CN107059523A - A kind of construction method that road is built on reclaimed ground and the subgrade strengthening structure of construction method formation - Google Patents

A kind of construction method that road is built on reclaimed ground and the subgrade strengthening structure of construction method formation Download PDF

Info

Publication number
CN107059523A
CN107059523A CN201710471393.8A CN201710471393A CN107059523A CN 107059523 A CN107059523 A CN 107059523A CN 201710471393 A CN201710471393 A CN 201710471393A CN 107059523 A CN107059523 A CN 107059523A
Authority
CN
China
Prior art keywords
layer
soil
bag
sump
laid
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710471393.8A
Other languages
Chinese (zh)
Inventor
尹长权
刘润
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin University
Original Assignee
Tianjin University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin University filed Critical Tianjin University
Priority to CN201710471393.8A priority Critical patent/CN107059523A/en
Publication of CN107059523A publication Critical patent/CN107059523A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C3/00Foundations for pavings
    • E01C3/04Foundations produced by soil stabilisation
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/10Restraining of underground water by lowering level of ground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/02Improving by compacting
    • E02D3/10Improving by compacting by watering, draining, de-aerating or blasting, e.g. by installing sand or wick drains
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/02Improving by compacting
    • E02D3/10Improving by compacting by watering, draining, de-aerating or blasting, e.g. by installing sand or wick drains
    • E02D3/103Improving by compacting by watering, draining, de-aerating or blasting, e.g. by installing sand or wick drains by installing wick drains or sand bags

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • General Engineering & Computer Science (AREA)
  • Hydrology & Water Resources (AREA)
  • Agronomy & Crop Science (AREA)
  • Soil Sciences (AREA)
  • Architecture (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

本发明公开了一种在吹填土地基上构建道路的施工方法及该施工方法形成的路基加固结构,通过将充填淤泥膜袋与三维复合排水网、集水井排水相结合,在吹填土上层形成硬壳结构,初步形成路基结构;然后,打设深层塑料排水板,铺设砂层,并通过设置超载预压荷载,向膜袋层和吹填土地基施加压力,以进一步促进膜袋内的充填淤泥土水分的排出和吹填土地基水分的排出,实现同时对充泥袋和深层地基土进行加固;当路基变形条件满足工程需求后卸掉荷载,修筑上部路基和路面。

The invention discloses a construction method for constructing a road on a dredged fill soil foundation and a roadbed reinforcement structure formed by the construction method. By combining the filled silt film bag with a three-dimensional composite drainage network and water collection well drainage, the upper layer of the dredged fill soil The hard shell structure is formed, and the subgrade structure is initially formed; then, the deep plastic drainage board is laid, the sand layer is laid, and the pressure is applied to the membrane bag layer and the blown fill soil foundation by setting an overload preload to further promote the drainage in the membrane bag. The water discharge of the filled silt soil and the water discharge of the dredged soil foundation realize simultaneous reinforcement of the mud bag and deep foundation soil; when the deformation conditions of the roadbed meet the engineering requirements, the load is removed, and the upper roadbed and road surface are built.

Description

一种在吹填土地基上构建道路的施工方法及该施工方法形成 的路基加固结构A construction method for constructing a road on a dredger filled soil foundation and the formation of the construction method roadbed reinforcement structure

技术领域technical field

本发明属于土木工程软弱地基道路结构的设计与施工技术领域,具体涉及一种在吹填土地基上构建道路的施工方法。The invention belongs to the technical field of design and construction of road structures on weak foundations of civil engineering, and in particular relates to a construction method for building roads on dredging and filling soil foundations.

背景技术Background technique

近年来随着我国港口建设的快速发展,土地资源不足的现象日益突出,围海造陆已经成为现今大多数港口城市解决工业用地的重要手段。In recent years, with the rapid development of my country's port construction, the phenomenon of insufficient land resources has become increasingly prominent, and land reclamation has become an important means for most port cities to solve industrial land.

为了吹填造陆、防潮防浪及运输方面的要求,需要在吹填土上面建造海挡、围埝和道路。传统方法需要大量外运粉细砂、山皮土、块石等地工程材料。这些地材的开采、运输以及施工既对材料的采集地点造成环境破坏,又对海洋均有造成污染及破坏,同时。工程量大、费用高。因此,为了降低成本,保护环境,需要研发一种新型道路施工的方法。In order to meet the requirements of land reclamation, tide and wave prevention, and transportation, it is necessary to build sea blocks, fences and roads on the dredger fill. The traditional method requires a large amount of external engineering materials such as silt, fine sand, mountain soil, and block stones. The mining, transportation and construction of these ground materials not only cause environmental damage to the location where the materials are collected, but also cause pollution and damage to the ocean. The amount of work is large and the cost is high. Therefore, in order to reduce costs and protect the environment, it is necessary to develop a new method for road construction.

发明内容Contents of the invention

本发明的目的在于克服现有技术的不足,提供一种在吹填土地基上构建道路的施工方法。The purpose of the invention is to overcome the deficiencies of the prior art and provide a construction method for constructing a road on a dredged fill foundation.

本发明是通过以下技术方案实现的:The present invention is achieved through the following technical solutions:

一种在吹填土地基上构建道路的施工方法,其包括以下步骤:A construction method for constructing a road on a dredger filled soil foundation, comprising the following steps:

步骤一:排出地表积水,在原泥面(0)上铺设荆笆或竹笆或网状竹排作为基础工作垫层(1),根据集水井井位情况安放集水井底箱(2),并竖直安装集水井接管(3);Step 1: Drain the accumulated water on the surface, lay brambles or bamboo fences or netted bamboo rafts on the original mud surface (0) as the foundation work cushion (1), place the bottom box of the water collection well (2) according to the well position of the water collection well, and Vertically install the sump connecting pipe (3);

步骤二:在工作垫层(1)上铺设一层土工无纺布(4),并使集水井接管(3)穿过土工无纺布预留的袖筒(5);Step 2: laying a layer of geotechnical non-woven fabric (4) on the working cushion (1), and making the water collection well connecting pipe (3) pass through the reserved sleeve (5) of the geotechnical non-woven fabric;

步骤三:在土工无纺布(4)上铺设一层三维复合排水网(6),并使集水井接管(3)穿过三维复合排水网(6)预留的袖筒(7);Step 3: Lay a layer of three-dimensional composite drainage network (6) on the geotextile non-woven fabric (4), and make the water collection well connecting pipe (3) pass through the reserved sleeve (7) of the three-dimensional composite drainage network (6);

步骤四:在三维复合排水网(6)上铺设一层土工膜袋(8),然后向第一层土工膜袋(8)内充填第一层淤泥质土(9);集水井进行排水,待第一层淤泥(9)固结形成一定强度后,然后重复步骤三和步骤四,继续进行新一层三维复合排水网铺设6和土工膜袋铺设,并充填淤泥质土,直至施工至预设顶标高处;Step 4: Lay a layer of geomembrane bag (8) on the three-dimensional composite drainage network (6), then fill the first layer of muddy soil (9) into the first layer of geomembrane bag (8); After the first layer of silt (9) is consolidated to form a certain strength, then repeat steps 3 and 4, continue to lay a new layer of three-dimensional composite drainage network 6 and geomembrane bag laying, and fill with muddy soil until the construction reaches the predetermined level. Set the top elevation;

步骤五:在最顶层土工膜袋上铺设一层土工无纺布防护层(10),保证无纺布防护层(10)覆盖整个基面,并将其边缘埋入土体;Step 5: Lay a layer of geotechnical non-woven protective layer (10) on the topmost geomembrane bag, ensure that the non-woven protective layer (10) covers the entire base surface, and embed its edge into the soil;

步骤六:在无纺布防护层(10)上铺设砂层(11),然后打设竖向塑料排水板(12),塑料排水板底端深入至吹填土地基层,塑料排水板(12)板头掩埋在砂层(11)中;Step 6: Lay a sand layer (11) on the non-woven protective layer (10), and then set up a vertical plastic drainage board (12), the bottom of the plastic drainage board goes deep into the dredging and filling soil base, and the plastic drainage board (12) The board head is buried in the sand layer (11);

步骤七:在砂层(11)上铺设山皮土结构层(13);Step 7: laying the mountain soil structure layer (13) on the sand layer (11);

步骤八:在山皮土结构层(13)上逐层铺设堆载荷载(14),并进行集水井排水;当变形条件满足工程需求时将堆载荷载(14)卸除,停止集水井排水;Step 8: Lay the heap load (14) layer by layer on the mountain soil structure layer (13), and drain the water collection well; remove the heap load (14) when the deformation conditions meet the engineering requirements, and stop the drainage of the water collection well ;

步骤九:在山皮土结构层(13)上施工砌筑坡肩(15),并施工路面基层(16)和路面面层(17),道路结构完成。Step 9: constructing a masonry shoulder (15) on the mountain soil structure layer (13), and constructing a pavement base (16) and a pavement surface (17), and the road structure is completed.

在上述技术方案中,集水井接管为铁质材料,并进行防腐处理,分节安装,密布多个排水孔洞,外附无纺布滤层;集水井底箱为空腔箱形体,不透水,上方开敞,内部设置潜水泵及排水管路;集水井接管底端密封安装在集水井底箱上,并将排水管路引出集水井接管,从而构成集水井排水系统。In the above technical scheme, the connection pipe of the water collection well is made of iron material, and is treated with anticorrosion, installed in sections, densely covered with multiple drainage holes, and a non-woven filter layer is attached outside; the bottom box of the water collection well is a hollow box shape, impermeable, The top is open, and the submersible pump and drainage pipeline are installed inside; the bottom end of the sump well connection is sealed and installed on the bottom box of the sump well, and the drainage pipeline is led out of the sump well connection, thus forming the drainage system of the sump well.

在上述技术方案中,土工膜袋内的淤泥质土采集自施工当地的软弱土,从而更加方便、经济、环保;充填淤泥质土时,可以根据土性添加淤泥落淤试剂,加速落淤,若一次充填度不足时,可分2次充填,满足层厚要求;根据土体强度增长情况,一般需3天~7天可以进行上一层三维复合排水网铺设和土工膜袋铺设。In the above technical scheme, the silt soil in the geomembrane bag is collected from the weak soil in the construction site, which is more convenient, economical and environmentally friendly; when filling the silt soil, a silt drop reagent can be added according to the soil properties to accelerate the silt drop, If the one-time filling degree is insufficient, it can be filled in two times to meet the layer thickness requirements; according to the increase in soil strength, it usually takes 3 to 7 days to lay the upper layer of three-dimensional composite drainage network and geomembrane bag.

上述施工过程中形成的路基加固结构:在原泥面上铺设工作垫层,工作垫层上依次铺设有多层填充有淤泥质土的膜袋层,且在各膜袋层之间设置有三维复合排水网;在最顶层的膜袋层上铺设砂层,砂层以下打设有竖向塑料排水板,塑料排水板底端深入至吹填土地基层,塑料排水板(12)板头掩埋在砂层(11)中;在膜袋层、三维复合排水网、砂层中竖直设置有集水井;砂层上铺设山皮土结构层,山皮土结构层上铺设堆载荷载层。The subgrade reinforcement structure formed during the above construction process: a working cushion is laid on the raw mud surface, and multiple layers of membrane bags filled with silty soil are successively laid on the working cushion, and a three-dimensional composite layer is arranged between each membrane bag layer. Drainage net; Lay sand layer on the film bag layer of the top layer, be equipped with vertical plastic drainage board below the sand layer, the bottom of plastic drainage board goes deep into the base of dredging and filling soil, and the head of plastic drainage board (12) is buried in the sand In the layer (11), a water collection well is vertically arranged in the film bag layer, the three-dimensional composite drainage network and the sand layer; a mountain soil structure layer is laid on the sand layer, and a heap load bearing layer is laid on the mountain soil structure layer.

本发明的优点和有益效果为:Advantage of the present invention and beneficial effect are:

1,在铺设膜袋层过程中,利用各膜袋层之间的三维复合排水网作为横向排水通道,膜袋层受压后其内部的淤泥质土中的水分被排出,排出的水分沿三维复合排水网横向汇集至集水井内部,然后利用潜水泵将集水井内的水排出,从而快速降低膜袋层淤泥质土的含水量,在吹填土上层形成初步的硬质路基结构;1. In the process of laying the film bag layer, the three-dimensional composite drainage network between the film bag layers is used as the horizontal drainage channel. After the film bag layer is compressed, the water in the muddy soil inside is discharged, and the discharged water flows along the three-dimensional The composite drainage network is collected horizontally to the inside of the water collection well, and then the water in the water collection well is discharged by the submersible pump, thereby rapidly reducing the water content of the silty soil in the film bag layer, and forming a preliminary hard roadbed structure on the upper layer of the dredger fill soil;

然后,打设深层塑料排水板,铺设砂层,并通过设置超载预压荷载,向膜袋层和吹填土地基施加压力,以进一步促进膜袋内的充填淤泥土水分的排出和吹填土地基水分的排出;排水时,塑料排水板作为竖向排水通道,吹填土地基的水分和淤泥质土的水分会进入塑料排水板,塑料排水板的水分通过砂层和三维复合排水网横向汇集至集水井内部(因为三维复合排水网的横向排水通道可能由于打设深层塑料排水板而发生局部堵塞,所以在塑料排水板板头上设置砂层,砂层作为横向排水通道,可以保证塑料排水板的水分沿砂层横向汇集至集水井),然后利用潜水泵将集水井内的水排出,从而实现同时对膜袋层和深层吹填土地基进行加固。Then, lay a deep plastic drainage board, lay a sand layer, and apply pressure to the film bag layer and the blown fill soil foundation by setting an overload preload to further promote the drainage of the filled silt soil moisture in the film bag and the blown fill soil. Drainage of foundation moisture; when draining, the plastic drainage board is used as a vertical drainage channel, and the water in the filled soil foundation and the water in the muddy soil will enter the plastic drainage board, and the water in the plastic drainage board is collected horizontally through the sand layer and the three-dimensional composite drainage network To the inside of the water collection well (because the horizontal drainage channel of the three-dimensional composite drainage network may be partially blocked due to the deep plastic drainage board, so a sand layer is set on the head of the plastic drainage board, and the sand layer is used as a horizontal drainage channel to ensure plastic drainage. The water in the slab is collected laterally along the sand layer to the water collection well), and then the submersible pump is used to discharge the water in the water collection well, so as to realize the simultaneous reinforcement of the membrane bag layer and the deep dredged fill soil foundation.

2,土工膜袋内的淤泥质土采集自施工当地的软弱土,从而更加方便、经济、环保。2. The muddy soil in the geomembrane bag is collected from the weak soil in the construction site, which is more convenient, economical and environmentally friendly.

3,集水井降低了水位,水位位于底层三维复合排水网位置,使充填膜袋内土体和下部地基土体的有效应力增加,有效加固荷载增大。3. The water level of the water collection well is lowered, and the water level is located at the position of the three-dimensional composite drainage network at the bottom, which increases the effective stress of the soil in the filled membrane bag and the soil of the lower foundation, and increases the effective reinforcement load.

4,通过在土工膜袋内充填淤泥质土,膜袋有效截断了水体补充通道,减小周边水体对充填膜袋内土体的不利影响。4. By filling the geomembrane bag with silty soil, the film bag effectively cuts off the water supplement channel and reduces the adverse effects of the surrounding water on the soil in the filled film bag.

5,三维复合排水网在充填膜袋的下方集排水时,能够利用水的自身重力促进集水(即膜袋内土体的水受自身重力向下流入三维复合排水网),区别于传统预压上排水时需克服水的自身重力。5. When the three-dimensional composite drainage network collects and drains water under the filled membrane bag, it can use the gravity of the water to promote water collection (that is, the water in the soil in the membrane bag flows downward into the three-dimensional composite drainage network due to its own gravity), which is different from the traditional prefabricated drainage network. It is necessary to overcome the self gravity of the water when pressing on the drainage.

6,本发明的施工方法可在吹填土地基上直接进行施工,有很好的适应性。6. The construction method of the present invention can be directly constructed on the dredged fill soil foundation, and has good adaptability.

附图说明Description of drawings

图1为本发明的道路结构示意图。Fig. 1 is a schematic diagram of the road structure of the present invention.

图2为图1的A点局部放大示意图。FIG. 2 is a partially enlarged schematic diagram of point A in FIG. 1 .

具体实施方式detailed description

下面结合具体实施例进一步说明本发明的技术方案。The technical solutions of the present invention will be further described below in conjunction with specific embodiments.

参见附图1-2,一种在吹填土地基上构建道路的施工方法,其包括以下步骤:Referring to accompanying drawing 1-2, a kind of construction method of constructing road on dredging fill foundation, it may further comprise the steps:

步骤一:排出地表积水,在原泥面(0)上铺设荆笆或竹笆或网状竹排作为基础工作垫层(1),根据集水井井位情况安放集水井底箱(2),并竖直安装集水井接管(3);Step 1: Drain the accumulated water on the surface, lay brambles or bamboo fences or netted bamboo rafts on the original mud surface (0) as the foundation work cushion (1), place the bottom box of the water collection well (2) according to the well position of the water collection well, and Vertically install the sump connecting pipe (3);

步骤二:在工作垫层(1)上铺设一层土工无纺布(4),并使集水井接管(3)穿过土工无纺布预留的袖筒(5);Step 2: laying a layer of geotechnical non-woven fabric (4) on the working cushion (1), and making the water collection well connecting pipe (3) pass through the reserved sleeve (5) of the geotechnical non-woven fabric;

步骤三:在土工无纺布(4)上铺设一层三维复合排水网(6),并使集水井接管(3)穿过三维复合排水网(6)预留的袖筒(7);Step 3: Lay a layer of three-dimensional composite drainage network (6) on the geotextile non-woven fabric (4), and make the water collection well connecting pipe (3) pass through the reserved sleeve (7) of the three-dimensional composite drainage network (6);

步骤四:在三维复合排水网(6)上铺设一层土工膜袋(8),然后向第一层土工膜袋(8)内充填第一层淤泥质土(9);集水井进行排水,待第一层淤泥(9)固结形成一定强度后,然后重复步骤三和步骤四,继续进行新一层三维复合排水网铺设6和土工膜袋铺设,并充填淤泥质土,直至施工至预设顶标高处;Step 4: Lay a layer of geomembrane bag (8) on the three-dimensional composite drainage network (6), then fill the first layer of muddy soil (9) into the first layer of geomembrane bag (8); After the first layer of silt (9) is consolidated to form a certain strength, then repeat steps 3 and 4, continue to lay a new layer of three-dimensional composite drainage network 6 and geomembrane bag laying, and fill with muddy soil until the construction reaches the predetermined level. Set the top elevation;

步骤五:在最顶层土工膜袋上铺设一层土工无纺布防护层(10),保证无纺布防护层(10)覆盖整个基面,并将其边缘埋入土体;Step 5: Lay a layer of geotechnical non-woven protective layer (10) on the topmost geomembrane bag, ensure that the non-woven protective layer (10) covers the entire base surface, and embed its edge into the soil;

步骤六:在无纺布防护层(10)上铺设砂层(11),然后打设竖向塑料排水板(12),塑料排水板底端深入至吹填土地基层,塑料排水板(12)板头掩埋在砂层(11)中;Step 6: Lay a sand layer (11) on the non-woven protective layer (10), and then set up a vertical plastic drainage board (12), the bottom of the plastic drainage board goes deep into the dredging and filling soil base, and the plastic drainage board (12) The board head is buried in the sand layer (11);

步骤七:在砂层(11)上铺设山皮土结构层(13);Step 7: laying the mountain soil structure layer (13) on the sand layer (11);

步骤八:在山皮土结构层(13)上逐层铺设堆载荷载(14),并进行集水井排水,;当变形条件满足工程需求时将堆载荷载(14)卸除,停止集水井排水;Step 8: Lay the heap load (14) layer by layer on the mountain soil structure layer (13), and drain the water collection well; when the deformation conditions meet the engineering requirements, remove the heap load (14) and stop the water collection well drain;

步骤九:回填集水井或将集水井取出,在山皮土结构层(13)上施工砌筑坡肩(15),并施工路面基层(16)和路面面层(17),道路结构完成。Step 9: backfill the water collection well or take out the water collection well, build a masonry shoulder (15) on the mountain soil structure layer (13), and construct the road base (16) and road surface (17), and the road structure is completed.

在本实施例中,三维复合排水网的抗压强度不小于14KN/m,导水率不小于1/m/s,厚度不小于6mm,袖筒直径60cm,长度60cm,采用土工无纺布进行包裹,并用橡胶皮筋绑扎;In this embodiment, the compressive strength of the three-dimensional composite drainage network is not less than 14KN/m, the hydraulic conductivity is not less than 1/m/s, the thickness is not less than 6mm, the diameter of the sleeve is 60cm, and the length is 60cm. It is wrapped with geotechnical non-woven fabric , and tied with rubber bands;

集水井接管为铁质材料,并进行防腐处理,分节安装,集水井接管管壁密布多个排水孔洞,集水井接管每节高度为1m,外附无纺布滤层,直径为50cm;集水井底箱为高度为65cm的空腔箱形体,不透水,上方开敞,内部设置潜水泵及排水管路;集水井接管底端密封安装在集水井底箱上,并将排水管路引出集水井接管,从而构成集水井排水系统;The connection pipe of the water collection well is made of iron material, and it is anti-corrosion treated. It is installed in sections. The wall of the connection pipe of the water collection well is densely covered with multiple drainage holes. The bottom box of the water well is a cavity box-shaped body with a height of 65cm, which is impermeable and open at the top, and is equipped with a submersible pump and drainage pipeline inside; The water well is connected to form a water collection well drainage system;

土工膜袋由裂膜丝土工布进行缝制,采用包缝或丁缝法,断裂强力不小于20kN/m,垂直渗透参数不小于10-3cm/s;The geomembrane bag is sewn by the split silk geotextile, using the overlock or slit method, the breaking strength is not less than 20kN/m, and the vertical permeability parameter is not less than 10 -3 cm/s;

土工膜袋内的淤泥质土采集自施工当地的软弱土,从而更加方便、经济、环保;充填淤泥质土时,可以根据土性添加淤泥落淤试剂,加速落淤,若一次充填度不足时,可分2次充填,满足层厚要求;根据土体强度增长情况,一般需3天~7天可以进行上一层三维复合排水网铺设和土工膜袋铺设;The silt soil in the geomembrane bag is collected from the weak soil in the construction site, which is more convenient, economical and environmentally friendly; when filling the silt soil, you can add silt silting reagents according to the soil properties to speed up silting, if the filling degree is insufficient , can be filled in two times to meet the layer thickness requirements; according to the increase in soil strength, it usually takes 3 to 7 days to lay the upper layer of three-dimensional composite drainage net and geomembrane bag;

土工无纺布采用200g/m2,袖筒直径60cm,长度60cm;The geotextile non-woven fabric is 200g/m 2 , the sleeve diameter is 60cm, and the length is 60cm;

堆载荷载采用山皮土,高度3m,卸载标准为工后预估沉降不大于30cm,且连续两个月沉降观测沉降量不超过5mm/月;The heap load is made of mountain soil with a height of 3m. The unloading standard is that the estimated settlement after construction is not greater than 30cm, and the settlement observed for two consecutive months does not exceed 5mm/month;

砂层厚度为30cm;The thickness of the sand layer is 30cm;

最后形成的道路结构的边坡坡度宜为1:1;The slope slope of the final road structure should be 1:1;

路面基层为水泥稳定性材料。The pavement base is cement stabilized material.

上述施工方法的地基加固原理如下:The foundation reinforcement principle of the above construction method is as follows:

在铺设膜袋层过程中,利用各膜袋层之间的三维复合排水网作为横向排水通道,膜袋层受压后其内部的淤泥质土中的水分被挤出,挤出的水分沿三维复合排水网横向汇集至集水井内部,然后利用潜水泵将集水井内的水排出,从而快速降低膜袋层淤泥质土的含水量,在吹填土上层形成初步的硬质路基结构;In the process of laying the film bag layer, the three-dimensional composite drainage network between the film bag layers is used as the horizontal drainage channel. The composite drainage network is collected horizontally to the inside of the water collection well, and then the water in the water collection well is discharged by the submersible pump, thereby rapidly reducing the water content of the silty soil in the film bag layer, and forming a preliminary hard roadbed structure on the upper layer of the dredger fill soil;

然后,打设深层塑料排水板,铺设砂层,并通过设置超载预压荷载,向膜袋层和吹填土地基施加压力,以进一步促进膜袋内的充填淤泥土水分的排出和吹填土地基水分的排出;排水时,塑料排水板作为竖向排水通道,吹填土地基的水分和淤泥质土的水分会进入塑料排水板,塑料排水板的水分通过砂层和三维复合排水网横向汇集至集水井内部(因为三维复合排水网的横向排水通道可能由于膜袋层压力过大而发生堵塞或者压塌,所以在塑料排水板板头上设置砂层,砂层作为横向排水通道,可以保证塑料排水板的水分沿砂层横向汇集至集水井),然后利用潜水泵将集水井内的水排出,从而实现同时对膜袋层和深层吹填土地基进行加固。Then, lay a deep plastic drainage board, lay a sand layer, and apply pressure to the film bag layer and the blown fill soil foundation by setting an overload preload to further promote the drainage of the filled silt soil moisture in the film bag and the blown fill soil. Drainage of foundation moisture; when draining, the plastic drainage board is used as a vertical drainage channel, and the water in the filled soil foundation and the water in the muddy soil will enter the plastic drainage board, and the water in the plastic drainage board is collected horizontally through the sand layer and the three-dimensional composite drainage network To the inside of the water collection well (because the horizontal drainage channel of the three-dimensional composite drainage network may be blocked or collapsed due to the excessive pressure of the film bag layer, so a sand layer is set on the head of the plastic drainage board, and the sand layer is used as a horizontal drainage channel to ensure The water in the plastic drainage board collects horizontally along the sand layer to the water collection well), and then uses the submersible pump to drain the water in the water collection well, so as to realize the simultaneous reinforcement of the film bag layer and the deep filling soil foundation.

以上对本发明做了示例性的描述,应该说明的是,在不脱离本发明的核心的情况下,任何简单的变形、修改或者其他本领域技术人员能够不花费创造性劳动的等同替换均落入本发明的保护范围。The present invention has been described as an example above, and it should be noted that, without departing from the core of the present invention, any simple deformation, modification or other equivalent replacements that can be made by those skilled in the art without creative labor all fall within the scope of this invention. protection scope of the invention.

Claims (4)

1. a kind of fill the construction method that mud bag builds road on reclaimed ground, it is characterised in that comprises the following steps:
Step one:Surface pond is discharged, working cushion layer based on chaste tree basketry or bamboo sheathing or netted bamboo raft is laid on former mud face (0) (1) sump under casing (2), and vertically-mounted sump adapter (3), are laid according to sump well location situation;
Step 2:One layer of geotechnological non-woven fabrics (4) is laid on working cushion layer (1), and sump is taken over (3) and passes through geotechnological nonwoven The reserved sleeve (5) of cloth;
Step 3:One layer of three-dimensional composite drainage network (6) is laid on geotechnological non-woven fabrics (4), and sump is taken over (3) and passes through three Tie up the reserved sleeve (7) of composite drainage network (6);
Step 4:One layer of geomembrane bag (8) is laid on three-dimensional composite drainage network (6), then into first layer geomembrane bag (8) Fill first layer muck soil (9);Sump carries out draining, after first layer mud (9) consolidation forms some strength, Ran Houchong Multiple step 3 and step 4, proceed new one layer three-dimensional composite drainage network laying 6 and geomembrane bag laying, and fill Muddy Bottoms Soil, until constructing to default top mark eminence;
Step 5:The geotechnological non-woven fabrics overcoat (10) of one layer of laying on top geomembrane bag, it is ensured that non-woven fabrics overcoat (10) whole basal plane is covered, and by its edge embedded soil body;
Step 6:Layer of sand (11) is laid on non-woven fabrics overcoat (10), vertical plastic draining board (12), plastic row is then set Water plate bottom is deeply to reclaimed ground layer, and plastic draining board (12) wrench is buried in layer of sand (11);
Step 7:Mountain skin soil structure layer (13) is laid on layer of sand (11);
Step 8:Preloading load (14) is successively laid on mountain skin soil structure layer (13), and carries out sump draining;Work as modified strip By preloading load (14) removal when part meets engineering demand, stop sump draining;
Step 9:Slope shoulder (15), and sub-surface of constructing (16) and top course are built in construction by laying bricks or stones on mountain skin soil structure layer (13) (17), road structure is completed.
2. according to claim 1 fill the construction method that mud bag builds road on reclaimed ground, it is characterised in that:Collection Well adapter is ferrous material, and carries out preservative treatment, and merogenesis is installed, and gather multiple draining holes, outer attached non-woven fabrics filtering layer;Collection Well under casing is cavity box-like body, and waterproof, top is open, and inside sets immersible pump and discharge pipe line;Sump takes over bottom It is sealingly mounted on sump under casing, and discharge pipe line is drawn into sump adapter, so as to constitutes sump drainage system.
3. according to claim 1 fill the construction method that mud bag builds road on reclaimed ground, it is characterised in that:Soil Muck soil in work film bag is gathered from local weak soil of constructing;When filling muck soil, mud is added according to soil nature and falls to become silted up Reagent, accelerates to fall to become silted up;According to soil strength growth pattern, by carry out within 3 days~7 days the three-dimensional composite drainage network laying of last layer and Geomembrane bag laying.
4. a kind of subgrade strengthening that mud bag builds the construction method formation of road is filled on reclaimed ground described in claim 1 Structure, it is characterised in that:Laid on former mud face and be equipped with multilayer on working cushion layer, working cushion layer successively filled with muck soil Film bag layer, and each film bag layer between be provided with three-dimensional composite drainage network;Layer of sand, layer of sand are laid on the film bag layer of top Vertical plastic draining board has been set below, and plastic draining board bottom is deeply to reclaimed ground layer, plastic draining board (12) wrench It is buried in layer of sand (11);Sump is vertically arranged with film bag layer, three-dimensional composite drainage network, layer of sand;Mountain is laid on layer of sand Laying preloading load layer on skin soil structure layer, mountain skin soil structure layer.
CN201710471393.8A 2017-06-20 2017-06-20 A kind of construction method that road is built on reclaimed ground and the subgrade strengthening structure of construction method formation Pending CN107059523A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710471393.8A CN107059523A (en) 2017-06-20 2017-06-20 A kind of construction method that road is built on reclaimed ground and the subgrade strengthening structure of construction method formation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710471393.8A CN107059523A (en) 2017-06-20 2017-06-20 A kind of construction method that road is built on reclaimed ground and the subgrade strengthening structure of construction method formation

Publications (1)

Publication Number Publication Date
CN107059523A true CN107059523A (en) 2017-08-18

Family

ID=59595711

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710471393.8A Pending CN107059523A (en) 2017-06-20 2017-06-20 A kind of construction method that road is built on reclaimed ground and the subgrade strengthening structure of construction method formation

Country Status (1)

Country Link
CN (1) CN107059523A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107675693A (en) * 2017-09-27 2018-02-09 中国二十冶集团有限公司 The soft base comprehensive processing method of road peat soil
CN109763388A (en) * 2019-01-16 2019-05-17 安徽鸿宇路桥工程有限公司 A kind of road structure and its construction method
CN111851199A (en) * 2020-07-19 2020-10-30 中铁上海工程局集团有限公司 Temporary construction access road with silt landform and construction method thereof
CN112663593A (en) * 2020-12-17 2021-04-16 安徽建筑大学 Expansive soil foundation drainage system
CN114990950A (en) * 2022-07-14 2022-09-02 中国二十冶集团有限公司 Construction method suitable for reinforcing bad road subgrade

Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1730344A1 (en) * 1990-07-18 1992-04-30 Государственный Проектный Институт "Укрводоканалпроект" Hydraulic fill hydraulic structure
CN1172191A (en) * 1997-07-18 1998-02-04 付长宏 Method for drainage-strengthening of hydraulic-filled soft clay
JP2000319847A (en) * 1999-05-14 2000-11-21 Toyo Constr Co Ltd Covering method for face of slope of rubble mound
CN2911010Y (en) * 2006-06-09 2007-06-13 华南理工大学 Fast reinforcing apparatus for blowing-filling sludge ground
CN101220588A (en) * 2007-01-09 2008-07-16 同济大学 A soft foundation treatment method
CN101270571A (en) * 2007-03-20 2008-09-24 张伯谦 Reinforcing method for demixing sole weight, prepressing water discharge concretion combination dynamic consolidation soft ground base
CN101302757A (en) * 2008-03-07 2008-11-12 张伯谦 Method for quickly processing heavy layer soft soil foundation
CN101701442A (en) * 2009-11-04 2010-05-05 天津大学 Method of building road with large silt filling bag to squeeze silt on deep dredging fill mud
CN102226335A (en) * 2011-04-18 2011-10-26 中交四航工程研究院有限公司 Foundation treatment method for controlling post-construction settlement and deformation of soft soil
CN103031836A (en) * 2013-01-08 2013-04-10 中交四航工程研究院有限公司 Method for quickly building road on new reclamation sludge foundation
CN203200742U (en) * 2013-04-18 2013-09-18 中交上海航道勘察设计研究院有限公司 Drainage consolidation device for processing hydraulic reclamation soft clay
CN104264656A (en) * 2014-09-26 2015-01-07 福建省建研勘察设计院 Method of reinforcing soft soil foundations through downward drainage during vacuum preloading
CN104831688A (en) * 2015-05-14 2015-08-12 广西梧州运龙港船机械制造有限公司 Method for cofferdam construction

Patent Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1730344A1 (en) * 1990-07-18 1992-04-30 Государственный Проектный Институт "Укрводоканалпроект" Hydraulic fill hydraulic structure
CN1172191A (en) * 1997-07-18 1998-02-04 付长宏 Method for drainage-strengthening of hydraulic-filled soft clay
JP2000319847A (en) * 1999-05-14 2000-11-21 Toyo Constr Co Ltd Covering method for face of slope of rubble mound
CN2911010Y (en) * 2006-06-09 2007-06-13 华南理工大学 Fast reinforcing apparatus for blowing-filling sludge ground
CN101220588A (en) * 2007-01-09 2008-07-16 同济大学 A soft foundation treatment method
CN101270571A (en) * 2007-03-20 2008-09-24 张伯谦 Reinforcing method for demixing sole weight, prepressing water discharge concretion combination dynamic consolidation soft ground base
CN101302757A (en) * 2008-03-07 2008-11-12 张伯谦 Method for quickly processing heavy layer soft soil foundation
CN101701442A (en) * 2009-11-04 2010-05-05 天津大学 Method of building road with large silt filling bag to squeeze silt on deep dredging fill mud
CN102226335A (en) * 2011-04-18 2011-10-26 中交四航工程研究院有限公司 Foundation treatment method for controlling post-construction settlement and deformation of soft soil
CN103031836A (en) * 2013-01-08 2013-04-10 中交四航工程研究院有限公司 Method for quickly building road on new reclamation sludge foundation
CN203200742U (en) * 2013-04-18 2013-09-18 中交上海航道勘察设计研究院有限公司 Drainage consolidation device for processing hydraulic reclamation soft clay
CN104264656A (en) * 2014-09-26 2015-01-07 福建省建研勘察设计院 Method of reinforcing soft soil foundations through downward drainage during vacuum preloading
CN104831688A (en) * 2015-05-14 2015-08-12 广西梧州运龙港船机械制造有限公司 Method for cofferdam construction

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107675693A (en) * 2017-09-27 2018-02-09 中国二十冶集团有限公司 The soft base comprehensive processing method of road peat soil
CN109763388A (en) * 2019-01-16 2019-05-17 安徽鸿宇路桥工程有限公司 A kind of road structure and its construction method
CN111851199A (en) * 2020-07-19 2020-10-30 中铁上海工程局集团有限公司 Temporary construction access road with silt landform and construction method thereof
CN112663593A (en) * 2020-12-17 2021-04-16 安徽建筑大学 Expansive soil foundation drainage system
CN114990950A (en) * 2022-07-14 2022-09-02 中国二十冶集团有限公司 Construction method suitable for reinforcing bad road subgrade

Similar Documents

Publication Publication Date Title
CN106759825B (en) Construction method of sponge urban green land water storage system
CN103031836B (en) A kind of method of building road on new hydraulically filled sludge ground fast
CN101250868B (en) Precipitation prepressing association motive power induration deep densification method
CN102995599B (en) Anti-freeze anti-seepage water diversion treatment method of collapsible loess water-conveyance canal
LU500273B1 (en) New comprehensive dewatering and drainage method and drainage device for mudstone subway station
CN103031837A (en) Method for reinforcing deep and soft soil foundation by combining well-points dewatering with preloading
CN107059523A (en) A kind of construction method that road is built on reclaimed ground and the subgrade strengthening structure of construction method formation
CN203174616U (en) Clay foundation rain falling and water saving system
CN205839779U (en) A kind of sandy soil stratum base pit dewatering water level following catch pit structure
CN207143981U (en) 3rd is rich water half diagenesis Sandstone Section Metro station excavation discharge structure
CN110670613A (en) Anti-seepage structure of foundation pit elevator shaft and construction method thereof
CN110093971B (en) Combined water pump house of underground tunnel and construction method thereof
CN102383408B (en) Greening method for high water level impermeable saline and alkaline lands and greening system
CN103266633A (en) Seepage-proof sewage discharging and floodwater draining method for tailing reservoir in wet metallurgy
CN109778625A (en) A kind of express highway roadbed structure that dregs class building castoff fills
CN104711968B (en) Negative-pressure three-dimensional flow-guiding disturbance impact solidification dredger filling method
CN101666082A (en) Laminated consolidation method for reinforcing muddy soft soil foundation
CN107268364A (en) The construction method that mud bag builds road is filled on reclaimed ground
CN103774639A (en) Preloading system and construction method
CN113250139B (en) Composite protection structure for underground water layer of surface mine
CN212405094U (en) High water content clay fill foundation drainage system
CN209482427U (en) A through-wall concealed pipe drainage structure
CN206477347U (en) The water storage structure of basement
CN207031949U (en) A kind of subgrade strengthening structure that road is built on reclaimed ground
CN108914959A (en) A kind of foundation structure and its construction method built suitable for mountain area room

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170818

RJ01 Rejection of invention patent application after publication