CN107165411A - A kind of Constructional Col-umn Construction technique - Google Patents

A kind of Constructional Col-umn Construction technique Download PDF

Info

Publication number
CN107165411A
CN107165411A CN201710368389.9A CN201710368389A CN107165411A CN 107165411 A CN107165411 A CN 107165411A CN 201710368389 A CN201710368389 A CN 201710368389A CN 107165411 A CN107165411 A CN 107165411A
Authority
CN
China
Prior art keywords
constructional
discharge duct
constructional column
construction technique
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710368389.9A
Other languages
Chinese (zh)
Inventor
石永龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC5 Group Corp Ltd
Original Assignee
China MCC5 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC5 Group Corp Ltd filed Critical China MCC5 Group Corp Ltd
Priority to CN201710368389.9A priority Critical patent/CN107165411A/en
Publication of CN107165411A publication Critical patent/CN107165411A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G13/00Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills
    • E04G13/02Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills for columns or like pillars; Special tying or clamping means therefor
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/02Conveying or working-up concrete or similar masses able to be heaped or cast
    • E04G21/06Solidifying concrete, e.g. by application of vacuum before hardening

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention discloses a kind of Constructional Col-umn Construction technique, including step:Step 1) concreting hole is reserved on the corresponding collar tie beam of constructional column in pre- pour;Step 2) constructional column reinforcing bar colligation;Step 3) construction column template is set;The junction of masonry and constructional column is built into horse tooth trough;Step 4) constructional column casting concrete, in agent structure pouring construction, inserts on the outside of a discharge duct, the discharge duct in concreting hole and brushes interleaving agent.Constructional column casting concrete, in agent structure pouring construction, a discharge duct is inserted in concreting hole, interleaving agent is brushed on the outside of the discharge duct, by inserting a discharge duct in concreting hole, the gas in mixed mud on the one hand can be effectively excluded, drainage on the other hand can be played a part of by discharge duct, because mixed mud has polymerization, by drainage mixed mud can be made to flow in each horse tooth trough recess.

