, substrate 2 agilely is cut to before embankment 8 with 75mm gap using annular saw.
Then kerbstone 14 is engaged with each other with clay pearl 22, to ensure waterproof seal.Once installing and fixing kerbstone 14, then spread
If moisture layer of cloth 4.First, plastic grain is measured with equal amount using with the SMG MixMatic M6008 of additional hopper
Fed with rubber grain with the PU that these particles are added to 14 weight %.Then SMG PlanoMatic P936 are used by the area
Domain is laid to 40mm depth, and with every m2The region is laid for 20kg mixing materials and the ratio of 2.8kgPU adhesives.Paving
If the final superficial tolerance of layer is+- 10mm on 3 meters of straight flanges.After moisture layer of cloth 4 is solidified 48 hours, Deltec is usedTM
Bat tester tests the layer.The average result of 10 test positions is as follows:
● power reduces -50.2%
● areal deformation -5.4mm
● energy recovers -35.8%
Once moisture layer of cloth 4 is fully cured, then turf 6 is installed in a usual manner, and filled with rubber grain and sand
Mixture.Turf 6 is laid up to the embankment 8 on all sides and laid to same level.
Strain testing
Laboratory strain survey is carried out with the sample of the moisture layer of cloth 4 of explanation manufacture same as the previously described embodiments under compression
Try to determine its Young's modulus.Sample size is 250 square millimeters, and nominal thickness is 40mm.The nominal density of sample is
520kg/m3.Using Instron compressors, the ability of its load unit is 10kN.Load board is:100mm top compression plates,
300mm bottoms compression plate.
Test program is as follows:
1. compression speed is set as 5 mm/mins.
2. apply 50N small bases load (seating load) to sample when testing and starting to ensure good contact,
And deformation gauge is set as 0mm.
3. sample is subjected to false static load circulation twice.Maintenance load (creep) test is assessed using other circulation
Effect.
A. by sample compression until 2500N default load.Then load is removed, checks sample either with or without any damage mark
As.
B. by sample compression until 5000N default load.Then load is removed, checks sample either with or without any damage mark
As.
C. by the default load of sample compression to 2500N, and the time kept for 7 hours will be loaded.
4. sample is observed during compressing and load and deformational behavior in real time is observed.
Vertical strain under 2500N is evaluated as about 10%.Power and the gradient of deformation curve allow sample (spring) rigidity
Evaluation in the range of 600kN/m.Stress/strain as shown by data (elasticity) rigidity module is about 3.2MPa.
The test is repeated with the thick samples of the 24mm with preceding sample same composition.It has 490Kg/m3It is nominal
Density.Vertical strain under 2500N is about 17%, and the gradient of power and deformation curve allows the evaluation of sample (spring) rigidity to exist
In the range of 570kN/m.Stress/strain as shown by data (elasticity) rigidity module is about 2MPa.
Operation
The operation of sports ground 1 is described referring now to Fig. 1 and Fig. 2.In use, the rainwater on sports ground 1 is fallen
Penetrated into by synthetic turf 6 in moisture layer of cloth 4.The horizontal plane of substrate 2 allows water distribution in whole sports ground 1, by water
Capillarity and its open architecture auxiliary in distribution layer 4.Entrance 18 to drainage channel 16 is located at the upper surface of base material 2
Bituminous coating 12 height at, and allow water to escape into drainage channel 16, it can be flow to by outlet 30 from here
Room 28, then flow to storm drain systems 34 by valve stream door 32.If desired, can shutoff valve stream door, its reclaimed water will be in row
It is standby in aquaporin 16, until it reaches the level height of entrance 18.Any further rainfall will be retained in receiving area 24.
The predeterminated level height that can be maintained at water level in moisture layer of cloth 4 with control valve stream door 32, or can be set to slow
Slowly water is discharged into storm drain systems 34 to allow decay.
In warm period, extra water can be introduced into water management equipment 26 by feed pipe 36, so as to accommodate area 24
In water level be increased in the level height of moisture layer of cloth 4.By increasing water level completely or partially to flood synthetic turf
6, sports ground 1 can be cooled rapidly.Then the motion specified is made it possible to achieve from accommodating the discharge water of area 24, and artificial turf
Layer 6 can continue to evaporate moisture, so as to keep the cooling of sports ground 1.Although it should be noted that not shown in the design, water pipe
Reason equipment 26 can be provided with buffer container, so that allow the part of sports ground 1 to be filled and empty before match starts,
The buffer container is with the capacity or the part receiving area size at least above moisture layer of cloth 4 for being equal to receiving area's size
Capacity.
Therefore, the present invention is described by reference to above-mentioned some embodiments.It will be recognized that these embodiments can have
Well known to a person skilled in the art various modifications and substitutions forms.Especially, the arrangement and its design of base construction can be based on
Local geological conditions and available material.The thickness and ratio of the granular materials of moisture layer of cloth, kerbstone size and dimension, row
Water hole frequency, size and dimension, water inlet and exit point decay and water flow velocity, and water input and extracting device can all depend on
In performance requirement, it is possible to different from the design schematically illustrated.
Without departing from the spirit and scope of the invention, can also be to structure as described herein in addition to those described above
Much changed with technology.Therefore, although specific embodiment has been described, but these are only examples, it is not intended to limit this
The scope of invention.
Claims (22)
1. a kind of sports ground, it includes:
Stable, impermeable substrate;
It is located at the moisture layer of cloth in substrate;
Synthetic turf on moisture layer of cloth;
Embankment, the embankment limits the periphery of sports ground and the height of at least synthetic turf is extended to from substrate;And
Drainage channel, the drainage channel has entrance at the height to be connected with moisture layer of cloth, with allow the water to from
Water distribution laminar flow enters drainage channel, and vice versa.
2. sports ground according to claim 1, wherein drainage channel are integrally formed by embankment.
3. the sports ground according to claim 1 or claim 2, it further comprises water management equipment, the water management
Be arranged to control height of the water in drainage channel, with determine whether water from water distribution laminar flow enter drainage channel in or it is anti-
It is as the same.
4. sports ground according to any one of the preceding claims, wherein drainage channel are below moisture layer of cloth and above
Extension.
5. sports ground according to any one of the preceding claims, wherein stable, impermeable substrate includes stabilization
Soil base.
6. sports ground according to any one of the preceding claims, wherein stable, impermeable substrate is including impermeable
Property film or coating.
7. the upper surface basic horizontal of sports ground according to any one of the preceding claims, wherein moisture layer of cloth, preferably
What is had is in easy flights in 1/100 and optionally less than 1/300.
8. sports ground according to any one of the preceding claims, wherein moisture layer of cloth include the plastic grain recycled
And adhesive.
9. sports ground according to any one of the preceding claims, wherein moisture layer of cloth have between 20% and 70%,
Optionally about 45% voidage.
10. sports ground according to any one of the preceding claims, wherein moisture layer of cloth have 10mm and 100mm it
Between, optionally about 40mm depth.
11. the Young's modulus under compression of sports ground according to any one of the preceding claims, wherein moisture layer of cloth
Between 0.1MPa and 50MPa, preferably between 1MPa and 10MPa, more preferably between 2MPa and 5MPa.
12. sports ground according to any one of the preceding claims, it further comprises being arranged on moisture layer of cloth and artificial
Elastic layer between divot.
13. at least upper end of sports ground according to any one of the preceding claims, wherein embankment includes elastomeric material.
14. a kind of method of tectonic movement, it includes:
Stable, impermeable substrate is provided;
Moisture layer of cloth in substrate is provided;
Synthetic turf is installed on moisture layer of cloth;
Embankment is formed, the embankment limits the periphery of sports ground and the height of at least synthetic turf is extended to from substrate;With
And
The drainage channel connected with moisture layer of cloth is provided, so that water can enter drainage channel from water distribution laminar flow, otherwise also
So.
15. method according to claim 14, wherein providing substrate is included existing on-site soil stabilization to more than 15
CBR and preferably at least 100mm depth.
16. the method according to claims 14 or 15, provides impermeable wherein forming substrate and being included on stable base
Property film or coating.
17. the method according to any one of claim 14 to 16, is included wherein providing moisture layer of cloth and including laying in situ
The plastic grain of recycling and the semi-fluid substance of adhesive, make semi-fluid substance levelling, and cause semi-fluid substance solidification
To form Rigid Porous layer.
18. the method according to any one of claim 14 to 16, wherein providing moisture layer of cloth is included with by recycling
Plastic grain pre-formed porous plate lay substrate.
19. the method according to any one of claim 14 to 18, wherein forming embankment includes installing hollow kerbstone, from
And form complete drainage channel.
20. a kind of method for cooling down sports ground, the sports ground is included on the porous moisture layer of cloth that impermeability is accommodated in area
Synthetic turf, methods described, which is included in the whole region of sports ground, will accommodate area with water and fill to being enough to submerge at least portion
Divide the depth of synthetic turf, then discharge water from area is accommodated.
21. a kind of make the method that water is decayed in sports ground, the sports ground is included in the porous water in impermeability receiving area
Synthetic turf on distribution layer, methods described is included in the Pluvial and rainfall and is not raining or almost do not having accommodating to collect in area
The discharge from area is accommodated is controlled during rain.
22. the method according to claim 20 or claim 21, wherein sports ground are to appoint according in claim 1 to 13
Sports ground described in one, or, sports ground according to the method any one of claim 14 to 19 by constructing.
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
PCT/NL2014/050896 WO2016099253A1 (en) | 2014-12-19 | 2014-12-19 | Sports field construction |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107208384A true CN107208384A (en) | 2017-09-26 |
Family
ID=52339260
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201480084557.6A Pending CN107208384A (en) | 2014-12-19 | 2014-12-19 | Sports ground is constructed |
Country Status (7)
Country | Link |
---|---|
US (1) | US10385520B2 (en) |
EP (1) | EP3234262B1 (en) |
CN (1) | CN107208384A (en) |
AU (1) | AU2014414156B2 (en) |
DK (1) | DK3234262T3 (en) |
ES (1) | ES2767374T3 (en) |
WO (1) | WO2016099253A1 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113330161A (en) * | 2018-11-20 | 2021-08-31 | 荷兰蓝色世界有限公司 | Sports field and method for forming and operating a sports field |
Families Citing this family (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US10130089B2 (en) | 2014-07-24 | 2018-11-20 | Live Holdings LLC | Fishing caddy system and method |
NL2014271B1 (en) * | 2015-02-10 | 2016-10-13 | Desso Sports B V | Substructure for an artificial grass field. |
NL2014621B1 (en) | 2015-04-13 | 2017-01-20 | Ten Cate Thiolon Bv | Modular Structure For Installing An Artificial Playing Field. |
EP3495555B1 (en) * | 2017-12-07 | 2020-12-16 | Advanced Polymer Technology Corp. | Method for manufacturing an artificial turf system and such a system |
CN109183555B (en) * | 2018-10-29 | 2024-10-01 | 江苏摩高建设科技有限公司 | Prefabricated plastic ground layer and construction method thereof |
PT116117B (en) * | 2020-02-17 | 2023-06-05 | Amorim Cork Composites S A | RECREATIONAL PAVEMENT CONSTRUCTION PROCESS |
CN111424495B (en) * | 2020-04-21 | 2024-10-22 | 中国电建集团成都勘测设计研究院有限公司 | Integrated curb double-filtering drainage device and construction method |
GB202308158D0 (en) * | 2023-05-31 | 2023-07-12 | Flushu Ltd | Water management system |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0373282A1 (en) * | 1988-12-13 | 1990-06-20 | "H.R.B. Chemie Hiroba Belgium" | Process for constructing and keeping up a terrain, particularly a sports ground, and terrain constructed according to this process |
CN2635719Y (en) * | 2003-06-02 | 2004-08-25 | 谢昌德 | Artificial lawn sports field structure with permeability and elasticity |
CN202925421U (en) * | 2012-10-29 | 2013-05-08 | 国家体育总局体育科学研究所 | Ventilating, temperature control and water circulation system for playground lawn |
NL2009968C2 (en) * | 2012-12-12 | 2014-06-16 | Oranjewoud Realisatie B V | BASIC CONSTRUCTION FOR AN ARTIFICIAL GRASS FIELD, SPORTS FIELD PROVIDED THEREOF AND METHOD FOR THIS. |
CN103924497A (en) * | 2014-04-17 | 2014-07-16 | 大连德合东马市政工程有限公司 | Football field with permeable, water-holding and fertilizer-retaining granular structured soil |
Family Cites Families (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3418897A (en) * | 1967-06-12 | 1968-12-31 | Robert A.R. Humalainen | Artificial playing surface |
GB2352954B (en) | 1999-08-04 | 2003-11-05 | Charles Lawrence Surfaces Plc | Playing field with integrated irrigation and recycling system |
US20030092531A1 (en) * | 2001-11-09 | 2003-05-15 | Daluise Daniel A. | Vertical to horizontal draining synthetic turf |
GB2399532B (en) | 2003-03-19 | 2007-10-24 | Econoplas Ltd | Method of manufacturing drainage/irrigation elements from recycled plastics |
US7758749B2 (en) * | 2006-06-21 | 2010-07-20 | General Sports Venue Llc | Drainage filtration system for synthetic turf field |
KR101675109B1 (en) * | 2010-08-06 | 2016-11-11 | 삼성전자주식회사 | Enhanced luminescence light emitting device usiung surface plasmon resonance and method of fabricating the same |
CZ22210U1 (en) * | 2010-12-27 | 2011-05-16 | TENNIS Zlín, a. s. | Building system of external sports ground surface covered with synthetic grass |
FR2971797B1 (en) * | 2011-02-21 | 2014-03-28 | Travaux Et D Amenagements Regionaux Soc D | DEVICE FOR STABILIZING POROUS SOIL |
GB201105755D0 (en) | 2011-04-05 | 2011-05-18 | Ten Cate Thiolon Bv | ATP base construction |
US9267243B2 (en) * | 2011-06-20 | 2016-02-23 | John E. Kreikemeier | Surface and sub-surface drain system |
-
2014
- 2014-12-19 EP EP14825195.2A patent/EP3234262B1/en active Active
- 2014-12-19 ES ES14825195T patent/ES2767374T3/en active Active
- 2014-12-19 DK DK14825195.2T patent/DK3234262T3/en active
