CN108764610A - Standard technology construction management of project method based on big data, storage medium - Google Patents

Standard technology construction management of project method based on big data, storage medium Download PDF

Info

Publication number
CN108764610A
CN108764610A CN201810324765.9A CN201810324765A CN108764610A CN 108764610 A CN108764610 A CN 108764610A CN 201810324765 A CN201810324765 A CN 201810324765A CN 108764610 A CN108764610 A CN 108764610A
Authority
CN
China
Prior art keywords
project
construction
management
standard
information
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810324765.9A
Other languages
Chinese (zh)
Other versions
CN108764610B (en
Inventor
陈群
刘林
李文峰
王世杰
曾开发
黄瑜锋
王杰钦
陈镇西
余成柱
陈哲
陈龙
陈文灵
黄骞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujian University of Technology
Original Assignee
Fujian University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujian University of Technology filed Critical Fujian University of Technology
Priority to CN201810324765.9A priority Critical patent/CN108764610B/en
Publication of CN108764610A publication Critical patent/CN108764610A/en
Application granted granted Critical
Publication of CN108764610B publication Critical patent/CN108764610B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06313Resource planning in a project environment
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Economics (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Tourism & Hospitality (AREA)
  • Marketing (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Biodiversity & Conservation Biology (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Educational Administration (AREA)
  • Game Theory and Decision Science (AREA)
  • Development Economics (AREA)
  • Data Mining & Analysis (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The present invention provides a kind of standard technology construction management of project method based on big data, storage medium, and method includes S1:Process engineering project construction normal data and standard construction information according to magnanimity generate standard technology construction management of project database;S2:After the project essential information for obtaining corresponding technical routine, management platform corresponding with technical routine is generated according to the database;Management platform includes inventory editor module, budget management module, progress control module and info push module.The present invention utilizes big data technology, standardized construction technique and workflow are collected by magnanimity engineering project, to project cost, progress, Quality Control, management position action, it realizes the construction management of project system under quality standardization pipe diameter design, help is provided for construction site management and enterprise in charge of construction's project management.

Description

Standard technology construction management of project method based on big data, storage medium
Technical field
The present invention relates to Data Analysis Services fields, particularly relate to a kind of standard technology engineering project based on big data Execution management method therefor, storage medium.
Background technology
Project management system is widely used in domestic and international construction project.Current project management system solves The problem of management tool, but also fall behind relatively in terms of the intelligent management and control.
Existing project management system can not solve:A project costs Automatic generation of information, b project construction progresses are automatic The problems such as layout, the standardization of c project integrations, d project manager's task automatic push.
Therefore, demand provides a kind of project management system that can be solved the above problems.
Invention content
The technical problem to be solved by the present invention is to:A kind of standard technology Construction of Engineering Projects pipe based on big data is provided Reason method, storage medium can realize intelligent, quality standardization management and control process engineering project construction.
In order to solve the above-mentioned technical problem, the technical solution adopted by the present invention is:
A kind of standard technology construction management of project method based on big data, including:
S1:Process engineering project construction normal data and standard construction information according to magnanimity generate standard technology work Journey item construction management database;
S2:After the project essential information for obtaining a corresponding technical routine, generates according to the database and specified with described one The corresponding management platform of project;The management platform include inventory editor module, budget management module, progress control module and Info push module;
The inventory editor module, the standard construction technology for creating and editing the corresponding technical routine;
The budget management module corresponds to the construction budget of the technical routine and estimates for generating under standard construction technology Data;
The progress control module, the schedule for generating the corresponding technical routine, and carry out Schedule monitoring;
Info push module, for push include construction working task and standardization control method information, while pre- If summarizing unfinished work according to push receipt in the time, and forms report and push to responsible person concerned.
Another technical solution provided by the invention is:
A kind of computer storage media, is stored thereon with computer program, which realizes above-mentioned when being executed by processor All steps that standard technology construction management of project method based on big data is included.
The beneficial effects of the present invention are:The present invention is constructed with the process engineering project construction normal data and standard of magnanimity Based on engineering method, by big data technology, standard technology construction management of project database is generated;Start in new project Before, it can be by calling the database, the standard technology engineering project automatically generated after typing essential information for the project is applied Work management platform;It can realize that the project include the reference of standard construction technology, task distribution, task standardization by the platform The whole management and control that control method push, Schedule monitoring, engineering relevant information summarize etc..It is soft that the present invention changes conventional items management The artificial collection and input of part bulk items data, greatly improve the efficiency of construction standardization management, realize construction data Intelligence, standardization collect and call.
Description of the drawings
Fig. 1 is a kind of flow diagram of the standard technology construction management of project method based on big data of the present invention;
Fig. 2 is that the flow of the standard technology construction management of project method based on big data of the embodiment of the present invention one is shown It is intended to.
Specific implementation mode
To explain the technical content, the achieved purpose and the effect of the present invention in detail, below in conjunction with embodiment and coordinate attached Figure is explained.
The design of most critical of the present invention is:With the process engineering project construction normal data and standard construction of magnanimity Based on, standard technology construction management of project database is generated by big data technology;By calling database automatic Generate the management platform of technical routine;Whole management and control is carried out to the project by platform.
Fig. 1 is please referred to, the present invention provides a kind of standard technology construction management of project method based on big data, packet It includes:
S1:Process engineering project construction normal data and standard construction information according to magnanimity generate standard technology work Journey item construction management database;
S2:After the project essential information for obtaining a corresponding technical routine, generates according to the database and specified with described one The corresponding management platform of project;The management platform include inventory editor module, budget management module, progress control module and Info push module;
The inventory editor module, the standard construction technology for creating and editing the corresponding technical routine;
The budget management module corresponds to the construction budget of the technical routine and estimates for generating under standard construction technology Data;
The progress control module, the schedule for generating the corresponding technical routine, and carry out Schedule monitoring;
Info push module, for push include construction working task and standardization control method information, while pre- If summarizing unfinished work according to push receipt in the time, and forms report and push to responsible person concerned.
As can be seen from the above description, the beneficial effects of the present invention are:The present invention utilizes big data technology, passes through magnanimity engineering Project collects standardized construction technique and workflow, to project cost, progress, Quality Control, management position action, realizes matter Construction management of project system under amount standardization pipe diameter design, is construction site management and enterprise in charge of construction's project management Help is provided.
Further, the S1 is specially:
The room of extraction magnanimity is built, municipal project includes engineering project classification, engineering cost information, project elevation or number of plies letter Breath, project management personnel depaly standard, construction working logic flow, technological standards quality requirement, technological operation standard work When process engineering project construction normal data;The normal data is combined with standard construction information, forms standard work Skill construction management of project database.
Seen from the above description, basic number of the process engineering project construction normal data as database of magnanimity is extracted According to ensureing the reliability of database data.
Further, the management platform further includes store keeping module, builder's diary module and inspection of quality module;
The store keeping module, the material item for generating the corresponding technical routine, and pipe is carried out to material Reason;
The builder's diary module is used for recording materials entry test situation and construction speed, and according to current construction Progress is in conjunction with the standardized construction Process Production realtime construction data in the inventory editor module;
The inspection of quality module for retaining the technical routine includes operational staff, performance, of problems Inspection of quality data.
Seen from the above description, management platform can also realize the store keeping for technical routine, record construction day simultaneously Will and inspection of quality, further complete platform function provide to the user and more intelligentized manage help.
Further, the S1 is specially:
S11:That extract magnanimity includes engineering project classification ui, engineering cost information li, project elevation or number of plies information vi、 Project management personnel depaly standard ψiWith construction working logic flow fiAnd technological operation standard work force ti, technological standards Quality requirement hi, standard construction information mi, project square metre or milimeter number information niRoom build, Municipal Engineering Projects data xi, the engineering project data xiIt is represented by xi=<ui,li,vii,fi,ti,hi,mi,ni>, i is the number of project under construction x;
S12:To the engineering project data xiIt is handled, obtains the project standardization under standard construction state Construction data collection, standard technology Construction of Engineering Projects pipe is built according to the data set Manage database.
Further, the S2 is specially:
Step 21:According to the database, engineering project classification u is specified by typing onea, a specified project elevation or Number of plies information va, corresponding project square metre or milimeter number information na, obtain the engineering project data of the corresponding technical routine xa
Step S22:Engineering project data x according to the technical routineaGenerate the standard work of the corresponding technical routine Skill construction management of project platform.
Seen from the above description, it can realize that the room of magnanimity is built in automation, the engineering project data of municipal project carry out Extraction, processing, obtain the project standardized construction data set under standard construction state, in this, as standard technology engineering Item construction management database provides data support for the quality standard management of follow-up concrete engineering project.
Further, the method further includes:
S3:The index feedback information for receiving the technical routine, in the management platform, to its engineering cost information la, project elevation or number of plies information va, project management personnel depaly standard ψaWith construction working logic flow fa, Yi Jigong Skill operation standard working hour ta, technological standards quality requirement ha, standard construction information maIt is adjusted.
Seen from the above description, it can realize after the completion of project, database can be anti-according to the index of technical routine a Present the intelligent adjustment that situation carries out database index.
Another technical solution provided by the invention is:
A kind of computer storage media, is stored thereon with computer program, which realizes above-mentioned when being executed by processor All steps that standard technology construction management of project method based on big data is included.
As can be seen from the above description, the beneficial effects of the present invention are:
It corresponds to one of ordinary skill in the art will appreciate that realizing all or part of flow in above-mentioned technical proposal, being can It is realized with instructing relevant hardware by computer program, the program can be stored in one and computer-readable deposit In storage media, the program is when being executed, it may include such as the flow of above-mentioned each method.
Embodiment one
Fig. 2 is please referred to, the standard technology construction management of project method based on big data that the present embodiment provides a kind of should Method includes the following steps:
One, data acquire:
Step 11:Extraction magnanimity room builds, the engineering project classification of municipal project, engineering cost information (people containing standard, material, Machine quantity), project elevation or number of plies information, project management personnel depaly standard, construction working logic flow, technological standards The information such as quality requirement, technological operation standard work force, combined standard construction information form standard technology Construction of Engineering Projects Manage database;
Magnanimity engineering project data include engineering project classification ui, engineering cost information li, project elevation or number of plies information vi, project management personnel depaly standard ψiWith construction working logic flow fiAnd technological operation standard work force ti, technique Standard prescriptions hi, standard construction information mi, project square metre or milimeter number information ni, engineering project data xiIt can table It is shown as xi=<ui,li,vii,fi,ti,hi,mi,ni>, i is the number of project under construction x.
Step 12:The project data of magnanimity is handled, the project standardization under standard construction state is obtained and applies Work data setStandard technology construction management of project number is set up based on the data set According to library.
Step 13:Set data base call need manual typing project as:Engineering project classification u, project elevation or number of plies letter Cease v, project square metre or milimeter number information n.
Two, new projects' data are extracted, and form project management platform:
Step 21:The works category information u of new projects a is defined in systemsa, project elevation or number of plies information vaAnd item Mesh square metre or milimeter number information na
Step 22:According to the database, the standard technology construction management of project of system automatically generated new projects a is flat Platform;
The standard technology construction management of project platform includes at least:
A, standardized construction technique inventory editor module, for creating and editing standard construction technology, the standard construction Technique information includes the standard technology practice under standard construction technology modularization, required cost, required time, required uses material, institute Standard construction technology information is stated to be storable in the Cloud Server;
B, budget management module is standardized, for generating the construction budget estimated data under a set of standard construction technology, institute It includes Master Cost, labour cost and machinery expenses to state standardization budget data, and the Engineering Standardization budget data can store In the Cloud Server;
C, progress control module is standardized, for schedule, Schedule monitoring, in each standard construction technology information The period planning of modular process, progress can be automatically formed by standard construction technology information, and the actual progress is used Gantt chart indicates;
D, standardized materials management module estimates number needed for the engineering under a set of standard construction technology for generating with material Include that material, artificial and mechanical appliances, the Engineering Standardization are storable in institute with material data according to, standardization material data It states in Cloud Server;
E, builder's diary module, be used for recording materials entry test situation and construction speed, and according to current construction into Combining standardized construction technology is spent to generate a realtime construction data, and the realtime construction data are storable in the Cloud Server In;
F, inspection of quality module, for by Real-time Feedback after the completion of standardized construction technique, executor to be retained in system Member, performance, there are related datas such as problems, the engineering performance data are storable in the Cloud Server.
Three, project management system information pushes:
Step 31, platform automatically control construction working task, standardization according to associated construction project management personal information The information such as method processed carry out mobile phone push;
Step 32, daily according to push task receipt summarize unfinished work automatically, and formed report carry out related responsibility People pushes.
Four, standard technology construction management of project system self-regulation is whole:
Step 4, according to new projects' a procedure management informations, for the engineering cost information l in standard databasea, engineering mark High or number of plies information va, project management personnel depaly standard ψaWith construction working logic flow faAnd technological operation standard Working hour ta, technological standards quality requirement ha, standard construction information maIt is adjusted again.
The present embodiment is formed by retrieving magnanimity engineering project standardization effort information by engineering cost information li, engineering Absolute altitude or number of plies information vi, project management personnel depaly standard ψiWith construction working logic flow fiAnd technological operation mark Quasi- working hour ti, technological standards quality requirement hi, standard construction information miThe Engineering Standardization work letter of equal key messages composition Cease library;In new projects a implementations, as setting engineering project engineering classification information ua, project elevation or number of plies information vaAnd project Square metre or milimeter number information naAfterwards, the standard technology project management system that will automatically generate new projects a, automatically generates work The key messages such as Cheng Chengben, construction quality, project progress, person works' task packet, and can be appointed according to person works' responsibility Business push;In the project implementation process, project jobs in operation report can be generated in time according to project feedback situation and pushed; After the completion of project, database can carry out the intelligent of database index according to the index feedback of project a and adjust.
Embodiment two
The present embodiment corresponding embodiment one provides a kind of computer storage media, is stored thereon with computer program, the journey Sequence can realize the standard technology engineering project based on big data described in above-described embodiment one when being executed by the processor of system All steps that execution management method therefor is included.
In conclusion standard technology construction management of project method provided by the invention based on big data, storage are situated between Matter collects standardized construction technique and workflow using big data technology by magnanimity engineering project, to project cost, into Degree, Quality Control, management position action realize the construction management of project system under quality standardization pipe diameter design, to apply Work field management and enterprise in charge of construction's project management provide help.
Example the above is only the implementation of the present invention is not intended to limit the scope of the invention, every to utilize this hair Equivalents made by bright specification and accompanying drawing content are applied directly or indirectly in relevant technical field, include similarly In the scope of patent protection of the present invention.

Claims (7)

1. a kind of standard technology construction management of project method based on big data, which is characterized in that including:
S1:Process engineering project construction normal data and standard construction information according to magnanimity generate standard technology engineering item Mesh construction management database;
S2:After the project essential information for obtaining a corresponding technical routine, generated and a technical routine according to the database Corresponding management platform;The management platform includes inventory editor module, budget management module, progress control module and information Pushing module;
The inventory editor module, the standard construction technology for creating and editing the corresponding technical routine;
The budget management module corresponds to the construction budget of the technical routine and estimates number for generating under standard construction technology According to;
The progress control module, the schedule for generating the corresponding technical routine, and carry out Schedule monitoring;
Info push module, for push include construction working task and standardization control method information, while when default It is interior to summarize unfinished work according to push receipt, and form report and push to responsible person concerned.
2. the standard technology construction management of project method based on big data as described in claim 1, which is characterized in that institute Stating S1 is specially:
Extraction magnanimity room build, municipal project include engineering project classification, engineering cost information, project elevation or number of plies information, Project management personnel depaly standard, construction working logic flow, technological standards quality requirement, technological operation standard work force Process engineering project construction normal data;The normal data is combined with standard construction information, forms standard technology work Journey item construction management database.
3. the standard technology construction management of project method based on big data as described in claim 1, which is characterized in that institute It further includes store keeping module, builder's diary module and inspection of quality module to state management platform;
The store keeping module, the material item for generating the corresponding technical routine, and material is managed;
The builder's diary module is used for recording materials entry test situation and construction speed, and according to current construction speed In conjunction with the standardized construction Process Production realtime construction data in the inventory editor module;
The inspection of quality module includes operational staff, performance, quality of problems for retaining the technical routine Product acceptance data.
4. the standard technology construction management of project method based on big data as described in claim 1, which is characterized in that institute Stating S1 is specially:
S11:That extract magnanimity includes engineering project classification ui, engineering cost information li, project elevation or number of plies information vi, engineering Project manager's configuration standard ψiWith construction working logic flow fiAnd technological operation standard work force ti, technological standards quality It is required that hi, standard construction information mi, project square metre or milimeter number information niRoom build, Municipal Engineering Projects data xi, institute State engineering project data xiIt is represented by xi=<ui,li,vii,fi,ti,hi,mi,ni>, i is the number of project under construction x;
S12:To the engineering project data xiIt is handled, obtains the project standardized construction under standard construction state Data setStandard technology construction management of project number is built according to the data set According to library.
5. the standard technology construction management of project method based on big data as claimed in claim 4, which is characterized in that institute Stating S2 is specially:
Step 21:According to the database, engineering project classification u is specified by typing onea, specified a project elevation or the number of plies Information va, corresponding project square metre or milimeter number information na, obtain the engineering project data x of the corresponding technical routinea
Step S22:Engineering project data x according to the technical routineaGenerate the standard technology engineering of the corresponding technical routine Item construction management platform.
6. the standard technology construction management of project method based on big data as claimed in claim 5, which is characterized in that institute The method of stating further includes:
S3:The index feedback information for receiving the technical routine, in the management platform, to its engineering cost information la, engineering Absolute altitude or number of plies information va, project management personnel depaly standard ψaWith construction working logic flow faAnd technological operation mark Quasi- working hour ta, technological standards quality requirement ha, standard construction information maIt is adjusted.
7. a kind of computer storage media, is stored thereon with computer program, which is characterized in that when the program is executed by processor Realize that the standard technology construction management of project method based on big data described in the claims 1-6 any one is wrapped All steps contained.
CN201810324765.9A 2018-04-12 2018-04-12 Standard process engineering project construction management method based on big data and storage medium Active CN108764610B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810324765.9A CN108764610B (en) 2018-04-12 2018-04-12 Standard process engineering project construction management method based on big data and storage medium

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810324765.9A CN108764610B (en) 2018-04-12 2018-04-12 Standard process engineering project construction management method based on big data and storage medium

Publications (2)

Publication Number Publication Date
CN108764610A true CN108764610A (en) 2018-11-06
CN108764610B CN108764610B (en) 2022-04-01

Family

ID=63981612

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810324765.9A Active CN108764610B (en) 2018-04-12 2018-04-12 Standard process engineering project construction management method based on big data and storage medium

Country Status (1)

Country Link
CN (1) CN108764610B (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109816255A (en) * 2019-01-29 2019-05-28 珠海金慧科技有限公司 Self iteration intelligent algorithm of house ornamentation construction reference
CN109886576A (en) * 2019-02-20 2019-06-14 司空科技股份有限公司 Task management method, device and storage medium are delivered in digitlization
CN110378668A (en) * 2019-06-28 2019-10-25 赣州和永软件开发有限责任公司 The method and system of engineering project information initialization is carried out with item base template library
CN110458413A (en) * 2019-07-16 2019-11-15 北京朗道新科智能科技有限公司 A kind of working procedure management method, system, storage medium and electric terminal
CN111291994A (en) * 2020-02-12 2020-06-16 普元信息技术股份有限公司 Multi-project management system and method suitable for agile development mode in big data environment
CN111813745A (en) * 2020-07-27 2020-10-23 中交路桥北方工程有限公司 System, device and method for civil construction technology and standard query
CN113379244A (en) * 2021-06-10 2021-09-10 筑橙科技(深圳)有限公司 Construction progress calculation method and system based on spraying robot construction
CN113434760A (en) * 2021-06-25 2021-09-24 平安国际智慧城市科技股份有限公司 Construction method recommendation method, device, equipment and storage medium
CN114626833A (en) * 2022-04-18 2022-06-14 国网北京市电力公司 Construction standard process supervision method, device, equipment and medium
CN118096089A (en) * 2024-04-25 2024-05-28 浙江龙腾畅想软件有限公司 Engineering project management method, system and medium based on data platform

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101064027A (en) * 2006-04-28 2007-10-31 施威 Architectural engineering construction technique normalizing knowledge base data structure
CN103136626A (en) * 2011-11-29 2013-06-05 北京建龙重工集团有限公司 On-line management method for engineering project
CN104809591A (en) * 2015-05-11 2015-07-29 东北电力大学 Electric power construction engineering supervision mechanism based on big data
CN106203798A (en) * 2016-06-30 2016-12-07 国网山东省电力公司经济技术研究院 A kind of engineering construction work plan preparation method
CN106845935A (en) * 2017-01-12 2017-06-13 深圳云联万企科技有限公司 A kind of method and system of engineering project flow template
CN106951444A (en) * 2017-02-17 2017-07-14 深圳市嘉力达节能科技股份有限公司 Architectural engineering information processing method and device
CN107358340A (en) * 2017-06-23 2017-11-17 深圳云联万企科技有限公司 A kind of project management system based on list of engineering
CN107480912A (en) * 2017-08-31 2017-12-15 福建四创软件有限公司 Hydraulic engineering construction comprehensive management system based on big data analysis and Internet of Things

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101064027A (en) * 2006-04-28 2007-10-31 施威 Architectural engineering construction technique normalizing knowledge base data structure
CN103136626A (en) * 2011-11-29 2013-06-05 北京建龙重工集团有限公司 On-line management method for engineering project
CN104809591A (en) * 2015-05-11 2015-07-29 东北电力大学 Electric power construction engineering supervision mechanism based on big data
CN106203798A (en) * 2016-06-30 2016-12-07 国网山东省电力公司经济技术研究院 A kind of engineering construction work plan preparation method
CN106845935A (en) * 2017-01-12 2017-06-13 深圳云联万企科技有限公司 A kind of method and system of engineering project flow template
CN106951444A (en) * 2017-02-17 2017-07-14 深圳市嘉力达节能科技股份有限公司 Architectural engineering information processing method and device
CN107358340A (en) * 2017-06-23 2017-11-17 深圳云联万企科技有限公司 A kind of project management system based on list of engineering
CN107480912A (en) * 2017-08-31 2017-12-15 福建四创软件有限公司 Hydraulic engineering construction comprehensive management system based on big data analysis and Internet of Things

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109816255A (en) * 2019-01-29 2019-05-28 珠海金慧科技有限公司 Self iteration intelligent algorithm of house ornamentation construction reference
CN109886576A (en) * 2019-02-20 2019-06-14 司空科技股份有限公司 Task management method, device and storage medium are delivered in digitlization
CN110378668A (en) * 2019-06-28 2019-10-25 赣州和永软件开发有限责任公司 The method and system of engineering project information initialization is carried out with item base template library
CN110458413A (en) * 2019-07-16 2019-11-15 北京朗道新科智能科技有限公司 A kind of working procedure management method, system, storage medium and electric terminal
CN111291994A (en) * 2020-02-12 2020-06-16 普元信息技术股份有限公司 Multi-project management system and method suitable for agile development mode in big data environment
CN111813745A (en) * 2020-07-27 2020-10-23 中交路桥北方工程有限公司 System, device and method for civil construction technology and standard query
CN111813745B (en) * 2020-07-27 2024-06-04 中交路桥建设有限公司 System, device and method for inquiring civil engineering technology and standard
CN113379244A (en) * 2021-06-10 2021-09-10 筑橙科技(深圳)有限公司 Construction progress calculation method and system based on spraying robot construction
CN113434760A (en) * 2021-06-25 2021-09-24 平安国际智慧城市科技股份有限公司 Construction method recommendation method, device, equipment and storage medium
CN113434760B (en) * 2021-06-25 2022-12-27 平安国际智慧城市科技股份有限公司 Construction method recommendation method, device, equipment and storage medium
CN114626833A (en) * 2022-04-18 2022-06-14 国网北京市电力公司 Construction standard process supervision method, device, equipment and medium
CN118096089A (en) * 2024-04-25 2024-05-28 浙江龙腾畅想软件有限公司 Engineering project management method, system and medium based on data platform

Also Published As

Publication number Publication date
CN108764610B (en) 2022-04-01

Similar Documents

Publication Publication Date Title
CN108764610A (en) Standard technology construction management of project method based on big data, storage medium
US6073108A (en) Task-based classification and analysis system
TWI834657B (en) Method for scheduling semiconductor back-end factories
CN101976240B (en) Form number generating method and system
CN104471595A (en) Workflow management device and workflow management method
EP1468374A2 (en) Method and system for asset transition project management
Goryachev et al. “Smart factory”: intelligent system for workshop resource allocation, scheduling, optimization and controlling in real time
CN104318354A (en) Task information processing method and system
CN102073926A (en) Automatic intelligent briefing generation method
CN107480882A (en) A kind of system and method for generating BPM
CN110110978A (en) A kind of MES system for cabinet automatic assembly line
CN110032154B (en) Production control method and system for small-batch products
CN113537943A (en) Universal workflow engine and construction method thereof
Hu Information lifecycle modeling framework for construction project lifecycle management
CN112308516A (en) Target project information generation method and related equipment
CN115169658B (en) Inventory consumption prediction method, system and storage medium based on NPL and knowledge graph
Rao et al. On-line simulation for shop floor control in manufacturing execution system
CN115689788A (en) Financial data analysis method
CN115600797A (en) Task processing method, device, equipment and medium
CN105446289B (en) By the method and system of the timestamp of manufacturing execution system collection work state
JP2008299496A (en) Operation simulator and program
CN110515611B (en) Document number generation method
CN109492953A (en) A kind of provide multiple forms of energy to complement each other monitoring and managing method and system based on Building Information Model
CN108305023A (en) A kind of method that electronic assemblies industry realizes automatic job distribution
JP2003280728A (en) Production scheduling control method and production scheduling control program

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant