CN113673013A - Pile cap elevation calculation method and system based on BIM technology - Google Patents

Pile cap elevation calculation method and system based on BIM technology Download PDF

Info

Publication number
CN113673013A
CN113673013A CN202110912271.4A CN202110912271A CN113673013A CN 113673013 A CN113673013 A CN 113673013A CN 202110912271 A CN202110912271 A CN 202110912271A CN 113673013 A CN113673013 A CN 113673013A
Authority
CN
China
Prior art keywords
elevation
pile cap
pile
bim
cap
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110912271.4A
Other languages
Chinese (zh)
Inventor
谢铭
王宜彬
冯世永
刘靖烨
�田润
宋钰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN202110912271.4A priority Critical patent/CN113673013A/en
Publication of CN113673013A publication Critical patent/CN113673013A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F2111/00Details relating to CAD techniques
    • G06F2111/10Numerical modelling

Abstract

The invention relates to a pile cap elevation calculation method and a pile cap elevation calculation system based on a BIM technology, wherein the pile cap elevation calculation method comprises the following steps: acquiring a design drawing and design parameters of a pile cap to be constructed, and introducing the design drawing and the design parameters into BIM software to form a BIM model; and calculating and generating elevation data of the pile cap by utilizing BIM software according to the BIM model. The method effectively solves the problem of difficulty in calculating the elevation of the pile cap, is suitable for construction projects with large volume, multiple types of the pile caps and large elevation change of the pile cap, has high calculation efficiency and low cost, greatly reduces the error rate, and ensures the subsequent construction quality.