Description

A kind of Constructional Col-umn Construction technique
Technical field
The present invention relates to a kind of building engineering field, and in particular to a kind of Constructional Col-umn Construction technique.
Background technology
Conventional configurations post working measure is to set dustpan mouthful casting concrete in constructional column topmast, because concrete shrinks in itself Characteristic, can not be poured with beam bottom at the top of constructional column closely knit;Simultaneously because the construction of conventional configurations post can not be to constructional column coagulation Soil is fully vibrated, and constructional column tends to occur the common quality defects such as dew muscle, honeycomb, hole.
The content of the invention
The purpose of the present invention is to be to overcome prior art not enough, it is therefore intended that provide a kind of Constructional Col-umn Construction technique, solution Certainly existing Constructional Col-umn Construction, the problem of constructional column tends to occur the common quality defects such as dew muscle, honeycomb, hole.
The present invention is achieved through the following technical solutions:
A kind of Constructional Col-umn Construction technique, including step:
Step 1) concreting hole is reserved on the corresponding collar tie beam of constructional column in pre- pour;
Step 2) constructional column reinforcing bar colligation;
Step 3) construction column template is set;The junction of masonry and constructional column is built into horse tooth trough;
Step 4) constructional column casting concrete, in agent structure pouring construction, a row is inserted in concreting hole Interleaving agent is brushed on the outside of feed channel, the discharge duct.
Further, the step 4), according to the strength grade of concrete of constructional column 1, from concreting hole 3 by coagulation Soil is poured into, while fully vibrated with minor diameter vibrating spear, concreting to beam Xia Kou positions.
Further, the minor diameter vibrating spear, which is used, is less than or equal to a diameter of 30mm vibrating spears.
Further, in addition to step 5), using than former collar tie beam 2 design the high grade of concrete pea gravel concreten or filling The solidifying native pouring hole 3 of filled therewith.
Further, the discharge duct 7 can be made of pvc pipe, the bottom sealing of the discharge duct 7, duct wall Upper entanglement is provided with multiple passages 8.
Further, the passage 8 is provided with screen pack 9.
Further, the external diameter of discharge duct 7 is more than or equal to 40mm.
Further, the step 3), the height of each horse tooth trough 6 is 200mm-300mm, and the recessed depth of horse tooth trough 6 exists 50-60mm, each horse tooth trough does fillet or chamfered.
The present invention compared with prior art, has the following advantages and advantages:
1st, a kind of Constructional Col-umn Construction technique of the invention, constructional column casting concrete, in agent structure pouring construction, mixed Solidifying soil pouring hole inserts on the outside of a discharge duct, the discharge duct and brushes interleaving agent, by being inserted in concreting hole A piece discharge duct, on the one hand can effectively exclude the gas in mixed mud, on the other hand can be played and drawn by discharge duct The effect of stream, because mixed mud has polymerization, can be such that mixed mud flows in each horse tooth trough recess by drainage;
2nd, the junction of a kind of Constructional Col-umn Construction technique of the invention, masonry and constructional column is built into horse tooth trough, each horse tooth trough Do fillet or chamfered.By setting horse tooth trough to effectively improve the bonding strength of constructional column and masonry, while can be with The anti-seismic performance and support strength of constructional column are improved, each horse tooth trough does fillet or chamfered in addition, can be fully solved structure Make post and occur the quality such as dew muscle, honeycomb, hole, mixed mud can be with smooth entrance horse tooth trough recess;
3rd, a kind of Constructional Col-umn Construction technique of the invention, constructional column concrete is connected closely knit free from flaw with agent structure, improves The anti-seismic performance of filling wall, with good application value.Engineering method construction technology is simple and practical, with construction efficiency Height, the features such as safety coefficient is high.
Brief description of the drawings
Accompanying drawing described herein is used for providing further understanding the embodiment of the present invention, constitutes one of the application Point, do not constitute the restriction to the embodiment of the present invention.In the accompanying drawings:
Fig. 1 is a kind of pillar structure schematic diagram of Constructional Col-umn Construction technique cast of the invention;
Fig. 2 is exhaust pipe structure schematic diagram of the present invention;
Mark and corresponding parts title in accompanying drawing:
1- constructional columns, 2- collar tie beams, 3- concretings hole, 4- constructional column reinforcing bars, 5- masonries, 6- horse tooth troughs, 7- blast pipes Road, 8- passages, 9- screen packs.
Embodiment
For the object, technical solutions and advantages of the present invention are more clearly understood, with reference to embodiment and accompanying drawing, to this Invention is described in further detail, and exemplary embodiment and its explanation of the invention is only used for explaining the present invention, does not make For limitation of the invention.
Embodiment
As shown in Figure 1-2, a kind of Constructional Col-umn Construction technique of the invention, it is main to use, reserved on beam concreting hole → Pouring hole sealing is reserved on constructional column reinforcing bar colligation → constructional column formwork erection → constructional column casting concrete → beam.
Specifically include step:
Step 1) concreting hole 3 is reserved on the corresponding collar tie beam 2 of constructional column 1 in pre- pour.
Step 2) 4 colligation of constructional column reinforcing bar.
Step 3) construction column template is set;The junction of masonry 5 and constructional column 1 is built into horse tooth trough 6.Step 3), each horse The height of tooth raft 6 is 200mm-300mm, and the recessed depth of horse tooth trough 6 is in 50-60mm, and each horse tooth trough does fillet or chamfered.
Step 4) 1 casting concrete of constructional column, in agent structure pouring construction, one is inserted in concreting hole 3 Brush interleaving agent in discharge duct 7, the outside of discharge duct 7.According to the strength grade of concrete of constructional column 1, poured from concrete Hole (3) is built to pour into concrete, while fully vibrated with minor diameter vibrating spear, concreting to beam Xia Kou positions.
Step 5), solidifying soil is filled using pea gravel concreten or grouting material that the high grade of concrete is designed than former collar tie beam 2 and poured Build hole (3).
Minor diameter vibrating spear, which is used, is less than or equal to a diameter of 30mm vibrating spears.The discharge duct 7 can use pvc pipe system Into the bottom of the discharge duct 7 is sealed, and entanglement is provided with multiple passages 8 on duct wall, for being vented.Passage 8 is provided with Screen pack 9 prevents mixed mud from entering in discharge duct 7.The external diameter of discharge duct 7 is more than or equal to 40mm.By in concreting A discharge duct is inserted in hole, on the one hand can effectively exclude the gas in mixed mud, on the other hand can be with by discharge duct Play a part of drainage, because mixed mud has polymerization, by drainage mixed mud can be made to flow to each horse tooth trough recess It is interior,
(1) concreting hole is reserved on beam
In main structure construction, vertically inserted in beam and interleaving agent is brushed on the outside of a pvc pipe, pvc pipe, facilitate pvc pipe Can smoothly it be taken out after beam concreting.PVC external diameter determines that minimum is not less than 40mm according to the spacing of beam steel.As schemed 2:
(2) constructional column casting concrete
After the completion of formwork erection, according to the strength grade of concrete of constructional column, concrete is poured into from beam is suitable for reading, while with Minor diameter vibrating spear (using 30mm vibrating spears) is fully vibrated, concreting to beam Xia Kou positions.
(3) pouring hole sealing is reserved on beam
Using the pea gravel concreten or grouting material filling pouring hole that the high grade of concrete is designed than former beam.
A kind of Constructional Col-umn Construction technique of the present invention, constructional column casting concrete, in agent structure pouring construction, in coagulation Native pouring hole inserts on the outside of a discharge duct, the discharge duct and brushes interleaving agent, by inserting one in concreting hole Root discharge duct, on the one hand can effectively exclude the gas in mixed mud, on the other hand can play drainage by discharge duct Effect because mixed mud has polymerization, by drainage mixed mud can be made to flow in each horse tooth trough recess;Masonry with The junction of constructional column is built into horse tooth trough, and each horse tooth trough does fillet or chamfered.By setting horse tooth trough effectively to carry The bonding strength of high constructional column and masonry, while the anti-seismic performance and support strength of constructional column can also be improved, each horse in addition Tooth raft does fillet or chamfered, can be fully solved constructional column and occur the quality such as dew muscle, honeycomb, hole, mixed mud can be suitable It is smooth to enter in horse tooth trough recess;Constructional column concrete is connected closely knit free from flaw with agent structure, improves the shock resistance of filling wall Can, with good application value.Engineering method construction technology is simple and practical, high with construction efficiency, the spy such as safety coefficient height Point.
The junction of masonry and constructional column should be built into horse tooth trough, and the height of each horse tooth trough is no more than 300mm, horse tooth trough Recessed depth is preferably 50-60mm.Current masonry building block generally uses autoclaved aerated concrete blocks, and aerated concrete building block modulus is highly 250mm is high, just as a gingival cyst of mucous gland in the newborn.When building by laying bricks or stones first piece of brick should be recessed, and meaning stings pin, then in order with entering with moving back block Build horse tooth trough (if bottom uses sand-lime brick masonry, also should be regarded as that a horse tooth trough is recessed to sting pin).No matter the recessed protrusion of horse tooth trough, It will be hung vertically with line pendant simultaneously, horse tooth trough masonry interface should put full sized brick face, and building block cut surface should be placed on inboard, it is ensured that horse tooth trough It is attractive in appearance.Constructional column reinforcement installation and masonry tension rib are pre-buried:The sectional dimension and arrangement of reinforcement of constructional column should meet design requirement.When setting When counting no requirement (NR), construction column section minimum widith cannot be less than 200mm, and the same wall thickness of thickness, longitudinal reinforcement is no less than 4 Φ 10, Stirrup can use the@200 of Ф 6.It should be anchored into beams of concrete or plate at the top and bottom of longitudinal reinforcement.Should accurately it be surveyed when pouring main body concrete Measure constructional column and indulge muscle position, it is ensured that joint bar position is accurate.To ensure that reinforcement location is accurate, the pre-buried construction of rear bar planting method can be used Post indulges muscle.According to the construction of rear bar planting method, drilling depth 60mm first blows off dust in hole with blowing cylinder before bar planting, then fills knot Structure glue or epoxy resin liquid, are replanted into reinforcing bar.Steel tie should be set between masonry and concrete-constituted pile.Steel tie should Along overall height setting is built by laying bricks or stones, tension rib interval is not to be exceeded 600mm and sets the tension ribs of 2 Ф 6.The tension rib of autoclaved aerated concrete masonry is buried Enter depth preferably 700mm, and tension rib end should add hook, the masonry thickness of mortarat bed joint for placing steel tie should be than drawknot steel The big 4mm of muscle diameter.
Constructional column model sheetinstallat and concrete placings:To have certain operating space when ensureing and pouring constructional column concrete, it is easy to Small vibrating rod is inserted, and the Screw arbor with nut at both-ends of construction column template is preferably arranged on the masonry of constructional column both sides, should not be arranged at construction In post.If Screw arbor with nut at both-ends is arranged in constructional column, the insertion of vibrating head can be hindered.Model sheetinstallat can divide three kinds of modes to carry out:① Deck-molding >=800mm at the top of constructional column, template can be sealed completely, and the side template of end one dresses up horn charging aperture, and charging aperture should compare Constructional column is higher by 100mm, charging aperture also should be completely poured when pouring post concrete, beat prominent concrete after form removal and chisel out.Such energy Ensure there is no space between concrete and back timber at the top of constructional column.2. deck-molding < 800mm at the top of constructional column, template side is completely sealed, separately One side template answers future insufficiency to be used as charging aperture and small-sized plug-in type vibrating rod, that is, pours construction column end and also remain one small section Concrete is not poured, it is necessary to carry out secondary teeming.The template of side is completely sealed during form removal to remove, and as secondary teeming template, had The template of breach side should be removed.Secondary teeming concrete should be made compared with dry and hard concrete (such as dough), and secondary teeming concrete fills up Nailing template again afterwards, the secondary outward appearance sign that pours of concrete is relatively obscured after form removal, and perception is preferable.3. do not have the constructional column of beam for top, apply Work method is fairly simple, can be poured in floor opening.No matter using which kind of form of construction work, pouring constructional column concrete must use Small-sized plug-in type vibrating rod (diameter 3cm), just can guarantee that concrete compaction.If being sticked along the concavo-convex edge of masonry horse tooth trough two-sided Glue, then seal the more tight not spillage of mould, constructional column and masonry boundary line are more attractive in appearance after form removal.
Above-described embodiment, has been carried out further to the purpose of the present invention, technical scheme and beneficial effect Describe in detail, should be understood that the embodiment that the foregoing is only the present invention, be not intended to limit the present invention Protection domain, within the spirit and principles of the invention, any modification, equivalent substitution and improvements done etc. all should be included Within protection scope of the present invention.

Claims (8)

1. a kind of Constructional Col-umn Construction technique, it is characterised in that including step:
Step 1) reserve concreting hole (3) on the corresponding collar tie beam (2) of constructional column (1) in pre- pour;
Step 2) constructional column reinforcing bar (4) colligation;
Step 3) construction column template is set;The junction of masonry (5) and constructional column (1) is built into horse tooth trough (6);
Step 4) constructional column (1) casting concrete, in agent structure pouring construction, one is inserted in concreting hole (3) Interleaving agent is brushed on the outside of discharge duct (7), the discharge duct (7).
2. a kind of Constructional Col-umn Construction technique according to claim 1, it is characterised in that:The step 4), according to constructional column (1) strength grade of concrete, pours into concrete from concreting hole (3), while being carried out fully with minor diameter vibrating spear Vibrate, concreting to beam Xia Kou positions.
3. a kind of Constructional Col-umn Construction technique according to claim 2, it is characterised in that:The minor diameter vibrating spear is using small In or equal to a diameter of 30mm vibrating spears.
4. a kind of Constructional Col-umn Construction technique according to claim 1, it is characterised in that:Also include step 5), using than original The pea gravel concreten of collar tie beam (2) the design high grade of concrete or the solidifying native pouring hole (3) of grouting material filling.
5. a kind of Constructional Col-umn Construction technique according to claim 1, it is characterised in that:The discharge duct (7) can use Pvc pipe is made, the bottom sealing of the discharge duct (7), and entanglement is provided with multiple passages (8) on duct wall.
6. a kind of Constructional Col-umn Construction technique according to claim 5, it is characterised in that:The passage (8) was provided with Filter screen (9).
7. a kind of Constructional Col-umn Construction technique according to claim 6, it is characterised in that:Discharge duct (7) external diameter is big In or equal to 40mm.
8. a kind of Constructional Col-umn Construction technique according to claim 1, it is characterised in that:The step 3), each horse tooth trough (6) height is 200mm-300mm, and horse tooth trough (6) recessed depth is in 50-60mm, and each horse tooth trough does fillet or chamfered.
CN201710368389.9A 2017-05-22 2017-05-22 A kind of Constructional Col-umn Construction technique Pending CN107165411A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710368389.9A CN107165411A (en) 2017-05-22 2017-05-22 A kind of Constructional Col-umn Construction technique

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710368389.9A CN107165411A (en) 2017-05-22 2017-05-22 A kind of Constructional Col-umn Construction technique

Publications (1)

Publication Number Publication Date
CN107165411A true CN107165411A (en) 2017-09-15

Family

ID=59820401

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710368389.9A Pending CN107165411A (en) 2017-05-22 2017-05-22 A kind of Constructional Col-umn Construction technique

Country Status (1)

Country Link
CN (1) CN107165411A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107882272A (en) * 2017-10-31 2018-04-06 启迪设计集团股份有限公司 Fill wall construction post
CN108118904A (en) * 2018-01-07 2018-06-05 中铁四局集团建筑工程有限公司 A kind of Constructional Col-umn Construction method
CN108999408A (en) * 2018-09-29 2018-12-14 北京首钢建设集团有限公司 A kind of building block of constructional column two sides uses the concreting method of chamfering
CN109208782A (en) * 2018-09-30 2019-01-15 中国二十二冶集团有限公司 Horse tooth trough building construction method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102535849A (en) * 2012-02-15 2012-07-04 中建三局第二建设工程有限责任公司 Constructional column top concreting method
CN203795847U (en) * 2013-12-12 2014-08-27 中国建筑第四工程局有限公司 Formwork set for concrete specially-shaped section column
BR102012028473A2 (en) * 2012-11-07 2014-09-23 Jacinto Teixeira Sobrinho CONSTRUCTIVE ARRANGEMENT APPLIED IN METAL FORM FOR CONCRETE PILLARS
CN203924729U (en) * 2014-06-27 2014-11-05 中建八局第二建设有限公司 Concrete pouring construction exhaust plant
CN204531065U (en) * 2015-03-08 2015-08-05 青岛一建集团有限公司 A kind of infilled wall constructional column that effectively can improve Forming Quality
CN106567543A (en) * 2016-10-26 2017-04-19 上海中锦建设集团股份有限公司 Slab-bottom structural concrete column reserved hole construction method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102535849A (en) * 2012-02-15 2012-07-04 中建三局第二建设工程有限责任公司 Constructional column top concreting method
BR102012028473A2 (en) * 2012-11-07 2014-09-23 Jacinto Teixeira Sobrinho CONSTRUCTIVE ARRANGEMENT APPLIED IN METAL FORM FOR CONCRETE PILLARS
CN203795847U (en) * 2013-12-12 2014-08-27 中国建筑第四工程局有限公司 Formwork set for concrete specially-shaped section column
CN203924729U (en) * 2014-06-27 2014-11-05 中建八局第二建设有限公司 Concrete pouring construction exhaust plant
CN204531065U (en) * 2015-03-08 2015-08-05 青岛一建集团有限公司 A kind of infilled wall constructional column that effectively can improve Forming Quality
CN106567543A (en) * 2016-10-26 2017-04-19 上海中锦建设集团股份有限公司 Slab-bottom structural concrete column reserved hole construction method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
百度文库: "构造柱施工工艺", 《HTTPS://WK.BAIDU.COM/VIEW/70986A32AE45B307E87101F69E3143323868F552?PCF=2》 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107882272A (en) * 2017-10-31 2018-04-06 启迪设计集团股份有限公司 Fill wall construction post
CN107882272B (en) * 2017-10-31 2020-06-02 启迪设计集团股份有限公司 Constructional column of filling wall
CN108118904A (en) * 2018-01-07 2018-06-05 中铁四局集团建筑工程有限公司 A kind of Constructional Col-umn Construction method
CN108999408A (en) * 2018-09-29 2018-12-14 北京首钢建设集团有限公司 A kind of building block of constructional column two sides uses the concreting method of chamfering
CN109208782A (en) * 2018-09-30 2019-01-15 中国二十二冶集团有限公司 Horse tooth trough building construction method

Similar Documents

Publication Publication Date Title
CN107165411A (en) A kind of Constructional Col-umn Construction technique
CH615236A5 (en)
CN102003069A (en) Construction method and pouring device for framework masonry infill wall structure
CN111719565A (en) Deep foundation pit support structure and construction method thereof
CN105839850A (en) Basement reverse-construction scape post-casting pre-stressed construction method
CN103469806A (en) Construction method for replacing brick forming die with prefabricated concrete foundation bearing platform side die
CN105696790B (en) A kind of double-deck coupling beam opening mould plate system and its engineering method applied to double-deck coupling beam
CN107178209A (en) A kind of constructional column and agent structure integrated construction method
CN205669281U (en) A kind of cast-in-place integral concrete frame wall filled with masonry system
CN108005255A (en) A kind of construction method of wall
CN109236033A (en) A kind of building prefabrication Assembled enclosing wall and its production technology
CN109113068A (en) A kind of inverse construction joint structure for building construction of deep basal pit
CN108412094A (en) The construction method and device of the hollow concrete wall of masonry between a kind of replacement shear wall
CN105155474B (en) Chute construction shaper and the construction method of chute
CN105696701B (en) A kind of suitable slope shear wall building development platform and its construction method
CN209066442U (en) A kind of inverse construction joint structure for building construction of deep basal pit
CN206539016U (en) Constructional column pours device
JP3015646U (en) Concrete block for earth retaining
CN110306561A (en) A kind of foundation pit hardness construction method of interlocking pile
CN109057066A (en) A kind of flexible connection anti-seismic structure and construction method
CN206707313U (en) A kind of foundation ditch edge protection prefabricated foundation
CN207538459U (en) A kind of support device suitable for masonry wall constructional column
CN207776878U (en) A kind of underground power house machine hole dividing pier structure
CN207077580U (en) Prefabricated constructional column formwork producing device
CN201915635U (en) Form erecting device free of bar planting for brickwork construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170915