CN106097149A - The method for designing of project of transmitting and converting electricity cost software based on BIM technology - Google Patents
The method for designing of project of transmitting and converting electricity cost software based on BIM technology Download PDFInfo
- Publication number
- CN106097149A CN106097149A CN201610453778.7A CN201610453778A CN106097149A CN 106097149 A CN106097149 A CN 106097149A CN 201610453778 A CN201610453778 A CN 201610453778A CN 106097149 A CN106097149 A CN 106097149A
- Authority
- CN
- China
- Prior art keywords
- project
- transmitting
- engineering
- converting electricity
- secondary development
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 230000005611 electricity Effects 0.000 title claims abstract description 39
- 238000005516 engineering process Methods 0.000 title claims abstract description 20
- 238000000034 method Methods 0.000 title claims abstract description 18
- 238000010276 construction Methods 0.000 claims abstract description 56
- 238000013461 design Methods 0.000 claims abstract description 11
- 238000011161 development Methods 0.000 claims description 50
- 238000004364 calculation method Methods 0.000 claims description 22
- 238000011156 evaluation Methods 0.000 claims description 18
- 230000003993 interaction Effects 0.000 claims description 6
- 230000002452 interceptive effect Effects 0.000 claims description 5
- 238000009795 derivation Methods 0.000 claims description 2
- 230000008901 benefit Effects 0.000 abstract description 4
- 238000004088 simulation Methods 0.000 abstract description 2
- 238000012827 research and development Methods 0.000 description 19
- 239000000463 material Substances 0.000 description 7
- 230000009466 transformation Effects 0.000 description 3
- 238000006243 chemical reaction Methods 0.000 description 2
- 238000009430 construction management Methods 0.000 description 2
- 239000011159 matrix material Substances 0.000 description 2
- 230000008569 process Effects 0.000 description 2
- 240000007594 Oryza sativa Species 0.000 description 1
- 235000007164 Oryza sativa Nutrition 0.000 description 1
- 238000004458 analytical method Methods 0.000 description 1
- 230000005540 biological transmission Effects 0.000 description 1
- 230000015572 biosynthetic process Effects 0.000 description 1
- 230000008859 change Effects 0.000 description 1
- 230000008878 coupling Effects 0.000 description 1
- 238000010168 coupling process Methods 0.000 description 1
- 238000005859 coupling reaction Methods 0.000 description 1
- 230000001419 dependent effect Effects 0.000 description 1
- 238000012938 design process Methods 0.000 description 1
- 238000009826 distribution Methods 0.000 description 1
- 239000000284 extract Substances 0.000 description 1
- 201000007227 lymph node tuberculosis Diseases 0.000 description 1
- -1 machine are idle Substances 0.000 description 1
- 230000008520 organization Effects 0.000 description 1
- 230000001915 proofreading effect Effects 0.000 description 1
- 230000007115 recruitment Effects 0.000 description 1
- 238000011160 research Methods 0.000 description 1
- 235000009566 rice Nutrition 0.000 description 1
- 239000007787 solid Substances 0.000 description 1
- 238000012800 visualization Methods 0.000 description 1
- 239000002699 waste material Substances 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/06—Energy or water supply
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E40/00—Technologies for an efficient electrical power generation, transmission or distribution
- Y02E40/70—Smart grids as climate change mitigation technology in the energy generation sector
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S10/00—Systems supporting electrical power generation, transmission or distribution
- Y04S10/50—Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications
Landscapes
- Business, Economics & Management (AREA)
- Health & Medical Sciences (AREA)
- Engineering & Computer Science (AREA)
- Economics (AREA)
- Public Health (AREA)
- Water Supply & Treatment (AREA)
- General Health & Medical Sciences (AREA)
- Human Resources & Organizations (AREA)
- Marketing (AREA)
- Primary Health Care (AREA)
- Strategic Management (AREA)
- Tourism & Hospitality (AREA)
- Physics & Mathematics (AREA)
- General Business, Economics & Management (AREA)
- General Physics & Mathematics (AREA)
- Theoretical Computer Science (AREA)
- Stored Programmes (AREA)
Abstract
The method for designing of a kind of project of transmitting and converting electricity cost software based on BIM technology, it realizes the account valuation of defeated journey of exchanging work by software, has the advantage that 1, optimizes design, strengthen investment control;2, construction simulation, information sharing, improves collaborative efficiency;3, a power industry professional construction difficult problem is effectively solved;4, construction costs intelligence computation, raises labour efficiency, and promotes management level;5, project of transmitting and converting electricity data information sharing, formulates for Industry Policy and provides foundation.
Description
Technical field
The present invention relates to power transformation engineering technical field, a kind of method for designing for power transformation engineering cost software.
Background technology
At present, electricity power engineering power transmission and transformation construction project detail design uses two dimensional surface detail design, design mistake, leakage
The scene frequencies such as item, specialty are overlapping are existing, and making engineering design change quantity increases, and job site is done over again, rebuild phenomenon seriously, throws
Money controls difficulty and increases.
China's building field Engineering Cost Management is chronically at following two situation:
Two dimension drawing+artificial manual calculation amount+manually organize valency.That is: construction costs determines, engineering labor and materials machine manages, engineering knot
Calculate the full manual operations of management.
Two dimension drawing+software calculation amount+software group valency.That is: construction costs determines and depends on two dimension drawing and cost software, engineering
The management of labor and materials machine, Engineering Settlement management manual operations.
Huge construction project, due to practitioner's difference of technology level, often manually operates the construction costs determined
Deviation is relatively big and the longest, and usual construction costs finally determines that the time is 1-2 after completion of works, makes engineering process manage
Middle no data foundation, by rule of thumb, the management of thick mad property, labor and materials machine tissue, supply without scientific basis, velocity of funds relatively slowly, people,
Material, machine are idle, waste situation is serious, and cost increases, and lacks strong competitiveness.Whole industry Cost Management level relatively foreign level
There is larger difference, need employing international advanced technology badly and promote management level.
Summary of the invention
It is an object of the invention to provide the method for designing of a kind of project of transmitting and converting electricity cost software based on BIM technology, it
The accurate budget of project of transmitting and converting electricity can be realized, improve the accuracy rate and work efficiency calculated.
It is an object of the invention to be realized by such technical scheme, specifically comprise the following steps that
1) utilize software Revit to set up project of transmitting and converting electricity BIM technology three-dimension modeling interface, be used for carrying engineering construction
Information;
2) data base and query and search interface are set up;
3) work load evaluation is set up;
4) Revit software secondary development interface API is utilized, it is achieved model is interactive with data double-way;
5) Revit software secondary development interface API is utilized, it is achieved model and quantities calculation one-way interaction;
6) utilize Revit software secondary development interface API, set up data base and select interface;
7) utilizing Revit software secondary development interface API, foundation is data base and selects interface;
8) utilize Revit software secondary development interface API, set up option storehouse and select interface;
9) utilize Revit software secondary development interface API, set up work load evaluation storehouse;
10) utilize Revit software secondary development interface API, resolve BIM model architecture quantities, generate corresponding engineering number
According to file, form computer capacity corresponding with engineering model interactive, and generate result of calculation according to computation rule, calculating error ±
2%;
11) utilize Revit software secondary development interface API, be created as retribution sheet format storehouse;
12) utilize Revit software secondary development interface API, set up achievement calculating formula format library;
13) Revit software secondary development interface API is utilized, it is achieved form selectively produces, query interface;
14) utilize Revit software secondary development interface API, realize quantities calculation formula, form derivation behaviour in the design phase
Make interface.
Further, step 2) described in set up data base and query and search interface include:
Set up power construction engineering norm for detailed estimates data base and query and search interface thereof;Set up power construction engineering budgetary estimate fixed
Volume data base and query and search interface.
Further, step 3) described in set up work load evaluation and include:
Set up power construction engineering norm for detailed estimates work load evaluation;Set up power construction engineering quota of budgetary estimate quantities
Computation rule;Set up project of transmitting and converting electricity valuating engineering work load with bill work load evaluation.
Further, step 9) described in set up work load evaluation storehouse and include:
Set up power construction engineering norm for detailed estimates work load evaluation storehouse;Set up power construction engineering quota of budgetary estimate engineering
Amount calculates rule base.
Further, step 10) described in formed computer capacity include power construction engineering norm for detailed estimates computer capacity,
Power construction engineering quota of budgetary estimate computer capacity and project of transmitting and converting electricity valuating engineering work load with bill computer capacity.
Further, step 11) described in be created as retribution sheet format storehouse and include: power construction engineering norm for detailed estimates form
Format library, power construction engineering quota of budgetary estimate statement form storehouse and project of transmitting and converting electricity valuating engineering work load with bill statement form
Storehouse.
Owing to have employed technique scheme, present invention have the advantage that:
1. optimize design, strengthen investment control
The present invention utilizes BIM technology to set up project of transmitting and converting electricity three-dimensional building information model, and it is real that solid presents project of transmitting and converting electricity
Body, the situations such as project engineering stage discovery design perforated scrofula of neck, mistake, specialty are overlapping, evade engineering design and cause investment to slip up
2. construction simulation, information sharing, improves collaborative efficiency
Project of transmitting and converting electricity working procedure is various, and specialty is intersected, and it is big that difficulty is coordinated in construction management, sets up in the technical program
Project of transmitting and converting electricity BIM model can be with model engineering site layout project and work progress, Optimizing Construction Scheme, improves collaborative efficiency.
3. construction costs intelligence computation, raises labour efficiency, and promotes management level
Establishment project of transmitting and converting electricity BIM model Criterion handbook, power engineering industry quota of budgetary estimate, norm for detailed estimates data
Storehouse, power engineering industry quota of budgetary estimate, norm for detailed estimates, valuating engineering work load with bill work load evaluation handbook, in conjunction with BIM
Technical research realizes project of transmitting and converting electricity quantities intelligence computation, determines construction costs, and forms visualization construction costs.Data provide
Source is shared, and reduces settlement dispute, raises labour efficiency.Strengthen power grid construction management level, effectively control construction investment.
4. project of transmitting and converting electricity data information sharing, formulates for Industry Policy and provides foundation
By all kinds of project of transmitting and converting electricity architecture informations are added up, utilize " big data " technology, formation construction costs index,
Amount, valency, take index, recruitment index, labor and materials machine distribu-tion index, engineering construction high-quality experience and the number such as construction organization preferred version
According to, set up the strong foundation of offer for industry system, policy.
Other advantages, target and the feature of the present invention will be illustrated to a certain extent in the following description, and
And to a certain extent, will be apparent to those skilled in the art based on to investigating hereafter, or can
To be instructed from the practice of the present invention.The target of the present invention and other advantages can be wanted by description below and right
Ask book to realize and obtain.
Accompanying drawing explanation
The accompanying drawing of the present invention is described as follows.
Fig. 1 is the schematic flow sheet of the present invention.
Detailed description of the invention
The invention will be further described with embodiment below in conjunction with the accompanying drawings.
The method for designing of a kind of project of transmitting and converting electricity cost software based on BIM technology, specifically comprises the following steps that
1, establishment project of transmitting and converting electricity BIM model Criterion handbook.
2, by utilizing BIM technology to set up project of transmitting and converting electricity threedimensional model, data source uses the BIM of autodesk, inc. to set
Meter software Revit, in designer's design process, automatization produces.
3, " power construction engineering norm for detailed estimates " data base is set up.
4, " power construction engineering quota of budgetary estimate " data base is set up.
5, establishment " power construction engineering norm for detailed estimates " work load evaluation handbook.
6, establishment " power construction engineering quota of budgetary estimate " work load evaluation handbook.
7, establishment " project of transmitting and converting electricity valuating engineering work load with bill " work load evaluation handbook.
8, design software Revit its second development interface API is used, it is ensured that the accurate corresponding premise of data and figure
Under, data structure conventional during extracting calculation amount, such as following table:
Data name | Unit | Describe | Acquisition mode |
Volume | m<sup>3</sup> | Volume | Secondary development api interface |
Area | ㎡ | Area | Secondary development api interface |
Height | mm | Highly | Secondary development api interface |
Width | mm | Width | Secondary development api interface |
Length | mm | Length | Secondary development api interface |
Face | Face structure | Secondary development api interface | |
Material | Material | Secondary development api interface | |
Type | Type | Secondary development api interface | |
Count | Number | Statistics |
9, Revit software secondary development interface API research and development, set up " power construction engineering norm for detailed estimates " quantities calculation rule
Then storehouse.
10, Revit software secondary development interface API research and development, set up " power construction engineering quota of budgetary estimate " quantities calculation
Rule base.
11, Revit software secondary development interface API research and development, set up " project of transmitting and converting electricity valuating engineering work load with bill " work
Journey amount calculates rule base.
12, Revit software secondary development interface API research and development, it is achieved model is interactive with data double-way.
13, Revit software secondary development interface API research and development, it is achieved model and computational engineering amount one-way interaction.
14, Revit software secondary development interface API research and development, set up parameter library and select interface.
15, Revit software secondary development interface API research and development, set up library of factors and select interface.
16, Revit software secondary development interface API research and development, set up option storehouse and select interface.
17, Revit software secondary development interface API research and development, analytical design method stage BIM model data, generate corresponding engineering
Amount data, form " power construction engineering quota of budgetary estimate " calculating formula, and can be with result of calculation and engineering model two-way interaction, in real time
Corrected Calculation rule and result, it is achieved error calculated rate ± 2%.
18, Revit software secondary development interface API research and development, resolve construction drawing stage BIM model data, generate corresponding work
Journey amount data, form " power construction engineering norm for detailed estimates " calculating formula, and can be real with result of calculation and engineering model two-way interaction
Time corrected Calculation rule and result, it is achieved error calculated rate ± 2%.
19, Revit software secondary development interface API research and development, resolve construction drawing stage BIM model data, generate corresponding work
Journey amount data, form " project of transmitting and converting electricity valuating engineering work load with bill " calculating formula, and can be double with engineering model with result of calculation
To interaction, real-time corrected Calculation rule and result, it is achieved error calculated rate ± 2%.
20, adjust project of transmitting and converting electricity BIM model Criterion handbook, jointly fit with quantities calculation reaching Engineering Modeling
With.
21, Revit software secondary development interface API research and development, set up " power construction engineering norm for detailed estimates " achievement form lattice
Formula storehouse.
22, Revit software secondary development interface API research and development, set up " power construction engineering quota of budgetary estimate " achievement form lattice
Formula storehouse.
23, Revit software secondary development interface API research and development, set up " project of transmitting and converting electricity valuating engineering work load with bill " and become
Retribution sheet format storehouse.
24, Revit software secondary development interface API research and development, set up achievement calculating formula format library.
25, " power construction engineering norm for detailed estimates " inquiry, search function and interface are set up.
26, " power construction engineering quota of budgetary estimate " inquiry, search function and interface are set up.
27, Revit software secondary development interface API research and development, it is achieved " power construction engineering norm for detailed estimates " quantities calculation
Formula, form derive operation interface.
28, Revit software secondary development interface API research and development, it is achieved " power construction engineering quota of budgetary estimate " quantities calculation
Formula, form derive operation interface.
29, Revit software secondary development interface API research and development, it is achieved " project of transmitting and converting electricity valuating engineering work load with bill " work
Journey amount calculating formula, form derive operation interface.
30, Revit software secondary development interface API research and development, it is achieved Report Server Management function and interface.
The using method of project of transmitting and converting electricity cost software is as follows:
1) the CAD plane drawing that modeling engineering teacher is designed by designing institute, utilizes Revit to draw building threedimensional model, and
The relevant information of typing graphics component in drawing process.This is the element task of whole BIM computing, the not model of software development
Farmland;
2) utilizing Revit to open BIM, amount calculation software can use when initializing application by norm
Model data.Therefore this software can be used as the plug-in unit of Revit and carries out initial work;List after can also having initialized
Solely run amendment or statistics, the report output work carrying out formula;
3) selecting the graphic element that i.e. will calculate in Revit graphics component, this is a single choice job, it is impossible to many
Choosing, i.e. will carry out the manual proof-reading of quota formula to each graphics component.Its flow process is as follows:
3-1) pattern selector prompting user selects to carry out the component object of quota calculation, such as wall, post, plate etc.;
3-2) user is after graphical interfaces selects corresponding graphics component, figure state highlighted;
3-3) now user has been selected figure to be analyzed by pattern selector, and extracts corresponding UniqueID, and it is right to generate
The Geometry information answered;
Geometry object needed for 3-4) graphical configuration device generates quota computed in software and data, such as the area of Face,
The length etc. of Edge;
3-5) Geometry object enters Geometry matching module, carries out Auto-matching.User is the most alternative
Amendment coupling object;
After 3-6) having revised, user preserves, and Geometry object can enter Geometry manager;Above section be with
The data manipulation that Revit figure is relevant, these parts are trusted by force and Revit figure, it is necessary to carry out in Revit;
4) arithmetic section can isolated operation, it is also possible to run in Revit plug-in unit.Its workflow is as follows:
4-1) formulat calculator is dependent on Geometry manager, but Geometry manager can from data base individually
Take out;
4-2) in formulat calculator, user can not meet user from Row sum-equal matrix and calculates the computation rule of wish, and public
Formula computer after Row sum-equal matrix completes, is reconstructed analysis to the company of user user automatically, errors excepted, and friendly prompting;
4-3) the formula provided by formulat calculator, is exported quantities, and enters according to the unit of user's self-defining
Row conversion automatically, as rice is converted into millimeter;
4-4) apply mechanically quota according to valuation rule, and carry out valuation conversion;
4-5) during mechanically used quota, user also can revise the quota data that system provides voluntarily;
4-6) report output.
Finally illustrating, above example is only in order to illustrate technical scheme and unrestricted, although with reference to relatively
The present invention has been described in detail by good embodiment, it will be understood by those within the art that, can be to the skill of the present invention
Art scheme is modified or equivalent, and without deviating from objective and the scope of the technical program, it all should be contained in the present invention
Right in the middle of.
Claims (6)
1. the method for designing of a project of transmitting and converting electricity cost software based on BIM technology, it is characterised in that specifically comprise the following steps that
1) utilize software Revit to set up project of transmitting and converting electricity BIM technology three-dimension modeling interface, be used for carrying engineering construction letter
Breath;
2) data base and query and search interface are set up;
3) work load evaluation is set up;
4) Revit software secondary development interface API is utilized, it is achieved model is interactive with data double-way;
5) Revit software secondary development interface API is utilized, it is achieved model and quantities calculation one-way interaction;
6) utilize Revit software secondary development interface API, set up data base and select interface;
7) utilizing Revit software secondary development interface API, foundation is data base and selects interface;
8) utilize Revit software secondary development interface API, set up option storehouse and select interface;
9) utilize Revit software secondary development interface API, set up work load evaluation storehouse;
10) utilize Revit software secondary development interface API, resolve BIM model architecture quantities, generate corresponding project data literary composition
Part, forms computer capacity corresponding with engineering model interactive, and generates result of calculation according to computation rule, calculate error ± 2%;
11) utilize Revit software secondary development interface API, be created as retribution sheet format storehouse;
12) utilize Revit software secondary development interface API, set up achievement calculating formula format library;
13) Revit software secondary development interface API is utilized, it is achieved form selectively produces, query interface;
14) utilize Revit software secondary development interface API, realize quantities calculation formula, form derivation operation circle in the design phase
Face.
2. the method for designing of project of transmitting and converting electricity cost software based on BIM technology as claimed in claim 1, it is characterised in that
Step 2) described in set up data base and query and search interface include:
Set up power construction engineering norm for detailed estimates data base and query and search interface thereof;Set up power construction engineering quota of budgetary estimate number
According to storehouse and query and search interface.
3. the method for designing of project of transmitting and converting electricity cost software based on BIM technology as claimed in claim 1, it is characterised in that
Step 3) described in set up work load evaluation and include:
Set up power construction engineering norm for detailed estimates work load evaluation;Set up power construction engineering quota of budgetary estimate quantities calculation
Rule;Set up project of transmitting and converting electricity valuating engineering work load with bill work load evaluation.
4. the method for designing of project of transmitting and converting electricity cost software based on BIM technology as claimed in claim 1, it is characterised in that
Step 9) described in set up work load evaluation storehouse and include:
Set up power construction engineering norm for detailed estimates work load evaluation storehouse;Set up power construction engineering quota of budgetary estimate engineering gauge
Calculate rule base.
5. the method for designing of project of transmitting and converting electricity cost software based on BIM technology as claimed in claim 1, it is characterised in that
Step 10) described in the computer capacity that formed to include power construction engineering norm for detailed estimates computer capacity, power construction engineering general
Calculate quota calculation scope and project of transmitting and converting electricity valuating engineering work load with bill computer capacity.
6. the method for designing of project of transmitting and converting electricity cost software based on BIM technology as claimed in claim 1, it is characterised in that
Step 11) described in be created as retribution sheet format storehouse and include: power construction engineering norm for detailed estimates statement form storehouse, power construction
Budgetary Estimates quota statement form storehouse and project of transmitting and converting electricity valuating engineering work load with bill statement form storehouse.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610453778.7A CN106097149A (en) | 2016-06-21 | 2016-06-21 | The method for designing of project of transmitting and converting electricity cost software based on BIM technology |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610453778.7A CN106097149A (en) | 2016-06-21 | 2016-06-21 | The method for designing of project of transmitting and converting electricity cost software based on BIM technology |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106097149A true CN106097149A (en) | 2016-11-09 |
Family
ID=57237746
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610453778.7A Pending CN106097149A (en) | 2016-06-21 | 2016-06-21 | The method for designing of project of transmitting and converting electricity cost software based on BIM technology |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106097149A (en) |
Cited By (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106530143A (en) * | 2016-11-08 | 2017-03-22 | 河南财政税务高等专科学校 | Engineering cost list service system |
CN106952023A (en) * | 2017-03-01 | 2017-07-14 | 广东中建普联科技股份有限公司 | Construction project Fast Quasi construction method and system |
CN107436928A (en) * | 2017-07-12 | 2017-12-05 | 国网山东省电力公司经济技术研究院 | The through-flow method of amount valency of substation project |
CN108280281A (en) * | 2018-01-18 | 2018-07-13 | 宋强 | A kind of construction cost control method and system based on BIM technology |
CN109165462A (en) * | 2018-09-11 | 2019-01-08 | 云南材材通信息技术有限公司 | Material utilization amount automatic monitoring method, device, system and can storage medium |
CN109472446A (en) * | 2018-09-30 | 2019-03-15 | 中铁第勘察设计院集团有限公司 | Project Budget preparation method based on BIM model |
CN109753717A (en) * | 2018-12-28 | 2019-05-14 | 国网浙江省电力有限公司经济技术研究院 | A kind of construction method of power distribution network component mathematical model and application |
CN109766605A (en) * | 2018-12-28 | 2019-05-17 | 国网浙江省电力有限公司经济技术研究院 | Method for building up in kind with the power distribution network full information mathematical model of value linkage |
CN109800497A (en) * | 2019-01-16 | 2019-05-24 | 深圳大学 | A kind of data sharing method and device based on Revit |
CN110909450A (en) * | 2019-10-22 | 2020-03-24 | 国网冀北电力有限公司经济技术研究院 | Intelligent design cost integrated acquisition method for power transmission line |
CN111507001A (en) * | 2020-04-17 | 2020-08-07 | 国网湖南省电力有限公司 | Method and system for calculating construction cost of power transformation project, readable storage medium and computer |
CN111507002A (en) * | 2020-04-17 | 2020-08-07 | 国网湖南省电力有限公司 | Method and system for mounting power transformation project, readable storage medium and computer |
CN117235876A (en) * | 2023-11-14 | 2023-12-15 | 中国建筑西南设计研究院有限公司 | Method and system for counting engineering quantity based on Rhinoceros |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20140121145A (en) * | 2013-04-05 | 2014-10-15 | 서울대학교산학협력단 | BIM based Integrated Management System for Constrcution Data |
-
2016
- 2016-06-21 CN CN201610453778.7A patent/CN106097149A/en active Pending
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20140121145A (en) * | 2013-04-05 | 2014-10-15 | 서울대학교산학협력단 | BIM based Integrated Management System for Constrcution Data |
Non-Patent Citations (2)
Title |
---|
刘睿等: ""BIM在变电站项目工程造价中的应用"", 《工程造价管理》 * |
李波: ""基于 BIM 的施工项目成本管理研究"", 《万方数据库》 * |
Cited By (17)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106530143A (en) * | 2016-11-08 | 2017-03-22 | 河南财政税务高等专科学校 | Engineering cost list service system |
CN106952023A (en) * | 2017-03-01 | 2017-07-14 | 广东中建普联科技股份有限公司 | Construction project Fast Quasi construction method and system |
CN107436928A (en) * | 2017-07-12 | 2017-12-05 | 国网山东省电力公司经济技术研究院 | The through-flow method of amount valency of substation project |
CN108280281A (en) * | 2018-01-18 | 2018-07-13 | 宋强 | A kind of construction cost control method and system based on BIM technology |
CN109165462A (en) * | 2018-09-11 | 2019-01-08 | 云南材材通信息技术有限公司 | Material utilization amount automatic monitoring method, device, system and can storage medium |
CN109472446B (en) * | 2018-09-30 | 2022-03-04 | 中铁第一勘察设计院集团有限公司 | BIM model-based engineering budget estimate planning method |
CN109472446A (en) * | 2018-09-30 | 2019-03-15 | 中铁第勘察设计院集团有限公司 | Project Budget preparation method based on BIM model |
CN109753717A (en) * | 2018-12-28 | 2019-05-14 | 国网浙江省电力有限公司经济技术研究院 | A kind of construction method of power distribution network component mathematical model and application |
CN109766605A (en) * | 2018-12-28 | 2019-05-17 | 国网浙江省电力有限公司经济技术研究院 | Method for building up in kind with the power distribution network full information mathematical model of value linkage |
CN109800497A (en) * | 2019-01-16 | 2019-05-24 | 深圳大学 | A kind of data sharing method and device based on Revit |
CN110909450A (en) * | 2019-10-22 | 2020-03-24 | 国网冀北电力有限公司经济技术研究院 | Intelligent design cost integrated acquisition method for power transmission line |
CN111507001A (en) * | 2020-04-17 | 2020-08-07 | 国网湖南省电力有限公司 | Method and system for calculating construction cost of power transformation project, readable storage medium and computer |
CN111507002A (en) * | 2020-04-17 | 2020-08-07 | 国网湖南省电力有限公司 | Method and system for mounting power transformation project, readable storage medium and computer |
CN111507001B (en) * | 2020-04-17 | 2023-04-14 | 国网湖南省电力有限公司 | Method and system for calculating construction cost of power transformation project, readable storage medium and computer |
CN111507002B (en) * | 2020-04-17 | 2023-09-26 | 国网湖南省电力有限公司 | Power transformation project mounting method, system, readable storage medium and computer |
CN117235876A (en) * | 2023-11-14 | 2023-12-15 | 中国建筑西南设计研究院有限公司 | Method and system for counting engineering quantity based on Rhinoceros |
CN117235876B (en) * | 2023-11-14 | 2024-01-30 | 中国建筑西南设计研究院有限公司 | Method and system for counting engineering quantity based on Rhinoceros |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106097149A (en) | The method for designing of project of transmitting and converting electricity cost software based on BIM technology | |
CN110046364A (en) | A kind of method for computing work amount based on BIM technology | |
CN104778753B (en) | The three-dimensional modeling implementation method of bridge reinforcement | |
Wijayakumar et al. | Automation of BIM quantity take-off to suit QS’s requirements | |
CN105574652A (en) | Planning big data management and control system of smart power distribution network and method | |
CN109359322A (en) | Novel water conservancy project BIM unique encodings method based on Omniclass sorting technique | |
CN105046432A (en) | Building dimensional guide construction method | |
CN110990914A (en) | BIM technology-based large boiler installation method | |
KR20160080388A (en) | Bim-based construction value engineering (ve) processing system | |
CN107229791A (en) | Cost of construction metering method and device | |
CN109948933A (en) | A kind of intelligent plant method of allocation plan and system | |
Wei et al. | Application of BIM technology in building water supply and drainage design | |
CN105631135B (en) | Based on ABAQUS excavation of foundation pit rapid modeling analysis system and its application method | |
CN109377092A (en) | A kind of modeling method of the project of transmitting and converting electricity valuation model based on BIM | |
CN110083926A (en) | A method of for subway line plane and vertical section integrated design | |
Faltejsek | BIM as an effective tool of project and facility management | |
CN104599061A (en) | Method for calculating project amount of road bridge engineering project | |
Wang | Analysis and application of BIM technology in the project goal control | |
Yan et al. | Dynamic control of integrated project management system based on engineering projects | |
CN117035700A (en) | BIM-based hydraulic and hydroelectric engineering forward collaborative design method | |
CN105469180A (en) | TPS based industrial cluster enterprise production coordinated management evaluating system | |
CN112184134B (en) | Network plan rationality evaluation dimension design method, evaluation method, system and device | |
Qin | The advantages of BIM application in EPC mode | |
CN106339810A (en) | Mathematic model corresponding to standard information providing and preliminary budget making | |
Qiu et al. | Application of BIM technology in construction engineering |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20161109 |