CN107152147A - A kind of concrete abrasion-resistant terrace construction technique - Google Patents

A kind of concrete abrasion-resistant terrace construction technique Download PDF

Info

Publication number
CN107152147A
CN107152147A CN201710466662.1A CN201710466662A CN107152147A CN 107152147 A CN107152147 A CN 107152147A CN 201710466662 A CN201710466662 A CN 201710466662A CN 107152147 A CN107152147 A CN 107152147A
Authority
CN
China
Prior art keywords
concrete
construction technique
terrace
carried out
abrasion
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710466662.1A
Other languages
Chinese (zh)
Inventor
周宁
宁少波
周茂
潘孝如
陈彩凤
白巧艳
王成章
王强
胡耿
郭正权
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SUZHOU JUNMAO CREATE ENGINEERING Co Ltd
Original Assignee
SUZHOU JUNMAO CREATE ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SUZHOU JUNMAO CREATE ENGINEERING Co Ltd filed Critical SUZHOU JUNMAO CREATE ENGINEERING Co Ltd
Priority to CN201710466662.1A priority Critical patent/CN107152147A/en
Publication of CN107152147A publication Critical patent/CN107152147A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F15/00Flooring
    • E04F15/12Flooring or floor layers made of masses in situ, e.g. seamless magnesite floors, terrazzo gypsum floors

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
  • Curing Cements, Concrete, And Artificial Stone (AREA)

Abstract

A kind of terrace construction technique belongs to floor construction technical field, relates generally to a kind of concrete abrasion-resistant terrace construction technique;The present invention produces that crack, poor toughness, anti-fatigue ability are low to solve terrace, and tensile strength is low, shock resistance fragmentation, and later maintenance maintenance cost is high, the problem of terrace service life is short;Comprise the following steps:Base treatment:Template is laid:Template laying is carried out according to concrete point bin location;Concreting:Constructed using sequence placing mode;Leveling, is constructed using being flattened from periphery to center centralized system, concrete surface flatness is met construction requirement;Wearing layer, the spreading of three progress high-abrasive materials of part are laid, and is carried out levelling;Maintenance:Sealing compound is sprayed, cracking is prevented;The slot cementation of fissures is constructed;The present invention solve concrete ground criticize the cracking occurred, hollowing, flake, the flatness quality problems such as not enough, reduce cost, and reduce the maintenance cost in later stage and the service life of extension terrace.

Description

A kind of concrete abrasion-resistant terrace construction technique
Technical field
A kind of terrace construction technique belongs to floor construction technical field, relates generally to a kind of concrete abrasion-resistant floor construction work Skill.
Background technology
The service range of terrace is modern industrial enterprises terrace, business terrace, big-and-middle-sized parking lot terrace, garage parking Level ground, commercial square, station terminal, school's sports ground, logistics warehouse terrace, hospital's terrace, office's terrace, swimming pool terrace, Tourist attraction terrace, various recreation centers terrace, various research and development fields terrace, in a word, as long as using the ground of concrete Level ground face can make terrace, and terrace has that anti-pressure ability is strong, wear-resistant Chengdu is high, dust-proof, grease proofing, impermeabilisation, easy to clean etc. Premium properties, in actual applications using more and more extensively, however, terrace is urgently to be resolved hurrily in the presence of some in work progress The problem of, for example terrace generation crack, poor toughness, anti-fatigue ability are low, and tensile strength is low, shock resistance fragmentation, later maintenance dimension Accomplish this height, terrace service life is short.
The content of the invention
In order to solve the above problems, the invention discloses a kind of concrete abrasion-resistant terrace construction technique, terrace is enhanced Toughness, crack resistance are strong, anti-fatigue ability is high, extend the service life of terrace.
The object of the present invention is achieved like this:
A kind of concrete abrasion-resistant terrace construction technique, comprises the following steps:
Step one:Base treatment:Basic unit is cleared up, absolute altitude is carried out and compacting is constructed;
Step 2:Template is laid:Template laying is carried out according to concrete point bin location;
Step 3:Concreting:Constructed using sequence placing mode;
Step 4:Leveling, is constructed using being flattened from periphery to center centralized system, and concrete surface flatness is met construction will Ask;
Step 5:Wearing layer, the spreading of three progress high-abrasive materials of part are laid, and is carried out levelling.
Step 6:Maintenance:Sealing compound is sprayed, cracking is prevented;
Step 7:The slot cementation of fissures is constructed.
The detailed process of base treatment described in step one includes:Base cleaning is clean;Bottom element soil is compacted;Paving If broken sandstone simultaneously and is conserved.
The plain soil compaction coefficient is 0.95, and flatness scope is 0-3mm.
Step 3 specifically includes procedure below:The double-deck polypropylene isolated film of laying;The preparation of concrete;Poured using a point storehouse The method of building is poured;Progress is vibrated levelling.
The preparation method of the concrete includes:Steel fibre, sand and rubble are stirred;Once add in stirring thing Add water mud, flyash, zeolite powder, silicon ash water and auxiliary agent is stirred.
The slump of the concrete is less than 5cm,.
Step 5 is specifically included:When concrete initial set is to 50%-60%, one layer of quartz sand particle is dispensed;Carry out floating carry Slurry, it is 0-3mm to make its flatness;Second of quartz sand particle spreading is carried out, floating warehouse, flatness reaches 0-3mm;Carry out the Three times quartz sand particle is dispensed, and floating warehouse, flatness reaches 0-2mm.
The ratio between consumption of three spreadings quartz sand particle is 4:1:1.
Step 7 is specifically included:After concreting 30h-60h, lancing operation is carried out, deep and concrete thickness ratio is stitched For between 1/3-3/5.
The slit width is 3-5mm.
The present invention compared with prior art, has the advantages that steel fibre is abundant and is uniformly filled in coagulation Each place of soil, is improved terrace toughness, using the terrace high mechanical properties of construction technology of the present invention, solves coagulation Soil criticize occur cracking, hollowing, flake, flatness not enough etc. quality problems, reduce cost, and reduce the later stage The service life of maintenance cost and extension terrace, without assembling reinforcement, in casting and compacting of concrete, it is not necessary to pump, improves and pours Speed, easy construction, without large-scale construction equipment, low cost, speed of application is fast, short time limit, with better economy effect Benefit;Rolled steel dosage reduction power consumption is reduced, low-carbon environment-friendly economizes on resources.
Embodiment
The specific embodiment of the invention is described in further detail below.
A kind of concrete abrasion-resistant terrace construction technique of the present embodiment, comprises the following steps:
Step one:Base treatment:Base cleaning is clean;Bottom element soil is compacted, the plain soil compaction coefficient is 0.95, flatness scope is 0-3mm;The broken sandstone of 15mm-30mm specifications is laid, laying depth is 20mm, and coefficient of loose laying is 1.2, it is compacted using 20t road rollers, compacting factor is more than in 0.95, compacting process according to actual needs, is moistened on a small quantity It is wet;0-15mm year sandstone is laid, thickness is 40mm, compacting is entered using road roller, carry out gap filling and levelling, laying is completed Conserved afterwards, the broken sandstone is the crushed-gravel that sand content is 3%,
Step 2:Template is laid:Template laying is carried out according to concrete point bin location, using the side form of channel-section steel seat concrete, and Fixed using triangular reinforced bar support;During formwork, the upper flat absolute altitude of template is consistent with bottom surface absolute altitude;
Step 3:Concreting:Constructed, specifically included using sequence placing mode:Lay the thick polypropylene of bilayer 0.15mm Provided with the epoxy glue layer that 0.1mm is thick between film, two layers of polypropylene film;Using double-deck isolated film as an entirety, Prevent occurring misplacing in work progress and breakage, meanwhile, epoxy glue layer has good insulation and toughness, to the later stage Concrete pour with good basic effect;
Transmission rod is installed, sets up straight by spacing of the power transmission between dry and transmission rod on locating template, locating template in template both sides Footpath is drilled, and transmission rod one end is fixed for one section, the transmission rod is uniformly arranged in transmission rod through drilling by spot welding with support At terrace plate thickness 1/2;The transmission rod is vertical with locating template, and the outside of transmission rod brushes pitch and carries out colligation again in advance On support,
The preparation of concrete:Steel fibre, sand and rubble are stirred;Cement, flyash, boiling are once added in stirring thing Stone flour, silicon ash water and auxiliary agent are stirred, and the content of the steel fibre is 20kg/m3;The slump of the concrete is less than 5cm, the intensity of concrete is that grade is C30.
Poured using sequence placing method, using catching up with slurry processes to be promoted, during concreting, virtual resurfacing thickness is than actual Thickness is higher by 5mm or so, is vibrated using vibrating spear, after completion is vibrated, is rolled repeatedly using steel pipe roller, until surface goes out Existing bleeding state;For the diamond-shaped area of building on the peripheries such as cylinder, diamond-shaped area pours one week after or so first, carries out secondary Pour, it is to avoid surrounding terrace stress, which is concentrated, produces crack;
Step 4:Leveling, is constructed using being flattened from periphery to center centralized system, and concrete surface flatness is met construction will Ask;
Step 5:When concrete initial set is to 50%-60%, one layer of quartz sand particle is dispensed;Carried out at least twice using trowel ray machine Polishing, is allowed to be combined with concrete, carries out floating warehouse, and it is 0-3mm to make its flatness;Second of quartz sand particle is carried out to spread Cloth, carries out trowel ray machine operation at least twice, and operation is crisscross to be carried out, and floating warehouse, flatness reaches 0-3mm;Carry out the 3rd Secondary quartz sand particle is dispensed, and is carried out at least three times and is not installed the trowel ray machine operation of disk additional, while coordinate craft to be polished, it is floating Warehouse, flatness reaches 0-2mm.
The ratio between consumption of three spreadings quartz sand particle is 4:1:1.
Step 6:Maintenance:Sprinkling sealing compound is conserved after abrasion-proof terrace construction 10h, and consumption is 0.2L/m2, prevent out Split, curing time is no less than 7d;
Step 7:The slot cementation of fissures is constructed.After concreting 30h-60h, lancing operation is carried out, deep and concrete thickness ratio is stitched For 2/3, slit width is 5mm;The debris such as microlith, cement mortar in the progress cementation of fissures, thorough cleaning slot, with air compressor machine or crack-cleaning machine Dust on seam bottom, latasuture is blown clean, and keeps drying;It is 3 that contracting, which seams closure material breadth depth ratio,:5, minimum crack pouring width is 6mm-8mm;The joint seal material breadth depth ratio on expansion joint (E.J.) material top is 3:2.
Terrace surface is handled.
The compression strength of the present embodiment concrete improves 15% compared with the normal concrete compression strength of ad eundem;From By expansion and contraction compared with normal concrete, 30% is reduced.

Claims (10)

1. a kind of concrete abrasion-resistant terrace construction technique, it is characterised in that:Comprise the following steps:
Step one:Base treatment:Basic unit is cleared up, absolute altitude is carried out and compacting is constructed;
Step 2:Template is laid:Template laying is carried out according to concrete point bin location;
Step 3:Concreting:Constructed using sequence placing mode;
Step 4:Leveling, is constructed using being flattened from periphery to center centralized system, and concrete surface flatness is met construction will Ask;
Step 5:Wearing layer, the spreading of three progress high-abrasive materials of part are laid, and is carried out levelling;
Step 6:Maintenance:Sealing compound is sprayed, cracking is prevented;
Step 7:The slot cementation of fissures is constructed.
2. a kind of concrete abrasion-resistant terrace construction technique according to claim 1, it is characterised in that:Described in step one at basic unit The detailed process of reason includes:Base cleaning is clean;Bottom element soil is compacted;Lay broken sandstone and and conserved.
3. a kind of concrete abrasion-resistant terrace construction technique according to claim 2, it is characterised in that:The plain soil compaction system Number is 0.95, and flatness scope is 0-3mm.
4. a kind of concrete abrasion-resistant terrace construction technique according to claim 1, it is characterised in that:Step 3 specifically include with Lower process:The double-deck polypropylene isolated film of laying;The preparation of concrete;Poured using sequence placing method;Progress, which is vibrated, looks for It is flat.
5. a kind of concrete abrasion-resistant terrace construction technique according to claim 4, it is characterised in that:The preparation of the concrete Method includes:Steel fibre, sand and rubble are stirred;Cement, flyash, zeolite powder, silicon ash are once added in stirring thing Water and auxiliary agent are stirred.
6. a kind of concrete abrasion-resistant terrace construction technique according to claim 4, it is characterised in that:The slump of the concrete Degree is less than 5cm.
7. a kind of concrete abrasion-resistant terrace construction technique according to claim 1, it is characterised in that:Step 5 is specifically included: When concrete initial set is to 50%-60%, one layer of quartz sand particle is dispensed;Floating warehouse is carried out, it is 0-3mm to make its flatness;Enter Second of quartz sand particle of row is dispensed, and floating warehouse, flatness reaches 0-3mm;Third time quartz sand particle spreading is carried out, it is floating Warehouse, flatness reaches 0-2mm.
8. a kind of concrete abrasion-resistant terrace construction technique according to claim 7, it is characterised in that:Three spreadings quartz The ratio between consumption of sand particle is 4:1:1.
9. a kind of concrete abrasion-resistant terrace construction technique according to claim 1, it is characterised in that:Step 7 is specifically included: After concreting 30h-60h, lancing operation is carried out, seam depth and concrete thickness ratio is between 1/3-3/5.
10. a kind of concrete abrasion-resistant terrace construction technique according to claim 1, it is characterised in that:The slit width is 3- 5mm。
CN201710466662.1A 2017-06-20 2017-06-20 A kind of concrete abrasion-resistant terrace construction technique Pending CN107152147A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710466662.1A CN107152147A (en) 2017-06-20 2017-06-20 A kind of concrete abrasion-resistant terrace construction technique

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710466662.1A CN107152147A (en) 2017-06-20 2017-06-20 A kind of concrete abrasion-resistant terrace construction technique

Publications (1)

Publication Number Publication Date
CN107152147A true CN107152147A (en) 2017-09-12

Family

ID=59796389

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710466662.1A Pending CN107152147A (en) 2017-06-20 2017-06-20 A kind of concrete abrasion-resistant terrace construction technique

Country Status (1)

Country Link
CN (1) CN107152147A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110835997A (en) * 2019-11-29 2020-02-25 上海宝冶集团有限公司 One-step construction molding construction process for wear-resistant terrace and structural plate
CN111620662A (en) * 2020-06-16 2020-09-04 湘潭大学 Concrete doped with modified zeolite
CN111962349A (en) * 2020-07-18 2020-11-20 北京住总第一开发建设有限公司 Wear-resistant concrete ground construction process
CN112282294A (en) * 2020-10-23 2021-01-29 安徽四建控股集团有限公司 Construction method of steel fiber wear-resistant terrace
CN112942764A (en) * 2021-01-29 2021-06-11 武汉固立达建筑科技有限公司 Terrace integrated structure and construction method thereof
CN114135077A (en) * 2021-11-08 2022-03-04 中建四局第六建设有限公司 Concrete super-building reset cutting floor construction method free of warehouse dividing strip structure

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS54127130A (en) * 1978-03-25 1979-10-02 Kanebo Ltd Method of executing floor foundation material
US20030091793A1 (en) * 2001-11-09 2003-05-15 Morton Steven E. Wear-resistant reinforcing coating
CN102691401A (en) * 2012-06-15 2012-09-26 北京城建建设工程有限公司 Construction method for large-area concrete weighbridge
CN104108911A (en) * 2013-04-17 2014-10-22 北京江达雷博建筑装饰品有限公司 Production formula and construction technology of ultra-wear-resistant ground
CN104314289A (en) * 2014-11-07 2015-01-28 广西壮族自治区冶金建设公司 Wear-resisting concrete terrace overall molding construction method
CN106401144A (en) * 2016-06-23 2017-02-15 青岛海川建设集团有限公司 Construction technology for addition type wear resisting concrete ground
CN105587102B (en) * 2016-03-01 2018-08-17 黑龙江泽林科技有限公司 A kind of wet construction method to the wet type high abrasion terrace that paves

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS54127130A (en) * 1978-03-25 1979-10-02 Kanebo Ltd Method of executing floor foundation material
US20030091793A1 (en) * 2001-11-09 2003-05-15 Morton Steven E. Wear-resistant reinforcing coating
CN102691401A (en) * 2012-06-15 2012-09-26 北京城建建设工程有限公司 Construction method for large-area concrete weighbridge
CN104108911A (en) * 2013-04-17 2014-10-22 北京江达雷博建筑装饰品有限公司 Production formula and construction technology of ultra-wear-resistant ground
CN104314289A (en) * 2014-11-07 2015-01-28 广西壮族自治区冶金建设公司 Wear-resisting concrete terrace overall molding construction method
CN105587102B (en) * 2016-03-01 2018-08-17 黑龙江泽林科技有限公司 A kind of wet construction method to the wet type high abrasion terrace that paves
CN106401144A (en) * 2016-06-23 2017-02-15 青岛海川建设集团有限公司 Construction technology for addition type wear resisting concrete ground

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
吕俊冕: "钢纤维混凝土配合比设计耐磨地坪施工技术的探讨", 《广东建材》 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110835997A (en) * 2019-11-29 2020-02-25 上海宝冶集团有限公司 One-step construction molding construction process for wear-resistant terrace and structural plate
CN111620662A (en) * 2020-06-16 2020-09-04 湘潭大学 Concrete doped with modified zeolite
CN111962349A (en) * 2020-07-18 2020-11-20 北京住总第一开发建设有限公司 Wear-resistant concrete ground construction process
CN112282294A (en) * 2020-10-23 2021-01-29 安徽四建控股集团有限公司 Construction method of steel fiber wear-resistant terrace
CN112942764A (en) * 2021-01-29 2021-06-11 武汉固立达建筑科技有限公司 Terrace integrated structure and construction method thereof
CN114135077A (en) * 2021-11-08 2022-03-04 中建四局第六建设有限公司 Concrete super-building reset cutting floor construction method free of warehouse dividing strip structure

Similar Documents

Publication Publication Date Title
CN107152147A (en) A kind of concrete abrasion-resistant terrace construction technique
CN102535296B (en) Construction method of superheavy-load reinforcement-free large-area seamless epoxy self-leveling terrace
CN105587102B (en) A kind of wet construction method to the wet type high abrasion terrace that paves
CN107143111A (en) A kind of construction method of abrasion-proof terrace
CN106401144A (en) Construction technology for addition type wear resisting concrete ground
CN105040554A (en) Garden path structure and paving construction technology thereof
CN207228171U (en) Concrete floor waterproofing node is worn under a kind of steel column
CN104929365B (en) Refuse of refuse burning generating plant discharging platform combined type surface construction technology
CN109457728A (en) A kind of steel reinforced concrete pipe gallery quickly builds construction method
JP6051497B1 (en) Inorganic material construction method
JP4537938B2 (en) Block pavement construction method
CN103790168A (en) Application method of soil nailing wall in deep foundation pit supporting
JP5974346B1 (en) Inorganic material construction method
CN104529322A (en) Iron tailings roller compacted concrete for pavement
CN108947464B (en) Ground surface layer based on phosphorus-magnesium material and construction process thereof
CN105155387A (en) Garden road structure
CN111042310A (en) Basement bottom plate structure and construction method thereof
CN104878672A (en) Stone-planted cement concrete bridge deck paving structure and method
CN213115347U (en) Dampproof ground
CN102535493B (en) Method for constructing inverted type foundation beam
CN114876155A (en) Construction process for polishing ground by using non-ignition fine stone concrete
CN108179672A (en) A kind of sponge-type road structure and its method for paving
CN109440572B (en) Construction method for laying temporary road in coal mine pit by prefabricated slab
CN106436517A (en) Construction method of soft soil anti-collapse concrete road surface
CN111851939A (en) Oil-seepage-preventing ground structure and construction method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170912