- 2014-12-19 US US15/537,469 patent/US10385520B2/en active Active
- 2014-12-19 WO PCT/NL2014/050896 patent/WO2016099253A1/en active Application Filing
- 2014-12-19 AU AU2014414156A patent/AU2014414156B2/en active Active
- 2014-12-19 CN CN201480084557.6A patent/CN107208384A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0373282A1 (en) * | 1988-12-13 | 1990-06-20 | "H.R.B. Chemie Hiroba Belgium" | Process for constructing and keeping up a terrain, particularly a sports ground, and terrain constructed according to this process |
CN2635719Y (en) * | 2003-06-02 | 2004-08-25 | 谢昌德 | Artificial lawn sports field structure with permeability and elasticity |
CN202925421U (en) * | 2012-10-29 | 2013-05-08 | 国家体育总局体育科学研究所 | Ventilating, temperature control and water circulation system for playground lawn |
NL2009968C2 (en) * | 2012-12-12 | 2014-06-16 | Oranjewoud Realisatie B V | BASIC CONSTRUCTION FOR AN ARTIFICIAL GRASS FIELD, SPORTS FIELD PROVIDED THEREOF AND METHOD FOR THIS. |
CN103924497A (en) * | 2014-04-17 | 2014-07-16 | 大连德合东马市政工程有限公司 | Football field with permeable, water-holding and fertilizer-retaining granular structured soil |
Non-Patent Citations (1)
Title |
---|
张汝栋: "《体育设施建设指南》", 31 March 2005, 人民体育出版社 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113330161A (en) * | 2018-11-20 | 2021-08-31 | 荷兰蓝色世界有限公司 | Sports field and method for forming and operating a sports field |
CN113330161B (en) * | 2018-11-20 | 2023-08-18 | 荷兰蓝色世界有限公司 | Playground and method for forming and operating a playground |
Also Published As
Publication number | Publication date |
---|---|
DK3234262T3 (en) | 2020-02-03 |
ES2767374T3 (en) | 2020-06-17 |
US20170328017A1 (en) | 2017-11-16 |
EP3234262B1 (en) | 2019-11-06 |
US10385520B2 (en) | 2019-08-20 |
AU2014414156A1 (en) | 2017-08-10 |
EP3234262A1 (en) | 2017-10-25 |
AU2014414156B2 (en) | 2020-07-23 |
NZ733868A (en) | 2021-09-24 |
WO2016099253A1 (en) | 2016-06-23 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107208384A (en) | Sports ground is constructed | |
CN106759126B (en) | Construction method of side slope support drainage channel | |
CN1566534A (en) | Environmental protection permeable pavement construction method | |
CN109989474A (en) | A kind of construction method of rain water collecting system | |
KR100966468B1 (en) | The water run-through-base combine armature mat with invisible water punctured pipe`s construction process | |
JP2009235760A (en) | Soil material for covering bank back slope surface, and covering method using the soil material | |
CN112663760A (en) | LID measure-based urban rainwater runoff regulation and control method | |
CN205999746U (en) | A kind of permeable plastic cement race track | |
CN111549603A (en) | Pavement considering water load coupling and construction method thereof | |
Amirjani | Clogging of permeable pavements in semi-arid areas | |
KR100966473B1 (en) | Structure of invisible waterway and construction method thereof including punctured pipes | |
RU2746485C1 (en) | Method of protecting slopes from water erosion | |
CN103015289A (en) | Environmental-protection water-permeation and gas exhaust artificial sport ground and supporting curing water-permeation layer construction method thereof | |
KR100716191B1 (en) | Reclaimed type infiltration facilities containing lightweight aggregate | |
NZ733868B2 (en) | Sports field construction | |
CN220057515U (en) | Road pavement structure | |
CN111395098B (en) | Water collecting structure of priority flow channel | |
Joodi et al. | Design of check dam for effective utilization of the Aflaj water resources | |
CN114197605B (en) | Water-saving rainwater wetting pond and construction method | |
RU2374381C2 (en) | Method for making road carpet | |
Shen et al. | A physical model demonstrating critical zone structure and flow processes in headwaters | |
CN118704495A (en) | Capillary blocking type expansion rock-soil slope ecological protection system | |
Chen | Maintenance and improvement in the ecological environment of the island: The design and application in high bearing structure pervious pavement | |
Ahmed et al. | RAINFALL INTENSITY EFFECTS ON Flexible PAVEMENT LAYERS | |
Pennington | London 2012 legacy: design and reuse of temporary equestrian platforms |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20170926 |