Description

Pile cap elevation calculation method and system based on BIM technology
Technical Field
The invention relates to the field of building construction, in particular to a pile cap elevation calculation method and a pile cap elevation calculation system based on a BIM technology.
Background
The most common problem is that the conversion elevation of a project with large volume, multiple types of bearing platforms and large elevation change of the pile bearing platform is easy to be confused and mistaken in the construction process, and the conversion error of the elevation of the pile top leads to the fact that pile splicing is needed in engineering construction, so that the engineering progress and the engineering quality are influenced.
Disclosure of Invention
The invention aims to overcome the defects of the prior art, provides a pile cap elevation calculation method and a pile cap elevation calculation system based on the BIM technology, solves the problem of difficulty in calculation of the elevation of the pile cap, is suitable for construction projects with large size, multiple types of the pile caps and large elevation change of the pile cap, and is high in calculation efficiency, low in cost, capable of greatly reducing error rate and capable of ensuring subsequent construction quality.
The technical scheme for realizing the purpose is as follows:
the invention provides a pile cap elevation calculation method based on a BIM technology, which comprises the following steps:
acquiring a design drawing and design parameters of a pile cap to be constructed, and introducing the design drawing and the design parameters into BIM software to form a BIM model;
and calculating and generating elevation data of the pile cap by utilizing BIM software according to the BIM model.
The method for calculating the elevation of the pile cap based on the BIM technology is adopted, the BIM model is established by obtaining the design drawing and the design parameters of the pile cap, and then BIM software is used for calculating and generating the elevation data of the pile cap according to the BIM model, so that the problem of difficulty in calculating the elevation of the pile cap is solved, the method is suitable for construction projects with large size, multiple types of the pile caps and large elevation change of the pile cap, the calculation efficiency is high, the cost is low, the error rate is greatly reduced, and the subsequent construction quality is ensured.
The pile cap elevation calculation method based on the BIM technology is further improved in that when the design drawing and the design parameters are led into the BIM software, the method further comprises the following steps:
and determining the type of the pile cap in BIM software according to a design drawing, and further inputting design parameters to generate a corresponding BIM model.
The pile cap elevation calculation method based on the BIM technology is further improved in that the design parameters comprise the pile cap elevation, the cap size and the length of the anchored cap.
The pile cap elevation calculation method based on the BIM technology is further improved in that the elevation data of the pile cap comprises the pile bottom elevation, the pile top elevation and the pile cap bottom elevation of the pile cap.
The invention also provides a pile cap elevation calculation system based on the BIM technology, which comprises the following steps:
the data acquisition module is used for acquiring a design drawing and design parameters of the pile cap;
the model establishing module is used for establishing a corresponding BIM (building information modeling) model according to the design drawing and the design parameters acquired by the data acquiring module; and
and the elevation calculation module is used for calculating and generating elevation data of the pile cap according to the BIM.
The pile cap elevation calculation system based on the BIM technology is further improved in that the design drawing comprises the arrangement position of the pile cap and the type of the pile cap;
the data acquisition module is used for acquiring the arrangement position and the type of the pile cap.
The pile cap elevation calculation system based on the BIM technology is further improved in that the design parameters comprise the pile cap elevation, the cap size and the anchoring-in cap length.
The pile cap elevation calculation system based on the BIM technology is further improved in that the elevation data of the pile cap comprises the pile bottom elevation, the pile top elevation and the pile cap bottom elevation of the pile cap.
Drawings
Fig. 1 is a flowchart of the pile cap elevation calculation method based on the BIM technology.
Detailed Description
The invention is further described with reference to the following figures and specific examples.
Referring to fig. 1, the invention provides a pile cap elevation calculation method based on the BIM technology, which is used for establishing a BIM model by obtaining design drawings and design parameters of a pile cap, and further utilizing BIM software to calculate and generate elevation data of the pile cap according to the BIM model, so that the problem of difficulty in calculation of the elevation of the pile cap is solved, and the method is suitable for construction projects with large size, multiple types of the pile caps and large elevation change of the pile cap, is high in calculation efficiency and low in cost, greatly reduces error rate, and ensures subsequent construction quality. The following describes the pile cap elevation calculation based on the BIM technology and the system method thereof in the present invention with reference to the accompanying drawings.
Referring to fig. 1, fig. 1 is a flowchart of a pile cap elevation calculation method based on the BIM technology. The method for calculating the elevation of the pile cap based on the BIM technology of the invention is described below with reference to FIG. 1.
As shown in fig. 1, the pile cap elevation calculation method based on the BIM technology of the present invention includes the following steps:
acquiring a design drawing and design parameters of a pile cap to be constructed, and introducing the design drawing and the design parameters into BIM software to form a BIM model;
and calculating and generating elevation data of the pile cap by utilizing BIM software according to the BIM model.
As a preferred embodiment of the present invention, when importing the design drawing and the design parameters into the BIM software, the method further includes:
and determining the type of the pile cap in BIM software according to a design drawing, and further inputting design parameters to generate a corresponding BIM model.
Specifically, the design parameters include pile bearing table elevation, bearing table size and anchor-in bearing table length.
Specifically, the elevation data of the pile cap includes a pile bottom elevation, a pile top elevation and a cap bottom elevation of the pile cap.
The specific embodiment of the invention is as follows:
determining the setting position and type of the pile cap according to a design drawing, and inputting design parameters of the pile cap to establish a BIM (building information modeling) model of the pile cap;
marking the information and the elevation of all pile cap by using the structure foundation annotation marking function, wherein the size and the elevation of the pile cap marked in the plane at the moment;
if the type of the pile cap and the design parameters of the pile cap are changed, the type of the pile cap is reset and the design parameters are input.
The invention also provides a pile cap elevation calculation system based on the BIM technology, which comprises the following steps:
the data acquisition module is used for acquiring a design drawing and design parameters of the pile cap;
the model establishing module is used for establishing a corresponding BIM (building information modeling) model according to the design drawing and the design parameters acquired by the data acquiring module; and
and the elevation calculation module is used for calculating and generating elevation data of the pile cap according to the BIM.
Further, the design drawing comprises the arrangement position of the pile cap and the type of the pile cap;
the data acquisition module is used for acquiring the arrangement position and the type of the pile cap.
Specifically, the design parameters include pile bearing table elevation, bearing table size and anchor-in bearing table length.
Specifically, the elevation data of the pile cap includes a pile bottom elevation, a pile top elevation and a cap bottom elevation of the pile cap.
The specific application method of the invention is as follows:
the data acquisition module acquires design drawings and design parameters of the pile cap to determine the setting position, type and design parameters of the pile cap, and the model establishment module establishes a BIM (building information modeling) model of the pile cap according to the data acquired by the data acquisition module;
calculating the elevation of the pile cap by utilizing an elevation calculation module according to the BIM model, and marking the size of the pile cap and the elevation of the pile top in the plane model;
if the type of the pile cap and the design parameters of the pile cap are changed, the type of the pile cap is obtained again and the design parameters are input.
While the present invention has been described in detail and with reference to the embodiments thereof as illustrated in the accompanying drawings, it will be apparent to one skilled in the art that various changes and modifications can be made therein. Therefore, certain details of the embodiments are not to be interpreted as limiting, and the scope of the invention is to be determined by the appended claims.

Claims (8)

1. A pile cap elevation calculation method based on a BIM technology is characterized by comprising the following steps:
acquiring a design drawing and design parameters of a pile cap to be constructed, and importing the design drawing and the design parameters into BIM software to form a BIM model;
and calculating and generating elevation data of the pile cap by utilizing the BIM software according to the BIM model.
2. The method for calculating the elevation of the pile cap based on the BIM technology of claim 1, wherein when the design drawing and the design parameters are imported into BIM software, the method further comprises the following steps:
and determining the type of the pile cap in the BIM software according to the design drawing, and further inputting the design parameters to generate a corresponding BIM model.
3. The BIM technology-based pile cap elevation calculation method of claim 1, wherein the design parameters include pile cap elevation, cap size and anchor-in cap length.
4. The BIM technology-based pile cap elevation calculation method of claim 1, wherein the elevation data of the pile cap includes a pile bottom elevation, a pile top elevation, and a cap bottom elevation of the pile cap.
5. A pile cap elevation calculation system based on BIM technology, comprising:
the data acquisition module is used for acquiring a design drawing and design parameters of the pile cap;
the model establishing module is used for establishing a corresponding BIM (building information modeling) model according to the design drawing acquired by the data acquisition module and the design parameters; and
and the elevation calculation module is used for calculating and generating elevation data of the pile cap according to the BIM.
6. The BIM technology-based pile cap elevation calculation method according to claim 5, wherein the design drawing includes an arrangement position of the pile cap and a type of the pile cap;
the data acquisition module is used for acquiring the arrangement position and the type of the pile cap.
7. The BIM technology-based pile cap elevation calculation method of claim 5, wherein the design parameters include pile cap elevation, cap size and anchor-in cap length.
8. The BIM technology-based pile cap elevation calculation method of claim 5, wherein the elevation data of the pile cap includes a pile bottom elevation, a pile top elevation, and a cap bottom elevation of the pile cap.
CN202110912271.4A 2021-08-10 2021-08-10 Pile cap elevation calculation method and system based on BIM technology Pending CN113673013A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110912271.4A CN113673013A (en) 2021-08-10 2021-08-10 Pile cap elevation calculation method and system based on BIM technology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110912271.4A CN113673013A (en) 2021-08-10 2021-08-10 Pile cap elevation calculation method and system based on BIM technology

Publications (1)

Publication Number Publication Date
CN113673013A true CN113673013A (en) 2021-11-19

Family

ID=78541988

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110912271.4A Pending CN113673013A (en) 2021-08-10 2021-08-10 Pile cap elevation calculation method and system based on BIM technology

Country Status (1)

Country Link
CN (1) CN113673013A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2018040838A1 (en) * 2016-08-29 2018-03-08 广州地铁设计研究院有限公司 Modeling and designing method for elevated structure bim model
CN110046364A (en) * 2018-01-16 2019-07-23 中国建筑第八工程局有限公司 A kind of method for computing work amount based on BIM technology
CN111506954A (en) * 2020-05-13 2020-08-07 中建三局第三建设工程有限责任公司 Pile length estimation method based on BIM model
CN111651823A (en) * 2020-06-05 2020-09-11 中建八局轨道交通建设有限公司 BIM technology-based foundation pit earth excavation amount calculation method
CN112699437A (en) * 2020-12-25 2021-04-23 深圳高速工程顾问有限公司 BIM bridge pile foundation length automatic calculation method, system, equipment and storage medium

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2018040838A1 (en) * 2016-08-29 2018-03-08 广州地铁设计研究院有限公司 Modeling and designing method for elevated structure bim model
CN110046364A (en) * 2018-01-16 2019-07-23 中国建筑第八工程局有限公司 A kind of method for computing work amount based on BIM technology
CN111506954A (en) * 2020-05-13 2020-08-07 中建三局第三建设工程有限责任公司 Pile length estimation method based on BIM model
CN111651823A (en) * 2020-06-05 2020-09-11 中建八局轨道交通建设有限公司 BIM technology-based foundation pit earth excavation amount calculation method
CN112699437A (en) * 2020-12-25 2021-04-23 深圳高速工程顾问有限公司 BIM bridge pile foundation length automatic calculation method, system, equipment and storage medium

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
李想: "BIM 技术在施工阶段深化设计中的应用", 《建筑技术 应用》, pages 122 - 124 *

Similar Documents

Publication Publication Date Title
CN102542901B (en) Line segment vacuating device for electronic map and method thereof
CN110990504B (en) Ship track compression method based on course and speed change rate
CN102855232B (en) A kind of tabular analysis adapts job operation
CN109408897B (en) PDMS-to-AutoCAD drawing size labeling identification-based conversion method and system
CN105512235B (en) A kind of GIS and AutoCAD method for interchanging data and intermediate file
CN101944128A (en) Data export and import method and device
CN105607902A (en) Component model based system visualization design and code generation system and method
CN109933324A (en) A kind of nuclear power DCS man-machine interface automatic generation method
KR20210128907A (en) A method, a device, an electronic equipment and a storage medium for extracting information
CN102314798B (en) Method and device for automatically simplifying shape points of polygonal surface elements of electronic map
CN113673013A (en) Pile cap elevation calculation method and system based on BIM technology
CN112100712A (en) Road lofting conversion method based on CAD and storage medium
CN102867322A (en) Method and device for realizing Chinese marking in three-dimensional scene
CN106406561B (en) Character library lattice generation method based on generator set controller
CN104484512A (en) Pattern generation method based on AUTOCAD in PDMS (plant design management system)
CN110069861B (en) Method and system for automatically generating curved surface type value table
CN105630750A (en) Business card picture processing method and apparatus
CN105095538B (en) The dimensionally-optimised system and method for connector
CN107861725B (en) iOS data reverse automatic analysis strategy
CN113015117A (en) User positioning method and device, electronic equipment and storage medium
CN102026033A (en) Method for displaying Myanmar by set-top box (STB)
CN111753344A (en) Generation method of assembly type component data set, CAD platform and storage medium
CN103929478A (en) Video and audio file storing and downloading method and system
CN107633543A (en) Consider the stripe shape corresponding method of local topology
CN112579723A (en) GIS-based infinite scaling optimization display method for power grid line

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination