CN106372787A - Progress plan quick compilation method based on BIM and big data - Google Patents
Progress plan quick compilation method based on BIM and big data Download PDFInfo
- Publication number
- CN106372787A CN106372787A CN201610761860.6A CN201610761860A CN106372787A CN 106372787 A CN106372787 A CN 106372787A CN 201610761860 A CN201610761860 A CN 201610761860A CN 106372787 A CN106372787 A CN 106372787A
- Authority
- CN
- China
- Prior art keywords
- construction
- component
- bim
- project
- information
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims abstract description 42
- 238000010276 construction Methods 0.000 claims abstract description 88
- 230000008569 process Effects 0.000 claims abstract description 15
- 238000005516 engineering process Methods 0.000 claims description 32
- 239000000463 material Substances 0.000 claims description 9
- 238000002360 preparation method Methods 0.000 claims description 8
- 238000007726 management method Methods 0.000 claims description 5
- 238000012795 verification Methods 0.000 claims description 5
- 238000009825 accumulation Methods 0.000 claims description 4
- 238000000605 extraction Methods 0.000 claims description 3
- 238000003780 insertion Methods 0.000 claims description 3
- 230000037431 insertion Effects 0.000 claims description 3
- 238000004519 manufacturing process Methods 0.000 claims description 3
- 238000011017 operating method Methods 0.000 claims description 3
- 238000012550 audit Methods 0.000 description 1
- 230000004888 barrier function Effects 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000005540 biological transmission Effects 0.000 description 1
- 238000009435 building construction Methods 0.000 description 1
- 238000004364 calculation method Methods 0.000 description 1
- 230000008859 change Effects 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000009415 formwork Methods 0.000 description 1
- 230000001788 irregular Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000013439 planning Methods 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
- G06Q10/06316—Sequencing of tasks or work
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
- G06Q10/103—Workflow collaboration or project management
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/08—Construction
Landscapes
- Business, Economics & Management (AREA)
- Human Resources & Organizations (AREA)
- Engineering & Computer Science (AREA)
- Strategic Management (AREA)
- Entrepreneurship & Innovation (AREA)
- Economics (AREA)
- General Business, Economics & Management (AREA)
- Theoretical Computer Science (AREA)
- Tourism & Hospitality (AREA)
- Physics & Mathematics (AREA)
- Marketing (AREA)
- General Physics & Mathematics (AREA)
- Operations Research (AREA)
- Quality & Reliability (AREA)
- General Health & Medical Sciences (AREA)
- Primary Health Care (AREA)
- Development Economics (AREA)
- Educational Administration (AREA)
- Health & Medical Sciences (AREA)
- Game Theory and Decision Science (AREA)
- Data Mining & Analysis (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention discloses a progress plan quick compilation method based on BIM and big data. The method comprises the following steps: 1) hierarchical naming management of project components; 2) project working day quota and component construction process standardization; 3) automatic generation of a progress plan based on BIM; 4) collection and analysis of actual construction progress; and 5) automatic updating of a progress plan automatic compilation quota database. The progress plan quick compilation method based on BIM and big data improves project progress plan compilation efficiency, improves project progress plan compilation scientificity and feasibility and ensures traceability of the whole process of the construction process information.
Description
Technical field
The present invention relates to building construction technology, more particularly, to a kind of quickly worked out based on the schedule of bim and big data
Method.
Background technology
Currently, construction projects are numerous, and during project construction, construction schedule is the one of project construction overall process
Individual important references, the establishment of construction schedule often devotes a tremendous amount of time, and the establishment of project schedule plan is often
Authorized personnel is carried out according to personal working experience, but everyone experience is irregular unclear, and the schedule quality of establishment is past
Past different, and there is also in practice in a large number because construction schedule establishment is inaccurate in engineering, lead to the engineering time
Not and the phenomenon such as the part construction team work holdup, largely effect on project construction progress.
Content of the invention
The technical problem to be solved in the present invention is for defect of the prior art, provides a kind of based on bim and several greatly
According to the quick preparation method of schedule.
The technical solution adopted for the present invention to solve the technical problems is: a kind of schedule based on bim and big data
Quick preparation method, comprises the following steps:
1) component is carried out with classification name, for the grading extraction of subsequent members information;Described rating includes project
Title, building information, floor information, location information, material information, element type and scale of construction information;
2) standardized construction technique is set for project construction, the standardization of construction technology includes the standard that technique overlaps logic
Change and the standardization of each construction technology method and construction requirement, specify the condition that each construction technology starts to construct, specifically apply
The operating procedure of work and resource requirement;The technological standardss storehouse of standard is set for standardized construction technique;
3) according to component name, the related process in construction technology standard storehouse is completed to mate with component automatically, combination member
Material information in classification name and element type, the construction of the component of this corresponding this material of Auto-matching and element type
Technique content and process sequence, then in conjunction with the scale of construction information of corresponding Technical quota and this component, calculate this component
The duration of each construction technology, produce the corresponding sequence of construction of each component and after the corresponding duration, in conjunction with setting from lower
On sequence of construction and the insertion of different operation condition, the construction schedule of automatic production project.
4) manual examination and verification are carried out to the component construction period automatically generating, and carry out local directed complete set as needed;
5) renewal in technological standardss storehouse: in the project implementation process, gather the actual construction time of each construction technology, if each construct
The actual construction time accumulation group number of technique exceedes given threshold, then calculate the meansigma methodss of the working-day norm of this technique, then count this
According to updating in working-day norm storehouse, replace the construction period quota specifying skill of starting building original.
By such scheme, described step 2) in zones of different exist construction technology difference according to the multiple technique of areal setting
Java standard library.
By such scheme, described step 5) in gather each construction technology actual construction time through related data through management personnel
Invalid data is rejected after examination & verification.
By such scheme, described step 5) in this data is updated in working-day norm storehouse, replace and specify skill of starting building original
Construction period quota when need to through related data through management personnel audit.
The beneficial effect comprise that: 1, present invention reduces the difficulty of schedule establishment, reduces to progress
The profile of planning personnel requires.
2nd, the present invention improves the science of schedule establishment, improves the enforceability of project schedule plan, more pastes
Close project construction actual.
3, present invention achieves the foundation of the big data of project scheduling management, facilitate the tracking to project progress message for the later stage
And inquiry.
4th, the automatically updating of working-day norm of the present invention, reduces the impact to project duration for the anthropic factor, and more science is accurate.
Brief description
Below in conjunction with drawings and Examples, the invention will be further described, in accompanying drawing:
Fig. 1 is the method flow diagram of the embodiment of the present invention;
Fig. 2 is the schematic flow sheet that component of the present invention and technology library Auto-matching generate schedule.
Specific embodiment
In order that the objects, technical solutions and advantages of the present invention become more apparent, with reference to embodiments, to the present invention
It is further elaborated.It should be appreciated that specific embodiment described herein, only in order to explain the present invention, is not used to limit
Determine the present invention.
As shown in figure 1, this project schedule plan preparation method includes following content.
The classification name of component, because different specialties is different to the extracted amount of component information, can by being classified name
To facilitate the grading extraction of component information, each takes what he needs, it is to avoid the redundancy of information, secondly, is named, is entered by unified model component
Inventory name during degree plan subitem name and commercial calculation amount, realizes the shared of information between specialty, eliminates and believe between specialty
The barrier of breath transmission, component classification name is as shown in Figure 2.
Construction technology standard, is project construction setting standardized construction technique, and the standardization of construction technology includes technique
The overlap joint standardization of logic and the standardization of each construction technology method and construction requirement, specify each construction technology and start to construct
Condition, the operating procedure of Specific construction and resource requirement etc., the technological standardss storehouse of standard is set on backstage, and zones of different deposits
In construction technology difference, different technological standardss storehouses can be set.
Technique Auto-matching, after completing model creation according to name requirement, backstage construction technology standard storehouse is according to component
Related process is completed to mate by title automatically with component, and in implementation process, component construction technology can be with identical components title
Model is mated, and combination member is classified material information and element type in name, this corresponding this material of Auto-matching
With construction technology content and the process sequence of the component of element type, then in conjunction with corresponding Technical quota and this component
Scale of construction information, calculates the duration of this each construction technology of component, produces the corresponding sequence of construction of each component and corresponding duration
Afterwards, in conjunction with the condition of the sequence of construction from bottom to top setting and different operation insertion, the construction of automatic production project is entered
Degree plan.For example this road construction technology of concrete column formwork can automatically with material properties for concrete column Components Matching, a key
Generation project construction schedule, can carry out the artificial fine setting of local, be illustrated in figure 2 and quickly generate after having produced schedule
The progress construction schedule of some component, can quickly generate the construction schedule of whole project in project construction.
Quota automatically updates, and backstage quota store can be automatically updated, in the project implementation process, project construction personnel
Require according to timing node, the beginning of each construction technology of timely typing and deadline, by the application of multiple projects, backstage exists
After the data of accumulation certain group number, analyzed by calculating, draw the meansigma methodss of the working-day norm of this technique, related data is through pipe
Update in working-day norm storehouse after reason personnel examination & verification, replace the construction period quota specifying skill of starting building original.By constantly counting
Constantly it is updated according to accumulation, so that working-day norm increasingly presses close to engineering construction reality, in implementation process, drawing as needed
Divide the background data base of zones of different.
It should be appreciated that for those of ordinary skills, can be improved according to the above description or be converted,
And all these modifications and variations all should belong to the protection domain of claims of the present invention.
Claims (4)
1. a kind of quick preparation method of the schedule based on bim and big data is it is characterised in that comprise the following steps:
1) component is carried out with classification name, for the grading extraction of subsequent members information;Described rating include project name,
Building information, floor information, location information, material information, element type and scale of construction information;
2) standardized construction technique is set for project construction, the standardization of construction technology include technique overlap the standardization of logic with
And the standardization of each construction technology method and construction requirement, specify the condition that each construction technology starts to construct, Specific construction
Operating procedure and resource requirement;The technological standardss storehouse of standard is set for standardized construction technique;
3) according to component name, the related process in construction technology standard storehouse is completed to mate with component automatically, combination member is classified
Material information in name and element type, the construction technology of the component of this corresponding this material of Auto-matching and element type
Content and process sequence, then in conjunction with the scale of construction information of corresponding Technical quota and this component, calculate this component each
The duration of construction technology, produce the corresponding sequence of construction of each component and after the corresponding duration, in conjunction with set from bottom to top
Sequence of construction and the condition of different operation insertion, the construction schedule of automatic production project.
4) manual examination and verification are carried out to the component construction period automatically generating, and carry out local directed complete set as needed;
5) renewal in technological standardss storehouse: in the project implementation process, gather the actual construction time of each construction technology, if each construction technology
Actual construction time accumulation group number exceed given threshold, then calculate the meansigma methodss of the working-day norm of this technique, then by this data more
Newly in working-day norm storehouse, replace the construction period quota specifying skill of starting building original.
2. the quick preparation method of the schedule based on bim and big data according to claim 1 is it is characterised in that institute
State step 2) in zones of different exist construction technology difference according to areal setting multiple technological standardss storehouse.
3. the quick preparation method of the schedule based on bim and big data according to claim 1 is it is characterised in that institute
State step 5) in gather each construction technology actual construction time through related data through management personnel examination & verification after reject invalid data.
4. the quick preparation method of the schedule based on bim and big data according to claim 1 is it is characterised in that institute
State step 5) in this data is updated in working-day norm storehouse, replace specify start building to need during the original construction period quota of skill through
Related data is audited through management personnel.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610761860.6A CN106372787A (en) | 2016-08-30 | 2016-08-30 | Progress plan quick compilation method based on BIM and big data |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610761860.6A CN106372787A (en) | 2016-08-30 | 2016-08-30 | Progress plan quick compilation method based on BIM and big data |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106372787A true CN106372787A (en) | 2017-02-01 |
Family
ID=57901120
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610761860.6A Pending CN106372787A (en) | 2016-08-30 | 2016-08-30 | Progress plan quick compilation method based on BIM and big data |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106372787A (en) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107237496A (en) * | 2017-07-13 | 2017-10-10 | 广东骏峰建筑科技有限公司 | A kind of high-rise building construction process |
CN108389026A (en) * | 2017-12-28 | 2018-08-10 | 广州建软科技股份有限公司 | A kind of power failure planning management system and method |
CN108427816A (en) * | 2017-08-12 | 2018-08-21 | 中民筑友科技投资有限公司 | A kind of structure attribute value calculation amount method, apparatus and system based on BIM |
CN108694191A (en) * | 2017-04-08 | 2018-10-23 | 大连万达集团股份有限公司 | The method of quick-searching component information in BIM models |
CN109522527A (en) * | 2018-11-30 | 2019-03-26 | 常州伟泰科技股份有限公司 | A method of site construction technology establishment is carried out using software systems |
CN110930044A (en) * | 2019-11-29 | 2020-03-27 | 伍知行 | Construction organization resource rapid configuration method and system |
CN115860499A (en) * | 2023-02-28 | 2023-03-28 | 安徽智享云科技有限公司 | Multi-professional work-type coordination construction management system based on BIM technology |
CN116307566A (en) * | 2023-03-12 | 2023-06-23 | 武汉大学 | Dynamic design system for large-scale building construction project construction organization scheme |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104751315A (en) * | 2015-04-01 | 2015-07-01 | 北京首钢自动化信息技术有限公司 | E-purchasing system and method |
CN105023201A (en) * | 2015-07-24 | 2015-11-04 | 中建三局第一建设工程有限责任公司 | Assembled building detailed design and construction method based on BIM (Building Information Modeling) and large data |
-
2016
- 2016-08-30 CN CN201610761860.6A patent/CN106372787A/en active Pending
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104751315A (en) * | 2015-04-01 | 2015-07-01 | 北京首钢自动化信息技术有限公司 | E-purchasing system and method |
CN105023201A (en) * | 2015-07-24 | 2015-11-04 | 中建三局第一建设工程有限责任公司 | Assembled building detailed design and construction method based on BIM (Building Information Modeling) and large data |
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108694191A (en) * | 2017-04-08 | 2018-10-23 | 大连万达集团股份有限公司 | The method of quick-searching component information in BIM models |
CN107237496A (en) * | 2017-07-13 | 2017-10-10 | 广东骏峰建筑科技有限公司 | A kind of high-rise building construction process |
CN108427816A (en) * | 2017-08-12 | 2018-08-21 | 中民筑友科技投资有限公司 | A kind of structure attribute value calculation amount method, apparatus and system based on BIM |
CN108389026A (en) * | 2017-12-28 | 2018-08-10 | 广州建软科技股份有限公司 | A kind of power failure planning management system and method |
CN109522527A (en) * | 2018-11-30 | 2019-03-26 | 常州伟泰科技股份有限公司 | A method of site construction technology establishment is carried out using software systems |
CN110930044A (en) * | 2019-11-29 | 2020-03-27 | 伍知行 | Construction organization resource rapid configuration method and system |
CN115860499A (en) * | 2023-02-28 | 2023-03-28 | 安徽智享云科技有限公司 | Multi-professional work-type coordination construction management system based on BIM technology |
CN115860499B (en) * | 2023-02-28 | 2023-05-05 | 安徽智享云科技有限公司 | BIM technology-based multi-specialty work coordination construction management system |
CN116307566A (en) * | 2023-03-12 | 2023-06-23 | 武汉大学 | Dynamic design system for large-scale building construction project construction organization scheme |
CN116307566B (en) * | 2023-03-12 | 2024-05-10 | 武汉大学 | Dynamic design system for large-scale building construction project construction organization scheme |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106372787A (en) | Progress plan quick compilation method based on BIM and big data | |
Yin et al. | Building information modelling for off-site construction: Review and future directions | |
He et al. | Mapping the managerial areas of Building Information Modeling (BIM) using scientometric analysis | |
Naghshbandi | BIM for facility management: challenges and research gaps | |
Kisi et al. | Optimal productivity in labor-intensive construction operations: Pilot study | |
CN106997511A (en) | Railway beam course management system and railway beam a management method based on BIM technology | |
CN108764610A (en) | Standard technology construction management of project method based on big data, storage medium | |
LU103216B1 (en) | Prefabricated building design and actual construction match evaluation method based on bim parameters | |
Thabet et al. | A 6-step systematic process for model-based facility data delivery | |
Elmaraghy et al. | An exploration of BIM and lean interaction in optimizing demolition projects | |
WO2024027437A1 (en) | Component parameter library-based method for integrated collaboration of prefabricated building design and construction | |
CN107229791A (en) | Cost of construction metering method and device | |
Handayani et al. | A building information modeling (BIM)-integrated system for evaluating the impact of change orders | |
CN111666619A (en) | BIM technology-based substation engineering implementation field digital management system | |
CN106779620A (en) | Digitized Design Platform building method based on IPD systems | |
Kisi et al. | Estimation of optimal productivity in labor-intensive construction operations: Advanced study | |
Chou et al. | Benefit evaluation of implementing BIM in construction projects | |
CN109740245A (en) | A kind of application method in the prefabricated middle BIM technology of bar desk Combinatorial resolution | |
Laurini et al. | Technology 4.0 for buildings management: from building site to the interactive building book | |
CN110032154B (en) | Production control method and system for small-batch products | |
WO2021042585A1 (en) | Cdm establishment method for building component | |
Dubler et al. | Using lean theory to identify waste associated with information exchanges on a building project | |
CN110377931A (en) | A kind of building analogy method based on BIM | |
CN113569306A (en) | BIM modeling implementation and application method of waste incineration power plant based on BIM technology | |
Ham et al. | BIM based construction project case analysis for facility life cycle management from the perspective of the client |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170201 |
|
RJ01 | Rejection of invention patent application after publication |