CN112308516A - Target project information generation method and related equipment - Google Patents

Target project information generation method and related equipment Download PDF

Info

Publication number
CN112308516A
CN112308516A CN202011190704.1A CN202011190704A CN112308516A CN 112308516 A CN112308516 A CN 112308516A CN 202011190704 A CN202011190704 A CN 202011190704A CN 112308516 A CN112308516 A CN 112308516A
Authority
CN
China
Prior art keywords
project
subtasks
target
scene
subtask
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202011190704.1A
Other languages
Chinese (zh)
Inventor
刘新
陈明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Launch Technology Co Ltd
Original Assignee
Shenzhen Launch Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Launch Technology Co Ltd filed Critical Shenzhen Launch Technology Co Ltd
Priority to CN202011190704.1A priority Critical patent/CN112308516A/en
Publication of CN112308516A publication Critical patent/CN112308516A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06311Scheduling, planning or task assignment for a person or group
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06316Sequencing of tasks or work

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Economics (AREA)
  • Tourism & Hospitality (AREA)
  • Marketing (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Game Theory and Decision Science (AREA)
  • Development Economics (AREA)
  • Educational Administration (AREA)
  • Data Mining & Analysis (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The embodiment of the application discloses a target project information generation method, which is used for generating corresponding task distribution lists for different projects and comprises the following steps: acquiring a target project scene; obtaining a subtask corresponding to the target project scene based on the target project scene query; acquiring personnel allocation information corresponding to the subtasks; and generating target project information corresponding to the target project scene based on the subtasks and the staff allocation information corresponding to the subtasks. The project information is used for enabling the distribution process of each task under the project to be clearer, improving the task distribution efficiency and avoiding the problem that certain tasks are not distributed with personnel or are distributed unclearly in the project execution process.

Description

Target project information generation method and related equipment
Technical Field
The embodiment of the application relates to the field of data processing, in particular to a target project information generation method and related equipment.
Background
Project management is a branch of management science, and the definition of project management is as follows: refers to the process of applying special knowledge, skills, tools and methods in project activities to enable projects to achieve or exceed set requirements and expectations under limited resource constraints. Project management is the overall monitoring and management of some activities (such as tasks) that successfully achieve a series of goals. This includes planning, progress-planning, and maintaining the progress of the activities that make up the project. A "project is a one-time task that needs to be completed in a defined resource and a defined time. Specifically, the method can be a project, a service, a research topic, an activity and the like. "project management" is the application of management knowledge, tools and techniques to project activities to solve project problems or fulfill project requirements. Management includes five main tasks, such as leading (leading), organizing (organizing), working (staffing), planning (planning), and controlling (controlling). "
Project Management (Project Management): various related skills, methods and tools are applied to develop various activities in terms of planning, organization, leadership, control and the like in order to meet or exceed requirements and expectations of various parties related to the project on the project. In the project management process, each stage has its own start-stop range, including the input file of the stage and the output file to be generated in the stage. Meanwhile, each stage has a control gate of the stage, namely, the important file to be generated when the stage is completed is also an important input file for entering the next stage. When each stage is finished, the next stage can be started only by passing through the control gate of the stage. The project management process of the IT industry generally comprises five parts: the method comprises the steps of starting a project, planning the project, implementing and controlling the project, ending the project and maintaining the project subsequently.
Many existing project management software require a project manager to distribute tasks to project composers according to project management experiences of the project manager, and the tasks have high requirements on the project manager management experiences, service levels and responsibility centers. Otherwise, the problems of lack of east and west tasks, wrong task hierarchy, lack of task delivery pieces, unreasonable task man-hour distribution, wrong task role distribution and the like can occur. This presents a significant challenge to project management, resulting in a low level of project management and project delay, making the overall project management more uncontrollable. The work task list is a list which integrates the planned tasks, the completed tasks and the future tasks, so that the work tasks can be known at a glance and effectively completed.
Disclosure of Invention
A first aspect of the embodiments of the present application provides a method for generating target project information, including:
acquiring a target project scene;
obtaining a subtask corresponding to the target project scene based on the target project scene query;
acquiring personnel allocation information corresponding to the subtasks;
and generating target project information based on the subtasks and the staff allocation information corresponding to the subtasks.
Based on the target project information generation method provided by the first aspect of the embodiment of the present application, optionally, the target project information includes a task allocation list, and the task allocation list includes an execution sequence of subtasks.
Based on the target project information generation method provided in the first aspect of the embodiment of the present application, optionally, the obtaining of the subtask corresponding to the target project scenario based on the target project scenario query includes:
acquiring subtasks corresponding to the target project scene and working hour information corresponding to each subtask based on the target project scene query;
and the task distribution list comprises the working hour information corresponding to the subtasks.
Based on the target project information generation method provided in the first aspect of the embodiment of the present application, optionally, before generating a task allocation list based on the subtasks and the staff allocation information corresponding to the subtasks, the method further includes:
acquiring project working hours;
and adjusting the working hours corresponding to the subtasks based on the project working hours.
Based on the target project information generation method provided in the first aspect of the embodiment of the present application, optionally, obtaining the subtask corresponding to the target project scenario based on the target project scenario query includes:
obtaining subtasks corresponding to the target project scene and required working material information corresponding to each subtask based on the target project scene query, wherein the required working material information comprises: and any one or more of role information corresponding to the subtask, subtask delivery parts, template files corresponding to the subtask, subtask standard working hours and subtask acceptance standards. .
And the task distribution list comprises the working material information corresponding to the subtasks.
Based on the target project information generation method provided by the first aspect of the embodiment of the present application, optionally,
before the obtaining of the staff allocation information corresponding to the subtask, the method further includes:
screening candidate personnel based on the task requirements of the subtasks to obtain pre-screened personnel;
and displaying the pre-screening personnel corresponding to the subtasks.
Based on the target project information generation method provided by the first aspect of the embodiment of the present application, optionally,
the method further comprises the following steps:
establishing a general scene item attribute library, wherein the general scene item attribute library comprises a plurality of project scenes and subtasks of the project scenes;
the obtaining of the subtask corresponding to the target project scenario based on the target project scenario query includes:
and inquiring in the general scene item attribute library based on the target item scene to obtain a subtask corresponding to the target item scene.
A second aspect of the embodiments of the present application provides a target item information generating apparatus, including:
the project scene acquisition unit is used for acquiring a target project scene;
the query unit is used for obtaining the subtask corresponding to the target project scene based on the target project scene query;
the personnel information acquisition unit is used for acquiring personnel allocation information corresponding to the subtasks;
and the generating unit is used for generating a task distribution list based on the personnel distribution information.
Based on the target item information generation apparatus provided in the second aspect of the embodiment of the present application, optionally,
the target project information comprises a task distribution list, and the task distribution list comprises the execution sequence of the subtasks.
Based on the target item information generation apparatus provided in the second aspect of the embodiment of the present application, optionally,
the query unit is specifically configured to: acquiring subtasks corresponding to the target project scene and working hour information corresponding to each subtask based on the target project scene query;
and the task distribution list comprises the working hour information corresponding to the subtasks.
Based on the target item information generating apparatus provided in the second aspect of the embodiment of the present application, optionally, the target item information generating apparatus further includes:
a project man-hour obtaining unit for obtaining project man-hours;
and the project work hour adjusting unit is used for adjusting the work hours corresponding to the sub-tasks based on the project work hours.
Based on the target item information generation apparatus provided in the second aspect of the embodiment of the present application, optionally,
the query unit is specifically configured to: obtaining subtasks corresponding to the target project scene and required working material information corresponding to each subtask based on the target project scene query, wherein the required working material information comprises: the task management system comprises one or more of role information corresponding to subtasks, subtask delivery parts, template files corresponding to subtasks, subtask standard working hours and subtask acceptance standards;
and the task distribution list comprises the working material information corresponding to the subtasks.
Based on the target item information generating apparatus provided in the second aspect of the embodiment of the present application, optionally, the target item information generating apparatus further includes:
the personnel pre-screening unit is used for screening candidate personnel based on the task requirements of the subtasks to obtain pre-screened personnel;
and displaying the pre-screening personnel corresponding to the subtasks.
Based on the target item information generating apparatus provided in the second aspect of the embodiment of the present application, optionally, the target item information generating apparatus further includes: the system comprises a scene item attribute library establishing unit, a task item attribute library creating unit and a task executing unit, wherein the scene item attribute library establishing unit is used for establishing a general scene item attribute library, and the general scene item attribute library comprises a plurality of project scenes and subtasks of the project scenes;
the query unit is specifically configured to: and inquiring in the general scene item attribute library based on the target item scene to obtain the subtask corresponding to the target item scene.
A third aspect of embodiments of the present application provides a computer device, including:
a central processing unit, a memory;
the memory is a transient memory or a persistent memory;
the central processor is configured to communicate with the memory, and execute the instruction operations in the memory on the people counting device to perform the method according to any one of the first aspect of the embodiments of the present application.
A fourth aspect of embodiments of the present application provides a computer-readable storage medium, comprising instructions, which, when executed on a computer, cause the computer to perform the method according to any one of the first aspect of embodiments of the present application.
A fifth aspect of embodiments of the present application provides a computer program product containing instructions, which when executed on a computer, cause the computer to perform the method according to any one of the first aspect of embodiments of the present application.
According to the technical scheme, the embodiment of the application has the following advantages: the project scene is obtained to obtain corresponding subtasks in the project scene, a user distributes proper personnel to each subtask, target project information is generated based on each subtask and the distributed personnel information, the distribution process of each task under the project is clearer through the target project information, the task distribution efficiency is improved, and the problem that certain tasks are not distributed with personnel or are distributed unclear in the project execution process is solved.
Drawings
In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the drawings needed to be used in the description of the embodiments or the prior art will be briefly introduced below, it is obvious that the drawings in the following description are only embodiments of the present application, and for those skilled in the art, other drawings can be obtained according to the provided drawings without creative efforts.
FIG. 1 is a schematic flow chart diagram illustrating an embodiment of a method for generating target project information according to the present application;
FIG. 2 is another schematic flow chart diagram illustrating an embodiment of a method for generating target project information according to the present application;
FIG. 3 is a schematic structural diagram of an embodiment of an apparatus for generating target item information according to the present application;
fig. 4 is another schematic structural diagram of an embodiment of a target item information generating apparatus according to the present application.
Detailed Description
In order to make the objects, technical solutions and advantages of the present application more apparent, the present application is described in further detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the present application and are not intended to limit the present application. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present application.
The terms "first," "second," "third," "fourth," and the like in the description and in the claims of the present application and in the above-described drawings (if any) are used for distinguishing between similar elements and not necessarily for describing a particular sequential or chronological order. It will be appreciated that the data so used may be interchanged under appropriate circumstances such that the embodiments described herein may be practiced otherwise than as specifically illustrated or described herein. Furthermore, the terms "comprises," "comprising," and "having," and any variations thereof, are intended to cover a non-exclusive inclusion, such that a process, method, system, article, or apparatus that comprises a list of steps or elements is not necessarily limited to those steps or elements expressly listed, but may include other steps or elements not expressly listed or inherent to such process, method, article, or apparatus.
It should be noted that the descriptions in this application referring to "first", "second", etc. are for descriptive purposes only and are not to be construed as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, a feature defined as "first" or "second" may explicitly or implicitly include at least one such feature. In addition, technical solutions between the various embodiments may be combined with each other, but must be based on the realization of the capability of a person skilled in the art, and when the technical solutions are contradictory or cannot be realized, the combination of the technical solutions should be considered to be absent and not be within the protection scope of the present application.
Referring to fig. 1, an embodiment of a method for generating target item information of the present application includes: step 101-step 105.
101. And acquiring a target project scene.
Acquiring a target project scene, and presetting different project scenes for different projects, such as: management Project (MP) Technical Development Project (TD), Technical Pre-Research Project (TR), sales Project (lead to case, LTC), Integrated Product Development Project (IPD), Custom Development Project (CD), Product Configuration Project (PC), Agile Development Project (AD), Technical Development Project (TD), Product Pre-Research Project (PR), Market Management Project (Market Management, GP), Growth Project (Growth Project, GP), Innovation Project (IP), etc., based on which a corresponding Project can be set, and corresponding scene information can be stored in a database as a scene information for a user to execute, and based on a scene information for a scene, a Project that is desired to be selected, and a scene information for a user to use, and so on The project scenario is not limited herein.
102. And acquiring a subtask corresponding to the target project scene based on the target project scene query.
And acquiring a subtask corresponding to the target project scene based on the target project scene query. After a target project scene selected by a user is acquired, a corresponding subtask in the project scene can be acquired based on the target project scene query, and for any project, the method generally comprises the following steps: and (4) planning the project. The three major subtasks of project implementation and project delivery can be further subdivided into a plurality of subtasks for different project scenarios, and meanwhile, a specific subtask different from other project scenarios can exist in each project scenario, for example, for a technical pre-research project, a pre-research report writing subtask also exists between project implementation and project delivery, and after project delivery, the subtask may also include work result introduction, technical review and the like, so that if a user selects a project scenario of the technical pre-research project, the corresponding to the technical pre-research project scenario can be correspondingly obtained: and (3) making a technical pre-research plan, and implementing seven subtasks of a technical pre-research project, writing a pre-research report, delivering the technical pre-research project, introducing a work result and evaluating the technology. It can be understood that there is a difference between the subtasks corresponding to different project scenarios, and specifically, each project scenario and the subtask corresponding to each project scenario may be stored in the database in an associated manner, so that the user may query and obtain the corresponding subtask after determining the project scenario, which is not limited herein.
It can be understood that, in a certain project scenario, there may be a precedence relationship in execution between the corresponding sub-tasks, and there may also be simultaneously executable sub-tasks, for example, in the above technical pre-research scenario. The execution sequence of the technical pre-research plan subtasks and the execution sequence of the technical pre-research project subtasks are established, the work result introduction subtasks and the technical review subtasks can be executed simultaneously, and after the subtasks corresponding to the target project scene are obtained, the subtasks can be sequenced according to the execution sequence of the subtasks and provided for the user, so that the user can better master the project execution condition, and the execution of the subsequent task distribution list generation process is facilitated.
It is noted that information related to the subtasks may be correspondingly stored for the subtasks stored in a project scenario, such as man-hours required to complete the subtasks, project materials required to perform the subtasks. The information such as the completion standard for determining whether the subtask is completed or not may be stored in the corresponding database or data table in association with the subtask, so as to perform the subsequent task distribution list generation process.
103. And acquiring the personnel allocation information corresponding to the subtasks.
And acquiring the personnel allocation information corresponding to the subtasks. Specifically, after the subtasks corresponding to the target project scenario are acquired, the user may allocate an executive staff to each subtask according to the task requirement of the subtask, for example, a responsible person is set for each subtask, so that the responsible person is determined to deliver the task based on the responsibility during subsequent project management and control. Meanwhile, a plurality of actual workers under the responsible person can be obtained, if a certain subtask is set to be responsible for the first person, the actual workers are set to be four workers of the first person, the second person, the third person and the fourth person to cooperate to complete the task, and it is worth noting that when the workers are distributed, a group or a department can be set to complete without setting specific workers, if a certain subtask is set to be completed by a first group or a financial department, the setting can be specifically determined according to actual conditions, and the setting is not limited here.
It can be understood that, when the user selects the staff corresponding to the subtask, the system can preliminarily screen the staff selectable by the user in advance, for example, when the system is applied to a technical pre-research project scene, the staff whose positions are salesmen or financial staff in company staff can be removed, and only the staff list in charge of technical work is provided for the user to select, so that the user can reduce the information to be processed, the efficiency of the staff allocation process is improved, and the system can be specifically determined according to the actual situation, and is not limited herein.
104. And generating target project information based on the subtasks and the staff allocation information corresponding to the subtasks.
And generating target project information based on the subtasks and the staff allocation information corresponding to the subtasks. The specific target project information comprises a task distribution list corresponding to a target project scene, and the task distribution list is generated based on personnel distribution information input by a user, wherein the specific task distribution list can comprise the name of the target project scene, subtasks corresponding to the project scene and personnel information correspondingly distributed for completing each subtask. It is understood that the task allocation list may further include time information for completing the task, and the specific time information may include time length information such as three working days, two weeks, and the like, and may also include specific date information such as 26 days 10/26 days 2020 to 28 days 10/28 months 2020, and the specific time information may be adjusted according to the actual situation. Meanwhile, the task allocation list may further include information such as data required in the execution process of each sub-task, a task result obtained after completion, and the like, and information such as importance degree, evaluation standard, task description, and the like of each sub-task, which may be determined specifically according to the actual situation, and is not limited herein.
According to the technical scheme, the embodiment of the application has the following advantages: the project scene is obtained to obtain corresponding subtasks in the project scene, a user distributes proper personnel to each subtask, target project information is generated based on each subtask and the distributed personnel information, the distribution process of each task under the project is clearer through the target project information, the task distribution efficiency is improved, and the problem that certain tasks are not distributed with personnel or are distributed unclear in the project execution process is solved.
Based on the embodiment provided in fig. 1, the present application further provides a more detailed embodiment, and specifically referring to fig. 2, the method for generating target item information includes:
201. and establishing a general scene item attribute library.
And establishing a general scene item attribute library. The general scene item attribute library comprises a plurality of project scenes and subtasks of the project scenes, and specifically, the scene item attribute library can comprise a plurality of project scenes, such as MP operation management, TR technology pre-research, IPD integrated product development, LTC sales, MM market management, AD agile development and the like, the scene item attribute library comprises fields of record ID, record father ID, scenes, attribute names, attribute descriptions, tags, creators, creation dates, modification dates and the like, and is used for representing the corresponding relation between each scene item and the subtask and information of the creators, creation dates, modification dates, specific attributes of the scene items, tags and the like of each scene item, and a user can complete the generation process of a task distribution list based on the scene item attribute library.
202. And acquiring a target project scene.
Specifically, because there are many project scenes, the project scenes can be classified according to the industries to which the project scenes belong, and the user can select the industries to which the projects belong first, such as: the IT industry, the design industry, the medical and medical industry, the financial industry, the accounting service industry, the electromechanical engineering industry, the building engineering industry, the light current engineering industry and the like. And selecting a certain project scene as a target project scene under the selected target industry. More specific application scenarios such as a management project scenario, a technology development project scenario, a technology pre-research project scenario, a sales project scenario, an integrated product development project scenario, a customized development project scenario, a product configuration project scenario, an agile development project scenario, a product pre-research project scenario, a market management project scenario, a growth project scenario, an innovation project scenario, and the like are selected in the IT industry.
Meanwhile, after the target project scene selected by the user is acquired, the ID, the name and the current date of the user can be stored as part of project information. The specific conditions may be determined according to actual conditions, and are not limited herein.
203. And acquiring subtasks corresponding to the target project scene and required working material information corresponding to each subtask based on the target project scene query.
And acquiring the subtasks corresponding to the target project scene and the required working material information corresponding to each subtask based on the target project scene query. Specifically, the query can be performed in the scene item attribute library according to the target item scene, and the subtasks corresponding to the target item scene and the required work material information corresponding to each subtask are obtained. Different subtasks are executed at different times for a project scenario comprising a plurality of subtasks, but can be roughly divided into several phases, each of which comprises a plurality of subtasks. The work material information required by the subtasks includes: information such as task name, phase to which the task belongs, schedule start time, schedule finish time, task number, principal role, importance degree, task score, task tool, standard duration, deliverable template, task description, task knowledge, task status, task progress, task acceptance standard, task attachment, custom task field, and the like. The work material information is used for assisting completion of the subtasks, and the specific types of the work material information can be added or deleted according to different types of target project scenes or subtasks, and can be specifically determined according to actual situations, which is not limited herein. It can be understood that, in the actual implementation process of the scheme, the content corresponding to the work material information may be obtained by presetting a scene item attribute library, or may be automatically filled and modified by the user. The working material information is set through different fields, and a user can modify each field according to the requirement of the user, and can additionally add or delete the fields. The specific situation can be determined according to the actual situation, and is not limited herein.
204. And acquiring project working hours.
And acquiring project working hours which can be preset by the system, such as taking the current date as project starting time and taking project ending time after three months. However, the project time required for different projects is often uncertain, and needs to be adjusted based on external factors, so that the user can set the project time, the specific project start time and project end time, or the duration of the project, which may be determined according to the actual situation, and is not limited herein.
205. And adjusting the working hours corresponding to the subtasks based on the project working hours.
And adjusting the working hours corresponding to the subtasks based on the project working hours. Specifically, the system can set preset working hours for corresponding project scenes and corresponding subtasks under the project scenes, and after the actual project working hours set by the user are obtained, the working hours required by each subtask in the project are adjusted based on the equal proportion of the difference between the actual project working hours and the preset working hours. And the man-hour distributed by each subtask meets the actual project man-hour requirement. Similarly, when the actual project time is larger than the preset time, the time corresponding to each subtask can be lengthened in equal proportion. It can be understood that, when the man-hours corresponding to the subtasks are adjusted, the user may also manually adjust the man-hours corresponding to the subtasks, and if a certain subtask is important, the work period of the subtask is not adjusted, but other subtasks are adjusted, which may be specifically adjusted according to the actual situation, and is not limited herein.
206. And screening candidate personnel based on the task requirements of the subtasks to obtain pre-screened personnel.
And screening candidate personnel based on the task requirements of the subtasks to obtain pre-screened personnel. Specifically, the system can pre-construct a personnel information database used in a company, wherein the personnel information database comprises information such as personnel names, positions of personnel, working contents corresponding to the personnel and the like. The system can carry out pre-screening according to the information stored in the personnel information database and factors in aspects such as task requirements, execution conditions, knowledge required by task execution and the like, wherein the task requirements are as follows: the staff of the planning department can carry out the subtask, the staff can be screened, the staff information of all the staff of the planning department is obtained after screening and serves as pre-screening staff to be provided for the user, and therefore the user is prevented from processing a large amount of staff information, the processing speed of the scheme is improved, and the usability of the scheme is improved.
207. And displaying the pre-screening personnel corresponding to the subtasks.
And displaying the pre-screening personnel corresponding to the subtasks. And displaying the pre-screening personnel corresponding to the subtask to a user, wherein the pre-screening personnel are personnel qualified for executing the subtask, so that the personnel allocation efficiency is improved by the user based on the pre-screening personnel selection personnel allocation, and the generation efficiency of the task allocation list is improved.
208. And acquiring the personnel allocation information corresponding to the subtasks.
And acquiring the personnel allocation information corresponding to the subtasks. Specifically, after the subtasks corresponding to the target project scenario are acquired, the user may select an actual executive person from the pre-screening staff according to the task requirements of each subtask, for example, a responsible person is set for each subtask, so that the responsible person is determined to deliver the task based on the responsibility during subsequent project management and control.
209. And generating a task distribution list based on the subtasks and the staff distribution information corresponding to the subtasks.
And generating a task distribution list based on the subtasks and the staff distribution information corresponding to the subtasks. The task allocation list comprises the execution sequence of the subtasks, the working material information corresponding to the subtasks and the working hour information corresponding to the subtasks. It will be appreciated that the task allocation manifest may also include a description of the entire project scenario as well as descriptions and detailed information for each subtask, the subtask required work material information including: task name, phase of belonging, schedule start time, schedule finish time, task number, principal role, importance degree, task score, task tool, standard duration, deliverable template, task description, task knowledge, task state, task progress, task acceptance standard, task attachment, custom task field, etc. The work material information is used for assisting completion of the subtasks, and the types of the specific work material information can be added or deleted according to different types of target project scenes or subtasks, and can be specifically determined according to actual situations, which is not limited herein. The fields set and edited by the user for each subtask before the task allocation list is generated can also be displayed in the task allocation list, so that the staff can better understand the task content, and the method can be specifically determined according to the actual situation, and is not limited herein.
According to the technical scheme, the embodiment of the application has the following advantages: the scheme provides a target project information generation method, subtasks corresponding to a project scene are obtained through the project scene, a user distributes proper personnel to each subtask, a task distribution list is generated based on each subtask and the distributed personnel information, each task distribution process under the project is clearer through the task list, the task distribution efficiency is improved, and the problem that certain tasks are not distributed with personnel or are distributed unclear in the project execution process is solved.
The above describes a target item information generation method in the application example, and the following describes a target item information generation apparatus in the embodiment of the present invention. Referring to fig. 3, an embodiment of the present application includes:
an item scene acquisition unit 301 for acquiring an item scene;
a query unit 302, configured to obtain a subtask corresponding to the target item scenario based on the target item scenario query;
a staff information obtaining unit 303, configured to obtain staff allocation information corresponding to the subtask;
a generating unit 304, configured to generate target task information based on the staff allocation information.
In this embodiment, the flow executed by each unit in the target item information generating apparatus is similar to the method flow described in the embodiment corresponding to fig. 1, and is not described herein again.
Optionally, the target item information includes a task allocation list, and the task allocation list includes an execution sequence of the subtasks.
Optionally, the querying unit 302 is specifically configured to: acquiring subtasks corresponding to the target project scene and working hour information corresponding to each subtask based on the target project scene query;
and the task distribution list comprises the working hour information corresponding to the subtasks.
Optionally, the target item information generating apparatus further includes:
a project man-hour obtaining unit for obtaining project man-hours;
and the project work hour adjusting unit is used for adjusting the work hours corresponding to the sub-tasks based on the project work hours.
Optionally, the querying unit 302 is specifically configured to: acquiring subtasks corresponding to the target project scene and required working material information corresponding to each subtask based on the target project scene query, wherein the required working material information comprises: and any one or more of role information corresponding to the subtask, subtask delivery parts, template files corresponding to the subtask, subtask standard working hours and subtask acceptance standards.
And the task distribution list comprises the working material information corresponding to the subtasks.
Optionally, the target item information generating apparatus further includes:
the personnel pre-screening unit is used for screening candidate personnel based on the task requirements of the subtasks to obtain pre-screened personnel;
and displaying the pre-screening personnel corresponding to the subtasks.
Optionally, the target item information generating apparatus further includes: the system comprises a scene item attribute library establishing unit, a task item attribute library creating unit and a task item attribute library creating unit, wherein the scene item attribute library establishing unit is used for establishing a general scene item attribute library which comprises a plurality of project scenes and subtasks of the project scenes;
the query is specifically for: and inquiring in the general scene item attribute library based on the target item scene to obtain a subtask corresponding to the target item scene.
Fig. 4 is a schematic structural diagram of a target project information generating apparatus according to an embodiment of the present disclosure, where the server 400 may include one or more Central Processing Units (CPUs) 401 and a memory 405, and the memory 405 stores one or more application programs or data.
In this embodiment, the specific functional module division in the central processing unit 401 may be similar to the functional module division manner of each unit described in the foregoing fig. 4, and is not described here again.
Memory 405 may be volatile storage or persistent storage, among other things. The program stored in memory 405 may include one or more modules, each of which may include a sequence of instructions operating on a server. Still further, the central processor 401 may be arranged to communicate with the memory 405, and to execute a series of instruction operations in the memory 405 on the server 400.
The server 400 may also include one or more power supplies 402, one or more wired or wireless network interfaces 403, one or more input-output interfaces 404, and/or one or more operating systems, such as Windows Server, Mac OS XTM, UnixTM, LinuxTM, FreeBSDTM, etc.
The central processing unit 401 may perform the operations performed by the target item information generating method in the embodiment shown in fig. 1, which are not described herein again.
The present invention also provides a computer-readable storage medium for implementing the functions of the target project information generation method, on which a computer program is stored, which, when executed by a processor, the processor may be adapted to perform the method as described in fig. 1.
It will be appreciated that the integrated units, if implemented in the form of software functional units and sold or used as a stand-alone product, may be stored in a corresponding one of the computer readable storage media or integrated as a computer program product for performing the above-described method. Based on such understanding, all or part of the flow of the method according to the above embodiments may be implemented by a computer program, which may be stored in a computer-readable storage medium and used by a processor to implement the steps of the above embodiments of the method. Wherein the computer program comprises computer program code, which may be in the form of source code, object code, an executable file or some intermediate form, etc. The computer-readable medium may include: any entity or device capable of carrying the computer program code, recording medium, usb disk, removable hard disk, magnetic disk, optical disk, computer Memory, Read-Only Memory (ROM), Random Access Memory (RAM), electrical carrier wave signals, telecommunications signals, software distribution medium, and the like. It should be noted that the computer readable medium may contain content that is subject to appropriate increase or decrease as required by legislation and patent practice in jurisdictions, for example, in some jurisdictions, computer readable media does not include electrical carrier signals and telecommunications signals as subject to legislation and patent practice.
The integrated unit, if implemented in the form of a software functional unit and sold or used as a stand-alone product, may be stored in a computer readable storage medium. Based on such understanding, the technical solution of the present invention may be embodied in the form of a software product, which is stored in a storage medium and includes several instructions for causing a computer device (which may be a personal computer, a server, or a network device) to execute all or part of the steps of the method according to the embodiments of the present invention. And the aforementioned storage medium includes: a U-disk, a removable hard disk, a Read-Only Memory (ROM), a Random Access Memory (RAM), a magnetic disk, an optical disk, or other various media capable of storing program codes.
It is clear to those skilled in the art that, for convenience and brevity of description, the specific working processes of the above-described systems, apparatuses and units may refer to the corresponding processes in the foregoing method embodiments, and are not described herein again.
In the several embodiments provided in the present application, it should be understood that the disclosed system, apparatus and method may be implemented in other manners. For example, the above-described apparatus embodiments are merely illustrative, and for example, the division of the units is only one logical functional division, and in actual implementation, there may be other divisions, for example, multiple units or components may be combined or integrated into another system, or some features may be omitted, or not executed. In addition, the shown or discussed mutual coupling or direct coupling or communication connection may be an indirect coupling or communication connection through some interfaces, devices or units, and may be in an electrical, mechanical or other form.
The units described as separate parts may or may not be physically separate, and parts displayed as units may or may not be physical units, may be located in one place, or may be distributed on a plurality of network units. Some or all of the units can be selected according to actual needs to achieve the purpose of the solution of the embodiment.
In addition, functional units in the embodiments of the present application may be integrated into one processing unit, or each unit may exist alone physically, or two or more units are integrated into one unit. The integrated unit can be realized in a hardware form, and can also be realized in a software functional unit form.
The above-mentioned embodiments are only used for illustrating the technical solutions of the present invention, and not for limiting the same; although the present invention has been described in detail with reference to the foregoing embodiments, it should be understood by those skilled in the art that: the technical solutions described in the foregoing embodiments may still be modified, or some technical features may be equivalently replaced; and such modifications or substitutions do not depart from the spirit and scope of the corresponding technical solutions of the embodiments of the present invention.

Claims (10)

1. A method for generating target item information, comprising:
acquiring a target project scene;
obtaining a subtask corresponding to the target project scene based on the target project scene query;
acquiring personnel allocation information corresponding to the subtasks;
and generating target project information based on the subtasks and the staff allocation information corresponding to the subtasks.
2. The method for generating the target project information according to claim 1, wherein the target project information includes a task allocation list, and the task allocation list includes an execution sequence of subtasks.
3. The method for generating the target project information according to claim 2, wherein the obtaining of the subtask corresponding to the target project scenario based on the target project scenario query includes:
acquiring subtasks corresponding to the target project scene and working hour information corresponding to each subtask based on the target project scene query;
and the task distribution list comprises the working hour information corresponding to the subtasks.
4. The method for generating target item information according to claim 3, wherein before generating a task allocation list based on the subtasks and the staff allocation information corresponding to the subtasks, the method further comprises:
acquiring project working hours;
and adjusting the working hours corresponding to the subtasks based on the project working hours.
5. The target item information generating method according to claim 2,
obtaining a subtask corresponding to the target project scenario based on the target project scenario query, including:
obtaining subtasks corresponding to the target project scene and required working material information corresponding to each subtask based on the target project scene query, wherein the required working material information comprises: any one or more of role information corresponding to the subtask, subtask delivery parts, template files corresponding to the subtask, subtask standard working hours and subtask acceptance standards;
and the task distribution list comprises the working material information corresponding to the subtasks.
6. The target item information generating method according to claim 2,
before the obtaining of the staff allocation information corresponding to the subtask, the method further includes:
screening candidate personnel based on the task requirements of the subtasks to obtain pre-screened personnel;
and displaying the pre-screening personnel corresponding to the subtasks.
7. The method of generating target item information according to claim 1, further comprising:
establishing a general scene item attribute library, wherein the general scene item attribute library comprises a plurality of project scenes and subtasks corresponding to the project scenes;
the obtaining of the subtask corresponding to the target project scenario based on the target project scenario query includes:
and inquiring in the general scene item attribute library based on the target item scene to obtain a subtask corresponding to the target item scene.
8. A target item information generating apparatus, comprising:
the project scene acquisition unit is used for acquiring a target project scene;
the query unit is used for obtaining the subtask corresponding to the target project scene based on the target project scene query;
the personnel information acquisition unit is used for acquiring personnel allocation information corresponding to the subtasks;
and the generating unit is used for generating target project information based on the subtasks and the personnel allocation information.
9. A computer device, comprising:
a central processing unit, a memory;
the memory is a transient memory or a persistent memory;
the central processor is configured to communicate with the memory, the instructions in the memory being executable on the computer to perform the method of any of claims 1-7.
10. A computer-readable storage medium comprising instructions that, when executed on a computer, cause the computer to perform the method of any one of claims 1-7.
CN202011190704.1A 2020-10-30 2020-10-30 Target project information generation method and related equipment Pending CN112308516A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011190704.1A CN112308516A (en) 2020-10-30 2020-10-30 Target project information generation method and related equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011190704.1A CN112308516A (en) 2020-10-30 2020-10-30 Target project information generation method and related equipment

Publications (1)

Publication Number Publication Date
CN112308516A true CN112308516A (en) 2021-02-02

Family

ID=74332845

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011190704.1A Pending CN112308516A (en) 2020-10-30 2020-10-30 Target project information generation method and related equipment

Country Status (1)

Country Link
CN (1) CN112308516A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113642924A (en) * 2021-08-30 2021-11-12 北京沃东天骏信息技术有限公司 Service resource matching method and device
CN113988526A (en) * 2021-09-28 2022-01-28 南方电网深圳数字电网研究院有限公司 Management method and device for diversified tasks

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20030236692A1 (en) * 2002-05-29 2003-12-25 Martin Hertel-Szabadi Project workforce management
CN102663554A (en) * 2012-04-11 2012-09-12 北京航空航天大学 Procedure customization method for project management
CN107609721A (en) * 2016-07-11 2018-01-19 上海新昇半导体科技有限公司 Project task distribution method, device, computer equipment and project management system
CN111476479A (en) * 2020-04-02 2020-07-31 网易(杭州)网络有限公司 Method, device and system for distributing tasks

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20030236692A1 (en) * 2002-05-29 2003-12-25 Martin Hertel-Szabadi Project workforce management
CN102663554A (en) * 2012-04-11 2012-09-12 北京航空航天大学 Procedure customization method for project management
CN107609721A (en) * 2016-07-11 2018-01-19 上海新昇半导体科技有限公司 Project task distribution method, device, computer equipment and project management system
CN111476479A (en) * 2020-04-02 2020-07-31 网易(杭州)网络有限公司 Method, device and system for distributing tasks

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113642924A (en) * 2021-08-30 2021-11-12 北京沃东天骏信息技术有限公司 Service resource matching method and device
CN113988526A (en) * 2021-09-28 2022-01-28 南方电网深圳数字电网研究院有限公司 Management method and device for diversified tasks

Similar Documents

Publication Publication Date Title
US7788237B2 (en) Method and system for tracking changes in a document
US6256651B1 (en) Time management workflow software
US6801820B1 (en) Method and apparatus for scheduling work orders in a manufacturing process
US20060106872A1 (en) Active agenda
US20160140501A1 (en) Collaborative project execution in the cloud
US20020062239A1 (en) Program planning management system
US20160070258A1 (en) Method for increasing the work performance of a manufacturing executing system (mes) and an enterprise resource planning system (erp)
US8280756B1 (en) Milestone initial scheduling
CN108764610A (en) Standard technology construction management of project method based on big data, storage medium
CN112308516A (en) Target project information generation method and related equipment
US20040083238A1 (en) Method, system, and storage medium for integrating project management tools
US8108232B1 (en) System and method for project contract management
KR102151550B1 (en) Method and apparatus for assisting strategy map management based on schedule-assessment item and todo-assessment item
KR20180013474A (en) Method and apparatus for assisting strategy map management based on schedule-assessment item and todo-assessment item
JPS59214964A (en) Conversational scheduling system
JP2000039904A (en) Project management system
US20100205225A1 (en) Method and Apparatus for Transforming a Process
US20060282241A1 (en) System modeling facilitating method and apparatus
CN116151582A (en) Automatic version scheduling method and device based on resource identification and storage medium
WO1994016397A2 (en) Method of enterprise-wide to do list scheduling
US7310562B2 (en) System and method for scheduling mold manufacturing
JP2006146530A (en) Scheduling support system
JPH0373257A (en) Production scheduling device
US9569257B2 (en) Method and system to perform time consuming follow-up processes
JP4318162B2 (en) Production schedule planning management method and production schedule planning management program

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20210202