CN107060703B - Multiple expansion sand control screen well completion technique tubular pile in a kind of casing - Google Patents

Multiple expansion sand control screen well completion technique tubular pile in a kind of casing Download PDF

Info

Publication number
CN107060703B
CN107060703B CN201710510990.7A CN201710510990A CN107060703B CN 107060703 B CN107060703 B CN 107060703B CN 201710510990 A CN201710510990 A CN 201710510990A CN 107060703 B CN107060703 B CN 107060703B
Authority
CN
China
Prior art keywords
variable buckle
tubular column
screen
completion tubular
packer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710510990.7A
Other languages
Chinese (zh)
Other versions
CN107060703A (en
Inventor
杨文领
张恒
王玥
陈世春
张文华
吴欣袁
张立娜
刘洋
于学良
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China National Petroleum Corp
CNPC Bohai Drilling Engineering Co Ltd
Original Assignee
CNPC Bohai Drilling Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CNPC Bohai Drilling Engineering Co Ltd filed Critical CNPC Bohai Drilling Engineering Co Ltd
Priority to CN201710510990.7A priority Critical patent/CN107060703B/en
Publication of CN107060703A publication Critical patent/CN107060703A/en
Application granted granted Critical
Publication of CN107060703B publication Critical patent/CN107060703B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B43/00Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
    • E21B43/14Obtaining from a multiple-zone well
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B43/00Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
    • E21B43/02Subsoil filtering
    • E21B43/10Setting of casings, screens, liners or the like in wells
    • E21B43/103Setting of casings, screens, liners or the like in wells of expandable casings, screens, liners, or the like
    • E21B43/108Expandable screens or perforated liners

Abstract

The invention discloses multiple expansion sand control screen well completion technique tubular piles in a kind of casing, it is connected in sequence including lower layer's completion tubular column and at least one upper layer completion tubular column, lower layer's completion tubular column is followed successively by screen casing guide shoe, lower variable buckle, expandable screen, upper variable buckle and hanging packer from bottom to top, and upper layer completion tubular column is followed successively by hanging packer from top to bottom, upper variable buckle, expansion sand control screen, lower variable buckle, mechanical-set packer, is located connector and horn mouth.Hanging packer and mechanical-set packer card sealing pipe column upper and lower ends respectively, the casing string and other layers of tubing string are separated;The horn mouth of top tubing string allows lower part oil gas to pass through, and realizes laminated up and down adopt;Lower layer's completion tubular column can be shut with tripping in blanking plug by being located connector, and blanking plug can be salvaged when needing to reopen;Upper and lower layer completion tubular column is relatively independent, and inside can realize the opening and closing of any layer position with tripping in separate zone production tubing string;Execute-in-place is convenient, and construction risk is low.

Description

Multiple expansion sand control screen well completion technique tubular pile in a kind of casing
Technical field
The present invention relates to a kind of well completion technique tubular pile, multiple expansion sand control screen well-completing process pipe in especially a kind of casing Column.
Background technique
Expandable screen completion technique can be used in barefoot completion and the complete well of well-case perforating, with mechanical swelling tool or hydraulic swollen Screen casing distending is plastically deformed screen casing by swollen tool, and the screen casing after expansion can be used as the support of the borehole wall, screen casing and the borehole wall Between there is no annular space, the migration and screen casing related to this for reducing sand grains are blocked.Due to there is no annular space between screen casing and the borehole wall, therefore Sand impinging and erosion problem can be reduced to the maximum extent, improve filter sand area to the maximum extent, and can be to reservoir reality Apply further operation processing and control.
As shown in Figure 1, conventional expandable screen completion tubular column be from bottom to top screen casing guide shoe 8, lower variable buckle 4, expandable screen 3, Upper variable buckle 2 and hanging packer 1,3 upper and lower ends of expandable screen connect upper variable buckle 2 and lower variable buckle by expandable screen special screw thread 4,3 upper end of expandable screen is connect by upper variable buckle 2 with hanging packer 1, and lower end is connect by lower variable buckle 4 with screen casing guide shoe 8, whole Set expandable screen is suspended in casing by hanging packer 1.
But if reservoir there are multiple substratums, there is interlayer perhaps water layer or there are edge-bottom water between layers, Completion tubular column needs to realize segmentation.
Summary of the invention
The technical problem to be solved by the invention is to provide multiple expansion sand control screen well-completing process pipes in a kind of casing Column can be further improved expandable screen completion technique applicability to realize that separate zone production function provides condition.
In order to solve the above-mentioned technical problem, the technical solution adopted by the present invention is that: multiple expansion sand screen in a kind of casing Pipe well completion technique tubular pile, including lower layer's completion tubular column and at least one upper layer completion tubular column are connected in sequence, and lower layer is complete Well casing column is followed successively by screen casing guide shoe, lower variable buckle, expandable screen, upper variable buckle and hanging packer, upper layer completion tubular column from bottom to top Be followed successively by from top to bottom hanging packer, upper variable buckle, expansion sand control screen, lower variable buckle, mechanical-set packer, be located connector and Horn mouth.
Lower layer's completion tubular column: expandable screen upper and lower ends connect upper variable buckle and lower change by expandable screen special screw thread Button, expandable screen upper end are connect by upper variable buckle with hanging packer, and lower end is connect by lower variable buckle with screen casing guide shoe;On described Layer completion tubular column: expandable screen upper and lower ends are connected by expandable screen special screw thread goes up variable buckle and lower variable buckle, on expandable screen End is connect by upper variable buckle with hanging packer, and lower end is connected by lower variable buckle with mechanical-set packer, and machinery sets packing Device is connected by being located connector with horn mouth.
The beneficial effects of the present invention are:
1. hanging packer and mechanical-set packer card sealing pipe column upper and lower ends respectively, by the casing string and other layers of pipe Column separates;
2. the horn mouth of top tubing string allows lower part oil gas to pass through, laminated up and down adopt is realized;
3. lower layer's completion tubular column can be shut with tripping in blanking plug by being located connector, blocking can be salvaged when needing to reopen Device;
4. upper and lower layer of completion tubular column is relatively independent, inside can realize opening for any layer position with tripping in separate zone production tubing string It closes;
5. execute-in-place is convenient, construction risk is low.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of conventional expandable screen completion tubular column;
Fig. 2 is the structural schematic diagram of multiple expansion sand control screen well completion technique tubular pile in casing of the invention.
Specific embodiment
Invention is further described in detail with reference to the accompanying drawings and detailed description:
As shown in Fig. 2, multiple expansion sand control screen well completion technique tubular pile in casing of the invention, including a complete well of lower layer Tubing string and at least one upper layer completion tubular column are connected in sequence, lower layer's completion tubular column be followed successively by from bottom to top screen casing guide shoe 8, under Variable buckle 4, expandable screen 3, upper variable buckle 2 and hanging packer 1, upper layer completion tubular column be followed successively by from top to bottom hanging packer 11, Upper variable buckle 12, lower variable buckle 14, mechanical-set packer 15, is located connector 16 and horn mouth 17 at expansion sand control screen 13.
Specifically, lower layer's completion tubular column: 3 upper and lower ends of expandable screen pass through in the connection of expandable screen special screw thread Variable buckle 2 and lower variable buckle 4,3 upper end of expandable screen are connect by upper variable buckle 2 with hanging packer 1, and lower end passes through lower variable buckle 4 and sieve Pipe guide shoe 8 connects;The upper layer completion tubular column: 13 upper and lower ends of expandable screen connect upper variable buckle by expandable screen special screw thread 12 and lower variable buckle 14,13 upper end of expandable screen connect by upper variable buckle 12 with hanging packer 11, lower end by lower variable buckle 14 with Mechanical-set packer 15 is connected, and mechanical-set packer 15 is connected by being located connector 16 with horn mouth 17.
The present embodiment at the middle and upper levels completion tubular column be one layer, conventional expandable screen completion tubular column be from bottom to top screen casing guide shoe 8, Lower variable buckle 4, expandable screen 3, upper variable buckle 2 and hanging packer 1,3 upper and lower ends of expandable screen pass through expandable screen special screw thread Variable buckle 2 and lower variable buckle 4 in connection, 3 upper end of expandable screen are connect by upper variable buckle 2 with hanging packer 1, and lower end passes through lower variable buckle 4 connect with screen casing guide shoe 8, and a whole set of expandable screen is suspended in casing by hanging packer 1.It is most lower when needing to realize segmentation One layer is conventional expandable screen completion tubular column, and top tubing string connects mechanical-set packer 15 in lower 14 lower end of variable buckle, is located and connects First 16 and horn mouth 17, tubing string is above and below respectively by hanging packer 11 and mechanical-set packer 15 by tubing string card Feng Duli Out, lower part oil gas enters top tubing string from horn mouth, when lower tubular column water outlet or other situations need to be shut to prevent When influencing upper layer tubing string, lower layer's tubing string can be blocked being located the matched blanking plug of tripping at connector 16, be opened again if necessary It only needs to salvage blanking plug when opening.
Completion tubular column tripping in is connected, sequence is screen casing guide shoe 8, lower variable buckle 4, expandable screen 3,2 and of upper variable buckle from bottom to up Hanging packer 1, tubing string in place after connecting pipeline pressure sit and hang and releasing equipment suspension packer 1, tripping in expansion tool is by expanded screen 3 distending of pipe.Upper operating is repeated, by top completion tubular column tripping in, sequence is horn mouth 17, is located connector 16, machine from bottom to up Tool set packer 15, lower variable buckle 14, expandable screen 13, upper variable buckle 12 and hanging packer 11, tubing string in place after connecting pipeline Pressure, which is sat, hangs and releasing equipment suspension packer 11, and tripping in expansion tool is by 13 distending of expandable screen, while by mechanical-set packer 15 set, and realize that upper and lower level completion tubular column separates.When the water outlet of lower layer's tubing string or other situations need to be shut to prevent shadow When ringing upper layer tubing string, using coiled tubing or cable wire power tool by blanking plug down toward being located in connector 16, if any must It only needs to salvage blanking plug when reopening.
Multiple expansion sand control screen well completion technique tubular pile in casing of the present invention, is mainly used in expandable screen after well-case perforating In completion practice, when there are multiple substratums for reservoir, there is interlayer perhaps water layer or there are edge-bottom waters between layers, use Expandable screen interval separation function may be implemented in the casing string, to realize that separate zone production function provides condition, can further mention High expansion screen pipe completion technique applicability.
In conclusion the contents of the present invention are not limited in the above embodiments, the knowledgeable people in same area can Can propose other embodiments easily within technological guidance's thought of the invention, but this embodiment is included in this hair Within the scope of bright.

Claims (1)

1. multiple expansion sand control screen well completion technique tubular pile in a kind of casing, which is characterized in that including lower layer's completion tubular column Completion tubular column is connected in sequence at least one upper layer, and upper and lower layer completion tubular column is relatively independent, and inside can be layered with tripping in Mining tubular column, lower layer's completion tubular column are followed successively by screen casing guide shoe (8), lower variable buckle (4), expandable screen (3), upper variable buckle from bottom to top (2) and hanging packer (1), upper layer completion tubular column are followed successively by hanging packer (11), upper variable buckle (12), expanded screen from top to bottom Pipe (13), mechanical-set packer (15), is located connector (16) and horn mouth (17) at lower variable buckle (14);Lower layer's completion tubular Column: expandable screen (3) upper and lower ends are threadedly coupled by expandable screen goes up variable buckle (2) and lower variable buckle (4), on expandable screen (3) End is connect by upper variable buckle (2) with hanging packer (1), and lower end is connect by lower variable buckle (4) with screen casing guide shoe (8);On described Layer completion tubular column: expandable screen (13) upper and lower ends are threadedly coupled upper variable buckle (12) and lower variable buckle (14) by expandable screen, swollen Swollen screen casing (13) upper end is connect by upper variable buckle (12) with hanging packer (11), and lower end is set by lower variable buckle (14) with machinery Packer (15) is connected, and mechanical-set packer (15) is connected by being located connector (16) with horn mouth (17).
CN201710510990.7A 2017-06-28 2017-06-28 Multiple expansion sand control screen well completion technique tubular pile in a kind of casing Active CN107060703B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710510990.7A CN107060703B (en) 2017-06-28 2017-06-28 Multiple expansion sand control screen well completion technique tubular pile in a kind of casing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710510990.7A CN107060703B (en) 2017-06-28 2017-06-28 Multiple expansion sand control screen well completion technique tubular pile in a kind of casing

Publications (2)

Publication Number Publication Date
CN107060703A CN107060703A (en) 2017-08-18
CN107060703B true CN107060703B (en) 2019-06-07

Family

ID=59613572

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710510990.7A Active CN107060703B (en) 2017-06-28 2017-06-28 Multiple expansion sand control screen well completion technique tubular pile in a kind of casing

Country Status (1)

Country Link
CN (1) CN107060703B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110924903A (en) * 2019-12-06 2020-03-27 中国石油集团渤海钻探工程有限公司 Selective plugging process pipe column for screen pipe well completion

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110500065B (en) * 2019-09-20 2024-03-08 德州众凯石油科技有限公司 Screen pipe structure capable of being floated and lowered into oil-gas well

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5954133A (en) * 1996-09-12 1999-09-21 Halliburton Energy Services, Inc. Methods of completing wells utilizing wellbore equipment positioning apparatus
US7048048B2 (en) * 2003-06-26 2006-05-23 Halliburton Energy Services, Inc. Expandable sand control screen and method for use of same
CN202900175U (en) * 2012-07-26 2013-04-24 中国石油天然气股份有限公司 Gas storage suspending pressure meter manometry completion pipe string
CN103758494B (en) * 2014-01-10 2015-06-10 东营市福利德石油科技开发有限责任公司 Horizontal well external staged fracturing sand control string and method
CN103726813B (en) * 2014-01-13 2016-05-11 安东柏林石油科技(北京)有限公司 In the outer packing ring of Oil/gas Well filter tubing string, set up the method for packing
CN203925434U (en) * 2014-05-15 2014-11-05 中国石油天然气股份有限公司 Underground natural gas storage tank horizontal well completion tubular pile
CN106401537A (en) * 2016-11-16 2017-02-15 中国石油大学(华东) Well completion pipe string of underground gas storage well and well completion method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110924903A (en) * 2019-12-06 2020-03-27 中国石油集团渤海钻探工程有限公司 Selective plugging process pipe column for screen pipe well completion

Also Published As

Publication number Publication date
CN107060703A (en) 2017-08-18

Similar Documents

Publication Publication Date Title
CN103339346B (en) For the method and apparatus completing multilevel well
CN107060703B (en) Multiple expansion sand control screen well completion technique tubular pile in a kind of casing
CN109154186A (en) Geothermal energy extracts underground system
CN103429843B (en) There is the flow control screen pipe assembly of reverse flow control ability
CN103573230B (en) A kind of selectivity production practice and its equipment
US9140098B2 (en) Downhole isolation and depressurization tool
CN103643931A (en) Completion and fracture integrated pipe column of offshore openhole horizontal well and construction method of pipe column
CN103912257B (en) A kind of dragging multiple fracturing device with pressure
CN205445558U (en) Novel double pump technology tubular column in pit
CN204283371U (en) Completion tubular column
US3630640A (en) Method and apparatus for gas-lift operations in oil wells
CN207080211U (en) A kind of hydraulic control multilevel hierarchy water injection string
US7048059B2 (en) Annulus pressure control system for subsea wells
CN108368735A (en) Downhole system
US2972379A (en) Pressure operated dual completion apparatus and method of positioning same in a well bore
CN208564457U (en) A kind of horizontal well multistage fracturing tubing string
US9359856B2 (en) Swellable packer in hookup nipple
CN101649732A (en) Sand recontrol technology without moving sand control pipe columns
CN110359875A (en) Extend airlift unit and method
RU2726096C1 (en) Method for completion of construction of production well with horizontal end of wellbore
CN203822281U (en) Under-pressure dragging type separate-layer fracturing device
CN105089601B (en) A kind of infinite stages sliding sleeve and process
CN112177581B (en) Repeated fracturing method for old well
CN107476785A (en) A kind of closed flow string of the double submersible electric pumps of Oil/gas Well series connection
CN103321626A (en) Fracture and sand prevention integrated completion pipe string and application method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20210208

Address after: 100007 No. 9 North Main Street, Dongcheng District, Beijing, Dongzhimen

Patentee after: CHINA NATIONAL PETROLEUM Corp.

Patentee after: CNPC Bohai Drilling Engineering Co.,Ltd.

Address before: China Petroleum Tianjin building Bohai Drilling Engineering Co., Ltd., No. 83, Second Street, economic and Technological Development Zone, Binhai New Area, Tianjin, 300457

Patentee before: CNPC Bohai Drilling Engineering Co.,Ltd.