CN107165468A - 一种电网电线杆加固加高装置的施工方法 - Google Patents
一种电网电线杆加固加高装置的施工方法 Download PDFInfo
- Publication number
- CN107165468A CN107165468A CN201710583115.1A CN201710583115A CN107165468A CN 107165468 A CN107165468 A CN 107165468A CN 201710583115 A CN201710583115 A CN 201710583115A CN 107165468 A CN107165468 A CN 107165468A
- Authority
- CN
- China
- Prior art keywords
- electric pole
- clip slot
- bracing means
- laid
- construction method
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H12/00—Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
- E04H12/34—Arrangements for erecting or lowering towers, masts, poles, chimney stacks, or the like
- E04H12/344—Arrangements for lifting tower sections for placing additional sections under them
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G23/00—Working measures on existing buildings
- E04G23/02—Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
- E04G23/0266—Enlarging
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H12/00—Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
- E04H12/02—Structures made of specified materials
- E04H12/12—Structures made of specified materials of concrete or other stone-like material, with or without internal or external reinforcements, e.g. with metal coverings, with permanent form elements
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H12/00—Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
- E04H12/20—Side-supporting means therefor, e.g. using guy ropes or struts
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Chemical & Material Sciences (AREA)
- Chemical Kinetics & Catalysis (AREA)
- Mechanical Engineering (AREA)
- Electrochemistry (AREA)
- Life Sciences & Earth Sciences (AREA)
- Materials Engineering (AREA)
- Wood Science & Technology (AREA)
- Electric Cable Installation (AREA)
- Suspension Of Electric Lines Or Cables (AREA)
- Foundations (AREA)
Abstract
本发明公开了一种电网电线杆加固加高装置的施工方法,包括抱箍装置和加固装置,其特征在于,所述加固装置均布布设在电线杆四周,加固装置包括支架,所述支架一面均布设有长销穿过电线杆,另一面设有夹槽,夹槽内布设有底部埋入泥土内的圆杆,夹箍通过紧固件将圆杆锁紧在夹槽上;本发明的有益效果:该装置及其施工方法在加固电线杆时,使用方便,节省人力,特别适合泥土质量差,冻土,还有台风,暴雨等气候恶劣的地区使用,实用性强,适合推广使用。
Description
技术领域
本发明涉及一种电力电网施工装置,具体涉及一种电网电线杆加固加高装置及其施工方法,属于电力施工技术领域。
背景技术
电力工程,即与电能的生产、输送、分配有关的工程,广义上还包括把电作为动力和能源在多种领域中应用的工程。
如一申请号为CN204098593U公开了一种老旧水泥电线杆加固装置,其特征在于:由纵向加固板、横向连接杆及外护板构成,在所述纵向加固板的板体中部制有外护板安装孔,所述的外护板通过螺钉将其安装于两两纵向加固板之间,在所述纵向加固板的两端还对称制有可调连接孔,该可调连接孔由2-4个相连通的连接孔构成,两两纵向加固板间通过该可调连接孔穿装有横向连接杆,在连接杆的两端通过螺母固位。本实用新型结构设计科学合理,具有结构简单、方便操作、杜绝老旧电线杆安全隐患、所需维修成本低、易于实现的优点,是一种具有较高创新性的老旧水泥电线杆加固装置。
又如一申请号为CN203393738U公开了一种免拉线的电线杆固定结构及固定基础,它包括电线杆,电线杆的根部设置有固定基础,固定基础为上端大下端小且纵截面呈梯形状的结构,固定基础的中心设置有固定槽,电线杆的根部插接在固定槽内;本实用新型的电杆固定结构通过对现有固定结构的改进,在电线杆的根部设置固定基础,固定基础的上端小下端大,这样就增加了电线杆根部与土地的接触面积,增加了电线杆架设后的稳定性,使电线杆的受外力能力与设置拉线或者钢结构杆塔的电线杆相同,具有结构简单、便于施工、成本低廉、美观实用、占地面积小且安全系数高的优点。
近年来,随着我国农村电网改造和移动通讯建设的进行,水泥电线杆的生产和应用得到了迅速的发展。然而,现有的电线杆有部分已经不能满足与房屋间的安全使用距离,造成安全隐患,这时就需要改造,但整体更换不仅成本高,而且影响居民正常生活,所以提出了加高电线杆的要求。
同时,近几年我国南方的气候条件变的恶劣,时而台风,暴雨等。这时需重视安全用电,就需要保证电线杆的稳定,因此也有了加固电线杆的需求。
发明内容
本发明克服了现有技术存在的问题,提出了一种电网电线杆加固加高装置及其施工方法,该装置及其施工方法特别适合泥土质量差,冻土,还有台风,暴雨等气候恶劣的地区使用,同时也能用来加高电线杆,确保电网设施运转正常。
本发明的具体技术方案如下:
一种电网电线杆加固加高装置,包括抱箍装置和加固装置,其特征在于,所述加固装置均布布设在电线杆四周,加固装置包括支架,所述支架一面均布设有长销穿过电线杆,另一面设有夹槽,夹槽内布设有底部埋入泥土内的圆杆,夹箍通过紧固件将圆杆锁紧在夹槽上;所述支架与电线杆抱紧接触处贴有橡胶垫,支架内部设有橡胶填充层。
所述抱箍装置包括套在电线杆上的圈套,所述圈套上设有紧固片,构件和连接片通过锁紧螺栓固定在紧固片上,所述构件内夹有斜加强杆,所述斜加强杆一端固定在构件内,一端埋入土中。
优先地,所述夹槽设有顶盖,圆杆与顶盖之间安装有缓冲垫。所述顶盖下方还设有盖板盖住夹箍。所述加固装置整体喷涂处理。
基于上述结构,本发明还提出一种电网电线杆加高施工方法,其包括以下步骤:
1)利用吊装设备将电线杆固定,将电线杆的中下部切断,使电线杆分为电线杆一和电线杆二;2)利用吊装设备将电线杆上吊,同时将拼接杆的下部连接在电线杆二;3)利用吊装设备使电线杆一连接拼接杆的上部;4)在电线杆一和电线杆二与拼接杆接触段注射混凝土,使三者连接在一起;5)在电线杆一与拼接杆连接处安装卡箍;6)安装加固装置,施工完成。
本发明的有益效果:该装置及其施工方法在加固电线杆时,使用方便,节省人力,特别适合泥土质量差,冻土,还有台风,暴雨等气候恶劣的地区使用,实用性强,适合推广使用。
附图说明
图1为本发明电网电线杆加固加高装置的结构示意图;
图2为本发明加固装置的结构示意图;
图3为抱箍装置的结构示意图;
图4为本发明电线杆加固完成之后的俯视图;
图5为本发明施工时工作示意图。
具体实施方式
如图所示,一种电网电线杆加固加高装置,包括抱箍装置2和加固装置4,所述加固装置4均布布设在电线杆1四周,加固装置4包括支架43,所述支架43一面均布设有长销41穿过电线杆1,另一面设有夹槽42,夹槽42内布设有底部埋入泥土内的圆杆44,夹箍45通过紧固件46将圆杆44锁紧在夹槽42上。所述支架43与电线杆1抱紧接触处贴有橡胶垫49,支架43内部设有橡胶填充层410,夹槽42上也贴有密封圈48。
抱箍装置2包括套在电线杆1上的圈套21,所述圈套21上设有紧固片22,构件23和连接片25通过锁紧螺栓24固定在紧固片22上,所述构件23内夹有斜加强杆6,所述斜加强杆6一端固定在构件23内,一端埋入土中。
夹槽42设有顶盖47,圆杆44与顶盖47之间安装有缓冲垫。所述夹槽设有顶盖,圆杆与顶盖之间安装有缓冲垫。所述顶盖47下方还设有盖板411盖住夹箍45。所述加固装置4整体喷涂处理,盖板411可以将夹箍45盖住防止其长时间暴露在恶劣条件下生锈。
使用时,首先将电线杆1利用吊装设备安装到预定位置,然后再将三块支架43贴着电线杆1周围放置,根据支架43的高度,均匀分布固定孔位,然后开始对电线杆1打通孔,需要注意三块支架43的定位孔要相对错开,不然在电线杆1上无法安装,然后安装好固定螺丝。
在支架43周围空地垂直打三个空洞,分别对应着三个圆杆44,稍远点的地方打一个与地面呈40°-50°的孔洞,然后用夹具夹持斜加强杆6,施加扭矩使之钻入地下并填埋,同时将夹箍45通过紧固件46将圆杆44锁紧在夹槽42上,并进行填埋,加固装置4安装完成,此外圆杆44的底部也可以为螺旋结构,这样便于下钻。
基于上述结构,本发明还提出一种电网电线杆加高施工方法,其特征在于,包括以下步骤:
1)利用吊装设备将电线杆1固定,将电线杆1的中下部切断,使电线杆分为电线杆一1A和电线杆二1B;
2)利用吊装设备将电线杆1上吊,同时将拼接杆3的下部连接在电线杆二1B;
3)利用吊装设备使电线杆一1A连接拼接杆3的上部;
4)在电线杆一1A和电线杆二1B与拼接杆3接触段注射混凝土,使三者连接在一起;
5)在电线杆一1A与拼接杆3连接处安装卡箍8;
6)安装加固装置4,施工完成。
除上述实施例外,本发明还可以有其他实施方式。凡采用等同替换或等效变换形成的技术方案,均落在本发明要求的保护范围。
Claims (1)
1.电网电线杆加固加高装置的施工方法,包括抱箍装置(2)和加固装置(4),其特征在于,所述加固装置(4)均布布设在电线杆(1)四周,加固装置(4)包括支架(43),所述支架(43)一面均布设有长销(41)穿过电线杆(1),另一面设有夹槽(42),夹槽(42)上布设有底部埋入泥土内的圆杆(44),夹箍(45)通过紧固件(46)将圆杆(44)锁紧在夹槽(42)上;
所述抱箍装置(2)包括套在电线杆(1)上的圈套(21),所述圈套(21)上设有紧固片(22),构件(23)和连接片(25)通过锁紧螺栓(24)固定在紧固片(22)上,所述构件(23)内夹有斜加强杆(6),所述斜加强杆(6)一端固定在构件(23)内,一端埋入土中;
所述电网电线杆加固加高装置的施工方法,包括:
1)利用吊装设备将电线杆(1)固定,将电线杆(1)的中下部切断,使电线杆分为电线杆一(1A)和电线杆二(1B);
2)利用吊装设备将电线杆一(1A)上吊,同时将拼接杆(3)的下部连接在电线杆二(1B);
3)利用吊装设备使电线杆一(1A)连接拼接杆(3)的上部;
4)在电线杆一(1A)和电线杆二(1B)与拼接杆(3)接触段注射混凝土,使三者连接在一起;
5)在电线杆一(1A)与拼接杆(3)连接处安装卡箍(8);
6)安装加固装置(4),施工完成;
所述夹槽(42)设有顶盖(47),圆杆(44)与顶盖(47)之间安装有缓冲垫。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710583115.1A CN107165468A (zh) | 2015-11-30 | 2015-11-30 | 一种电网电线杆加固加高装置的施工方法 |
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710583115.1A CN107165468A (zh) | 2015-11-30 | 2015-11-30 | 一种电网电线杆加固加高装置的施工方法 |
CN201510850996.XA CN105350816B (zh) | 2015-11-30 | 2015-11-30 | 电网电线杆加固加高装置 |
Related Parent Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510850996.XA Division CN105350816B (zh) | 2015-11-30 | 2015-11-30 | 电网电线杆加固加高装置 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107165468A true CN107165468A (zh) | 2017-09-15 |
Family
ID=55326863
Family Applications (3)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710583117.0A Withdrawn CN107299772A (zh) | 2015-11-30 | 2015-11-30 | 确保电网设施运转正常的电网电线杆加固加高装置 |
CN201710583115.1A Withdrawn CN107165468A (zh) | 2015-11-30 | 2015-11-30 | 一种电网电线杆加固加高装置的施工方法 |
CN201510850996.XA Expired - Fee Related CN105350816B (zh) | 2015-11-30 | 2015-11-30 | 电网电线杆加固加高装置 |
Family Applications Before (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710583117.0A Withdrawn CN107299772A (zh) | 2015-11-30 | 2015-11-30 | 确保电网设施运转正常的电网电线杆加固加高装置 |
Family Applications After (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510850996.XA Expired - Fee Related CN105350816B (zh) | 2015-11-30 | 2015-11-30 | 电网电线杆加固加高装置 |
Country Status (1)
Country | Link |
---|---|
CN (3) | CN107299772A (zh) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114508259A (zh) * | 2022-03-11 | 2022-05-17 | 国网山东省电力公司沂水县供电公司 | 一种电力施工用辅助电线杆快速安装的运输装置 |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105298205B (zh) * | 2015-11-30 | 2017-09-19 | 国网山东省电力公司枣庄供电公司 | 一种电网电线杆加固加高装置及其施工方法 |
CN106836933A (zh) * | 2017-03-07 | 2017-06-13 | 浙江工业大学 | 一种电线杆加固装置 |
CN107795181A (zh) * | 2017-10-08 | 2018-03-13 | 国网江西省电力公司电力科学研究院 | 一种配电网电杆拉线拉盘方法 |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4097165A (en) * | 1976-04-26 | 1978-06-27 | Quayle Jackson C | Pole top extension bracket |
KR20090050873A (ko) * | 2007-11-16 | 2009-05-20 | 선문대학교 산학협력단 | 전주 연장용 지지장치 및 이를 이용한 전주 연장 방법 |
CN102425327A (zh) * | 2011-12-08 | 2012-04-25 | 河南省电力公司洛阳供电公司 | 一种水泥电线杆加高杆 |
CN202467235U (zh) * | 2012-02-06 | 2012-10-03 | 宜阳县电业局 | 一种水泥电杆加固装置 |
CN203559610U (zh) * | 2013-09-24 | 2014-04-23 | 国家电网公司 | 一种直筒型电杆升高架 |
CN204189939U (zh) * | 2014-09-11 | 2015-03-04 | 福建省邮电规划设计院有限公司 | 原有通信天线支撑杆架改造的加固结构 |
CN104652910A (zh) * | 2014-12-26 | 2015-05-27 | 国家电网公司 | 一种水泥电线杆高度调节装置 |
Family Cites Families (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP5969741B2 (ja) * | 2010-08-18 | 2016-08-17 | 大日コンクリート工業株式会社 | 繊維材料により補強したコンクリートポール及びコンクリートポールの繊維材料による補強方法 |
JP5964730B2 (ja) * | 2012-11-21 | 2016-08-03 | 大嘉産業株式会社 | 中空柱状物の補強用の型枠及び補強材 |
CN204663119U (zh) * | 2015-05-14 | 2015-09-23 | 国家电网公司 | 混凝土电杆加固装置 |
CN105298205B (zh) * | 2015-11-30 | 2017-09-19 | 国网山东省电力公司枣庄供电公司 | 一种电网电线杆加固加高装置及其施工方法 |
-
2015
- 2015-11-30 CN CN201710583117.0A patent/CN107299772A/zh not_active Withdrawn
- 2015-11-30 CN CN201710583115.1A patent/CN107165468A/zh not_active Withdrawn
- 2015-11-30 CN CN201510850996.XA patent/CN105350816B/zh not_active Expired - Fee Related
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4097165A (en) * | 1976-04-26 | 1978-06-27 | Quayle Jackson C | Pole top extension bracket |
KR20090050873A (ko) * | 2007-11-16 | 2009-05-20 | 선문대학교 산학협력단 | 전주 연장용 지지장치 및 이를 이용한 전주 연장 방법 |
CN102425327A (zh) * | 2011-12-08 | 2012-04-25 | 河南省电力公司洛阳供电公司 | 一种水泥电线杆加高杆 |
CN202467235U (zh) * | 2012-02-06 | 2012-10-03 | 宜阳县电业局 | 一种水泥电杆加固装置 |
CN203559610U (zh) * | 2013-09-24 | 2014-04-23 | 国家电网公司 | 一种直筒型电杆升高架 |
CN204189939U (zh) * | 2014-09-11 | 2015-03-04 | 福建省邮电规划设计院有限公司 | 原有通信天线支撑杆架改造的加固结构 |
CN104652910A (zh) * | 2014-12-26 | 2015-05-27 | 国家电网公司 | 一种水泥电线杆高度调节装置 |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114508259A (zh) * | 2022-03-11 | 2022-05-17 | 国网山东省电力公司沂水县供电公司 | 一种电力施工用辅助电线杆快速安装的运输装置 |
CN114508259B (zh) * | 2022-03-11 | 2022-09-16 | 国网山东省电力公司沂水县供电公司 | 一种电力施工用辅助电线杆快速安装的运输装置 |
Also Published As
Publication number | Publication date |
---|---|
CN107299772A (zh) | 2017-10-27 |
CN105350816B (zh) | 2017-12-12 |
CN105350816A (zh) | 2016-02-24 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105350816B (zh) | 电网电线杆加固加高装置 | |
CN105298205B (zh) | 一种电网电线杆加固加高装置及其施工方法 | |
KR101238283B1 (ko) | 전봇대 지주 보강을 위한 보강커버판을 사용한 보강 방법 | |
CN207228145U (zh) | 一种电线杆的桩基结构 | |
CN206490407U (zh) | 一种高低压同杆架空线路结构 | |
CN207260144U (zh) | 电力地锚 | |
CN201627397U (zh) | 水泥电线杆 | |
CN102425327A (zh) | 一种水泥电线杆加高杆 | |
CN205979564U (zh) | 一种城市用电力钢管杆 | |
CN205502711U (zh) | 一种易安装的电线杆固定底座结构 | |
CN204668762U (zh) | 一种配电箱的安装支架 | |
CN206942282U (zh) | 一种加固型电力杆塔 | |
CN203895873U (zh) | 制作电缆终端用工作台 | |
CN204343778U (zh) | 一种线杆 | |
CN106869575A (zh) | 一种电杆及其制备方法 | |
CN210588892U (zh) | 一种5g基站建设用定位装置 | |
CN207419508U (zh) | 直埋式杆体基础 | |
CN203175134U (zh) | 用于升高输电线路塔接腿的桁架 | |
CN205296204U (zh) | 路灯杆基站的基础结构 | |
CN205777822U (zh) | 便携式组合拉线盘 | |
CN205389010U (zh) | 一种电杆、表箱接地装置 | |
CN206309105U (zh) | 一种用于10kV线路大跨越杆塔 | |
CN207426404U (zh) | 一种防雷设备 | |
CN210975870U (zh) | 一种通信工程铁塔用预制塔基 | |
CN204538635U (zh) | 避雷器安装用组合式定位架 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WW01 | Invention patent application withdrawn after publication | ||
WW01 | Invention patent application withdrawn after publication |
Application publication date: 20170915 |