CN106934540A - A kind of architecture engineering material cost budgeting method based on Revit - Google Patents

A kind of architecture engineering material cost budgeting method based on Revit Download PDF

Info

Publication number
CN106934540A
CN106934540A CN201710131581.6A CN201710131581A CN106934540A CN 106934540 A CN106934540 A CN 106934540A CN 201710131581 A CN201710131581 A CN 201710131581A CN 106934540 A CN106934540 A CN 106934540A
Authority
CN
China
Prior art keywords
model
attribute
coding
inventory
information
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710131581.6A
Other languages
Chinese (zh)
Inventor
赵钦
陈则钰
黑新宏
李哲
朱轶韵
桑国臣
范留明
简政
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xian University of Technology
Original Assignee
Xian University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xian University of Technology filed Critical Xian University of Technology
Priority to CN201710131581.6A priority Critical patent/CN106934540A/en
Publication of CN106934540A publication Critical patent/CN106934540A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06313Resource planning in a project environment
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Economics (AREA)
  • General Business, Economics & Management (AREA)
  • Theoretical Computer Science (AREA)
  • Marketing (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • General Physics & Mathematics (AREA)
  • General Health & Medical Sciences (AREA)
  • Health & Medical Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Biodiversity & Conservation Biology (AREA)
  • Development Economics (AREA)
  • Educational Administration (AREA)
  • Primary Health Care (AREA)
  • Game Theory and Decision Science (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a kind of architecture engineering material cost budgeting method based on Revit, following steps are specifically included:It is determined that needing the material classification of statistics;The entry parameter of various types of materials is determined according to material classification;Determine the objective attribute target attribute of model, the model entity matched with objective attribute target attribute in entry parameter is stored into model set unit;Each model in model set unit is extracted one by one, and in one 2-D data statistics list of write-in;The information of every a line in statistics list is extracted successively, and is imported in database, form the form of table;According to " 13 bill code " that is used in bid engineering, correspondence finds out the coding inventory of the table that step 5 is formed, and then sorts out inventory coding successively, makes each coding corresponding information attribute of correspondence;Estimated cost is drawn according to the coding inventory for drawing.The present invention can realize the architecture engineering material cost budgeting of reinforced concrete structure on Revit platforms.

Description

A kind of architecture engineering material cost budgeting method based on Revit
Technical field
The invention belongs to engineering material budget technical field, it is related to a kind of architecture engineering material cost based on Revit pre- Calculation method.
Background technology
The engineering budget management of China experienced the development of decades, and budget method is also continuous in conventional practice It is perfect, although to have certain development, but Construction Cost Industry development level exists with current economic, social development levels , still than larger, wherein Engineering Cost Management is bad, the degree that becomes more meticulous is not high, and real current situation is that material consumption is over-quota to disappear for gap The phenomenons such as consumption are very universal, for example, design portion fails the cost of the engineering project designed by consideration, item in engineering early stage The budget information channel in mesh portion is not smooth, and administrative skill falls behind etc..With the fast development of global economy, engineering construction project Quantity also expands with scale constantly, the fierceness for competing more of construction market, for cost control, how to improve enterprise Competitiveness, it is necessary to owner, design side, contractor have good cost control power.And cost look-ahead is control The effective way of cost, it is not only the starting point of cost management, and is the basis of project feasibility studies, is that bid is formulated The foundation of the base number of a tender, its importance is self-evident.
With computer technology continuing to develop in building engineering field application, many cost budgeting softwares are occurred in that, this Class software uses X-Y scheme technology mostly, is imported by plan, applies mechanically quota, and automatic price statistics is carried out by computer.But It is that this kind of software can only process X-Y scheme, it is impossible to expression model directly perceived, there is certain calculation error, is operated during tablet pattern Complexity, the complex steps in the calculating of quantities, in some instances it may even be possible to bring some unnecessary troubles, cause time and human resources On waste.
Into after 21 century, the development of 3-D technology is maked rapid progress, and BIM fields delayed effect of development in recent years is full, building Industrial application of information technology achievement is obvious to all.In some European countries, Japan, Singapore etc., the popularity rate of BIM reached 60% with On, and in the construction project application of some a small number of developed countries, BIM has run through planning, design, construction and the fortune in later stage In the stages such as dimension management, realize the circulation of data Life cycle.Certainly, in engineering cost budget field, BIM technology is Start to play its value.At present, Revit has already taken up important market money as the application software of a powerful BIM Source, this is a powerful medium that can carry BIM information, and correlation BIM models are set up by it, realizes the fortune to BIM information With and management.
The content of the invention
It is an object of the invention to provide a kind of architecture engineering material cost budgeting method based on Revit, can be in Revit The architecture engineering material cost budgeting of reinforced concrete structure is realized on platform.
The technical solution adopted in the present invention is, a kind of architecture engineering material cost budgeting method based on Revit, specifically Comprise the following steps:
Step 1, is respectively a set by the model filter of identical pel in whole model according to the classification of pel, from And determine to need the material classification of statistics;
Step 2, determines the entry parameter of the various types of materials of statistics in step 1, and the parameter includes attribute data, number of coordinates According to, geometric data;
Step 3, determines the objective attribute target attribute of model, the entry parameter of the various types of materials determined in whole scene traversal step 2, and The categorical attribute of each model is obtained, carries out matching judgement with objective attribute target attribute, if categorical attribute is identical with objective attribute target attribute, With success, all model entities that the match is successful are stored into model set unit;
Step 4, imposed a condition set, and each model in model set unit is traveled through successively, and to current model Attributive analysis is carried out, in the attribute that extraction "current" model is consistent with set of circumstances, and one 2-D data statistics list of write-in, Until each model extraction in model set unit is complete;
Step 5, extracts the information of every a line in statistics list successively, and imports in database, forms the form of table;
Step 6, according to " 13 bill code " that is used in bid engineering, correspondence finds out the volume of the table that step 5 is formed Code inventory, then sorts out inventory coding successively, makes each coding corresponding information attribute of correspondence;
Step 7, estimated cost is drawn according to the coding inventory drawn in step 6.
The features of the present invention is also resided in,
Attribute data is the attribute information that threedimensional model has in the step 2;The coordinate data is threedimensional model It is determined that three-dimensional system of coordinate in spatial orientation information;The geometric data is the geometry letter for expressing threedimensional model spatial form Breath.
The detailed process of the step 7 is:
The coding inventory that to be drawn in step 6 and type, material, shape in quota code database as unique key, by type, The consistent inventory calculation amount of material, shape information is associated with the sub- code database of quota, realizes a coding inventory calculation amount correspondence one Individual quota coding, if certain coding inventory calculation amount not with determine height coding and be successfully associated, the pedestrian that goes forward side by side is showed by system Work selection association, while just association results are exported in the form of form document, finally according to the reference price provided in quota store Lattice, manually calculate comprehensive unit price, by calculating comprehensive unit price and quantities, draw estimated cost.
The beneficial effects of the invention are as follows,
(1) this method can save the substantial amounts of time for budgeter.By the method, design work personnel can be conveniently From the model for having built up extract statistical engineering material consumption, be not required to budgeter and drawing imported into budget software Carry out identification again.
(2) this method can make the statistics of quantities more accurate.The quantities obtained using the method is exactly model reality The quantities of body, if the model built becomes more meticulous, degree is high, and resulting quantities also can be more fine, while avoiding people The phenomenons such as few calculation, the omission that work is caused.
(3) this method can effectively process design alteration.Under present circumstances, once run into relevant design alteration, no matter hand computation Or two-dimentional drawing zooming, it is required for recalculating on a large scale, imports drawing again.And by the budget method of BIM technology, when When model is changed, the consumption situation meeting synchronized update of material realizes intelligent, automation.
Specific embodiment
With reference to specific embodiment, the present invention is described in detail.
A kind of architecture engineering material cost budgeting method based on Revit of the present invention, based on the three-dimensional mould on Revit platforms Type, specifically includes following steps:
Step 1, is respectively a set by the model filter of identical pel in whole model according to the classification of pel, from And determine to need the material classification of statistics;
Used as information-based three-dimensional visible model, its model is included big Revit models equivalent to a database in model The data message of amount, the unique ID that has of each model is numbered, required for being easy to whole scene to follow the trail of and determine Model, Revit both defines class name to each model component, and the class of such as reinforcing bar is entitled " Rebar ", and the class of wall is entitled " WALL ", no matter the class name of which kind of form is " DOOR ", therefore is easy to that statistics will be needed according to the classification information of model Material is distinguished;
Step 2, determines the entry parameter of the various types of materials of statistics in step 1, and the parameter includes attribute data, number of coordinates According to, geometric data;
Attribute data is the attribute information that threedimensional model has, the title of such as pillar, material, the strength of materials, production Producer, date of built etc.;Coordinate data be threedimensional model it is determined that three-dimensional system of coordinate in spatial orientation information, such as concrete X, Y, Z coordinate of post center and each point etc.;Geometric data is the geological information for expressing threedimensional model spatial form, such as concrete column Section form, sectional dimension, height, diameter, length of reinforcing bar used etc..
Such as count radius, length, the intensity of reinforcing bar, the species of wall, height, area.Wrapped in the information model of Revit The all properties information of component, such as dimensions of beam, intensity, length are contained.
Step 3, determines the objective attribute target attribute of model, the entry parameter of the various types of materials determined in whole scene traversal step 2, and The categorical attribute of each model is obtained, carries out matching judgement with objective attribute target attribute, if categorical attribute is identical with objective attribute target attribute, With success, all model entities that the match is successful are stored into model set unit;
For example, in the data of reading model, building one " filter ", the class name of the regulation wall in model is " WALL ", every class name is that the model data of wall will be filtered out coming, and is put into the aggregation units of wall.
Step 4, imposed a condition set, and each model in model set unit is traveled through successively, and to current model Attributive analysis is carried out, in the attribute that extraction "current" model is consistent with set of circumstances, and one 2-D data statistics list of write-in, Until each model extraction in model set unit is complete;
Such as in the set of wall model data, due to there are many attribute datas in the model of wall, the function of such as wall is Exterior wall, material is concrete, and the data of the attribute that meets the requirements will be come out, and ineligible will be filtered. For another example the data message of column model is obtained, in the model set of post, the information of material, shape and quantities is respectively obtained, and Count according to this.
Step 5, extracts the information of every a line in statistics list successively, and imports in database, forms the form of table;
By taking certain concrete rectangular column as an example, information as shown in table 1 can be obtained.
Table 1
Step 6, according to " 13 bill code " that is used in bid engineering, correspondence finds out the volume of the table that step 5 is formed Code inventory, then sorts out inventory coding successively, makes each coding corresponding information attribute of correspondence;
For example in 010402001003 this coding, 01 refers to architectural engineering in engineering classification, during 04 represents professional classification Concrete, 02 refers to the concrete column in partitioned project, and 001 refers to the rectangular column of subdivisional work, and 003 is refinement coding.According to This classification information, builds inventory coded data storehouse as shown in table 2 below.
Table 2
Project code Project name Type Shape Material
010402002 Concrete rectangular stake Stake Rectangle Concrete
010403005 Concrete collar tie beam Beam Collar tie beam Concrete
010409003 Concrete profiled pile Post Abnormity Concrete
Type, material, shape be used as unique key in step 7, the coding inventory that will be drawn in step 6 and quota code database, The consistent inventory calculation amount of type, material, shape information is associated with the sub- code database (referring to table 3) of quota, a volume is realized One quota coding of code inventory calculation amount correspondence, if certain coding inventory calculation amount not with determine height coding and be successfully associated, by being System shows and carries out artificial selection association, while just association results are exported in the form of form document, finally according to quota The reference price provided in storehouse, manually calculates comprehensive unit price, by calculating comprehensive unit price and quantities, draws estimated cost.
Table 3
A kind of the characteristics of architecture engineering material cost budgeting method based on Revit of the present invention, is as follows:
(1) this method can save the substantial amounts of time for budgeter.By the method, design work personnel can be conveniently From the model for having built up extract statistical engineering material consumption, be not required to budgeter and drawing imported into budget software Carry out identification again.
(2) this method can make the statistics of quantities more accurate.The quantities obtained using the method is exactly model reality The quantities of body, if the model built becomes more meticulous, degree is high, and resulting quantities also can be more fine, while avoiding people The phenomenons such as few calculation, the omission that work is caused.
(3) this method can effectively process design alteration.Under present circumstances, once run into relevant design alteration, no matter hand computation Or two-dimentional drawing zooming, it is required for recalculating on a large scale, imports drawing again.And by the budget method of BIM technology, when When model is changed, the consumption situation meeting synchronized update of material realizes intelligent, automation.

Claims (3)

1. it is characterized in that:Specifically include following steps:
Step 1, is respectively a set by the model filter of identical pel in whole model, so that really according to the classification of pel The fixed material classification for needing to count;
Step 2, determines the entry parameter of various types of materials counted in step 1, and the parameter includes attribute data, coordinate data, several What data;
Step 3, determines the objective attribute target attribute of model, the entry parameter of the various types of materials determined in whole scene traversal step 2, and obtains The categorical attribute of each model, carries out matching judgement with objective attribute target attribute, if categorical attribute is identical with objective attribute target attribute, matches into Work(, all model entities that the match is successful are stored into model set unit;
Step 4, impose a condition set, each model in model set unit is traveled through successively, and current model is carried out Attributive analysis, in the attribute that extraction "current" model is consistent with set of circumstances, and one 2-D data statistics list of write-in, until Each model extraction in model set unit is complete;
Step 5, extracts the information of every a line in statistics list successively, and imports in database, forms the form of table;
Step 6, according to " 13 bill code " that is used in bid engineering, the coding that correspondence finds out the table that step 5 is formed is clear It is single, then inventory coding is sorted out successively, make each coding corresponding information attribute of correspondence;
Step 7, estimated cost is drawn according to the coding inventory drawn in step 6.
2. a kind of architecture engineering material cost budgeting method based on Revit according to claim 1, it is characterised in that: Attribute data is the attribute information that threedimensional model has in the step 2;The coordinate data be threedimensional model it is determined that Spatial orientation information in three-dimensional system of coordinate;The geometric data is the geological information for expressing threedimensional model spatial form.
3. a kind of architecture engineering material cost budgeting method based on Revit according to claim 1, it is characterised in that: The detailed process of the step 7 is:
The coding inventory that to be drawn in step 6 with type, material, shape in quota code database as unique key, by type, material The consistent inventory calculation amount of matter, shape information is associated with the sub- code database of quota, realizes a coding inventory calculation amount correspondence one Quota coding, if certain coding inventory calculation amount not with determine height coding and be successfully associated, showed by system and carried out and be artificial Selection association, while just association results are exported in the form of form document, finally according to the reference price provided in quota store, It is artificial to calculate comprehensive unit price, by calculating comprehensive unit price and quantities, draw estimated cost.
CN201710131581.6A 2017-03-07 2017-03-07 A kind of architecture engineering material cost budgeting method based on Revit Pending CN106934540A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710131581.6A CN106934540A (en) 2017-03-07 2017-03-07 A kind of architecture engineering material cost budgeting method based on Revit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710131581.6A CN106934540A (en) 2017-03-07 2017-03-07 A kind of architecture engineering material cost budgeting method based on Revit

Publications (1)

Publication Number Publication Date
CN106934540A true CN106934540A (en) 2017-07-07

Family

ID=59423480

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710131581.6A Pending CN106934540A (en) 2017-03-07 2017-03-07 A kind of architecture engineering material cost budgeting method based on Revit

Country Status (1)

Country Link
CN (1) CN106934540A (en)

Cited By (24)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108389004A (en) * 2018-03-16 2018-08-10 杭州市建筑设计研究院有限公司 A kind of engineering process dynamic cost managing and control system and method based on BIM technology
CN108492040A (en) * 2018-03-29 2018-09-04 新乡学院 A kind of intelligent building management device
CN108536981A (en) * 2018-04-18 2018-09-14 宁夏通信规划设计院(有限责任公司) Communication pipe engineering design efforts and the automation of material budget table generate model
CN108830662A (en) * 2018-07-18 2018-11-16 贵州汇杰兴邦电力工程有限公司 A kind of power engineering budget device and method
CN108920770A (en) * 2018-06-08 2018-11-30 上海大学 Based on the BIM component autocoding of Revit software and the method that is associated with BIM model
CN109087150A (en) * 2018-08-18 2018-12-25 深圳市江益达科技股份有限公司 Cost intelligent analysis method and device
CN109165462A (en) * 2018-09-11 2019-01-08 云南材材通信息技术有限公司 Material utilization amount automatic monitoring method, device, system and can storage medium
CN109190206A (en) * 2018-08-16 2019-01-11 中铁二局集团勘测设计院有限责任公司 It is a kind of for refine calculate steel structure bridge project amount modeling method
CN109426914A (en) * 2017-08-31 2019-03-05 上海宝冶集团有限公司 A kind of construction project amount of concrete control method based on BIM technology
CN109472426A (en) * 2017-09-07 2019-03-15 上海嘉实(集团)有限公司 Material cost management method, system, storage medium and the terminal device of live project
CN109472446A (en) * 2018-09-30 2019-03-15 中铁第勘察设计院集团有限公司 Project Budget preparation method based on BIM model
CN109670192A (en) * 2017-10-13 2019-04-23 上海宝冶建设工业炉工程技术有限公司 A kind of component ID batch extracting method based on BIM
CN110097137A (en) * 2019-05-10 2019-08-06 广东中建普联科技股份有限公司 The national standard quota user-defined feature data extraction method of Budgetary Estimates project data
CN111046476A (en) * 2019-12-24 2020-04-21 中煤科工集团武汉设计研究院有限公司 Method and system for coding information model and exchanging data of building foundation pit component
CN111259472A (en) * 2020-01-13 2020-06-09 上海思优建筑科技有限公司 Optimal design method and system for building structure
CN111353189A (en) * 2020-02-21 2020-06-30 广东三维家信息科技有限公司 Configuration method and device of home decoration line material and electronic equipment
CN111737787A (en) * 2019-03-25 2020-10-02 上海嘉实(集团)有限公司 Calculation method and calculation system for bent material, storage medium and electronic equipment
CN111737786A (en) * 2019-03-25 2020-10-02 上海嘉实(集团)有限公司 Calculation method and calculation system for board arrangement materials, storage medium and electronic equipment
CN112765714A (en) * 2021-01-21 2021-05-07 天津大学 BIM-based Chinese building life cycle environmental impact and cost accounting method
CN113158292A (en) * 2021-03-02 2021-07-23 广联达科技股份有限公司 Component matching method, engineering quantity calculation method, device and electronic equipment
CN113656402A (en) * 2021-07-13 2021-11-16 广东省国际工程咨询有限公司 Engineering project full life cycle data recording and storing method and device based on BIM
CN113863396A (en) * 2021-09-29 2021-12-31 北京中岩大地科技股份有限公司 Method for predicting construction cost of composite pile under consideration of multi-factor influence
CN114445129A (en) * 2022-01-13 2022-05-06 湖北国际物流机场有限公司 BIM coding system
CN116720695A (en) * 2023-06-07 2023-09-08 金联智能科技发展(深圳)有限公司 Engineering budget management method and system based on BIM technology

Cited By (30)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109426914A (en) * 2017-08-31 2019-03-05 上海宝冶集团有限公司 A kind of construction project amount of concrete control method based on BIM technology
CN109472426A (en) * 2017-09-07 2019-03-15 上海嘉实(集团)有限公司 Material cost management method, system, storage medium and the terminal device of live project
CN109670192A (en) * 2017-10-13 2019-04-23 上海宝冶建设工业炉工程技术有限公司 A kind of component ID batch extracting method based on BIM
CN108389004A (en) * 2018-03-16 2018-08-10 杭州市建筑设计研究院有限公司 A kind of engineering process dynamic cost managing and control system and method based on BIM technology
CN108492040A (en) * 2018-03-29 2018-09-04 新乡学院 A kind of intelligent building management device
CN108536981A (en) * 2018-04-18 2018-09-14 宁夏通信规划设计院(有限责任公司) Communication pipe engineering design efforts and the automation of material budget table generate model
CN108920770A (en) * 2018-06-08 2018-11-30 上海大学 Based on the BIM component autocoding of Revit software and the method that is associated with BIM model
CN108830662A (en) * 2018-07-18 2018-11-16 贵州汇杰兴邦电力工程有限公司 A kind of power engineering budget device and method
CN109190206A (en) * 2018-08-16 2019-01-11 中铁二局集团勘测设计院有限责任公司 It is a kind of for refine calculate steel structure bridge project amount modeling method
CN109087150A (en) * 2018-08-18 2018-12-25 深圳市江益达科技股份有限公司 Cost intelligent analysis method and device
CN109165462A (en) * 2018-09-11 2019-01-08 云南材材通信息技术有限公司 Material utilization amount automatic monitoring method, device, system and can storage medium
CN109472446A (en) * 2018-09-30 2019-03-15 中铁第勘察设计院集团有限公司 Project Budget preparation method based on BIM model
CN111737786B (en) * 2019-03-25 2024-01-30 上海嘉实(集团)有限公司 Calculation method, calculation system, storage medium and electronic equipment for bent plate material
CN111737787A (en) * 2019-03-25 2020-10-02 上海嘉实(集团)有限公司 Calculation method and calculation system for bent material, storage medium and electronic equipment
CN111737786A (en) * 2019-03-25 2020-10-02 上海嘉实(集团)有限公司 Calculation method and calculation system for board arrangement materials, storage medium and electronic equipment
CN111737787B (en) * 2019-03-25 2024-01-26 上海嘉实(集团)有限公司 Calculation method, calculation system, storage medium and electronic equipment for bent materials
CN110097137B (en) * 2019-05-10 2022-11-25 广东中建普联科技股份有限公司 National standard quota custom feature data extraction method for project data of engineering approximate calculation
CN110097137A (en) * 2019-05-10 2019-08-06 广东中建普联科技股份有限公司 The national standard quota user-defined feature data extraction method of Budgetary Estimates project data
CN111046476A (en) * 2019-12-24 2020-04-21 中煤科工集团武汉设计研究院有限公司 Method and system for coding information model and exchanging data of building foundation pit component
CN111259472A (en) * 2020-01-13 2020-06-09 上海思优建筑科技有限公司 Optimal design method and system for building structure
CN111259472B (en) * 2020-01-13 2023-03-14 上海思优建筑科技有限公司 Optimal design method and system for building structure
CN111353189A (en) * 2020-02-21 2020-06-30 广东三维家信息科技有限公司 Configuration method and device of home decoration line material and electronic equipment
CN112765714A (en) * 2021-01-21 2021-05-07 天津大学 BIM-based Chinese building life cycle environmental impact and cost accounting method
CN113158292A (en) * 2021-03-02 2021-07-23 广联达科技股份有限公司 Component matching method, engineering quantity calculation method, device and electronic equipment
CN113158292B (en) * 2021-03-02 2024-02-13 广联达科技股份有限公司 Component matching method, engineering amount calculating device and electronic equipment
CN113656402A (en) * 2021-07-13 2021-11-16 广东省国际工程咨询有限公司 Engineering project full life cycle data recording and storing method and device based on BIM
CN113863396A (en) * 2021-09-29 2021-12-31 北京中岩大地科技股份有限公司 Method for predicting construction cost of composite pile under consideration of multi-factor influence
CN114445129A (en) * 2022-01-13 2022-05-06 湖北国际物流机场有限公司 BIM coding system
CN114445129B (en) * 2022-01-13 2024-03-19 湖北国际物流机场有限公司 BIM coding system
CN116720695A (en) * 2023-06-07 2023-09-08 金联智能科技发展(深圳)有限公司 Engineering budget management method and system based on BIM technology

Similar Documents

Publication Publication Date Title
CN106934540A (en) A kind of architecture engineering material cost budgeting method based on Revit
CN103605970A (en) Drawing architectural element identification method and system based on machine learning
CN108959694A (en) A kind of BIM geometrical model construction method of big scale of construction complex building
CN111557015B (en) Patent map display device and patent map display method
CN114840900B (en) Automatic generation method of derivative BIM (building information modeling) component based on i-GBDT (generic block transformation) technology
CN113761622B (en) Parameterized city modeling method and device, storage medium and terminal equipment
CN108647450A (en) A kind of pre-buried big foundation bolt construction method based on BIM technology
CN109308361A (en) Construction method, system and the computer installation of three-dimensional reinforcing bar calculation amount model
CN104182456B (en) Spatial entity increment extraction method based on MRS-MM (Multi-Rules Supported Matching Model) target matching model
CN111047696B (en) Method for planning paying-off in three-dimensional space
CN107507188A (en) A kind of method and device based on machine learning extraction image information
CN108694260A (en) Application process of the BIM technology in Steel Bridge processing and manufacturing
CN108286978A (en) Road network automatic generating method and device and hybrid navigation system
CN114372940A (en) Real scene image synthesis method and system
CN115796972A (en) BIM technology-based quantity and price fusion implementation method
Liu et al. Statistical estimation of blast fragmentation by applying 3D laser scanning to muck pile
CN109242520A (en) A kind of potential user group localization method and device
US20110270582A1 (en) Systems and methods providing smart nodes for three-dimensional models
CN117473592B (en) Data display method and device based on industrial large model
CN111598990B (en) Method for reading DICOM data and generating Texture3D
Turrina et al. The reconstruction of a dynamic inventory model toward shared HBIM libraries for vaulted systems
CN114445129B (en) BIM coding system
CN110309332A (en) A kind of CAD model partial retrieval method merging Engineering Semantics
CN116258287B (en) Reinforcing steel bar blanking combination optimization method
CN114461714B (en) BIM code conversion system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170707