CN109426914A - A kind of construction project amount of concrete control method based on BIM technology - Google Patents
A kind of construction project amount of concrete control method based on BIM technology Download PDFInfo
- Publication number
- CN109426914A CN109426914A CN201710771245.8A CN201710771245A CN109426914A CN 109426914 A CN109426914 A CN 109426914A CN 201710771245 A CN201710771245 A CN 201710771245A CN 109426914 A CN109426914 A CN 109426914A
- Authority
- CN
- China
- Prior art keywords
- concrete
- amount
- component
- mapping
- model
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims abstract description 17
- 238000010276 construction Methods 0.000 title claims abstract description 15
- 238000005516 engineering process Methods 0.000 title claims abstract description 15
- 238000013507 mapping Methods 0.000 claims abstract description 39
- 238000004364 calculation method Methods 0.000 claims description 9
- 239000000463 material Substances 0.000 claims description 6
- 238000004458 analytical method Methods 0.000 claims description 3
- 239000003086 colorant Substances 0.000 claims description 2
- 241000208340 Araliaceae Species 0.000 description 1
- 235000005035 Panax pseudoginseng ssp. pseudoginseng Nutrition 0.000 description 1
- 235000003140 Panax quinquefolius Nutrition 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 235000008434 ginseng Nutrition 0.000 description 1
- 238000007689 inspection Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 239000002689 soil Substances 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
- G06Q10/06315—Needs-based resource requirements planning or analysis
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/08—Construction
Landscapes
- Business, Economics & Management (AREA)
- Human Resources & Organizations (AREA)
- Engineering & Computer Science (AREA)
- Strategic Management (AREA)
- Economics (AREA)
- General Business, Economics & Management (AREA)
- Theoretical Computer Science (AREA)
- Marketing (AREA)
- Tourism & Hospitality (AREA)
- Physics & Mathematics (AREA)
- Entrepreneurship & Innovation (AREA)
- General Physics & Mathematics (AREA)
- Health & Medical Sciences (AREA)
- Primary Health Care (AREA)
- Development Economics (AREA)
- Educational Administration (AREA)
- General Health & Medical Sciences (AREA)
- Game Theory and Decision Science (AREA)
- Operations Research (AREA)
- Quality & Reliability (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The construction project amount of concrete control method based on BIM technology that the present invention relates to a kind of, comprising steps of one, it establishes BIM model and component name is named, correct mapping relations between establishing model component and component name;Two, BIM model item information is inputted, simultaneously associated technical parameters are arranged in the mapping before calculating according to component mapping rule component;Three, be added as needed and modify sundry item information, check component whether Complete Mappings;Four, summarize computation model amount of concrete, output data;Five, it collects actual floor layer concrete and pours data and budget portion amount of concrete budget data, BIM amount of concrete is calculated into data and budget data and the live actually amount of pouring carries out summarizing comparison, and is sent to related personnel and discusses and analyze.The present invention applies in on-site concrete amount control process, can provide accurate concrete and calculate data, has for practical amount of concrete and the comparison of budget amount of concrete and implements meaning well.
Description
Technical field
The present invention relates to a kind of construction project amount of concrete control method, specifically a kind of building based on BIM technology
Build project amount of concrete control method.
Background technique
The practical concreting amount in scene and budget portion beam are easy to appear relatively large deviation, can not real-time control concreting
Amount, and be not easy to find out deviating cause, materials'use low efficiency, risk are low.
Summary of the invention
The present invention is directed to overcome the deficiencies of existing technologies, a kind of construction project amount of concrete control based on BIM technology is provided
Method processed provides new amount of concrete as reference data for scene, realizes the real-time control of concreting amount.
In order to solve the above-mentioned technical problem, the present invention is implemented as follows:
A kind of construction project amount of concrete control method based on BIM technology, it is characterised in that it includes the following steps:
Step 1 is established BIM model and is named to component name, correctly reflects between establishing model component and component name
Penetrate relationship;The corresponding one or more BIM model component of corresponding relationship, that is, model component content according to described in its title;
If including critical field required in mapping ruler in model component title, according to mapping ruler to corresponding model structure
Part carries out mapping calculation;If not including critical field required in mapping ruler in model component title, cannot achieve
The mapping calculation of model component;
Step 2 inputs BIM model item information, and simultaneously phase is arranged in the mapping before calculating according to component mapping rule component
Close technical parameter;
Step 3, is added as needed and modifies sundry item information, check component whether Complete Mappings;
Step 4 summarizes computation model amount of concrete, output data;
Step 5 collects actual floor layer concrete and pours data and budget portion amount of concrete budget data, by BIM concrete meter
It counts and carries out summarizing comparison according to budget data and the live actually amount of pouring, and be sent to related personnel and discuss and divide
Analysis.
The construction project amount of concrete control method based on BIM technology, it is characterised in that: described in step 1
Title includes dimension information, material information, the location information of model component.
The construction project amount of concrete control method based on BIM technology, it is characterised in that: project is believed in step 2
Breath is floor information, concrete strength information, indoor and outdoor height difference information.
The construction project amount of concrete control method based on BIM technology, it is characterised in that: checking in step 3 is
No Complete Mappings are mainly reflected by being distinguished to mapping mechanism and non-mapping mechanism by different colours convenient for quick check
Penetrate result.
The beneficial effects of the present invention are: the present invention uses in construction project work progress, pass through model name and component
The combination of mapping forms the amount of concrete output data based on BIM, and mixed by collecting practical concreting amount and budget portion
Solidifying soil amount of budget simultaneously compares three of the above data, and the application of BIM model is made to be not limited only to the lookup to drawing problem
With correction, better reflect reliability of BIM model during quantities calculation, convenient for each participant of project mutually exchange with
The reason of analyzing and finding out deviation plays a significant role in terms of improving materials'use efficiency, reduction risk.
Specific embodiment
A kind of construction project amount of concrete control method based on BIM technology, comprising:
1) it establishes BIM model and component name is named, correctly mapping is closed between establishing model component and component name
System;The corresponding one or more BIM model component of corresponding relationship, that is, model component content according to described in its title;If
Include critical field required in mapping ruler in model component title, then according to mapping ruler to corresponding model component into
Row mapping calculation;If not including critical field required in mapping ruler in model component title, model cannot achieve
The mapping calculation of component.The title includes dimension information, material information, location information of model component etc..
2) BIM model item information is inputted, simultaneously phase is arranged in the mapping before calculating according to component mapping rule component
Close technical parameter;Project information is floor information, concrete strength information, indoor and outdoor height difference information.It under special circumstances, can be with
It is modified according to the requirement of model actual conditions and calculation to computation rule, to guarantee the accuracy of calculated result.
3) according to needing to add and modify the high information of floor layer, the concrete material information of different layers relative superiority or inferiority, to be calculated
Element type and modification calculation basis, quota title, inventory title etc., by mapping mechanism and the progress of non-mapping mechanism
Distinguish can quickly inspection model mapping result, convenient for the accurate calculating of model;
4) amount of concrete calculated result is exported;The concrete calculated result of the output includes chart and explanatory note attachment;Institute
It states correlation graph and explanatory note includes but is not limited to quantity of goods produced summary sheet, project amount detail list, engineering figureofmerit table etc..
5) the amount of concrete data that actual floor layer concrete pours data Yu the budget of budget portion are collected, by BIM amount of concrete
It calculates data and budget portion budget data and the live actually amount of pouring carries out summarizing comparison, and be sent to relevant departments and begged for
By and analysis.
The present invention provides a kind of new ginseng about concrete Practical Project amount and amount of budget deviation for different departmental staffs
It examines as a result, improve work efficiency, reduces the risk of the project implementation.
Claims (4)
1. a kind of construction project amount of concrete control method based on BIM technology, it is characterised in that it includes the following steps:
Step 1 is established BIM model and is named to component name, correctly reflects between establishing model component and component name
Penetrate relationship;The corresponding one or more BIM model component of corresponding relationship, that is, model component content according to described in its title;
If including critical field required in mapping ruler in model component title, according to mapping ruler to corresponding model structure
Part carries out mapping calculation;If not including critical field required in mapping ruler in model component title, cannot achieve
The mapping calculation of model component;
Step 2 inputs BIM model item information, and simultaneously phase is arranged in the mapping before calculating according to component mapping rule component
Close technical parameter;
Step 3, is added as needed and modifies sundry item information, check component whether Complete Mappings;
Step 4 summarizes computation model amount of concrete, output data;
Step 5 collects actual floor layer concrete and pours data and budget portion amount of concrete budget data, by BIM concrete meter
It counts and carries out summarizing comparison according to budget data and the live actually amount of pouring, and be sent to related personnel and discuss and divide
Analysis.
2. the construction project amount of concrete control method according to claim 1 based on BIM technology, it is characterised in that: step
Title described in rapid one includes dimension information, material information, the location information of model component.
3. the construction project amount of concrete control method according to claim 1 based on BIM technology, it is characterised in that: step
Project information is floor information, concrete strength information, indoor and outdoor height difference information in rapid two.
4. the construction project amount of concrete control method according to claim 1 based on BIM technology, it is characterised in that: step
Check whether Complete Mappings mainly by distinguishing just to mapping mechanism and non-mapping mechanism by different colours in rapid three
Mapping result is checked in quick.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710771245.8A CN109426914A (en) | 2017-08-31 | 2017-08-31 | A kind of construction project amount of concrete control method based on BIM technology |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710771245.8A CN109426914A (en) | 2017-08-31 | 2017-08-31 | A kind of construction project amount of concrete control method based on BIM technology |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109426914A true CN109426914A (en) | 2019-03-05 |
Family
ID=65504728
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710771245.8A Pending CN109426914A (en) | 2017-08-31 | 2017-08-31 | A kind of construction project amount of concrete control method based on BIM technology |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109426914A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112528364A (en) * | 2020-11-30 | 2021-03-19 | 中国中元国际工程有限公司 | Beam-free floor design method based on lookup table |
CN117094686A (en) * | 2023-10-18 | 2023-11-21 | 中铁二十三局集团有限公司 | Dynamic monitoring method and system for whole concrete production and construction process |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20150047406A (en) * | 2013-10-24 | 2015-05-04 | 연세대학교 산학협력단 | System and method for converting ontology-based rule set into bim model checker rule set for bim quality check |
CN105302978A (en) * | 2015-11-10 | 2016-02-03 | 上海建工集团股份有限公司 | Quantity calculation method and device |
CN106600239A (en) * | 2016-12-28 | 2017-04-26 | 中建科技有限公司 | Assembly type building construction full process data cooperation management system based on BIM |
CN106934540A (en) * | 2017-03-07 | 2017-07-07 | 西安理工大学 | A kind of architecture engineering material cost budgeting method based on Revit |
-
2017
- 2017-08-31 CN CN201710771245.8A patent/CN109426914A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20150047406A (en) * | 2013-10-24 | 2015-05-04 | 연세대학교 산학협력단 | System and method for converting ontology-based rule set into bim model checker rule set for bim quality check |
CN105302978A (en) * | 2015-11-10 | 2016-02-03 | 上海建工集团股份有限公司 | Quantity calculation method and device |
CN106600239A (en) * | 2016-12-28 | 2017-04-26 | 中建科技有限公司 | Assembly type building construction full process data cooperation management system based on BIM |
CN106934540A (en) * | 2017-03-07 | 2017-07-07 | 西安理工大学 | A kind of architecture engineering material cost budgeting method based on Revit |
Non-Patent Citations (2)
Title |
---|
宋楠楠: "基于Revit的BIM构件标准化关键技术研究", 《中国优秀硕士学位论文全文数据库(工程科技II辑)》 * |
王茹 等: "基于我国清单计价规范的Revit模型工程量提取", 《图学学报》 * |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112528364A (en) * | 2020-11-30 | 2021-03-19 | 中国中元国际工程有限公司 | Beam-free floor design method based on lookup table |
CN117094686A (en) * | 2023-10-18 | 2023-11-21 | 中铁二十三局集团有限公司 | Dynamic monitoring method and system for whole concrete production and construction process |
CN117094686B (en) * | 2023-10-18 | 2024-01-26 | 中铁二十三局集团有限公司 | Dynamic monitoring method and system for whole concrete production and construction process |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109710990B (en) | BIM technology-based roller compacted concrete dam construction progress-cost cooperative control method | |
CN110046364A (en) | A kind of method for computing work amount based on BIM technology | |
De Wolf | Low carbon pathways for structural design: embodied life cycle impacts of building structures | |
CN109447481A (en) | A kind of live cost monitoring system and method based on threedimensional model | |
CN106202723A (en) | A kind of BIM subway work method | |
CN106372302A (en) | Tower crane automatic model selection and optimization system and method based on BIM (Building Information Modeling) technology | |
CN107818430A (en) | A kind of building engineering construction progress msg management method and system based on BIM | |
CN108592895A (en) | Construction detecting system based on 3 D laser scanning, method and apparatus | |
CN108537519A (en) | A kind of architectural design method based on BIM | |
Duncheva et al. | Multifaceted productivity comparison of off-site timber manufacturing strategies in Mainland Europe and the United Kingdom | |
CN106097149A (en) | The method for designing of project of transmitting and converting electricity cost software based on BIM technology | |
CN109426914A (en) | A kind of construction project amount of concrete control method based on BIM technology | |
Russell-Smith et al. | Dynamic life cycle assessment of building design and retrofit processes | |
CN106372787A (en) | Progress plan quick compilation method based on BIM and big data | |
Jun et al. | BIM-based carbon dioxide emission quantity assessment method in Korea | |
CN110750827A (en) | Progress management method based on BIM | |
Gade | A proposed solution to the problem of construction industry overruns: lean construction techniques and linear programming | |
KR101472461B1 (en) | Development system of BIM library for building assessment | |
Ji et al. | The application of BIM technology in the cost management of the whole process of construction projects | |
Goes et al. | Design coordination with Building Information Modeling: a case study | |
Leśniak et al. | Costs of facade systems execution | |
CN114925908A (en) | Information control method for construction progress of fabricated building | |
Menon et al. | Labour productivity measurement method using 3D BIM of a commercial project | |
Lee et al. | The development of automatic module for formwork layout using the BIM | |
CN104091015A (en) | C# sampling method for power transmission line iron tower and related framework |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190305 |