CN106812299A - A kind of hanging basket for overflow weir - Google Patents

A kind of hanging basket for overflow weir Download PDF

Info

Publication number
CN106812299A
CN106812299A CN201710147771.7A CN201710147771A CN106812299A CN 106812299 A CN106812299 A CN 106812299A CN 201710147771 A CN201710147771 A CN 201710147771A CN 106812299 A CN106812299 A CN 106812299A
Authority
CN
China
Prior art keywords
hoop
piece
fixed
overflow weir
wire rope
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710147771.7A
Other languages
Chinese (zh)
Other versions
CN106812299B (en
Inventor
张永先
孙晓巍
潘文浩
苏炜焕
何苗
于海波
王秀红
李晓曦
姜伟民
马广明
徐健
刘士军
丁洪伟
付庆波
孙凯
张剑
钟比佳
毛艳明
张铁钢
郑发光
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Liaoning Hua Hua Three Construction Engineering Technology Co Ltd
Original Assignee
Liaoning Hua Hua Three Construction Engineering Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Liaoning Hua Hua Three Construction Engineering Technology Co Ltd filed Critical Liaoning Hua Hua Three Construction Engineering Technology Co Ltd
Priority to CN201710147771.7A priority Critical patent/CN106812299B/en
Publication of CN106812299A publication Critical patent/CN106812299A/en
Application granted granted Critical
Publication of CN106812299B publication Critical patent/CN106812299B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/28Mobile scaffolds; Scaffolds with mobile platforms
    • E04G3/30Mobile scaffolds; Scaffolds with mobile platforms suspended by flexible supporting elements, e.g. cables
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/28Mobile scaffolds; Scaffolds with mobile platforms
    • E04G3/30Mobile scaffolds; Scaffolds with mobile platforms suspended by flexible supporting elements, e.g. cables
    • E04G3/32Hoisting devices; Safety devices
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B7/00Barrages or weirs; Layout, construction, methods of, or devices for, making same

Abstract

The present invention relates to a kind of hanging basket for overflow weir, include fixing device, mobile platform and power and control system, described fixing device includes steel wire rope group, and one end of steel wire rope group is fixed on the top of overflow weir or is fixed on sluice gate body steel construction;Described mobile platform includes fixed hoop and movable hoop, and movable hoop is two, is sleeved on the both sides of fixed hoop, and movable hoop is slidably connected with fixed hoop;Described power includes power cable, Comprehensive Control case and electric lift with control system, and power cable and Comprehensive Control case are arranged on fixed hoop, and power cable is connected with dam crest main junction box, there is provided 380V power electrics, accesses Comprehensive Control case;Electric power is matched somebody with somebody two to the utmost electric lifts by Comprehensive Control case, and for operation provides power supply, electric lift is fixed on sidebar piece and is connected with steel wire rope group.The present invention can realize testing inspection, repairing protection, the reinforcing construction to overflow weir position.Easy for installation, assembling is flexible.

Description

A kind of hanging basket for overflow weir
Technical field
The present invention relates to a kind of hanging basket for overflow weir.
Background technology
In testing inspection, repairing protection, reinforcing operation in concrete dam overflow weir, the method for early stage is to make It is fixed on gate structure with a plurality of rope, is punched on the concrete of overflow weir, using reinforcing bar cuttage in hole, rope Fix horizontally disposed scaffold jointly with reinforcing bar and form cat ladder shape scaffold of the spacing at 1 meter, operating personnel move along cat ladder Carry out work in every.This form of construction work needs to arrange large number of drilling in overflow weir, a large amount of cuttage reinforcing bars, rope and Scaffold is also required to a large amount of arrangements, and staff's activity on scaffold inconvenience, and man-hour of marching into the arena and withdraw is more long, and quantity is many Many drilling destroys original concrete structure, it is necessary to largely fill up reparation, reinforcing bar cuttage is numerous to be unfavorable for constructing operation, there is portion Divide potential safety hazard.
The content of the invention
It is an object of the invention to provide a kind of a kind of hanging basket for overflow weir for overflow weir, the hanging basket is used Safe ready.
In order to solve the problems, such as prior art, the technical solution adopted by the present invention is:
A kind of hanging basket for overflow weir, includes fixing device, mobile platform and power and control system,
Described fixing device includes steel wire rope group, and one end of steel wire rope group is fixed on the top of overflow weir or is fixed on On sluice gate body steel construction;
Described mobile platform includes fixed hoop and movable hoop, and movable hoop is two, is sleeved on the two of fixed hoop Side, movable hoop is slidably connected with fixed hoop;
Described power includes power cable, Comprehensive Control case and electric lift, power cable and comprehensive control with control system Case processed is arranged on fixed hoop, and power cable is connected with dam crest main junction box, there is provided 380V power electrics, accesses Comprehensive Control Case;Electric power is matched somebody with somebody two to the utmost electric lifts by Comprehensive Control case, and for operation provides power supply, electric lift is fixed on sidebar piece It is connected above and with steel wire rope group.
Handle and motor are installed, described movable hoop includes base plate, preceding column piece, rear column on described fixed hoop Piece, sidebar piece and column bobbin, are fixed with column bobbin on base plate, forward and backward column piece is connected with base plate by column bobbin and can be with column piece Axle is overturn for the center of circle;Plate outer side face is fixedly connected with sidebar piece, and preceding column piece is to be hinged with sidebar piece;Movable basket frame bottom plate Side is provided with spur rack, and spur gear is provided with fixed hoop, and spur gear is meshed with spur rack, and motor drives spur gear to do Circular motion, drive activity hoop horizontal movement;An inner orbit wheel, wheel rim inner surface are respectively installed at four angles of sidebar piece On be provided with wheel rim track, inner orbit wheel is placed in wheel rim track and can be slided along wheel rim track.
Bascule is also included, described bascule includes wheel rim tracks positioned lock, steel wire rope guide wheel group and column Piece positioning lock, steel wire rope guide wheel group is set on wheel rim track, and wheel rim tracks positioned lock, column piece are provided between wheel rim track It is connected with wheel rim track by column piece positioning lock.
The bottom of described fixed hoop is separately installed with castor group with the bottom of the both sides of movable hoop.
Described electric lift is frictional motor hoist, and by rubbing, steel wire rope provides driving force, along steel wire rope Motion.
Described base plate, preceding column piece, rear column piece, sidebar piece are welded by square steel mesh sheet.
Described power also includes cradle safety lock with control system.
Also include safety guarantee, caution system.
Advantage for present invention is with effect:
The present invention relates to a kind of hanging basket for overflow weir, the hanging basket can realize testing inspection to overflow weir position, Repairing protection, reinforcing construction.Easy for installation, assembling is flexibly, staff's field control can be along any curve form Overflow weir apparent motion, be easy to carry out testing inspection, repairing protection, reinforcing work.Hanging basket of the present invention can when withdrawing Quickly pack up, convenient transportation, reusable, safe and convenient.The width of mobile platform of the invention can be adjusted, and can not only be fitted The overflow weir of various curve forms is answered, while can adapt to the overflow weir of various width, tunneling boring operational requirements is met.This Invention being capable of high efficiency completion overflow weir tunneling boring operation.
Brief description of the drawings
Fig. 1 is a kind of use state of hanging basket for overflow weir of the invention with reference to figure;
Fig. 2 is the front view of mobile platform;
Fig. 3 is the side view of mobile platform;
In figure:1 fixing device, 2 anchoring bolts, 3 steel wire rope groups, 4 U-shape locks are buckled, 5 mobile platforms, 6 base plates, 7 preceding column pieces, after 8 column Piece, 9 sidebar pieces, 10 column bobbins, 11 wheel rim tracks, 12 castor groups, 13 telescopic joints, 14 spur gear groups, 15 little gears, 16 handles, 17 motors, 18 power cables, 19 Comprehensive Control casees, 20 electric lifts, 21 cradle safety locks, 22 wheel rim tracks positioneds lock, 23 Steel wire rope guide wheel group, 24 column piece positioning locks, 25 inner orbit wheels, 26 air feed systems, 27 water systems, 28 electric power supply systems, 29 Material Lift-on/Lift-off System, 30 safety ropes, 31 elevator safeties lock.
Specific embodiment
The invention will be further described below in conjunction with the accompanying drawings:
As shown in Figure 1:A kind of hanging basket for overflow weir of the invention, includes fixing device 1, mobile platform 5, power and control System processed and bascule,
Described fixing device includes steel wire rope group 3, for the overflow weir without steel-slag sand, steel is fixed using anchoring bolt 2 Cord group, in overflow weir weir crest drilling deep hole, one end of steel wire rope group is fixed on anchoring bolt;For the overflow for having steel-slag sand Weir face, steel wire rope group is fixed using U-shape lock button 4, by U-shape lock retaining ring on steel construction, is consolidated steel wire rope group using U-shape lock button It is scheduled on steel construction.
As shown in Figure 2,3, described mobile platform includes fixed hoop and movable hoop, and movable hoop 13 is two, It is sleeved on the both sides of fixed hoop.Power cable 18 and Comprehensive Control case 19 be installed on fixed hoop, fixed hoop top surface with Two slideways are each provided with bottom surface.Movable hoop is slided along slideway.
Described fixed hoop includes base plate, preceding column piece, rear column piece, handle 16 and motor 17.Described movable hoop It is sleeved in fixed hoop, it includes base plate 6, preceding column piece 7, rear column piece 8, sidebar piece 9 and column bobbin 10, described base plate, Preceding column piece, rear column piece, sidebar piece are welded by square steel mesh sheet.Column bobbin is fixed with base plate, forward and backward column piece passes through column Bobbin is connected with base plate and can be with column bobbin as the center of circle is overturn;The side of base plate is fixedly connected with sidebar piece, preceding column piece with Sidebar piece is to be hinged.The bottom of fixed hoop is separately installed with castor group with the bottom of the both sides of movable hoop.
Movable basket frame bottom plate side is provided with spur rack 14, and spur gear 15, spur gear are provided with the base plate of fixed hoop It is connected with handle and motor respectively by directly engaging transmission mutually, spur gear with spur rack, swinging handle can order about straight-tooth Wheel drives movable basket frame to be moved horizontally along spur gear group, and then the movable hoop at two ends is extended to both sides, the effect of handle Be manually or fine setting when use.Spur gear can also be driven to move in a circle by motor, motor fast turn-around drives straight Gear does and act into face drive activity hoop horizontal movement expanding.
Sidebar piece is stretched out on one end of fixed hoop installed in each movable hoop, is respectively installed at four angles of sidebar piece There is an inner orbit wheel 25, wheel rim track 11 is provided with wheel rim inner surface, inner orbit wheel is placed in wheel rim track and can edge The slip of wheel rim track.The effect of wheel rim has two, and one of effect is slided as the big roller of whole mechanism along overflow weir, is made With it two be used to adjusting it is fixed before and after column piece relative position, so that the weir face for adapting to different curved sections operates.
Described power includes power cable 18, Comprehensive Control case 19, cradle safety lock 21 and electronic liter with control system Drop machine 20, power cable is connected with dam crest main junction box, there is provided 380V power electrics, accesses Comprehensive Control case;Comprehensive Control case will Electric power matches somebody with somebody two to the utmost electric lifts, while 220V translation interfaces are provided with, for operation provides power supply, and can by conversion 36V, 12V power supplys needed for system such as security warning are provided.Electric lift is two frictional motor hoists, electric lift It is bolted on sidebar piece by four, one end of steel wire rope group is fixed on the top of overflow weir, and the other end passes through safety It is connected with electric lift after lock, by rubbing, steel wire rope provides driving force, and then is moved along steel wire rope.Cradle safety lock is installed The top of electric lift and with side basket(Column)Piece is fixedly mounted.Cradle safety lock is a kind of motor servo formula safety lockset, When electric lift is opened, cradle safety lock synchronous operation strengthens safe operation safeguard function.
Described bascule includes wheel rim tracks positioned lock 22, steel wire rope guide wheel group 23 and column piece positioning lock 24, steel Cord guide wheel group is set on wheel rim track, and wheel rim tracks positioned lock is provided between wheel rim track, and column piece is fixed by column piece Position lock is connected with wheel rim track.Wheel rim tracks positioned lock is mainly used in adjusting the relative position of wheel rim track and sidebar piece, makes During, mobile platform is run to specified location, it is necessary to adjust the position of base plate, general warranty base plate is arranged horizontally, with Just staff's operation is conducive to;The position that the position of the positioning lock of preceding column piece is locked with wheel rim tracks positioned substantially overlaps, therefore The phase that wheel rim track just have adjusted wheel rim track and electric lift with the relative position of preceding column piece and sidebar piece only need to be adjusted To position.
Steel wire rope guide wheel group is made up of one group of guide wheel, is set on wheel rim track, is provided with i.e. between wheel rim track Wheel rim tracks positioned is locked, it is therefore intended that when mobile platform is run to specified location, and steel wire rope guide wheel group is locked in into wheel rim rail certainly On road, make wheel rim track and preceding column piece, sidebar piece in the gravity and the pulling force of steel wire rope group of whole mechanism, concrete surface Basic fixed position is on overflow weir under the comprehensive function of frictional force, used as the unit that an interim globality is fixed.
Column piece positioning lock is connected to column piece and wheel rim track, when forward and backward column piece is made to adjust as needed, column piece positioning The flip angle for fixed hurdle piece is locked, because wheel rim track can be used as an interim fixed cell, therefore column Piece slides the column piece folding angle that can adjust the operating position by positioning lock along wheel rim track, and then adjusts out suitable appearance State is so as to operation.
A kind of described hanging basket for overflow weir, also includes safety guarantee, caution system.Described safety guarantor Barrier, caution system include safety guide rail, safety belt, safety rope, big cord lock, elevator safety lock 31, warning device, warning Lamp, is distributed in mobile platform surrounding, and safety guide rail is that, installed in forward and backward, sidebar piece safe linked network, safety rope is fixed on steel Structure, its purposes be ensure operating personnel safety and detection process it is safe and reliable, warn.
As shown in figure 1, the present invention is equipped with different technology supply systems, technology supply system according to different use demands It is arranged on dam crest.Described technology supply system is hung comprising air feed system 26, water system 27, electric power supply system 28, material Dress system 29.
Air feed system includes mute compressor, oil water separator, pressed gas storage tank, compressor outer cover noise-reducing device, wind Pipe, air pressure gun, tuyere, it is mainly used in pressed gas cleaning basal plane, the inspection of pressure wind, dried process, dry method drilling detection etc..
Water system mainly includes water tank, compression pump, high-voltage tube, high-pressure spray gun, Water slop injector, and it is mainly used in high pressure Water cleaning basal plane, packer permeability test, wet method drilling detection etc..
Electric power supply system includes external connection power electricity(380V)Interface and circuit, external power supply(220V)Interface and circuit, It is power autonomous(220V), provide mains lighting supply for oneself(36V), leakage protection system, external minitype gas dynamotor(220V)And phase The noise-reducing device answered.Preferentially use external power supply, secondly using power autonomous, electric power is not enough or without external power supply in the case of, open Use external minitype gas dynamotor(220V)Generate electricity.
Material Lift-on/Lift-off System is Miniature hanging device and rope, and material is carried out for overflow weir active section and gate pier top Transmission and instrument, the vertical delivering of equipment.

Claims (8)

1. a kind of hanging basket for overflow weir, it is characterised in that:Include fixing device, mobile platform and power is with control System,
Described fixing device includes steel wire rope group, and one end of steel wire rope group is fixed on the top of overflow weir or is fixed on On sluice gate body steel construction;
Described mobile platform includes fixed hoop and movable hoop, and movable hoop is two, is sleeved on the two of fixed hoop Side, movable hoop is slidably connected with fixed hoop;
Described power includes power cable, Comprehensive Control case and electric lift, power cable and comprehensive control with control system Case processed is arranged on fixed hoop, and power cable is connected with dam crest main junction box, there is provided 380V power electrics, accesses Comprehensive Control Case;Electric power is matched somebody with somebody two to the utmost electric lifts by Comprehensive Control case, and for operation provides power supply, electric lift is fixed on sidebar piece It is connected above and with steel wire rope group.
2. a kind of hanging basket for overflow weir according to claim 1, it is characterised in that:Pacify on described fixed hoop Equipped with handle and motor, described movable hoop includes base plate, preceding column piece, rear column piece, sidebar piece and column bobbin, solid on base plate Surely there is column bobbin, forward and backward column piece is connected with base plate by column bobbin and can be with column bobbin as the center of circle is overturn;Plate outer side face Sidebar piece is fixedly connected with, preceding column piece is to be hinged with sidebar piece;Movable basket frame bottom plate side is provided with spur rack, on fixed hoop Spur gear is installed, spur gear is meshed with spur rack, motor drives spur gear to move in a circle, drive activity hoop level fortune It is dynamic;An inner orbit wheel is respectively installed at four angles of sidebar piece, wheel rim track is provided with wheel rim inner surface, inner orbit wheel is put In can slide in wheel rim track and along wheel rim track.
3. a kind of hanging basket for overflow weir according to claim 1 and 2, it is characterised in that:Also include balance dress Put, described bascule includes wheel rim tracks positioned lock, steel wire rope guide wheel group and column piece positioning lock, steel wire rope guide wheel group set Loaded on wheel rim tracks positioned lock on wheel rim track, is provided between wheel rim track, column piece is by column piece positioning lock and wheel rim rail Road is connected.
4. a kind of hanging basket for overflow weir according to claim 1 and 2, it is characterised in that:Described fixed hoop Bottom be separately installed with castor group with the bottom of the both sides of movable hoop.
5. a kind of hanging basket for overflow weir according to claim 1, it is characterised in that:Described electric lift is Frictional motor hoist, by rubbing, steel wire rope provides driving force, is moved along steel wire rope.
6. a kind of hanging basket for overflow weir according to claim 2, it is characterised in that:Described base plate, preceding column piece, Column piece, sidebar piece are welded by square steel mesh sheet afterwards.
7. a kind of hanging basket for overflow weir according to claim 1, it is characterised in that:Described power and control system System also includes cradle safety lock.
8. a kind of hanging basket for overflow weir according to claim 1, it is characterised in that:Also include safety guarantee, Caution system.
CN201710147771.7A 2017-03-14 2017-03-14 Hanging basket for overflow weir surface Active CN106812299B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710147771.7A CN106812299B (en) 2017-03-14 2017-03-14 Hanging basket for overflow weir surface

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710147771.7A CN106812299B (en) 2017-03-14 2017-03-14 Hanging basket for overflow weir surface

Publications (2)

Publication Number Publication Date
CN106812299A true CN106812299A (en) 2017-06-09
CN106812299B CN106812299B (en) 2022-08-05

Family

ID=59116102

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710147771.7A Active CN106812299B (en) 2017-03-14 2017-03-14 Hanging basket for overflow weir surface

Country Status (1)

Country Link
CN (1) CN106812299B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107179399A (en) * 2017-07-05 2017-09-19 水利部交通运输部国家能源局南京水利科学研究院 A kind of high concrete dam surface automatic surveying device and method

Citations (24)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2597920A1 (en) * 1986-04-29 1987-10-30 Chuzeville Pierre Device enabling a ladder to be hung and displaced on a roof and ladder fitted with these elements
SU1384530A1 (en) * 1986-10-08 1988-03-30 Предприятие П/Я М-5287 Crane installation
CN2064358U (en) * 1989-12-21 1990-10-24 中国人民解放军吉林省军区后勤部修配厂 Small-size multi-function hydraulic electric engineering car
CN2138674Y (en) * 1992-12-05 1993-07-21 丁炜 Universal lifting scaffold
CN1235586A (en) * 1996-09-11 1999-11-17 L·S·卡尔皮塞克 Apparatus for inverting container means
JP2001261299A (en) * 2000-03-22 2001-09-26 Takashi Ikeno Setoff method and device for component force in sloping direction of force working on slope
JP2005307691A (en) * 2004-04-26 2005-11-04 Jfe Engineering Kk Work platform of underground type low temperature tank
CN101077751A (en) * 2006-05-24 2007-11-28 因温特奥股份公司 Elevator with frictional drive
CN101200976A (en) * 2007-11-27 2008-06-18 吴杰 Lifting scaffold for construction of chimney and shaft inner wall
CN102168412A (en) * 2011-03-15 2011-08-31 广东水电二局股份有限公司 Cradle and method for dam elevation construction by using same
US8056677B1 (en) * 2009-07-23 2011-11-15 Roberts Equipment, Inc. Lift system with articulably joined subchassis
CN102758336A (en) * 2012-06-06 2012-10-31 海尔集团公司 Tripower washing machine
CN102926529A (en) * 2011-08-11 2013-02-13 北京建筑工程学院 Self-elevating scaffold provided with telescoping platforms for building construction
CN203097255U (en) * 2012-12-27 2013-07-31 德州职业技术学院 Extensible building platform
CN203247547U (en) * 2013-03-06 2013-10-23 国家电网公司 Dam panel anti-ice device
CN103466518A (en) * 2013-08-15 2013-12-25 中建钢构有限公司 Steel structure construction platform and large gradient self-climbing system and telescopic platform system thereof
CN104586316A (en) * 2013-10-31 2015-05-06 无锡吊蓝机械制造有限公司 Adjustable slope hanging basket
KR20150063679A (en) * 2013-12-02 2015-06-10 고종화 Speed gear Ssing sing barqeui
CN204578443U (en) * 2014-09-17 2015-08-19 耐克斯特拉克尔有限公司 Solar energy tracking equipment
CN105081519A (en) * 2015-09-16 2015-11-25 中国葛洲坝集团第六工程有限公司 Welding method for large-scale surface hole radial gate leaves
CN205531270U (en) * 2016-03-18 2016-08-31 中国葛洲坝集团三峡建设工程有限公司 A movable hanging flower basket for concrete bracket slope
CN105908761A (en) * 2016-04-21 2016-08-31 四川蜀通港口航道工程建设有限公司 Construction technology of hanging basket moving platform for high slope
CN206000146U (en) * 2016-06-28 2017-03-08 中国一冶集团有限公司 Mobile operating platform installed by a kind of rack
CN206707248U (en) * 2017-03-14 2017-12-05 辽宁华三建设工程技术有限公司 A kind of hanging basket for overflow weir

Patent Citations (24)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2597920A1 (en) * 1986-04-29 1987-10-30 Chuzeville Pierre Device enabling a ladder to be hung and displaced on a roof and ladder fitted with these elements
SU1384530A1 (en) * 1986-10-08 1988-03-30 Предприятие П/Я М-5287 Crane installation
CN2064358U (en) * 1989-12-21 1990-10-24 中国人民解放军吉林省军区后勤部修配厂 Small-size multi-function hydraulic electric engineering car
CN2138674Y (en) * 1992-12-05 1993-07-21 丁炜 Universal lifting scaffold
CN1235586A (en) * 1996-09-11 1999-11-17 L·S·卡尔皮塞克 Apparatus for inverting container means
JP2001261299A (en) * 2000-03-22 2001-09-26 Takashi Ikeno Setoff method and device for component force in sloping direction of force working on slope
JP2005307691A (en) * 2004-04-26 2005-11-04 Jfe Engineering Kk Work platform of underground type low temperature tank
CN101077751A (en) * 2006-05-24 2007-11-28 因温特奥股份公司 Elevator with frictional drive
CN101200976A (en) * 2007-11-27 2008-06-18 吴杰 Lifting scaffold for construction of chimney and shaft inner wall
US8056677B1 (en) * 2009-07-23 2011-11-15 Roberts Equipment, Inc. Lift system with articulably joined subchassis
CN102168412A (en) * 2011-03-15 2011-08-31 广东水电二局股份有限公司 Cradle and method for dam elevation construction by using same
CN102926529A (en) * 2011-08-11 2013-02-13 北京建筑工程学院 Self-elevating scaffold provided with telescoping platforms for building construction
CN102758336A (en) * 2012-06-06 2012-10-31 海尔集团公司 Tripower washing machine
CN203097255U (en) * 2012-12-27 2013-07-31 德州职业技术学院 Extensible building platform
CN203247547U (en) * 2013-03-06 2013-10-23 国家电网公司 Dam panel anti-ice device
CN103466518A (en) * 2013-08-15 2013-12-25 中建钢构有限公司 Steel structure construction platform and large gradient self-climbing system and telescopic platform system thereof
CN104586316A (en) * 2013-10-31 2015-05-06 无锡吊蓝机械制造有限公司 Adjustable slope hanging basket
KR20150063679A (en) * 2013-12-02 2015-06-10 고종화 Speed gear Ssing sing barqeui
CN204578443U (en) * 2014-09-17 2015-08-19 耐克斯特拉克尔有限公司 Solar energy tracking equipment
CN105081519A (en) * 2015-09-16 2015-11-25 中国葛洲坝集团第六工程有限公司 Welding method for large-scale surface hole radial gate leaves
CN205531270U (en) * 2016-03-18 2016-08-31 中国葛洲坝集团三峡建设工程有限公司 A movable hanging flower basket for concrete bracket slope
CN105908761A (en) * 2016-04-21 2016-08-31 四川蜀通港口航道工程建设有限公司 Construction technology of hanging basket moving platform for high slope
CN206000146U (en) * 2016-06-28 2017-03-08 中国一冶集团有限公司 Mobile operating platform installed by a kind of rack
CN206707248U (en) * 2017-03-14 2017-12-05 辽宁华三建设工程技术有限公司 A kind of hanging basket for overflow weir

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
刘旭阳: "挂篮模板主桁架滑行轨道梁的力学计算", 《中国建筑金属结构》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107179399A (en) * 2017-07-05 2017-09-19 水利部交通运输部国家能源局南京水利科学研究院 A kind of high concrete dam surface automatic surveying device and method

Also Published As

Publication number Publication date
CN106812299B (en) 2022-08-05

Similar Documents

Publication Publication Date Title
CN205501818U (en) Steel trussed arch bridge bridge tool car
CN103183297B (en) Mobile rescue elevator and rescue vehicle
CN106194220A (en) Tunnel splash guard installs chassis
CN103306199A (en) Mounting method of bottom width overhaul hanging basket of bridge
CN205688343U (en) A kind of steel truss girder tool car
CN208235340U (en) It is a kind of can automatic lifting steel strand tension Mobile workbench
CN104831965B (en) Intelligentized liftable stereo garage and work method thereof
CN115465822A (en) Tunnel maintenance operation vehicle set and operation method thereof
CN205973684U (en) Portable insulating operation device of ascending a height of distribution lines
CN201392996Y (en) Power capacitor replacing device
CN206707248U (en) A kind of hanging basket for overflow weir
CN104909270B (en) Rope rolling rack, mountable and demountable gantry crane, and loading and unloading method
CN207856096U (en) A kind of fire-fighting equipment lifting deliverance apparatus
CN106812299A (en) A kind of hanging basket for overflow weir
KR101028631B1 (en) Movable bridge inspection equipment
CN203531352U (en) Hanging type movable working platform for storage tank maintenance
CN210366808U (en) Lifting and dismantling device for rail walking
CN106395560A (en) Embedded guide rail type double-arm fire rescue system for super high-rise building
CN209038990U (en) A kind of spliced EMU wiper upkeep operation platform
CN111634847A (en) Lifting device for electric power equipment installation and implementation method thereof
CN107386138B (en) Totally-enclosed sound insulation screen construction vehicle and totally-enclosed sound insulation screen installation method
CN207434895U (en) A kind of harbour container loop wheel machine
CN206279527U (en) A kind of deep concrete mixture ship pile frame system
CN212447267U (en) Fire-fighting rescue command vehicle capable of carrying unmanned aerial vehicle
CN205617771U (en) Construction operation platform and pipe -line transportation integrated device in high residential building elevartor shaft

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant