CN106836183A - A kind of Embankment Foundation soil layer plastic draining structure and its construction method - Google Patents

A kind of Embankment Foundation soil layer plastic draining structure and its construction method Download PDF

Info

Publication number
CN106836183A
CN106836183A CN201710094603.6A CN201710094603A CN106836183A CN 106836183 A CN106836183 A CN 106836183A CN 201710094603 A CN201710094603 A CN 201710094603A CN 106836183 A CN106836183 A CN 106836183A
Authority
CN
China
Prior art keywords
plastic draining
water
draining board
board
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710094603.6A
Other languages
Chinese (zh)
Other versions
CN106836183B (en
Inventor
刘学应
陈芃
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Tengtou Water Construction Co ltd
Original Assignee
Zhejiang University of Water Resources and Electric Power
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang University of Water Resources and Electric Power filed Critical Zhejiang University of Water Resources and Electric Power
Priority to CN201710094603.6A priority Critical patent/CN106836183B/en
Publication of CN106836183A publication Critical patent/CN106836183A/en
Application granted granted Critical
Publication of CN106836183B publication Critical patent/CN106836183B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/02Improving by compacting
    • E02D3/10Improving by compacting by watering, draining, de-aerating or blasting, e.g. by installing sand or wick drains

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Agronomy & Crop Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Soil Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

The invention discloses a kind of Embankment Foundation soil layer plastic draining structure and its construction method, including vacuum pumping box and at least two plastic draining boards, connected by horizontal water-supply-pipe between two neighboring plastic draining board, four-way valve is provided with horizontal water-supply-pipe, rubber cover plate is provided with the top surface of plastic draining board, rubber cover plate connects vacuum pumping box by drinking-water pipe, is connected by being connected flexible pipe between two neighboring rubber cover plate, and drainpipe is provided with the top surface of vacuum pumping box.Its construction method includes:Surveying and locating, plastic draining structure are installed, fill sand gravel layer and block stone setting cushion.The inventive method can meet the Embankment Foundation soil consolidation construction of the different soft bases of soil property, have more reliable plastic draining system compared with traditional concretion method, quickly can extract the moisture in soil layer out, improve the consolidation strength of soil layer.

Description

A kind of Embankment Foundation soil layer plastic draining structure and its construction method
Technical field
The present invention relates to a kind of Embankment Foundation soil layer plastic draining structure and its construction method.
Background technology
With the fast development of China's southeastern coast economy, various forms of Sea-Crossing Passages arise at the historic moment.Build sea wall phase For bridge, tunnel, with low cost, provide and ship shielded area and can rationally utilize sea wall two ends cutting excavation stone Square the advantages of.
And coastal area is due to the influence of river emptying into the sea, seabed is generally Muddy Bottoms soft layer, with water content is big, compression Property high, low intensity, the features such as bad hydraulic permeability and soil layer are thick, growth period is postbacked not in the presence of levee body deadweight and building load Uniform settlement, influences the firmness of building.Therefore plastic draining board concretion method uses more and more extensive.
Plastic draining plate of the prior art construction, due to only by extruding the draining that soil layer is realized to soil layer, not only It is less efficient, and can not quickly by the moisture discharge in soil layer, while draining is not thorough enough.
The content of the invention
A kind of Embankment Foundation soil layer plastic row is provided present invention aim at for the deficiency existing for prior art The technical scheme of water-bound and its construction method, is attached by by vacuum pumping box and plastic draining board, not only increases Drainage channel, accelerates the expulsion efficiency of soil body moisture, and compared with existing plastic draining board, extrusion drainage and vacuum is arranged Water is combined, with more preferable drainage performance, while the construction method can meet the Embankment Foundation soil consolidation of the different soft bases of soil property Construction, has more reliable plastic draining system compared with traditional concretion method, quickly can extract the moisture in soil layer out, carries The consolidation strength of soil layer high.
In order to solve the above-mentioned technical problem, the present invention is adopted the following technical scheme that:
A kind of Embankment Foundation soil layer plastic draining structure, it is characterised in that:Moulded including vacuum pumping box and at least two Material drain bar, is connected between two neighboring plastic draining board by horizontal water-supply-pipe, and four-way valve is provided with horizontal water-supply-pipe, is moulded Rubber cover plate is provided with the top surface for expecting drain bar, rubber cover plate connects vacuum pumping box by drinking-water pipe, two neighboring Connected by being connected flexible pipe between rubber cover plate, drainpipe is provided with the top surface of vacuum pumping box;By by vacuum pumping box Be attached with plastic draining board, not only increase drainage channel, accelerate the expulsion efficiency of soil body moisture, and with existing modeling Material drain bar is compared, and extrusion drainage is combined with vacuum drainage, with more preferable drainage performance, improves consolidating for Embankment Foundation soil layer Knot speed and consolidation quality, horizontal water-supply-pipe can realize the transmission of moisture between adj acent plastic drain bar, make moisture not The same uniform draining of soil layer energy, improves the stability and reliability of whole Embankment Foundation soil layer, in the work of vacuum pumping box Under, the moisture in soil layer enters plastic draining board, the drainpipe output through rubber cover plate and drinking-water pipe from vacuum pumping box, The quick discharge of moisture is realized, when the water in plastic draining board is more, can be by adjacent plastic draining by being connected flexible pipe Water in plate is allocated, and is more uniformly distributed the carrying capacity of each drinking-water pipe, improves the efficiency of draining.
Further, permeable hole is evenly arranged with four lateral surfaces of plastic draining board, is provided with permeable hole permeable Film, wherein be provided with reinforcing plate muscle on two relative lateral surfaces, plastic draining board is internally provided with water delivery cavity, water delivery Core body is provided with cavity, core body matches with water delivery cavity, screwed hole is provided with four lateral surfaces of plastic draining board, Screwed hole is threadedly coupled with horizontal water-supply-pipe, and the top of plastic draining board is provided with step, and the water in soil layer can be by permeable Film enters in plastic draining board through permeable hole, prevents sandy soil from blocking permeable hole, improves the transfer efficiency of moisture, and reinforcing plate muscle is effective The intensity of plastic draining board is improve, makes plastic draining board more stable reliability during sinking, core body divides water delivery cavity Into multiple transfer passages, meet each passage and individually circulate, prevent local stoppages and influence the overall work of plastic draining board to imitate Removing and installing for horizontal water-supply-pipe is easy in rate, the design of screwed hole, prevents leak.
Further, the bottom of plastic draining board is provided with A-frame, and A-frame reduces plastic draining board and sinking During bottom and soil layer contact area, reduce the resistance of sinking, plastic draining board is more easily reached submergence depth, Improve flexibility during construction.
Further, core body includes substrate and deflector, and deflector Vertical Uniform is connected to the both sides up and down of substrate, substrate The first water hole is evenly arranged with bottom surface, the second water hole, the first water hole and the second water delivery are provided with the side of substrate Hole is mutually perpendicular to connection, and effectively can be separated for water delivery cavity by substrate and deflector, positioned at plastic draining board bottom Water enters rubber cover plate by the first water hole, and the water in two neighboring plastic draining board is defeated through first by the second water hole Water hole is delivered in rubber cover plate.
Further, vacuum cavity is provided with rubber cover plate, restraining position ring block is set on the bottom surface of vacuum cavity, spacing ring with Step matches, and the left and right sides of vacuum cavity is symmetrically arranged with water inlet interface, and being provided with water outlet on the top surface of rubber cover plate connects Mouthful, water outlet mouthpiece is connected with vacuum cavity, is buckled on step by spacing ring, realizes rubber cover plate with plastic draining board It is tightly connected, prevents from being influenceed because of gas leakage the transfer efficiency of moisture, and then influences the consolidation rate of Embankment Foundation, two neighboring rubber Water inlet interface is connected by being connected flexible pipe between glue cover plate, the mutual circulation of water is realized, drainage efficiency is improved.
Further, suction pump is provided with vacuum pumping box, at least three water inlet pipes is connected with the side of suction pump, entered Magnetic valve is provided with water pipe, the top surface of suction pump connects drainpipe by connection tube, by the design of magnetic valve, Ke Yi In time being cut off pipeline during leakage occurs in water inlet pipe, from the Pipeline transport water of other normal works, improves plastic draining knot The stability and reliability of structure.
A kind of Embankment Foundation soil layer described above construction method of plastic draining structure, it is characterised in that including following step Suddenly:
1) surveying and locating
A, area and shape first according to Embankment Foundation determine the construction location of plastic draining structure, and according to sea wall ground The soil property water content of base selects the size of corresponding plastic draining board;
B and then construction area is delineated in the relevant position of Embankment Foundation according to drawing, and the construction area is carried out clearly Reason, is transported after being tedded with the rooter topsoil thick to 50~80cm of the construction area surface with transport vehicle;
C, leveling treatment is then carried out with rammer compacter to construction area, and present situation soil matrix top surface after leveling lays one layer The geotextiles that size matches with construction area, will be fixed with anchor pole around geotextiles with ground, prevent mud from entering The sand gravel layer on top and influence drainage effect, while geotextiles use 250g/m2Polypropylene woven cloth, then in geotextiles Surface is determined the installation site of plastic draining board by the design requirement of drawing, and sprinkles white pulverized limestone as mark in respective regions Note, while stamping setting-out stake in the both sides of mark position;
2) plastic draining structure is installed
A, the center of the lifting rope of hoisting machine and plastic draining board is connected first, three are carried on plastic draining board One end of angle support is vertical down, and plastic draining board is hoisted to the mark position of construction area, then by plastic draining board At the uniform velocity transferred, until two sides of plastic draining board are clipped between setting-out stake, then on the top surface of plastic draining board One piece of thickness of covering is the baffle plate of 30cm, and main force's axle of board-plugging device is propped up into baffle plate, using the hydraulic pressure sinking device of board-plugging device, is made Board-plugging device main force axle it is synchronous with plastic draining board sink, until the top of the position that be connected with lifting rope of plastic draining board and setting-out Flush, untie lifting rope, and remove hoisting machine;
B then with board-plugging device continue inserting piling plastic draining board, the submergence depth of plastic draining board is reached design requirement Depth, the hydraulic means closed on board-plugging device, and main force's axle of board-plugging device is removed, and baffle plate is removed, while setting-out stake is extracted, use Clay is filled;
C, then core body is vertically loaded into plastic draining board it is fixed, makes the second water hole in substrate side surfaces and modeling Screwed hole alignment on material drain bar side, then installs rubber cover plate on the top surface of plastic draining board, with fluid sealant by rubber Encapsulation process is carried out at glue cover plate and the gap of plastic draining board;
D, after plastic draining board is installed and terminated, the construction of next plastic draining board is carried out with above-mentioned steps, until All Plastic Drain Slab Constructions in geotextiles terminate;
E, horizontal water-supply-pipe will be installed again between two adjacent plastic draining boards of back and forth or left and right, and in horizontal water-supply-pipe Center four-way valve is installed, connected by longitudinal water-supply-pipe between two neighboring four-way valve, make whole plastic draining structure It is distributed in spatial networks, will be attached by being connected flexible pipe between two adjacent rubber cover plates of left and right, and carry out at sealing Reason;
Horizontal stand is installed in f, the position of last 40~50cm above geotextiles, vacuum is installed on horizontal stand and is drawn water Case, and the rubber cover plate on each single plastic draining board is connected into vacuum pumping box by drinking-water pipe, and on rubber cover plate Another water outlet mouthpiece is attached by drinking-water pipe with the water outlet mouthpiece on adjacent rubber cover plate, prevents air directly from going out Water interface enters in plastic draining board, then by the top of vacuum pumping box by the externally connected water-storing device of drainpipe;
3) sand gravel layer is filled
After the installation of plastic draining structure terminates, sand gravel is laid in geotextiles, laying sand gravel is carried out in five times, from Under up every time laying thickness be followed successively by 10cm, 10cm, 20cm, 20cm and 20cm, lay ground floor when, by rubber cover plate On the junction of water outlet mouthpiece and drinking-water pipe laid with the sand gravel of 1~3cm of particle diameter, remaining position selection particle diameter is 5~8cm Sand gravel laying, until ground floor laying is finished, and remaining each layer is laid using the laying method of ground floor, until Sand gravel layer laying is finished;
4) block stone setting cushion
After sand gravel layer laying terminates, bagged sand first is covered around exposed vacuum pumping box, and drainpipe is erected Directly position, then dumped rocks protecting foundation, and properly protect.
The present invention is by adopting the above-described technical solution, have the advantages that:
1st, it is attached by by vacuum pumping box and plastic draining board, not only increases drainage channel, accelerates soil mass water The expulsion efficiency for dividing, and compared with existing plastic draining board, extrusion drainage is combined with vacuum drainage, with preferably row Aqueous energy, improves the consolidation rate and consolidation quality of Embankment Foundation soil layer;
2nd, horizontal water-supply-pipe can realize the transmission of moisture between adj acent plastic drain bar, make the soil layer that moisture is different The uniform draining of energy, improves the stability and reliability of whole Embankment Foundation soil layer;
3rd, in the presence of vacuum pumping box, the moisture in soil layer enters plastic draining board, through rubber cover plate and drinking-water pipe Drainpipe output from vacuum pumping box, realizes the quick discharge of moisture, when the water in plastic draining board is more, by rank Connecing flexible pipe can be allocated the water in adjacent plastic draining board, be more uniformly distributed the carrying capacity of each drinking-water pipe, improve The efficiency of draining;
4th, A-frame reduces the contact area of plastic draining board bottom and soil layer in sinking watching, reduces what is sunk Resistance, enables plastic draining board more easily to reach submergence depth, improves flexibility during construction;
5th, reinforcing plate muscle effectively increases the intensity of plastic draining board, makes plastic draining board more stable during sinking Reliable, water delivery cavity is divided into multiple transfer passages, meets each passage and individually circulate by core body, is prevented local stoppages and is influenceed modeling Expect the whole work efficiency of drain bar;
6th, construction method step of the invention is simple, can meet the Embankment Foundation soil consolidation construction of the different soft bases of soil property, There is more reliable plastic draining system compared with traditional concretion method, quickly can extract the moisture in soil layer out, improve soil The consolidation strength of layer.
Brief description of the drawings
The invention will be further described below in conjunction with the accompanying drawings:
Fig. 1 is plastic draining structure in a kind of Embankment Foundation soil layer plastic draining structure of the invention and its construction method Design sketch;
Fig. 2 is the connection diagram of plastic draining board in the present invention;
Fig. 3 is the structural representation of core body in the present invention;
Fig. 4 is the partial enlarged drawing at I in Fig. 2;
Fig. 5 is the structural representation of rubber cover plate in the present invention;
Fig. 6 is the structural representation of vacuum pumping box in the present invention.
In figure:1- plastic draining boards;2- vacuum pumping boxes;3- rubber cover plates;4- drinking-water pipes;5- drainpipes;6- linkings are soft Pipe;7- transverse direction water-supply-pipes;8- four-way valves;9- water delivery cavitys;10- reinforcing plate muscle;11- screwed holes;12- permeable holes;13- triangle branch Frame;14- core bodys;15- substrates;16- deflectors;The water holes of 17- first;The water holes of 18- second;19- steps;20- vacuum cavities; 21- water outlet mouthpieces;22- spacing rings;23- water inlet interfaces;24- suction pumps;25- water inlet pipes;26- magnetic valves;27- connection tubes.
Specific embodiment
As shown in Figures 1 to 6, it is a kind of Embankment Foundation soil layer plastic draining structure of the invention, including vacuum pumping box 2 With at least two plastic draining boards 1, connected by horizontal water-supply-pipe 7 between two neighboring plastic draining board 1, horizontal water-supply-pipe 7 On be provided with four-way valve 8, be evenly arranged with permeable hole 12 on four lateral surfaces of plastic draining board 1, is respectively provided with permeable hole 12 There is water permeable membrane, wherein be provided with reinforcing plate muscle 10 on two relative lateral surfaces, plastic draining board 1 is internally provided with water delivery Core body 14 is provided with cavity 9, water delivery cavity 9, core body 14 matches with water delivery cavity 9, core body 14 includes substrate 15 and water conservancy diversion Plate 16, the Vertical Uniform of deflector 16 is connected to the both sides up and down of substrate 15, and the first water delivery is evenly arranged with the bottom surface of substrate 15 Hole 17, is provided with the second water hole 18 on the side of substrate 15, the first water hole 17 is mutually perpendicular to connect with the second water hole 18, Effectively can be separated for water delivery cavity 9 by substrate 15 and deflector 16, and the water positioned at the bottom of plastic draining board 1 passes through first Water hole 17 enters rubber cover plate 3, and the water in two neighboring plastic draining board 1 passes through the second water hole 18 through the first water hole 17 are delivered in rubber cover plate 3, and screwed hole 11, screwed hole 11 and transverse direction are provided with four lateral surfaces of plastic draining board 1 Water-supply-pipe 7 is threadedly coupled, and the top of plastic draining board 1 is provided with step 19, and the water in soil layer can be by water permeable membrane through permeable Hole 12 enters in plastic draining board 1, prevents sandy soil from blocking permeable hole 12, improves the transfer efficiency of moisture, and reinforcing plate muscle 10 is effective The intensity of plastic draining board 1 is improve, makes the more stable reliability during sinking of plastic draining board 1, core body 14 is by water delivery chamber Body 9 is divided into multiple transfer passages, meets each passage and individually circulates, and prevents local stoppages and influences the entirety of plastic draining board 1 Removing and installing for horizontal water-supply-pipe 7 is easy in operating efficiency, the design of screwed hole 11, prevents leak, the bottom of plastic draining board 1 A-frame 13 is provided with, A-frame 13 reduces the contact area of plastic draining board 1 bottom and soil layer in sinking watching, Reduce the resistance of sinking, plastic draining board 1 is more easily reached submergence depth, improve flexibility during construction.
Rubber cover plate 3 is provided with the top surface of plastic draining board 1, rubber cover plate 3 connects vacuum and takes out by drinking-water pipe 4 Water tank 2, is provided with vacuum cavity 20 in rubber cover plate 3, sets restraining position ring block 22 on the bottom surface of vacuum cavity 20, spacing ring 22 with Step 19 matches, and the left and right sides of vacuum cavity 20 is symmetrically arranged with water inlet interface 23, is provided with the top surface of rubber cover plate 3 Water outlet mouthpiece 21, water outlet mouthpiece 21 is connected with vacuum cavity 20, is buckled on step 19 by spacing ring 22, realizes serum cap Plate 3 is tightly connected with plastic draining board 1, prevents from being influenceed because of gas leakage the transfer efficiency of moisture, and then influence Embankment Foundation Consolidation rate, water inlet interface 23 is connected between two neighboring rubber cover plate 3 by being connected flexible pipe 6, realizes the mutual circulation of water, is carried Drainage efficiency high.
Connected by being connected flexible pipe 6 between two neighboring rubber cover plate 3, draining is provided with the top surface of vacuum pumping box 2 Suction pump 24 is provided with pipe 5, vacuum pumping box 2, at least three water inlet pipes 25, water inlet pipe are connected with the side of suction pump 24 Magnetic valve 26 is provided with 25, the top surface of suction pump 24 connects drainpipe 5 by connection tube 27, by setting for magnetic valve 26 Meter, in time can cut off pipeline when water inlet pipe 25 occurs and leaking, and from the Pipeline transport water of other normal works, improve The stability and reliability of plastic draining structure;It is attached with plastic draining board 1 by by vacuum pumping box 2, is not only increased Drainage channel, accelerates the expulsion efficiency of soil body moisture, and compared with the existing plastic draining board 1, by extrusion drainage with it is true Idle discharge water is combined, and with more preferable drainage performance, improves the consolidation rate and consolidation quality of Embankment Foundation soil layer, horizontal water-supply-pipe 7 transmission that can realize moisture between adj acent plastic drain bar 1, enable the uniform draining of the different soil layer of moisture, improve The stability and reliability of whole Embankment Foundation soil layer, in the presence of vacuum pumping box 2, the moisture in soil layer enters plastics Drain bar 1, the drainpipe 5 through rubber cover plate 3 and drinking-water pipe 4 from vacuum pumping box 2 is exported, and realizes the quick discharge of moisture, When the water in plastic draining board 1 is more, the water in adjacent plastic draining board 1 can be allocated by being connected flexible pipe 6, The carrying capacity of each drinking-water pipe 4 is more uniformly distributed, the efficiency of draining is improved.
A kind of Embankment Foundation soil layer construction method of plastic draining structure described above, comprises the following steps:
1) surveying and locating
A, area and shape first according to Embankment Foundation determine the construction location of plastic draining structure, and according to sea wall ground The soil property water content of base selects the size of corresponding plastic draining board 1;
B and then construction area is delineated in the relevant position of Embankment Foundation according to drawing, and the construction area is carried out clearly Reason, is transported after being tedded with the rooter topsoil thick to 50~80cm of the construction area surface with transport vehicle;
C, leveling treatment is then carried out with rammer compacter to construction area, and present situation soil matrix top surface after leveling lays one layer The geotextiles that size matches with construction area, will be fixed with anchor pole around geotextiles with ground, prevent mud from entering The sand gravel layer on top and influence drainage effect, while geotextiles use 250g/m2Polypropylene woven cloth, then in geotextiles Surface is determined the installation site of plastic draining board 1 by the design requirement of drawing, and sprinkles white pulverized limestone conduct in respective regions Mark, while stamping setting-out stake in the both sides of mark position;
2) plastic draining structure is installed
A, first by the lifting rope of hoisting machine and plastic draining board 1 (technical standard of plastic draining board is as shown in table 1) Heart position is connected, on plastic draining board 1 one end with A-frame 13 vertically down, and by the handling of plastic draining board 1 To the mark position of construction area, then plastic draining board 1 is at the uniform velocity transferred, until two sides of plastic draining board 1 It is clipped between setting-out stake, it is the baffle plate of 30cm that one piece of thickness is then covered on the top surface of plastic draining board 1, by the master of board-plugging device Power axle props up baffle plate, using the hydraulic pressure sinking device of board-plugging device, makes the sinking synchronous with plastic draining board 1 of board-plugging device main force axle, directly Flushed with the top of setting-out stake to the position that plastic draining board 1 is connected with lifting rope, untie lifting rope, and remove hoisting machine;
B and then continue inserting piling plastic draining board 1 with board-plugging device, the submergence depth of plastic draining board 1 is reached design requirement Depth, the hydraulic means closed on board-plugging device, and remove main force's axle of board-plugging device removes baffle plate, while setting-out stake is extracted, It is filled with clay;
C, then core body 14 is vertically loaded into plastic draining board 1 it is fixed, makes the second water delivery on the side of substrate 15 Hole 18 is alignd with the screwed hole 11 on the side of plastic draining board 1, and rubber cover plate 3 is then installed on the top surface of plastic draining board 1, Encapsulation process will be carried out with fluid sealant at the gap of rubber cover plate 3 and plastic draining board 1;
D, after plastic draining board 1 is installed and terminated, the construction of next plastic draining board 1 is carried out with above-mentioned steps, directly The construction of all plastic draining boards 1 on to geotextiles terminates;
E, horizontal water-supply-pipe 7 will be installed again between two adjacent plastic draining boards 1 of back and forth or left and right, and in horizontal water delivery Four-way valve 8 is installed in the center of pipe 7, is connected by longitudinal water-supply-pipe between two neighboring four-way valve 8, makes whole plastic draining Structure is distributed in spatial networks, will be attached by being connected flexible pipe 6 between two adjacent rubber cover plates 3 of left and right, and carry out Encapsulation process;
Horizontal stand is installed in f, the position of last 40~50cm above geotextiles, vacuum is installed on horizontal stand and is drawn water Case 2, and the rubber cover plate 3 on each single plastic draining board 1 is connected into vacuum pumping box 2 by drinking-water pipe 4, and serum cap Another water outlet mouthpiece 21 is attached by drinking-water pipe 4 with the water outlet mouthpiece 21 on adjacent rubber cover plate 3 on plate 3, is prevented Air directly enters in plastic draining board 1 from water outlet mouthpiece 21, then the top of vacuum pumping box 2 is connected by drainpipe 5 To outside water-storing device;
The technical standard of the plastic draining board of table 1
3) sand gravel layer is filled
After the installation of plastic draining structure terminates, sand gravel is laid in geotextiles, laying sand gravel is carried out in five times, from Under up every time laying thickness be followed successively by 10cm, 10cm, 20cm, 20cm and 20cm, lay ground floor when, by rubber cover plate Water outlet mouthpiece 21 on 3 is laid with the junction of drinking-water pipe 4 with the sand gravel of 1~3cm of particle diameter, and remaining position selection particle diameter is 5 The sand gravel laying of~8cm, until ground floor laying is finished, and remaining each layer is spread using the laying method of ground floor If, until sand gravel layer laying is finished;
4) block stone setting cushion
After sand gravel layer laying terminates, bagged sand is first covered around exposed vacuum pumping box 2, and by drainpipe 5 It is vertically oriented, then dumped rocks protecting foundation, and properly protect, soil indicator change is as shown in table 2 before and after reinforcing.
Table 2 reinforces front and rear soil indicator change
Specific embodiment of the invention is these are only, but technical characteristic of the invention is not limited thereto.It is any with this hair Based on bright, to realize essentially identical technique effect, done ground simple change, equivalent or modification etc., all cover Among protection scope of the present invention.

Claims (7)

1. a kind of Embankment Foundation soil layer plastic draining structure, it is characterised in that:Including vacuum pumping box and at least two plastics Drain bar, is connected between the two neighboring plastic draining board by horizontal water-supply-pipe, and four are provided with the horizontal water-supply-pipe Port valve, is provided with rubber cover plate on the top surface of the plastic draining board, the rubber cover plate connects described by drinking-water pipe Vacuum pumping box, is connected between the two neighboring rubber cover plate by being connected flexible pipe, is set on the top surface of the vacuum pumping box It is equipped with drainpipe.
2. a kind of Embankment Foundation soil layer plastic draining structure according to claim 1, it is characterised in that:The plastic row Permeable hole is evenly arranged with four lateral surfaces of water plate, water permeable membrane is provided with the permeable hole, wherein relative two It is provided with reinforcing plate muscle on the lateral surface, the plastic draining board is internally provided with water delivery cavity, the water delivery cavity Core body is inside provided with, the core body matches with the water delivery cavity, is respectively provided with four lateral surfaces of the plastic draining board There is screwed hole, the screwed hole is threadedly coupled with the horizontal water-supply-pipe, and the top of the plastic draining board is provided with step.
3. a kind of Embankment Foundation soil layer plastic draining structure according to claim 2, it is characterised in that:The plastic row The bottom of water plate is provided with A-frame.
4. a kind of Embankment Foundation soil layer plastic draining structure according to claim 2, it is characterised in that:The core body bag Substrate and deflector are included, the deflector Vertical Uniform is connected to the both sides up and down of the substrate, on the bottom surface of the substrate It is even to be provided with the first water hole, the second water hole, first water hole and described second are provided with the side of the substrate Water hole is mutually perpendicular to connection.
5. a kind of Embankment Foundation soil layer plastic draining structure according to claim 2, it is characterised in that:The serum cap Vacuum cavity is provided with plate, restraining position ring block, the spacing ring and the step phase are set on the bottom surface of the vacuum cavity Match somebody with somebody, the left and right sides of the vacuum cavity is symmetrically arranged with water inlet interface, and being provided with water outlet on the top surface of the rubber cover plate connects Mouthful, the water outlet mouthpiece is connected with the vacuum cavity.
6. a kind of Embankment Foundation soil layer plastic draining structure according to claim 1, it is characterised in that:The vacuum is taken out Suction pump is provided with water tank, at least three water inlet pipes are connected with the side of the suction pump, be respectively provided with the water inlet pipe The top surface for having magnetic valve, the suction pump connects the drainpipe by connection tube.
7. a kind of Embankment Foundation soil layer as claimed in claim 1 construction method of plastic draining structure, it is characterised in that bag Include following steps:
1) surveying and locating
A, area and shape first according to Embankment Foundation determine the construction location of plastic draining structure, and according to Embankment Foundation Soil property water content selects the size of corresponding plastic draining board;
B and then construction area is delineated in the relevant position of Embankment Foundation according to drawing, and the construction area is cleared up, used The rooter topsoil thick to 50~80cm of the construction area surface is transported after tedding with transport vehicle;
C, leveling treatment is then carried out with rammer compacter to construction area, and present situation soil matrix top surface after leveling lays one layer of size The geotextiles matched with construction area, will be fixed, then in the table of geotextiles with anchor pole around geotextiles with ground Face is determined the installation site of plastic draining board by the design requirement of drawing, and sprinkles white pulverized limestone as mark in respective regions Note, while stamping setting-out stake in the both sides of mark position;
2) plastic draining structure is installed
A, the center of the lifting rope of hoisting machine and plastic draining board is connected first, with triangle branch on plastic draining board One end of frame is vertical down, and plastic draining board is hoisted to the mark position of construction area, then carries out plastic draining board At the uniform velocity transfer, until two sides of plastic draining board are clipped between setting-out stake, then covered on the top surface of plastic draining board One piece of thickness is the baffle plate of 30cm, and main force's axle of board-plugging device is propped up into baffle plate, using the hydraulic pressure sinking device of board-plugging device, makes plate Owner's power axle sinking synchronous with plastic draining board, until the position that plastic draining board is connected with lifting rope is neat with the top of setting-out stake It is flat, lifting rope is untied, and remove hoisting machine;
B and then continue inserting piling plastic draining board with board-plugging device, the submergence depth of plastic draining board is reached the depth of design requirement Degree, the hydraulic means closed on board-plugging device, and remove main force's axle of board-plugging device removes baffle plate, while setting-out stake is extracted, with viscous Soil is filled;
C, then core body is vertically loaded into plastic draining board it is fixed, makes the second water hole and the plastic row in substrate side surfaces Screwed hole alignment on water plate side, then installs rubber cover plate, with fluid sealant by serum cap on the top surface of plastic draining board Encapsulation process is carried out at plate and the gap of plastic draining board;
D, after plastic draining board is installed and terminated, the construction of next plastic draining board is carried out with above-mentioned steps, until geotechnological All Plastic Drain Slab Constructions on cloth terminate;
E, horizontal water-supply-pipe will be installed again between two adjacent plastic draining boards of back and forth or left and right, and in horizontal water-supply-pipe Four-way valve is installed in heart position, is connected by longitudinal water-supply-pipe between two neighboring four-way valve, makes whole plastic draining structure in sky Between net distribution, will be attached by being connected flexible pipe between two adjacent rubber cover plates of left and right, and carry out encapsulation process;
Horizontal stand is installed in f, the position of last 40~50cm above geotextiles, and vacuum pumping box is installed on horizontal stand, And the rubber cover plate on each single plastic draining board is connected into vacuum pumping box by drinking-water pipe, and it is another on rubber cover plate Individual water outlet mouthpiece is attached by drinking-water pipe with the water outlet mouthpiece on adjacent rubber cover plate, prevents air from directly being connect from water outlet Enter in plastic draining board at mouthful, then by the top of vacuum pumping box by the externally connected water-storing device of drainpipe;
3) sand gravel layer is filled
After plastic draining structure is installed and terminated, sand gravel is laid in geotextiles, laying sand gravel is carried out in five times, from lower past The thickness of upper laying every time is followed successively by 10cm, 10cm, 20cm, 20cm and 20cm, when ground floor is laid, by rubber cover plate Water outlet mouthpiece is laid with the junction of drinking-water pipe with the sand gravel of 1~3cm of particle diameter, and remaining position selection particle diameter is the sand of 5~8cm Gravel is laid, until ground floor laying is finished, and remaining each layer is laid using the laying method of ground floor, until gravel Rock layers laying is finished;
4) block stone setting cushion
After sand gravel layer laying terminates, bagged sand is first covered around exposed vacuum pumping box, and drainpipe is fixed vertically Position, then dumped rocks protecting foundation, and properly protect.
CN201710094603.6A 2017-02-21 2017-02-21 A kind of Embankment Foundation soil layer plastic draining structure and its construction method Active CN106836183B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710094603.6A CN106836183B (en) 2017-02-21 2017-02-21 A kind of Embankment Foundation soil layer plastic draining structure and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710094603.6A CN106836183B (en) 2017-02-21 2017-02-21 A kind of Embankment Foundation soil layer plastic draining structure and its construction method

Publications (2)

Publication Number Publication Date
CN106836183A true CN106836183A (en) 2017-06-13
CN106836183B CN106836183B (en) 2019-01-15

Family

ID=59134751

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710094603.6A Active CN106836183B (en) 2017-02-21 2017-02-21 A kind of Embankment Foundation soil layer plastic draining structure and its construction method

Country Status (1)

Country Link
CN (1) CN106836183B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111945758A (en) * 2020-08-27 2020-11-17 河南科技大学 Reusable dewatering tank, foundation pit operation surface dewatering system and method
CN117661536A (en) * 2023-12-12 2024-03-08 山东省建筑设计研究院有限公司 Soft soil foundation reinforcing structure

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20120008473U (en) * 2011-06-01 2012-12-11 주식회사 성호폴리텍 Horizontal collector drain by vacuum
CN103806437A (en) * 2014-03-10 2014-05-21 王军 Double-layer vacuum preloading and hydraulic reclamation soft foundation processing method
JP2016014256A (en) * 2014-07-02 2016-01-28 五洋建設株式会社 Vacuum consolidation method combined with banking
CN105649002A (en) * 2015-12-29 2016-06-08 上海强劲地基工程股份有限公司 Rapid treatment system and rapid treatment method for soft soil foundation
CN105804047A (en) * 2016-04-06 2016-07-27 浙江水利水电学院 Water drainage device and method for increasing water drainage and consolidation speed of filled sludge
CN105887799A (en) * 2016-04-06 2016-08-24 浙江水利水电学院 Drainage device for shallow silt foundation treatment and laying method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20120008473U (en) * 2011-06-01 2012-12-11 주식회사 성호폴리텍 Horizontal collector drain by vacuum
CN103806437A (en) * 2014-03-10 2014-05-21 王军 Double-layer vacuum preloading and hydraulic reclamation soft foundation processing method
JP2016014256A (en) * 2014-07-02 2016-01-28 五洋建設株式会社 Vacuum consolidation method combined with banking
CN105649002A (en) * 2015-12-29 2016-06-08 上海强劲地基工程股份有限公司 Rapid treatment system and rapid treatment method for soft soil foundation
CN105804047A (en) * 2016-04-06 2016-07-27 浙江水利水电学院 Water drainage device and method for increasing water drainage and consolidation speed of filled sludge
CN105887799A (en) * 2016-04-06 2016-08-24 浙江水利水电学院 Drainage device for shallow silt foundation treatment and laying method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111945758A (en) * 2020-08-27 2020-11-17 河南科技大学 Reusable dewatering tank, foundation pit operation surface dewatering system and method
CN117661536A (en) * 2023-12-12 2024-03-08 山东省建筑设计研究院有限公司 Soft soil foundation reinforcing structure
CN117661536B (en) * 2023-12-12 2024-05-24 山东省建筑设计研究院有限公司 Soft soil foundation reinforcing structure

Also Published As

Publication number Publication date
CN106836183B (en) 2019-01-15

Similar Documents

Publication Publication Date Title
CN100554596C (en) Vacuum preloading method for non-water discharge sand cushion
CN100549304C (en) A kind of nothing sealing fast vacuum prepressing method
CN102127908B (en) Method for quickly reinforcing ultra-soft soil foundation by using bagged sand cushion
CN107587578B (en) Drainage type muck pool and soil pressure balance shield muck multidimensional seepage dewatering method
CN101906772B (en) Fast consolidation method of blow-filled soft soil for land reclamation
CN107587557A (en) Outdoor water engineering construction method
CN101225656B (en) Method for rapidly reinforcing ultra-soft soil superficial layer
CN102587352A (en) Hot-water draining consolidation processing device and hot-water draining consolidating processing method for soft soil foundation
CN102220757B (en) Immediate processing method for drainage solidifying of super soft soil shallow surface space
CN202232370U (en) Greening system for treatment of high water level impervious saline-alkali soil
CN102817354B (en) Method for dredging soft foundation by dredger fill and reinforcement
CN106284081A (en) A kind of blast cofferdam is as cast-in-place box beam bracket foundation construction method
CN110080169B (en) Construction method for building land by enclosing sea based on basement utilization
CN112411518A (en) Soft foundation section vacuum combined surcharge preloading construction method
CN107059523A (en) A kind of construction method that road is built on reclaimed ground and the subgrade strengthening structure of construction method formation
CN102383408B (en) Greening method for high water level impermeable saline and alkaline lands and greening system
CN101768951A (en) Retaining and protecting method for vacuum preloading foundation excavation at soft soil road section
CN106836183B (en) A kind of Embankment Foundation soil layer plastic draining structure and its construction method
CN105484229B (en) Vacuum preloading method is sealed suitable for the overlying mud layer of the soft base in waters
CN107642101A (en) A kind of rocky bed steel cofferdam back cover leak stopping and guarded drainage construction method
CN102704458A (en) Sand-free cushion layer vacuum-surcharge preloading reinforcement device and method for soft ground
CN104746506A (en) Soft soil combined preloading structure and construction method
CN114855762B (en) Device and method for closing and sealing tailings pond
CN217399609U (en) Device for closing and sealing tailing pond
CN107514005A (en) A kind of instrument and its construction method for improving Application of light well point precipitation efficiency

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20220126

Address after: 315000 room 415, 159 Hongdu Road, Jiangbei District, Ningbo City, Zhejiang Province

Patentee after: NINGBO HUITONG ECOLOGICAL ENGINEERING CONSTRUCTION Co.,Ltd.

Address before: 310018 508 Xuefu street, Xiasha Higher Education East District, Hangzhou, Zhejiang

Patentee before: ZHEJIANG University OF WATER RESOURCES AND ELECTRIC POWER

TR01 Transfer of patent right
CP03 Change of name, title or address

Address after: 315000 Tengtou Village, Xiaowangmiao Street, Fenghua District, Ningbo City, Zhejiang Province (Room 309 and 310, Third Floor, No. 399 Siming Road)

Patentee after: Zhejiang Tengtou Water Construction Co.,Ltd.

Country or region after: China

Address before: 315000 room 415, 159 Hongdu Road, Jiangbei District, Ningbo City, Zhejiang Province

Patentee before: NINGBO HUITONG ECOLOGICAL ENGINEERING CONSTRUCTION Co.,Ltd.

Country or region before: China

CP03 Change of name, title or address