CN105544701A - 一种预制混凝土沟道的施工工艺 - Google Patents
一种预制混凝土沟道的施工工艺 Download PDFInfo
- Publication number
- CN105544701A CN105544701A CN201510882933.2A CN201510882933A CN105544701A CN 105544701 A CN105544701 A CN 105544701A CN 201510882933 A CN201510882933 A CN 201510882933A CN 105544701 A CN105544701 A CN 105544701A
- Authority
- CN
- China
- Prior art keywords
- raceway groove
- construction
- channel
- precast concrete
- merogenesis
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E03—WATER SUPPLY; SEWERAGE
- E03F—SEWERS; CESSPOOLS
- E03F3/00—Sewer pipe-line systems
- E03F3/06—Methods of, or installations for, laying sewer pipes
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B5/00—Artificial water canals, e.g. irrigation canals
- E02B5/02—Making or lining canals
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Health & Medical Sciences (AREA)
- Life Sciences & Earth Sciences (AREA)
- Hydrology & Water Resources (AREA)
- Public Health (AREA)
- Water Supply & Treatment (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
本发明是一种预制混凝土沟道的施工工艺,包括的步骤有:a、分节:根据垂直运输机械的负荷能力,依沟道的长度合理分节,所述的沟道为钢筋混凝土沟道;b、沟道加工:分段模板式加工预制各分节沟道;沟道接口两侧预埋埋件,接口处按咬口设计;c、地基处理及垫层施工:挖除沟道垫层的软土,然后用砂或碎石换填平整,经分层夯实至设计要求的密实度,浇筑沟道垫层;d、测量定位;e、分节吊装就位;f、连接固定;g、验收。本发明所述的一种预制混凝土沟道的施工工艺,施工便捷,能够有效控制产品质量,不受天气和地理环境影响;施工速度快,将安装土建交叉施工影响降到最低;具有良好的抗渗和抗震性能;作业面小,对周围环境影响低等。
Description
技术领域
本发明涉及混凝土沟道施工领域,尤其涉及一种预制混凝土沟道的施工工艺。
背景技术
钢筋混凝土沟道是薄壁的密水结构,抗渗性要求高。传统的施工方法以现浇混凝土结构为主,现浇混凝土沟道通常约20m/段,分段间隔长度大,地基如有不均匀沉降或受外荷载(地震)作用,易发生折断,因此对纵向基础承载力要求高,纵向配筋要加大。又由于混凝土沟道的钢筋密、侧壁薄、沟道现浇施工空间受限,给施工中模板支设和混凝土浇筑带来了很大的难度;且现浇作业受季节、气候及环境温度的影响,容易造成混凝土表面的通病缺陷;混凝土沟道现浇分段间采用橡胶止水带连接,分段施工缝连接处,工序复杂,也是容易出现渗漏的薄弱环节,混凝土的施工质量很难保证。此外,现浇沟道模板投入量大、施工周期长,安装和土建交叉施工进度会受影响。
发明内容
本发明为实现上述目的,提供一种预制混凝土沟道的施工工艺,包括的步骤有:
a、分节:
根据垂直运输机械的负荷能力,依沟道的长度合理分节,所述的沟道为钢筋混凝土沟道;
b、沟道加工:
分段模板式加工预制各分节沟道;沟道接口两侧预埋埋件,接口处按咬口设计;
c、地基处理及垫层施工:
挖除沟道垫层的软土,然后用砂或碎石换填平整,经分层夯实至设计要求的密实度,浇筑沟道垫层;
d、测量定位:
根据控制网及图纸的坐标引测出沟道的中心线,在沟道垫层上弹出中心线和侧壁边线;转弯处轴线和边线标记加密,用墨线连接形成圆弧,同时在每节预制的沟道上弹出中心线;
e、分节吊装就位:
预制分节沟道达到设计强度后,用吊车吊装就位,对称设置吊点位置,弯段不论长度均设置三个吊点,两端各设置一个,另一个设置在两吊点的中轴线上,与前两个组成等腰三角形,这个吊点用于控制弯段的平度,吊装时钢丝绳和3t倒链配合,每节沟道间采用橡胶圈连接;
f、连接固定:
沟道的外部将锁扣与预制沟道壁预埋件焊接,每节之间用紧固螺栓固定,紧固螺栓外部用螺母连接;
g、验收。
所述的沟道每节长度为2-3m。
所述的沟道加工为工厂化加工。
所述的锁扣为槽钢锁扣。
本发明的有益效果是:本发明所述的一种预制混凝土沟道的施工工艺,施工便捷,能够有效控制产品质量,不受天气和地理环境影响;施工速度快,将安装土建交叉施工影响降到最低;具有良好的抗渗和抗震性能;作业面小,产生废弃物少,对周围环境影响低等。
附图说明
图1为本发明所述的一种预制混凝土沟道的施工工艺的结构示意图;
图2为本发明所述的一种预制混凝土沟道的施工工艺的A-A向视图;
其中:1-沟道;2-预埋件;3-螺母;4-锁扣;5-紧固螺栓;6-橡胶圈。
具体实施方式
以下将结合本发明的实施例参照附图进行详细叙述。
一种预制混凝土沟道的施工工艺,包括的步骤有:
a、分节:
根据垂直运输机械的负荷能力,依沟道1的长度合理分节,所述的沟道1为钢筋混凝土沟道;
b、沟道1加工:
分段模板式加工预制各分节沟道1;沟道1接口两侧预埋埋件,接口处按咬口设计;
c、地基处理及垫层施工:
挖除沟道1垫层的软土,然后用砂或碎石换填平整,经分层夯实至设计要求的密实度,浇筑沟道1垫层;
d、测量定位:
根据控制网及图纸的坐标引测出沟道1的中心线,在沟道1垫层上弹出中心线和侧壁边线;转弯处轴线和边线标记加密,用墨线连接形成圆弧,同时在每节预制的沟道1上弹出中心线;
e、分节吊装就位:
预制分节沟道1达到设计强度后,用吊车吊装就位,对称设置吊点位置,弯段不论长度均设置三个吊点,两端各设置一个,另一个设置在两吊点的中轴线上,与前两个组成等腰三角形,这个吊点用于控制弯段的平度,吊装时钢丝绳和3t倒链配合,每节沟道1间采用橡胶圈6连接;
f、连接固定:
沟道1的外部将锁扣4与预制沟道壁预埋件2焊接,每节之间用紧固螺栓5固定,紧固螺栓5外部用螺母3连接;
g、验收。
所述的沟道1每节长度为2-3m。
所述的沟道1加工为工厂化加工。
所述的锁扣4为槽钢锁扣。
所述的预制混凝土沟道的施工工艺适用于各种规格要求及设计荷重要求。
所述的预制混凝土沟道的施工工艺采取在工厂预先制成沟道1,能够有效控制施工质量,与现场浇筑混凝土施工比较,其施工不受天气和地理环境影响;预制沟道1节省了开槽后现场钢筋绑扎、模板支立、浇筑混凝土和现场混凝土养护等几个环节的施工;在现场一次性完成施工,现场作业速度大约1m/10min,速度快,将安装土建交叉施工影响降到最低;每节沟道1间采用咬口连接,接口处加垫橡胶圈6能承受1.0-2.0MPa的抗渗要求,且沟道1节间伸缩性较现浇结构有所提高,在地基发生不均匀沉降或管道产生位移、折角时,仍能保持良好的抗渗和抗震性能;采取2-3m/节工厂化加工预制,模板投入量小,能够有效控制产品质量。
以上所述仅是本发明的优选实施方式,应当指出,对于本技术领域的普通技术人员来说,在不脱离本发明原理的前提下,还可以做出若干改进和润饰,这些改进和润饰也应视为本发明的保护范围。
Claims (4)
1.一种预制混凝土沟道的施工工艺,其特征在于,包括的步骤有:
a、分节:
根据垂直运输机械的负荷能力,依沟道(1)的长度合理分节,所述的沟道(1)为钢筋混凝土沟道;
b、沟道(1)加工:
分段模板式加工预制各分节沟道(1);沟道(1)接口两侧预埋埋件,接口处按咬口设计;
c、地基处理及垫层施工:
挖除沟道(1)垫层的软土,然后用砂或碎石换填平整,经分层夯实至设计要求的密实度,浇筑沟道(1)垫层;
d、测量定位:
根据控制网及图纸的坐标引测出沟道(1)的中心线,在沟道(1)垫层上弹出中心线和侧壁边线;转弯处轴线和边线标记加密,用墨线连接形成圆弧,同时在每节预制的沟道(1)上弹出中心线;
e、分节吊装就位:
预制分节沟道(1)达到设计强度后,用吊车吊装就位,对称设置吊点位置,弯段不论长度均设置三个吊点,两端各设置一个,另一个设置在两吊点的中轴线上,与前两个组成等腰三角形,这个吊点用于控制弯段的平度,吊装时钢丝绳和3t倒链配合,每节沟道(1)间采用橡胶圈(6)连接;
f、连接固定:
沟道(1)的外部将锁扣(4)与预制沟道壁预埋件(2)焊接,每节之间用紧固螺栓(5)固定,紧固螺栓(5)外部用螺母(3)连接;
g、验收。
2.根据权利要求1所述的一种预制混凝土沟道的施工工艺,其特征在于,所述的沟道(1)每节长度为2-3m。
3.根据权利要求2所述的一种预制混凝土沟道的施工工艺,其特征在于,所述的沟道(1)加工为工厂化加工。
4.根据权利要求1或2所述的一种预制混凝土沟道的施工工艺,其特征在于,所述的锁扣(4)为槽钢锁扣。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510882933.2A CN105544701A (zh) | 2015-12-03 | 2015-12-03 | 一种预制混凝土沟道的施工工艺 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510882933.2A CN105544701A (zh) | 2015-12-03 | 2015-12-03 | 一种预制混凝土沟道的施工工艺 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN105544701A true CN105544701A (zh) | 2016-05-04 |
Family
ID=55824218
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510882933.2A Pending CN105544701A (zh) | 2015-12-03 | 2015-12-03 | 一种预制混凝土沟道的施工工艺 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105544701A (zh) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107023035A (zh) * | 2017-04-18 | 2017-08-08 | 黑龙江省中信路桥材料有限公司 | 箱涵连接施工工艺 |
CN107724499A (zh) * | 2017-09-27 | 2018-02-23 | 广东景源建设工程有限公司 | 污水管道的施工方法与基座 |
CN110886299A (zh) * | 2019-10-31 | 2020-03-17 | 中冶天工集团有限公司 | 一种易施工管线沟道及其顶板浇筑方法 |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2495706Y (zh) * | 2001-09-07 | 2002-06-19 | 麻丰年 | 组装式预制钢筋混凝土方渠 |
JP2009221737A (ja) * | 2008-03-17 | 2009-10-01 | Kajima Corp | 水理構造物補修用パネルの接合構造 |
CN102174803A (zh) * | 2011-04-01 | 2011-09-07 | 中国科学院水利部成都山地灾害与环境研究所 | 一种组装式泥石流排导槽及其施工方法 |
CN103334359A (zh) * | 2013-06-26 | 2013-10-02 | 中国建筑股份有限公司 | 装配式预制钢筋混凝土路面板及路面施工方法 |
CN104466869A (zh) * | 2014-12-05 | 2015-03-25 | 浙江省电力设计院 | 一种钢筋混凝土装配式电缆沟及制作方法 |
CN104805866A (zh) * | 2015-04-30 | 2015-07-29 | 黑龙江宇辉新型建筑材料有限公司 | 预制的综合管廊及施工方法 |
JP2015137450A (ja) * | 2014-01-20 | 2015-07-30 | 前田製管株式会社 | コンクリート製水路の設置構造 |
-
2015
- 2015-12-03 CN CN201510882933.2A patent/CN105544701A/zh active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2495706Y (zh) * | 2001-09-07 | 2002-06-19 | 麻丰年 | 组装式预制钢筋混凝土方渠 |
JP2009221737A (ja) * | 2008-03-17 | 2009-10-01 | Kajima Corp | 水理構造物補修用パネルの接合構造 |
CN102174803A (zh) * | 2011-04-01 | 2011-09-07 | 中国科学院水利部成都山地灾害与环境研究所 | 一种组装式泥石流排导槽及其施工方法 |
CN103334359A (zh) * | 2013-06-26 | 2013-10-02 | 中国建筑股份有限公司 | 装配式预制钢筋混凝土路面板及路面施工方法 |
JP2015137450A (ja) * | 2014-01-20 | 2015-07-30 | 前田製管株式会社 | コンクリート製水路の設置構造 |
CN104466869A (zh) * | 2014-12-05 | 2015-03-25 | 浙江省电力设计院 | 一种钢筋混凝土装配式电缆沟及制作方法 |
CN104805866A (zh) * | 2015-04-30 | 2015-07-29 | 黑龙江宇辉新型建筑材料有限公司 | 预制的综合管廊及施工方法 |
Non-Patent Citations (1)
Title |
---|
全国一级建造师执业资格考试试题分析小组: "《2014全国一级建造师执业资格考试考点精编+历年真题 市政公用工程管理与实务》", 31 March 2014, 机械工业出版社 * |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107023035A (zh) * | 2017-04-18 | 2017-08-08 | 黑龙江省中信路桥材料有限公司 | 箱涵连接施工工艺 |
CN107724499A (zh) * | 2017-09-27 | 2018-02-23 | 广东景源建设工程有限公司 | 污水管道的施工方法与基座 |
CN110886299A (zh) * | 2019-10-31 | 2020-03-17 | 中冶天工集团有限公司 | 一种易施工管线沟道及其顶板浇筑方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104294753B (zh) | 一种桥梁预制空心墩柱连接结构及施工工法 | |
CN103195076B (zh) | 淤泥质深基坑塔吊基础施工方法 | |
CN102747677B (zh) | 一种桥梁及其施工方法 | |
CN105019475A (zh) | 预制装配整体式混凝土综合管廊及施工工法 | |
CN104179174B (zh) | 一种多孔注浆管异形桩及其成桩方法 | |
CN103669866B (zh) | 地下室钢筋混凝土柱节点连接结构的施工方法 | |
CN205205857U (zh) | 预制装配整体式混凝土综合管廊 | |
CN108035594A (zh) | 钢筋混凝土筒仓结构预制减压锥体施工方法 | |
CN103806377A (zh) | 一种桥梁大吨位多桩基的整体主动托换结构及托换方法 | |
CN107246005A (zh) | 超大直径钻埋钢管空心基桩及其施工方法 | |
CN103741812A (zh) | 一种型钢混凝土叠合梁与中柱连接节点 | |
CN105544701A (zh) | 一种预制混凝土沟道的施工工艺 | |
CN103603435B (zh) | 一种装配式混凝土抗震梁柱框架及其施工方法 | |
CN106593470A (zh) | 高渗透性富水砂层盾构端头加固体系及其施工方法 | |
CN102817378B (zh) | 超大直径盾构隧道近距离穿越城市高架桩基的施工方法 | |
CN106988333B (zh) | 带有插筋灌芯的预制承台及其施工工艺 | |
CN207047881U (zh) | 带有插筋灌芯的预制承台 | |
CN102286982A (zh) | 用于低温环境施工的深基坑预制围护结构 | |
CN113502835A (zh) | 一种湿连接蜂窝状装配式格梁护坡结构 | |
CN204174527U (zh) | 一种桥梁预制空心墩柱连接结构 | |
CN103527217B (zh) | 密集桩基环境下小曲率半径盾构隧道管片及其制造方法 | |
CN106948267A (zh) | 一种牌坊门楼式桥梁索塔塔柱同步施工方法 | |
CN203891060U (zh) | 盖挖逆作车站主体结构的永久钢管柱定位系统 | |
CN107940102B (zh) | 地下原水管道保护施工方法 | |
CN106120578B (zh) | 一种山区公路深埋园管涵控制裂缝的施工方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20160504 |