CN110046364A - A kind of method for computing work amount based on BIM technology - Google Patents

A kind of method for computing work amount based on BIM technology Download PDF

Info

Publication number
CN110046364A
CN110046364A CN201810041468.3A CN201810041468A CN110046364A CN 110046364 A CN110046364 A CN 110046364A CN 201810041468 A CN201810041468 A CN 201810041468A CN 110046364 A CN110046364 A CN 110046364A
Authority
CN
China
Prior art keywords
bim
threedimensional model
component
project
amount based
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810041468.3A
Other languages
Chinese (zh)
Other versions
CN110046364B (en
Inventor
陈阳
吴福利
王启桃
王文元
战胜
朱文兵
温卫军
张曾水
张凯
崔璨
严韦
潘雨漫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN201810041468.3A priority Critical patent/CN110046364B/en
Publication of CN110046364A publication Critical patent/CN110046364A/en
Application granted granted Critical
Publication of CN110046364B publication Critical patent/CN110046364B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Abstract

The invention discloses a kind of method for computing work amount based on BIM technology, includes the following steps: to receive, check, review drawing;BIM threedimensional model is established according to design drawing;BIM threedimensional model carries out dynamic management;Incorporation engineering actual conditions carry out collision detection to BIM threedimensional model;According to BIM threedimensional model collision detection as a result, adjustment and modification BIM threedimensional model;The customized computation rule in BIM threedimensional model;It calculates and summarizes in BIM software, and export bill of quantities.It can be modeled fully according to architectural engineering actual conditions using the present invention, can really reflect building structure truth, improve the accuracy of quantities calculation;The customized computation rule in BIM software, accurately calculates the parameter of each dimension of component, improves the quality of quantities calculation;The raising of quantities calculation quality is of great significance to the result of project cost, and the present invention has good social and economic benefit.

Description

A kind of method for computing work amount based on BIM technology
Technical field
The present invention relates to building fields, and in particular to a kind of method for computing work amount based on BIM technology.
Background technique
Original method for computing work amount is budgeter according to local quota, by tools such as calculators on paper document It carrying out engineering list, calculates, working efficiency is lower, and computational accuracy is low, it is easy to happen mistake, and inconvenient adjustment, once occur Adjustment, quantities calculation need to calculate from the beginning.
With the development of computer application, the promotion of engineering technology gradually develops excel software, figure calculation amount software Equal quantities calculations mode, but these quantities calculation modes still remain problems, are not able to satisfy the quick hair of construction industry It opens up, major defect existing for traditional method for computing work amount is as follows:
1, can not correctly reflect the relationship of reducing between different component, especially labyrinth completely reduces relationship, because It is wrong that this will cause quantities calculation;
2, because building system is huge, it is unable to automatic identification in general figure calculation amount software and checks graphic plotting mistake Accidentally;
3, modern building fabric is complicated and changeable, and the calculation method of project amount also changes therewith, and calculates and require to get over Come it is higher, most of software cannot completely customized computation rule;
4, during quantities calculation, regular software can not achieve the visualization of computation model;
It is badly in need of new technology with the high speed development of building trade based on above many reasons and solves these problems.
Summary of the invention
The present invention in order to solve the above problem used by technical solution are as follows: a kind of quantities calculation side based on BIM technology Method, comprising the following steps:
S1: receiving and checks design drawing: receiving the design drawing from designing unit, the design drawing includes design Illustrate, architectural working drawing, structural working drawing, profession in-depth figure;Drawing is checked and adjusts, Suitable content includes the plane position of component It sets, range, figure layer, ratio, size and absolute altitude;
S2: establish BIM threedimensional model according to design drawing: the BIM threedimensional model of establishing includes the following three types mode:
S21 is modeled by hand: independent that BIM threedimensional model is established in BIM software according to design drawing;
S22 leads figure modeling: importing design drawing, identifies and establish BIM threedimensional model;
S23 receives model: directly receiving the BIM threedimensional model that completion has been established from designing unit;
S3: according to construction speed, dynamic management is carried out to BIM threedimensional model;According to project progress, in BIM threedimensional model Middle drafting measure project, the measure project include scaffold, template, brick fetal membrane, post-cast strip, the earthwork;
S4: incorporation engineering actual conditions carry out collision detection to BIM threedimensional model;
S5: according to S4 collision detection as a result, carrying out the adjustment of BIM threedimensional model, the index of adjustment includes the plane meter of component Very little, positional relationship, absolute altitude and material;
S6: according to quantities calculation demand, work load evaluation is defined in BIM software;
S7: obtaining entire projects amount by calculating to summarize according to work load evaluation, according to component screening parameter, Export required project amount table.
Preferably, the component include basis, pile framing, column, beam, wall, plate, roofing, stair, door and window, wall decoration, Face decoration, furred ceiling.
The basis includes stake, strip footing, box foundation, brick foundation.
The column includes rectangular column, circular columns, steel structure column, sleeper.
The beam includes Vierendeel girder, collar tie beam, girder steel, roofing Vierendeel girder, coupling beam, concealed beam, Cantilever Beams, lintel.
The wall includes concrete walls, brick wall, masonry wall.
The plate includes floorboard, roof boarding, cantilevered plate.
Preferably, the BIM software is Revit.
Preferably, it is modeled by hand described in S21, comprising the following steps:
S211: establishing item argument information, and the parameter information includes the absolute altitude of component, project basic point, elevational point;
S212: according to design drawing median-plane location, planar dimension relationship, axis net is established in BIM software;
S213: according to architectural working drawing, structural working drawing, respective members information is established, and according to the height of component, thickness Degree, length, the gradient, sectional dimension, material, power, strength grade, fire-protection rating, the scope of application, specifications and models, company-information Define structure attribute;
S214: according to component present position in drawing, respective members are arranged in BIM threedimensional model.
Preferably, figure modeling is led described in the step S22, comprising the following steps:
S221: design drawing is directed into BIM software identification module, and carries out drawing segmentation;
S222: identification axis net, and establish BIM threedimensional model axis net;
S223: component is imported and establishes BIM threedimensional model by successively identification means;
S224: by component according to height, thickness, length, the gradient, sectional dimension, material, power, strength grade, fire prevention etc. Grade, the scope of application, specifications and models, company-information carry out attribute definition respectively, complete BIM three-dimension modeling.
It is clear that the provided drawing of designing unit is comprehensively, specification, figure layer are arranged, and modeling pattern, which can be selected preferentially, leads figure modeling, This method convenient and efficient can quickly establish BIM threedimensional model.
Preferably, measure project described in step S3 includes scaffold, template, brick fetal membrane, vertical transport, post-cast strip, the earthwork.
Preferably, collision detection described in step S4, comprising:
Method 1: setting roaming checks, with the visual angle of people, roams in virtual BIM threedimensional model, and in inspection model Collision situation between each component;
Method 2: setting hard collision inspection, BIM software calculate intersection-type collision between component and component automatically;
Method 3: setting soft collision inspection parameter, the parameter are construction reasonable operation space, that is, refer to component and component Between construction minimum can operating space;
Any one inspection method in three of the above method.Certainly according to demand, a variety of methods can also be selected mutual Review, improves the accuracy of collision detection.
If collision detection is errorless, S6 operation can be entered step.If collision detection is wrong, component correlation is adjusted Parameter information, if can not adjust, designing unit is fed back to, is redesigned by designing unit's component, according to new design drawing Paper models again.
Preferably, work load evaluation described in step S6, comprising:
S61: measuring according to bill of quantities and standardize, and the computation rule in bill of quantities metering specification is input to BIM Software calculates corresponding project amount, realizes seamless interfacing with bill of quantities;
S62: according to location engineering budget ration, corresponding work load evaluation being inputted in BIM software, subsequent to obtain The project amount arrived is consistent with engineering budget ration;
S63: according to engineering practice of construction needs, inputting work load evaluation on demand, and it is actually required to be computed export Project amount,
Any one method in three of the above method.Certainly according to demand, a variety of methods can also be used, obtain a variety of meters Result is calculated for instructing real work.
Preferably, screening parameter described in step S7 include height, thickness, length, the gradient, sectional dimension, material, power, Strength grade, fire-protection rating, specifications and models, company-information, absolute altitude, range, floor.
Preferably, project amount table described in step S7 includes that part-to-item project amount inventory and pricing table, measure project are clear Single and pricing table, other item bill and pricing table, inventory component detail list.
The part-to-item project amount inventory and pricing table, measure item and pricing table, other item bill and meter Valence table, inventory component detail list are according to " construction project bill of quantities metering specification " and " construction project Engineering Quantity List Pricing Specification ".
The project amount table further includes lower material list, single member detail list.
Bring of the present invention has the beneficial effect that method for computing work amount of the invention, can be fully according to architectural engineering reality Border situation carries out three-dimensional modeling, and the overlap joint and the relationship of reducing between different component can really reflect;Pass through touching in BIM software Audit function is hit, with automatic identification and place wrong in model can be checked, it is possible to reduce cause work because of drawing, model errors The wrong situation of journey amount;By true three-dimension model, and customized computation rule, various Complex Different Shape components ginsengs can be calculated Number, engineering accuracy of measurement are sufficient for real work demand.By implementing the invention, can with power-assisted Chinese architectural trade high speed development, A kind of simple, quick, accurate, convenient and fast method for computing work amount is provided for construction industry, improves the effect in construction engineering cost field Rate has good Social benefit and economic benefit.
Detailed description of the invention
Fig. 1 is a kind of method for computing work amount flow diagram based on BIM technology of the present invention;
Fig. 2 is that selection imports CAD diagram paper menu schematic diagram in the embodiment of the present invention;
Fig. 3 is selection drawing file schematic diagram in the embodiment of the present invention;
Fig. 4 is that wall BIM threedimensional model menu schematic diagram is established in the embodiment of the present invention;
Fig. 5 is that three-dimensional view angle checks BIM threedimensional model schematic diagram in the embodiment of the present invention;
Fig. 6 is practice of construction situation and former design threedimensional model contrast schematic diagram in the embodiment of the present invention;
Fig. 7 is collision detection menu selection schematic diagram in the embodiment of the present invention;
Fig. 8 is that collision detection component selects schematic diagram in the embodiment of the present invention;
Fig. 9 is collision detection result schematic diagram in the embodiment of the present invention;
Figure 10 is that soft collision checks menu selection schematic diagram in the embodiment of the present invention;
Figure 11 is that soft collision inspection item selects schematic diagram in the embodiment of the present invention;
Figure 12 is that soft collision inspection result exports menu schematic diagram in the embodiment of the present invention;
Figure 13 is selection material schematic diagram in the embodiment of the present invention;
Figure 14 is project amount table schematic diagram in the embodiment of the present invention;
Figure 15 is part-to-item project amount inventory and pricing table schematic diagram in the embodiment of the present invention;
Figure 16 is measure item and pricing table schematic diagram in the embodiment of the present invention.
Specific embodiment
Below in conjunction with specific attached drawing 1~16, the present invention is further illustrated.
As shown in Figure 1, providing a kind of method for computing work amount based on BIM technology, comprising the following steps:
S1: receiving and checks design drawing: receiving the design drawing from designing unit, the design drawing includes design Illustrate, architectural working drawing, structural working drawing, profession in-depth figure;Drawing is checked and adjusts, Suitable content includes member planar position It sets, range, figure layer, ratio, size and absolute altitude;
S2: BIM threedimensional model mode is established with figure is led with Revit software according to design drawing: specific as follows:
(1) selection " the importing CAD " button in Revit menu, as shown in Figure 2;
(2) selection needs the drawing imported in file, as shown in Figure 3;
(3) it identifies axis net, and establishes BIM threedimensional model axis net;
(4) successively identification means, import modeling systems for component;
(5) according to the component-wall identified, the threedimensional model of wall is established, as shown in Figure 4;
(6) by component according to height, thickness, length, the gradient, sectional dimension, material, power, strength grade, fire prevention etc. Grade, the scope of application, specifications and models, company-information carry out attribute definition respectively,
Complete BIM three-dimension modeling;
(7) three-dimension modeling situation is checked with three-dimensional view angle after BIM three-dimension modeling, as shown in Figure 5.
S3: according to construction speed, dynamic management is carried out to BIM threedimensional model;According to project progress, in BIM threedimensional model Middle drafting measure project, measure project include scaffold, template, brick fetal membrane, post-cast strip, the earthwork;And it will in BIM threedimensional model Practice of construction situation is compared with former design conditions, as shown in Figure 6;
S4: incorporation engineering actual conditions carry out collision detection to BIM threedimensional model;The following steps are included:
S41: setting roaming checks, with the visual angle of people, roams in virtual BIM threedimensional model, and each in inspection model Collision situation between component;
S42: setting hard collision inspection, BIM software calculate intersection-type collision between component and component automatically;
S421: selection " the operation collision detection " in Revit menu, as shown in Figure 7;
S422: can be with unrestricted choice, by taking wall and wall collision detection as an example, as shown in Figure 8 in collision project;
S423: inspection result occurs, and clicks operation result and checks, as shown in Figure 9;
S43: setting soft collision inspection parameter, the parameter are construction reasonable operation space, that is, refer to component and component it Between construction minimum can operating space;
S431: pass through third party software: navisworks software carries out collision detection, converts Revit file to Navisworks file;
S432: " clash detective " is selected in navisworks menu;
S433: it adds and checks in navisworks software, as shown in Figure 10;
S434: collision detection element type is selected in navisworks software, as shown in figure 11;
S435: export operation result, as shown in figure 12;
S5: according to S4 collision detection as a result, carrying out the adjustment of BIM threedimensional model, the index of adjustment includes the plane meter of component Very little, positional relationship, absolute altitude and material;
If collision detection is errorless, S6 operation can be entered step.If collision detection is wrong, component correlation is adjusted Parameter information, if can not adjust, designing unit is fed back to, is redesigned by designing unit's component, according to new design drawing Paper models again.
S6: fixed according to valuating engineering work load with bill in Revit software according to the requirement of valuating engineering work load with bill Adopted work load evaluation;
S7: entire projects amount is obtained by calculating to summarize according to work load evaluation, wall member is selected, selects material Matter (as shown in figure 13) exports required wall project amount table (as shown in figure 14), can additionally export project amount branch Subdivisional work amount inventory and pricing table (as shown in figure 15) can also export measure item and pricing table (such as Figure 16 institute Show).
As shown in Fig. 2, for selection in Revit menu under step S2 " importing CAD " button schematic diagram, it should by selection Button can import cad file.
As shown in figure 3, choosing the cad file that can beat for selection needs the drawing imported in file under step S2 It opens.
As shown in figure 4, by, according to the component-wall identified, establishing the threedimensional model of wall under step S2, similarly, can choose The components such as door, window, column, roof, floor, and establish corresponding threedimensional model.
As shown in figure 5, to check three-dimension modeling situation after BIM three-dimension modeling under step S2 with three-dimensional view angle, Check threedimensional model, can freely adjust the angle of observation in software, can any 360 degree select, whether observing and nursing deposit In problem.
As shown in fig. 6, compare practice of construction situation and former design conditions in BIM threedimensional model for step S3, It is former design scheme in the circle of the left side, is site operation status in the circle of the right, it was found that designs inconsistent place with former in scene.
As shown in fig. 7, selecting " operation collision detection " in Revit menu for step S421.
As shown in figure 8, can be with unrestricted choice, by taking wall and wall collision detection as an example, also in collision project for step S422 It can choose wall and column, the multiple choices mode such as stair and accommodation rail.
As shown in figure 9, occurring for step S423 inspection result, clicks operation result and check.
As shown in Figure 10, it adds and checks in navisworks software for step S433.
As shown in figure 11, collision detection element type, Yi Qiang and wind are selected in navisworks software for step S434 For pipe, air hose and air hose also can choose, it is also an option that wall and wall.
As shown in figure 12, operation result is exported for step S435, collision detection result can directly be exported by clicking the button.
As shown in figure 13, to select material option under step S7, the project amount of the material can be exported.
As shown in figure 14, to export required wall project amount table under step S7, the table is merely illustrative.
It as shown in figure 15, is export project amount part-to-item project amount inventory and pricing table under step S7, branch's subitem work Journey amount inventory and pricing table are to belong to form template specified in " construction project valuating engineering work load with bill ".
It as shown in figure 16, is export project amount measure item and pricing table under step S7, measure item and meter Valence table is to belong to form template specified in " construction project valuating engineering work load with bill ".
Project amount can be visualized using the present invention, the management of mobilism, and close with engineering practice It is connected, can have both been fed back again with guiding construction, practice of construction situation using this method in BIM threedimensional model, and promote construction group Knit the common progress with construction technology.Using the present invention can quickly, it is accurate, dynamically reflect engineering practice, and can be in time Calculate whole or required local project amount.Especially to the implementation of large complicated irregular building structure, having can not estimate The value of amount.
The above content is a further detailed description of the present invention in conjunction with specific preferred embodiments, and it cannot be said that Specific implementation of the invention is only limited to these instructions, and for those skilled in the art to which the present invention belongs, is not being taken off Under the premise of from present inventive concept, a number of simple deductions or replacements can also be made, all shall be regarded as belonging to protection of the invention Range.

Claims (10)

1. a kind of method for computing work amount based on BIM technology, it is characterised in that: the following steps are included:
S1: receiving and checks design drawing: receiving the design drawing from designing unit, the design drawing includes that design is said Bright, architectural working drawing, structural working drawing, profession in-depth figure;Drawing is checked and adjusts, Suitable content includes the plane position of component It sets, range, figure layer, ratio, size and absolute altitude;
S2: establish BIM threedimensional model according to design drawing: the BIM threedimensional model of establishing includes the following three types mode:
S21 is modeled by hand: independent that BIM threedimensional model is established in BIM software according to design drawing;
S22 leads figure modeling: importing design drawing, identifies and establish BIM threedimensional model;
S23 receives model: directly receiving the BIM threedimensional model that completion has been established from designing unit;
S3: according to construction speed, dynamic management is carried out to BIM threedimensional model;According to project progress, drawn in BIM threedimensional model Measure project processed;
S4: incorporation engineering actual conditions carry out collision detection to BIM threedimensional model;
S5: according to S4 collision detection as a result, carrying out the adjustment of BIM threedimensional model, the index of adjustment includes the planar dimension of component, position Set relationship, absolute altitude and material;
S6: according to quantities calculation demand, work load evaluation is defined in BIM software;
S7: entire projects amount is obtained by calculating to summarize according to work load evaluation, according to component screening parameter, export Required project amount table.
2. a kind of method for computing work amount based on BIM technology according to claim 1, it is characterised in that: the component Including basis, pile framing, column, beam, wall, plate, roofing, stair, door and window, wall decoration, ground decoration, furred ceiling.
3. a kind of method for computing work amount based on BIM technology according to claim 1, it is characterised in that: the BIM is soft Part is Revit.
4. a kind of method for computing work amount based on BIM technology according to claim 1, it is characterised in that: step S21 institute State manual modeling, comprising the following steps:
S211: establishing item argument information, and the parameter information includes the absolute altitude of component, project basic point, elevational point;
S212: according to design drawing median-plane location, planar dimension relationship, axis net is established in BIM software;
S213: according to architectural working drawing, structural working drawing, respective members information is established, and according to the height of component, thickness, length Degree, the gradient, sectional dimension, material, power, strength grade, fire-protection rating, the scope of application, specifications and models, company-information define structure Part attribute;
S214: according to component present position in drawing, respective members are arranged in BIM threedimensional model.
5. a kind of method for computing work amount based on BIM technology according to claim 1, it is characterised in that: step S22 institute It states and leads figure modeling, comprising the following steps:
S221: design drawing is directed into BIM software identification module, and carries out drawing segmentation;
S222: identification axis net, and establish BIM threedimensional model axis net;
S223: component is imported and establishes BIM threedimensional model by successively identification means;
S224: by component according to height, thickness, length, the gradient, sectional dimension, material, power, strength grade, fire-protection rating, The scope of application, specifications and models, company-information carry out attribute definition respectively, complete BIM three-dimension modeling.
6. a kind of method for computing work amount based on BIM technology according to claim 1, it is characterised in that: step S3 institute The measure project of stating includes scaffold, template, brick fetal membrane, vertical transport, post-cast strip, the earthwork.
7. a kind of method for computing work amount based on BIM technology according to claim 1, it is characterised in that: step S4 institute State collision detection, comprising:
Method 1: setting roaming checks, with the visual angle of people, roams in virtual BIM threedimensional model, and each structure in inspection model Collision situation between part;
Method 2: setting hard collision inspection, BIM software calculate intersection-type collision between component and component automatically;
Method 3: setting soft collision inspection parameter, the parameter are construction reasonable operation space, that is, are referred between component and component Construct minimum can operating space,
Any one inspection method in three of the above method.
8. a kind of method for computing work amount based on BIM technology according to claim 1, it is characterised in that: step S6 institute State work load evaluation, comprising:
Method 1: measuring according to bill of quantities and standardize, and it is soft that the computation rule in bill of quantities metering specification is input to BIM Part calculates corresponding project amount, realizes seamless interfacing with bill of quantities;
Method 2: according to location engineering budget ration, corresponding work load evaluation being inputted in BIM software, subsequent available Project amount it is consistent with engineering budget ration;
Method 3: according to engineering practice of construction needs, inputting work load evaluation on demand, is computed export work actually required Cheng Liang,
Any one method in three of the above method.
9. a kind of method for computing work amount based on BIM technology according to claim 1, it is characterised in that: step S7 institute Stating screening parameter includes height, thickness, length, the gradient, sectional dimension, material, power, strength grade, fire-protection rating, specification type Number, company-information, absolute altitude, range, floor.
10. a kind of method for computing work amount based on BIM technology according to claim 1, it is characterised in that: step S7 institute Stating project amount table includes part-to-item project amount inventory and pricing table, measure item and pricing table, other item bill With pricing table, inventory component detail list.
CN201810041468.3A 2018-01-16 2018-01-16 Engineering quantity calculation method based on BIM technology Active CN110046364B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810041468.3A CN110046364B (en) 2018-01-16 2018-01-16 Engineering quantity calculation method based on BIM technology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810041468.3A CN110046364B (en) 2018-01-16 2018-01-16 Engineering quantity calculation method based on BIM technology

Publications (2)

Publication Number Publication Date
CN110046364A true CN110046364A (en) 2019-07-23
CN110046364B CN110046364B (en) 2022-10-25

Family

ID=67272981

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810041468.3A Active CN110046364B (en) 2018-01-16 2018-01-16 Engineering quantity calculation method based on BIM technology

Country Status (1)

Country Link
CN (1) CN110046364B (en)

Cited By (40)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110442998A (en) * 2019-08-14 2019-11-12 杭州品茗安控信息技术股份有限公司 A kind of Building Information Model dividing method, device, system and storage medium
CN110532663A (en) * 2019-08-24 2019-12-03 中铁四局集团第三建设有限公司 A kind of collaborative modeling woprk standardization process based on BIM
CN110580581A (en) * 2019-09-02 2019-12-17 中国一冶集团有限公司 construction site engineering progress monitoring system based on engineering drawing
CN110795789A (en) * 2019-10-29 2020-02-14 中建四局贵州投资建设有限公司 Application method in scaffold engineering based on BIM (building information modeling) cooperation technology
CN110956032A (en) * 2019-12-04 2020-04-03 广联达科技股份有限公司 Model and model matching method and device, storage medium and electronic equipment
CN110968904A (en) * 2019-11-12 2020-04-07 广州市第一市政工程有限公司 BIM technology-based method for calculating shape and earth volume of earth excavation side slope
CN110992475A (en) * 2019-12-12 2020-04-10 中国水利水电第八工程局有限公司 Method, system and medium for rapidly calculating engineering quantity of any part of large-volume concrete in hydraulic and hydroelectric engineering
CN111027124A (en) * 2019-12-18 2020-04-17 中国建筑第八工程局有限公司 BIM-based pile foundation bearing platform optimization method
CN111079263A (en) * 2019-11-22 2020-04-28 久瓴(上海)智能科技有限公司 Building main body structure generation method and device, computer equipment and storage medium
CN111210162A (en) * 2020-01-14 2020-05-29 中资锐诚工程项目管理有限公司 BIM-based whole process engineering pricing management method and BIM-based whole process engineering management system
CN111222786A (en) * 2020-01-04 2020-06-02 河南惠德工程咨询有限公司 Engineering cost control system based on BIM technology
CN111460565A (en) * 2020-04-15 2020-07-28 中国十七冶集团有限公司 BIM technology-based foundation construction optimization method
CN111506997A (en) * 2020-04-15 2020-08-07 国网福建省电力有限公司漳州供电公司 Power engineering quantity calculation method based on BIM
CN111651802A (en) * 2019-12-31 2020-09-11 广联达科技股份有限公司 Method and system for generating template scaffold customized scheme and storage medium
CN111709081A (en) * 2020-06-22 2020-09-25 苏州柝创智慧建筑科技有限公司 Construction cost control system based on BIM technology
CN111950052A (en) * 2020-07-20 2020-11-17 湖南工学院 BIM technology-based exterior cladding construction method for integrally-assembled building
CN111985038A (en) * 2020-08-28 2020-11-24 广联达科技股份有限公司 Method and device for calculating engineering quantity of space to be repaired
CN112016148A (en) * 2020-08-31 2020-12-01 广联达科技股份有限公司 Method and system for calculating stair engineering quantity
CN112035913A (en) * 2020-07-16 2020-12-04 中国二十冶集团有限公司 Pressure-bearing equipment foundation computer modeling method
CN112035911A (en) * 2020-07-16 2020-12-04 中国二十冶集团有限公司 Wall reserved joint bar modeling method
CN112035914A (en) * 2020-07-17 2020-12-04 中国二十冶集团有限公司 Outer arc tangent line electric calculation combination modeling fine adjustment method
CN112182727A (en) * 2020-10-23 2021-01-05 筑友智造科技投资有限公司 Method and device for automatically laying supporting pieces of building engineering and readable storage medium
CN112364404A (en) * 2020-10-14 2021-02-12 广东电网有限责任公司阳江供电局 Three-dimensional digital design intelligent mold overturning and picture examining method
CN112382353A (en) * 2020-10-30 2021-02-19 东南大学 Automatic calculation method and application of defect maintenance material for lock chamber wall of ship lock
CN112464347A (en) * 2020-12-04 2021-03-09 河南金途科技集团股份有限公司 Construction quantity statistical method and device for building component, server and storage medium
CN112632665A (en) * 2020-12-18 2021-04-09 中国二十冶集团有限公司 BIM modeling method for special-shaped upper cup opening of equipment foundation
CN112733230A (en) * 2020-12-31 2021-04-30 江苏美城建筑规划设计院有限公司 Building electromechanical pipeline comprehensive optimization method based on BIM technology
CN112818565A (en) * 2021-02-26 2021-05-18 同济大学建筑设计研究院(集团)有限公司 BIM technology-based underground water pool anti-floating checking calculation method
CN112836256A (en) * 2020-12-21 2021-05-25 中建安装集团有限公司 Calculation method based on BIM electromechanical model
CN112907281A (en) * 2021-02-05 2021-06-04 广东丰帆工程咨询有限公司 Engineering cost management method and system based on BIM technology
CN112948938A (en) * 2021-03-12 2021-06-11 中国建筑第八工程局有限公司 Method for calculating and identifying overweight beam through BIM three-dimensional modeling
CN113221231A (en) * 2021-06-08 2021-08-06 长春昆仑建设股份有限公司 Engineering quantity statistical calculation method based on BIM model
CN113378282A (en) * 2021-06-30 2021-09-10 中国二冶集团有限公司 BIM-based residential building template matching and collision inspection method and system
CN113569306A (en) * 2021-04-13 2021-10-29 中国天楹股份有限公司 BIM modeling implementation and application method of waste incineration power plant based on BIM technology
CN113673013A (en) * 2021-08-10 2021-11-19 中国建筑第八工程局有限公司 Pile cap elevation calculation method and system based on BIM technology
CN113742824A (en) * 2021-08-26 2021-12-03 苏州筑百年建筑科技有限公司 Lightweight steel structure smart collaborative design cloud platform and operation method thereof
CN115293749A (en) * 2022-10-08 2022-11-04 深圳市地铁集团有限公司 Method, system and equipment for deriving engineering quantity list based on BIM
CN115618461A (en) * 2022-09-30 2023-01-17 广州拓欧信息技术有限公司 Component deduction correction method and device of BIM model and computer equipment
CN115661553A (en) * 2022-12-14 2023-01-31 深圳市地铁集团有限公司 BIM-based rail transit member classification method, system and equipment
CN116933370A (en) * 2023-08-01 2023-10-24 中建二局第三建筑工程有限公司 Calculation system and method for intelligent accurate modeling of disc buckle type scaffold

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2016034027A1 (en) * 2014-09-01 2016-03-10 深圳汇林达科技有限公司 Method and system for formwork matching of three-dimensional spatial software
CN105956762A (en) * 2016-04-28 2016-09-21 上海宝冶集团有限公司 Engineering budgeting price combination method based on BIM and cloud platform
CN106845925A (en) * 2016-12-26 2017-06-13 钟炜 Engineering based on the BIM amount of calculating quickly and project high in the clouds collaborative platform soon is to amount method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2016034027A1 (en) * 2014-09-01 2016-03-10 深圳汇林达科技有限公司 Method and system for formwork matching of three-dimensional spatial software
CN105956762A (en) * 2016-04-28 2016-09-21 上海宝冶集团有限公司 Engineering budgeting price combination method based on BIM and cloud platform
CN106845925A (en) * 2016-12-26 2017-06-13 钟炜 Engineering based on the BIM amount of calculating quickly and project high in the clouds collaborative platform soon is to amount method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
安培等: "基于BIM的三维算量在超高层建筑项目中的研究与应用", 《施工技术》 *

Cited By (55)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110442998A (en) * 2019-08-14 2019-11-12 杭州品茗安控信息技术股份有限公司 A kind of Building Information Model dividing method, device, system and storage medium
CN110532663A (en) * 2019-08-24 2019-12-03 中铁四局集团第三建设有限公司 A kind of collaborative modeling woprk standardization process based on BIM
CN110580581A (en) * 2019-09-02 2019-12-17 中国一冶集团有限公司 construction site engineering progress monitoring system based on engineering drawing
CN110795789A (en) * 2019-10-29 2020-02-14 中建四局贵州投资建设有限公司 Application method in scaffold engineering based on BIM (building information modeling) cooperation technology
CN110968904A (en) * 2019-11-12 2020-04-07 广州市第一市政工程有限公司 BIM technology-based method for calculating shape and earth volume of earth excavation side slope
CN110968904B (en) * 2019-11-12 2023-02-24 广州市第一市政工程有限公司 BIM technology-based method for calculating shape and earth volume of earth excavation side slope
CN111079263A (en) * 2019-11-22 2020-04-28 久瓴(上海)智能科技有限公司 Building main body structure generation method and device, computer equipment and storage medium
CN111079263B (en) * 2019-11-22 2023-06-16 久瓴(江苏)数字智能科技有限公司 Building main body structure generation method, device, computer equipment and storage medium
CN110956032A (en) * 2019-12-04 2020-04-03 广联达科技股份有限公司 Model and model matching method and device, storage medium and electronic equipment
CN110956032B (en) * 2019-12-04 2023-06-27 广联达科技股份有限公司 Model and model pairing method and device, storage medium and electronic equipment
CN110992475A (en) * 2019-12-12 2020-04-10 中国水利水电第八工程局有限公司 Method, system and medium for rapidly calculating engineering quantity of any part of large-volume concrete in hydraulic and hydroelectric engineering
CN110992475B (en) * 2019-12-12 2023-10-31 中国水利水电第八工程局有限公司 Method, system and medium for rapidly calculating engineering quantity of any part of large-volume concrete of hydraulic and hydroelectric engineering
CN111027124B (en) * 2019-12-18 2022-10-11 中国建筑第八工程局有限公司 BIM-based pile foundation bearing platform optimization method
CN111027124A (en) * 2019-12-18 2020-04-17 中国建筑第八工程局有限公司 BIM-based pile foundation bearing platform optimization method
CN111651802A (en) * 2019-12-31 2020-09-11 广联达科技股份有限公司 Method and system for generating template scaffold customized scheme and storage medium
CN111222786A (en) * 2020-01-04 2020-06-02 河南惠德工程咨询有限公司 Engineering cost control system based on BIM technology
CN111210162A (en) * 2020-01-14 2020-05-29 中资锐诚工程项目管理有限公司 BIM-based whole process engineering pricing management method and BIM-based whole process engineering management system
CN111506997A (en) * 2020-04-15 2020-08-07 国网福建省电力有限公司漳州供电公司 Power engineering quantity calculation method based on BIM
CN111460565A (en) * 2020-04-15 2020-07-28 中国十七冶集团有限公司 BIM technology-based foundation construction optimization method
CN111709081A (en) * 2020-06-22 2020-09-25 苏州柝创智慧建筑科技有限公司 Construction cost control system based on BIM technology
CN112035913A (en) * 2020-07-16 2020-12-04 中国二十冶集团有限公司 Pressure-bearing equipment foundation computer modeling method
CN112035913B (en) * 2020-07-16 2023-04-07 中国二十冶集团有限公司 Pressure-bearing equipment foundation computer modeling method
CN112035911B (en) * 2020-07-16 2023-04-25 中国二十冶集团有限公司 Wall reserved dowel bar modeling method
CN112035911A (en) * 2020-07-16 2020-12-04 中国二十冶集团有限公司 Wall reserved joint bar modeling method
CN112035914B (en) * 2020-07-17 2023-12-22 中国二十冶集团有限公司 Outer arc tangent line electric calculation combined modeling refinement adjustment method
CN112035914A (en) * 2020-07-17 2020-12-04 中国二十冶集团有限公司 Outer arc tangent line electric calculation combination modeling fine adjustment method
CN111950052A (en) * 2020-07-20 2020-11-17 湖南工学院 BIM technology-based exterior cladding construction method for integrally-assembled building
CN111950052B (en) * 2020-07-20 2022-06-14 湖南工学院 BIM technology-based exterior cladding construction method for integrally-assembled building
CN111985038A (en) * 2020-08-28 2020-11-24 广联达科技股份有限公司 Method and device for calculating engineering quantity of space to be repaired
CN111985038B (en) * 2020-08-28 2023-11-17 广联达科技股份有限公司 Engineering amount calculating method and device for space to be repaired
CN112016148A (en) * 2020-08-31 2020-12-01 广联达科技股份有限公司 Method and system for calculating stair engineering quantity
CN112364404A (en) * 2020-10-14 2021-02-12 广东电网有限责任公司阳江供电局 Three-dimensional digital design intelligent mold overturning and picture examining method
CN112182727A (en) * 2020-10-23 2021-01-05 筑友智造科技投资有限公司 Method and device for automatically laying supporting pieces of building engineering and readable storage medium
CN112382353B (en) * 2020-10-30 2024-04-05 东南大学 Automatic calculation method and application of ship lock chamber wall defect maintenance material
CN112382353A (en) * 2020-10-30 2021-02-19 东南大学 Automatic calculation method and application of defect maintenance material for lock chamber wall of ship lock
CN112464347A (en) * 2020-12-04 2021-03-09 河南金途科技集团股份有限公司 Construction quantity statistical method and device for building component, server and storage medium
CN112632665A (en) * 2020-12-18 2021-04-09 中国二十冶集团有限公司 BIM modeling method for special-shaped upper cup opening of equipment foundation
CN112632665B (en) * 2020-12-18 2023-03-14 中国二十冶集团有限公司 BIM modeling method for special-shaped upper cup opening of equipment foundation
CN112836256A (en) * 2020-12-21 2021-05-25 中建安装集团有限公司 Calculation method based on BIM electromechanical model
CN112733230A (en) * 2020-12-31 2021-04-30 江苏美城建筑规划设计院有限公司 Building electromechanical pipeline comprehensive optimization method based on BIM technology
CN112907281A (en) * 2021-02-05 2021-06-04 广东丰帆工程咨询有限公司 Engineering cost management method and system based on BIM technology
CN112818565A (en) * 2021-02-26 2021-05-18 同济大学建筑设计研究院(集团)有限公司 BIM technology-based underground water pool anti-floating checking calculation method
CN112818565B (en) * 2021-02-26 2022-07-12 同济大学建筑设计研究院(集团)有限公司 BIM technology-based underground water pool anti-floating checking calculation method
CN112948938A (en) * 2021-03-12 2021-06-11 中国建筑第八工程局有限公司 Method for calculating and identifying overweight beam through BIM three-dimensional modeling
CN113569306A (en) * 2021-04-13 2021-10-29 中国天楹股份有限公司 BIM modeling implementation and application method of waste incineration power plant based on BIM technology
CN113221231A (en) * 2021-06-08 2021-08-06 长春昆仑建设股份有限公司 Engineering quantity statistical calculation method based on BIM model
CN113378282A (en) * 2021-06-30 2021-09-10 中国二冶集团有限公司 BIM-based residential building template matching and collision inspection method and system
CN113673013A (en) * 2021-08-10 2021-11-19 中国建筑第八工程局有限公司 Pile cap elevation calculation method and system based on BIM technology
CN113742824A (en) * 2021-08-26 2021-12-03 苏州筑百年建筑科技有限公司 Lightweight steel structure smart collaborative design cloud platform and operation method thereof
CN115618461A (en) * 2022-09-30 2023-01-17 广州拓欧信息技术有限公司 Component deduction correction method and device of BIM model and computer equipment
CN115293749A (en) * 2022-10-08 2022-11-04 深圳市地铁集团有限公司 Method, system and equipment for deriving engineering quantity list based on BIM
CN115293749B (en) * 2022-10-08 2022-12-27 深圳市地铁集团有限公司 Method, system and equipment for deriving engineering quantity list based on BIM
CN115661553A (en) * 2022-12-14 2023-01-31 深圳市地铁集团有限公司 BIM-based rail transit member classification method, system and equipment
CN116933370A (en) * 2023-08-01 2023-10-24 中建二局第三建筑工程有限公司 Calculation system and method for intelligent accurate modeling of disc buckle type scaffold
CN116933370B (en) * 2023-08-01 2024-02-02 中建二局第三建筑工程有限公司 Calculation system and method for intelligent accurate modeling of disc buckle type scaffold

Also Published As

Publication number Publication date
CN110046364B (en) 2022-10-25

Similar Documents

Publication Publication Date Title
CN110046364A (en) A kind of method for computing work amount based on BIM technology
CN111062081A (en) Underground continuous wall construction method based on BIM technology
CN104392482B (en) Substation project project three-dimensional calculation amount model generation system and method
CN109785436A (en) A kind of management method of the reinforcing bar information Life cycle based on BIM technology
US10445438B1 (en) Surveying spaces and usage information of structures for facilities management
CN109583149A (en) Super large lid rolling stock section in-depth modernization system and its construction method based on BIM management
CN106097149A (en) The method for designing of project of transmitting and converting electricity cost software based on BIM technology
Shi et al. 5D BIM applications in quantity surveying: dynamo and 3D printing technologies
CN110990914A (en) BIM technology-based large boiler installation method
CN109933900A (en) A kind of construction three dimensional field cloth modeling method based on BIM technology
CN114580056A (en) BIM-based comprehensive pipe gallery main body structure parametric design method
CN113011832A (en) Engineering cost system based on BIM
CN112465390A (en) BIM-based subway station construction progress management method
CN209486723U (en) A kind of construction management application platform based on BIM technology application
CN109162459A (en) A kind of big section rings beam construction method of hyperbolic bonded prestress
CN111539614A (en) Modeling method for clean operating room based on BIM technology
Hongyan et al. Comparative analysis of civil engineering quantity calculation based on glodon gtj and revit
Li et al. Application of BIM Technology in Calculation of a Residential Building
Zhen Application and Innovation of BIM Technology in Construction Management Stage of Large Medical Construction Projects
Li et al. Application research of BIM technology in water supply and drainage engineering
Yang Application of BIM during lean construction of high-rise buildings
CN115222372A (en) Construction cooperative management method based on BIM technology
Katke Time and Cost Control of Construction Project using 5D BIM process
Lee et al. The development of automatic module for formwork layout using the BIM
Duan Research on the efficiency path of civil construction management engineering based on BIM technology

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant