CN107023035A - 箱涵连接施工工艺 - Google Patents
箱涵连接施工工艺 Download PDFInfo
- Publication number
- CN107023035A CN107023035A CN201710252935.2A CN201710252935A CN107023035A CN 107023035 A CN107023035 A CN 107023035A CN 201710252935 A CN201710252935 A CN 201710252935A CN 107023035 A CN107023035 A CN 107023035A
- Authority
- CN
- China
- Prior art keywords
- box culvert
- tensioning
- steelframe
- culvert
- box
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/10—Tunnels or galleries specially adapted to house conduits, e.g. oil pipe-lines, sewer pipes ; Making conduits in situ, e.g. of concrete ; Casings, i.e. manhole shafts, access or inspection chambers or coverings of boreholes or narrow wells
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/045—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/16—Arrangement or construction of joints in foundation structures
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- General Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Oil, Petroleum & Natural Gas (AREA)
- Chemical & Material Sciences (AREA)
- Sewage (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
本发明涉及箱涵连接施工工艺,属于箱涵工程技术领域,包括:张拉设备、吊点、手拉葫芦、张拉勾、张拉钢架、定位器、混凝土底板和待装箱涵,在已完成的混凝土底板上用墨线弹出待装箱涵的两个侧边线作为箱涵安装的控制线,在两端控制线上均安装有两个定位器,将张拉钢架,固定在待装箱涵右下端,箱涵上下端面均设置有四个吊点,待装箱涵与相邻箱涵的吊点通过手拉葫芦相连,张拉勾钩挂在张拉钢架,另一端与张拉设备相连。本发明保证了相邻箱涵边缘之间的一致,提高了箱涵之间的结构稳定性,为密封装置提供了安装条件,提高了箱涵的使用寿命,相邻箱涵通过钢索连接,使其成为一个整体,保证后续安装的进行。
Description
技术领域
本发明涉及箱涵连接施工工艺,属于箱涵工程技术领域。
背景技术
现浇钢筋混凝土箱涵作为将电力、通讯,燃气、供热、给排水等各种工程管线集于一体的隧道空间,施工较为方便,相较管涵更加经济。目前,箱涵承插口连接紧固时,张拉机的张拉点作用于箱涵的下方,箱涵下边缘的接口缝隙达到标准后,上边缘的缝隙远没有达到标准,严重影响了箱涵的使用寿命,以及整体的稳定性。
发明内容
本发明的目的是为了解决上述技术问题,进而提供箱涵连接施工工艺,提高了箱涵系统稳定性。
本发明的技术方案:
箱涵连接施工工艺,包括以下步骤,
步骤一、在混凝土底板上用墨线弹出箱涵的两个侧边线作为箱涵安装的控制线,两条控制线之间的距离为箱涵横向外边线的宽度;
步骤二、在每条控制线上设置定位器;
步骤三、将箱涵放入两条控制线上的定位器之间;
步骤四、吊装下一个箱涵,并保持其与前一个箱涵间距为20cm;
步骤五、将张拉钢架固定步骤四所述的下一个箱涵的右侧;
步骤六、箱涵顶面上设置有四个吊点,下一个箱涵和与其相邻的箱涵上的吊点通过手拉葫芦相连;
步骤七、张拉勾的一端钩挂在张拉钢架,张拉勾另一端与置于混凝土底板上的张拉设备相连,张拉设备接通电源,检查液压站是否正常,电机是否正常;
步骤八、打开张拉设备电源开关,上端手拉葫芦同时运动,观察张拉设备上的压力表,达到规定数值时切断张拉设备电源;
步骤九、重复步骤四至步骤八,完成箱涵连接。
进一步,以完成连接的相邻箱涵通过钢索临时锁紧。
本发明具有以下有益效果:
本发明保证了相邻箱涵边缘之间的一致,提高了箱涵之间的结构稳定性,为密封装置提供了安装条件,提高了箱涵的使用寿命,相邻箱涵通过钢索连接,使其成为一个整体,保证后续安装的进行。
附图说明
图1为本发明的结构示意图。
具体实施方式
以下将结合附图对本发明进行详细说明。
箱涵连接施工工艺,包括以下步骤,
步骤一、在混凝土底板8上用墨线弹出箱涵9的两个侧边线作为箱涵安装的控制线,两条控制线之间的距离为箱涵横向外边线的宽度;
步骤二、在每条控制线上设置定位器7;
步骤三、将箱涵9放入两条控制线上的定位器7之间;
步骤四、吊装下一个箱涵9,并保持其与前一个箱涵间距为20cm;
步骤五、将张拉钢架6固定步骤四所述的下一个箱涵9的右侧;
步骤六、箱涵顶面上设置有四个吊点2,下一个箱涵9和与其相邻的箱涵上的吊点2通过手拉葫芦4相连;
步骤七、张拉勾5的一端钩挂在张拉钢架6,张拉勾5另一端与置于混凝土底板8上的张拉设备1相连,张拉设备1接通电源,检查液压站是否正常,电机是否正常;
步骤八、打开张拉设备1电源开关,上端手拉葫芦4同时运动,观察张拉设备上的压力表,达到规定数值时切断张拉设备1电源;
步骤九、重复步骤四至步骤八,完成箱涵连接。
所述以完成连接的相邻箱涵通过钢索3临时锁紧。
相邻箱涵边缘之间的一致,提高了箱涵之间的结构稳定性,为密封装置提供了安装条件,提高了箱涵的使用寿命,相邻箱涵通过钢索连接,使其成为一个整体,保证后续安装的进行。
Claims (2)
1.箱涵连接施工工艺,其特征在于,包括以下步骤,
步骤一、在已完成的混凝土底板(8)上用墨线弹出待装箱涵(9)的两个侧边线作为箱涵安装的控制线,两条控制线之间的距离为箱涵横向外边线的宽度;
步骤二、在两端控制线上均安装有两个定位器(7);
步骤三、将所述待装箱涵(9)放入定位器(7)之间,待装箱涵(9)与前箱涵间距为20cm;
步骤四、将张拉钢架(6),固定在待装箱涵(9)右下端;
步骤五、所述箱涵上下端面均设置有四个吊点(2),待装箱涵(9)与相邻箱涵的吊点(2)通过手拉葫芦(4)相连;
步骤六、张拉勾(5)钩挂在张拉钢架(6),另一端与张拉设备(1)相连,张拉设备(1)接通电源,检查液压站是否正常,电机是否正常;
步骤七、打开张拉设备(1)电源开关,上端手拉葫芦(4)同时运动,观察压力表,达到规定数值时停止。
2.根据权利要求1所述的箱涵连接施工工艺,其特征在于,所述以完成连接的相邻箱涵通过钢索(3)临时锁紧。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710252935.2A CN107023035A (zh) | 2017-04-18 | 2017-04-18 | 箱涵连接施工工艺 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710252935.2A CN107023035A (zh) | 2017-04-18 | 2017-04-18 | 箱涵连接施工工艺 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107023035A true CN107023035A (zh) | 2017-08-08 |
Family
ID=59527489
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710252935.2A Pending CN107023035A (zh) | 2017-04-18 | 2017-04-18 | 箱涵连接施工工艺 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107023035A (zh) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2019076057A1 (zh) * | 2017-10-19 | 2019-04-25 | 中国建筑工程(香港)有限公司 | 具有顶推装置与箱涵推块连接结构的箱涵中继顶推系统 |
WO2019076055A1 (zh) * | 2017-10-19 | 2019-04-25 | 中国建筑工程(香港)有限公司 | 具有顶推架组件的箱涵中继顶推系统 |
WO2019076053A1 (zh) * | 2017-10-19 | 2019-04-25 | 中国建筑工程(香港)有限公司 | 箱涵中继顶推系统及其使用方法 |
WO2019076056A1 (zh) * | 2017-10-19 | 2019-04-25 | 中国建筑工程(香港)有限公司 | 具有移动机构的箱涵中继顶推系统 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP5335949B2 (ja) * | 2012-03-13 | 2013-11-06 | 旭コンクリート工業株式会社 | コンクリート製品の施工方法及び伸長装置 |
CN105544701A (zh) * | 2015-12-03 | 2016-05-04 | 中国能源建设集团天津电力建设有限公司 | 一种预制混凝土沟道的施工工艺 |
CN106151679A (zh) * | 2015-04-23 | 2016-11-23 | 五冶集团上海有限公司 | 大口径钢筋混凝土管道牵引式对口方法 |
CN106141991A (zh) * | 2016-08-31 | 2016-11-23 | 石河子开发区天浩管业有限责任公司 | 承插管道连接安装设备 |
-
2017
- 2017-04-18 CN CN201710252935.2A patent/CN107023035A/zh active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP5335949B2 (ja) * | 2012-03-13 | 2013-11-06 | 旭コンクリート工業株式会社 | コンクリート製品の施工方法及び伸長装置 |
CN106151679A (zh) * | 2015-04-23 | 2016-11-23 | 五冶集团上海有限公司 | 大口径钢筋混凝土管道牵引式对口方法 |
CN105544701A (zh) * | 2015-12-03 | 2016-05-04 | 中国能源建设集团天津电力建设有限公司 | 一种预制混凝土沟道的施工工艺 |
CN106141991A (zh) * | 2016-08-31 | 2016-11-23 | 石河子开发区天浩管业有限责任公司 | 承插管道连接安装设备 |
Non-Patent Citations (1)
Title |
---|
《建筑工人职业技能培训教材》编委会: "《管道工》", 30 September 2016 * |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2019076057A1 (zh) * | 2017-10-19 | 2019-04-25 | 中国建筑工程(香港)有限公司 | 具有顶推装置与箱涵推块连接结构的箱涵中继顶推系统 |
WO2019076055A1 (zh) * | 2017-10-19 | 2019-04-25 | 中国建筑工程(香港)有限公司 | 具有顶推架组件的箱涵中继顶推系统 |
WO2019076053A1 (zh) * | 2017-10-19 | 2019-04-25 | 中国建筑工程(香港)有限公司 | 箱涵中继顶推系统及其使用方法 |
WO2019076056A1 (zh) * | 2017-10-19 | 2019-04-25 | 中国建筑工程(香港)有限公司 | 具有移动机构的箱涵中继顶推系统 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107023035A (zh) | 箱涵连接施工工艺 | |
KR100564298B1 (ko) | 지중선로관 보호장치 | |
CN101752820B (zh) | 地埋线缆保护套 | |
KR20080024852A (ko) | 765킬로볼트 2회선 송전선로에서 스페이서댐퍼활선교체공법 | |
CN101082382A (zh) | 使用管架组件对管道和综合管路的铺设方法 | |
JP5335949B2 (ja) | コンクリート製品の施工方法及び伸長装置 | |
US9225156B2 (en) | Conduit spacer assembly | |
CN103958821B (zh) | 用于安装能量链的方法和设备 | |
CN106838464A (zh) | 一种长距离输送管道及π型补偿器水上漂浮安装方法 | |
CN103231993B (zh) | 室内gis运输就位装置及使用方法 | |
KR101030350B1 (ko) | 매설된 배전 지중 케이블에 의한 감전방지를 위한 보안장치 | |
KR101043559B1 (ko) | 절연 폴과 완철 홀더를 이용한 전선 가이선이 없는 무정전 전주교체공법 | |
CN212479067U (zh) | 一种地铁隧道壁打孔台车 | |
CN107794840B (zh) | 一种桥梁大直径排水钢管安装装置及其施工方法 | |
CN205452985U (zh) | 一种新型电缆支架 | |
JP6036333B2 (ja) | パイプライン敷設方法 | |
CN105155552B (zh) | 基坑临时锚索支护用钢绞线的回收装置及回收方法 | |
KR101852409B1 (ko) | 장거리 케이블 캐리장치의 풀링 로프 회수용 클립 | |
KR101538519B1 (ko) | 신설 철도터널내 급전선과 비절연보호선 설치장치 및 이를 이용한 가선 방법 | |
CN108343180A (zh) | 超高层建筑单元式玻璃幕墙安装施工工法 | |
CN103199469A (zh) | 电缆固定装置 | |
CN208874239U (zh) | 电力电缆用钢承插式预制混凝土多孔导管 | |
JP7177537B1 (ja) | 地中超高圧送電ケーブル撤去方法 | |
CN109428309B (zh) | 基坑临时用电系统及其施工方法 | |
CN109193543B (zh) | 一种综合管廊避雷装置及避雷方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170808 |
|
RJ01 | Rejection of invention patent application after publication |