CN106812213B - The quick construction method in place of column muscle at PC Structure Beam-column node - Google Patents

The quick construction method in place of column muscle at PC Structure Beam-column node Download PDF

Info

Publication number
CN106812213B
CN106812213B CN201710130448.9A CN201710130448A CN106812213B CN 106812213 B CN106812213 B CN 106812213B CN 201710130448 A CN201710130448 A CN 201710130448A CN 106812213 B CN106812213 B CN 106812213B
Authority
CN
China
Prior art keywords
column
place
lifting
control
muscle
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710130448.9A
Other languages
Chinese (zh)
Other versions
CN106812213A (en
Inventor
沙峰峰
吕厚俊
罗曙东
黄国春
刘洋
高路恒
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NANTONG HUAXIN CONSTRUCTION ENGINEERING GROUP Co Ltd
Original Assignee
NANTONG HUAXIN CONSTRUCTION ENGINEERING GROUP Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NANTONG HUAXIN CONSTRUCTION ENGINEERING GROUP Co Ltd filed Critical NANTONG HUAXIN CONSTRUCTION ENGINEERING GROUP Co Ltd
Priority to CN201710130448.9A priority Critical patent/CN106812213B/en
Publication of CN106812213A publication Critical patent/CN106812213A/en
Application granted granted Critical
Publication of CN106812213B publication Critical patent/CN106812213B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/20Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of concrete, e.g. reinforced concrete, or other stonelike material
    • E04B1/21Connections specially adapted therefor

Abstract

The invention discloses a kind of quick construction methods in place of column muscle at PC Structure Beam-column node, include the following steps: prefabricated post lifting front pillar muscle position adjustment;The lifting of prefabricated post;The lifting of precast beam;Bullet controls mold control line in place;It controls mold installation, fix;Bean column node template construction;Bean column node concreting and maintenance;Mold is controlled to remove, have enough to meet the need;Upper segmented column lifting is in place.The present invention lifts quickly auxiliary tool in place as prefabricated post using control mold during PC Structure Beam-column node construction, column muscle position after being poured by control mold to column muscle position and node concrete at bean column node before the lifting of upper segmented column is in place carries out repeatedly adjustment and controls, ensure that column muscle can be quick, accurate in place when construction in later period, effectively increase lifting efficiency, a large amount of mounting cost is saved, the duration is greatly shortened.

Description

The quick construction method in place of column muscle at PC Structure Beam-column node
Technical field
The present invention relates to a kind of column muscle control methods in place, and in particular to column muscle is quickly at a kind of PC Structure Beam-column node Position construction method.
Background technique
At home and abroad development speed is very fast for prefabricated construction, and in China, prefabricated construction construction technology is mature Degree be not also it is very high, especially PC structural elements connecting node tectonic sieving and component be accurate, quick aspect in place, reinforce It is a major issue for being currently badly in need of capturing to component connecting node tectonic sieving, construction and quick location control, to subtract Few cost.
Summary of the invention
Goal of the invention: the present invention aiming at the shortcomings in the prior art, uses control during PC Structure Beam-column node construction Molding jig lifts quickly auxiliary tool in place as prefabricated post, by control mold to bean column node before the lifting of upper segmented column is in place Column muscle position after place column muscle position and node concrete pour carries out repeatedly adjustment and control, it is ensured that column muscle energy when construction in later period It is enough quick, accurate in place, lifting efficiency is effectively increased, a large amount of mounting cost is saved, greatly shortens a kind of PC knot of duration The quick construction method in place of column muscle at structure bean column node.
Technical solution: the quick construction method in place of column muscle at a kind of PC Structure Beam-column node of the present invention, including such as Lower step:
(1) prefabricated post site acceptance: can be pre- by control mold auxiliary when prefabricated post is transported from factory to engineering site The checking and accepting of column processed is more than the component of code requirement to column muscle design position deviation, forbids to march into the arena;
(2) prefabricated post lifting front pillar muscle position adjustment: prefabricated post is secondary prefabricated using control mold inspection before lifting The deviation situation of column column muscle, and just successive step appropriate is carried out, column muscle excessive error as caused by the human factors such as lifting Component, when construction also forbids to lift, be lifted after to be adjusted;
(3) lifting of prefabricated post: the precast column unit of control mould secondary passed examination has been passed through to column muscle, can carry out Lifting construction, when lifting, will reinforce the protection work to component, and the especially protection to column muscle avoids the factors such as lifting collision from leading Column muscle position is caused to generate biggish deviation.It therefore, also will be by code requirement to the column muscle error in place and to prefabricated post in place It tightens control;
(4) lifting of precast beam: before hoisting beam, the Hoisting Position of check column and adjustment, the good beam of bullet is in place on shaft The lifting of the laggard cross girders of control line, and the lifting error of beam is rationally controlled, while avoiding interference pre- in precast beam hoisting process Column column muscle processed;
(5) bullet controls mold control line in place: after prefabricated beam column lifting is in place, will control mold in the top surface of precast beam Position line pop-up pops up control mold control line in place, again based on the position line for controlling mold again preferably in order to the later period Check work in work progress;
(6) bean column node template construction;Template uses aluminum dipping form at bean column node, guarantees node concrete presentation quality, During formwork, the protection of column muscle at Ying Jiaqiang node;
(7) bean column node concreting with vibrate;It carries out bean column node concreting according to design requirement and vibrates, Column muscle is avoided in work progress crosses large disturbances;
(8) control mold installation, fixed: bean column node concreting is finished with vibrating, before concrete initial set, according to The control die location line and control line of prefabricated top surface of the beam carry out the installation of control mold immediately and fix, and are passed through and are fixed using steel wire U-loop is fixed in beam body, is checked again for, is adjusted to column muscle position after fixed;
(9) control mold is removed, is had enough to meet the need: with regard to dismountable control after bean column node concrete actual strength, which reaches certain, to be required Molding jig, and control mold is used in turn, the column muscle position after control mold is removed substantially has met lifting in place It is required that the best position of check column muscle again;
(10) segmented column lifting is in place on: by having carried out adjustment control to column muscle position using control mold, in lifting When segmented column can quickly, accurate contraposition, the lifting of segmented column works in place in completion.
Further, single column muscle position alignment error must not exceed 2mm before the prefabricated post in the step (2) lifts, always Scapus muscle error must not exceed 5mm.
Further, the prefabricated post in the step (3) lifts control errors: plane error is no more than 2mm, and absolute altitude error is not More than 3mm, the error of perpendicularity is no more than 0.4%.
Further, the error after the beam installation in the step (4) is fixed is no more than 2mm.
Further, the error of position line of control mold is no more than 3mm in the step (5), controls the control in place of mold Linear distance position line 100-200mm, in order to carry out control and adjustment in place to control mold.
Further, being fixed temporarily for mold is fixed in beam body using steel wire across fixed U-loop in the step (8), Wherein steel wire uses the high tensile steel wire of diameter 3-6mm, and the absolute altitude in place for controlling die top should be bigger than PC structure top surface of the beam absolute altitude 150-200mm, so that slot milling carries out the Local treatment etc. of node concrete.
Further, node concrete intensity when control mold is removed in the step (9) must reach design strength 85% or more.
The utility model has the advantages that the present invention is fast as prefabricated post lifting using control mold during PC Structure Beam-column node construction Speed auxiliary tool in place, by control mold to column muscle position and node concrete at bean column node before the lifting of upper segmented column is in place Column muscle position progress repeatedly adjustment and control after pouring, it is ensured that column muscle can be quick, accurate in place when construction in later period, effectively mentions High lifting efficiency, saves a large amount of mounting cost, greatly shortens the duration.
Specific embodiment
The present invention is further explained in the light of specific embodiments:
Embodiment 1
The quick construction method in place of column muscle, includes the following steps: at a kind of PC Structure Beam-column node
(1) prefabricated post site acceptance: can be pre- by control mold auxiliary when prefabricated post is transported from factory to engineering site The checking and accepting of column processed is more than the component of code requirement to column muscle design position deviation, forbids to march into the arena;
(2) prefabricated post lifting front pillar muscle position adjustment: prefabricated post is secondary prefabricated using control mold inspection before lifting The deviation situation of column column muscle, and just successive step appropriate is carried out, column muscle excessive error as caused by the human factors such as lifting Component, when construction also forbids to lift, be lifted after to be adjusted, and single column muscle position alignment error must not before prefabricated post lifts More than 2mm, total scapus muscle error must not exceed 5mm;
(3) lifting of prefabricated post: the precast column unit of control mould secondary passed examination has been passed through to column muscle, can carry out Lifting construction, when lifting, will reinforce the protection work to component, and the especially protection to column muscle avoids the factors such as lifting collision from leading Column muscle position is caused to generate biggish deviation.It therefore, also will be by code requirement to the column muscle error in place and to prefabricated post in place It tightens control, prefabricated post lifts control errors: plane error is no more than 2mm, and absolute altitude error is no more than 3mm, and the error of perpendicularity is not More than 0.4%;
(4) lifting of precast beam: before hoisting beam, the Hoisting Position of check column and adjustment, the good beam of bullet is in place on shaft The lifting of the laggard cross girders of control line, and the lifting error of beam is rationally controlled, while avoiding interference pre- in precast beam hoisting process Column column muscle processed, the error after beam installation is fixed are no more than 2mm;
(5) bullet controls mold control line in place: after prefabricated beam column lifting is in place, will control mold in the top surface of precast beam Position line pop-up pops up control mold control line in place, again based on the position line for controlling mold again preferably in order to the later period Check work in work progress, the error of position line for controlling mold are no more than 3mm, control the control line in place of mold apart from position Line 100mm is set, in order to carry out control and adjustment in place to control mold;
(6) bean column node template construction;Template uses aluminum dipping form at bean column node, guarantees node concrete presentation quality, During formwork, the protection of column muscle at Ying Jiaqiang node;
(7) bean column node concreting with vibrate;It carries out bean column node concreting according to design requirement and vibrates, Column muscle is avoided in work progress crosses large disturbances;
(8) control mold installation, fixed: bean column node concreting is finished with vibrating, before concrete initial set, according to The control die location line and control line of prefabricated top surface of the beam carry out the installation of control mold immediately and fix, and are passed through and are fixed using steel wire U-loop is fixed in beam body, and wherein steel wire uses the high tensile steel wire of diameter 3mm, and the absolute altitude in place for controlling die top should compare PC The big 150mm of structure top surface of the beam absolute altitude, so that slot milling carries out the Local treatment etc. of node concrete;
(9) control mold is removed, is had enough to meet the need: with regard to dismountable control after bean column node concrete actual strength, which reaches certain, to be required Molding jig, and control mold is used in turn, the column muscle position after control mold is removed substantially has met lifting in place It is required that preferably the position of check column muscle, node concrete intensity when control mold is removed must reach design strength again 85% or more.
(10) segmented column lifting is in place on: by having carried out adjustment control to column muscle position using control mold, in lifting When segmented column can quickly, accurate contraposition, the lifting of segmented column works in place in completion.
Embodiment 2
The quick construction method in place of column muscle, includes the following steps: at a kind of PC Structure Beam-column node
(1) prefabricated post site acceptance: can be pre- by control mold auxiliary when prefabricated post is transported from factory to engineering site The checking and accepting of column processed is more than the component of code requirement to column muscle design position deviation, forbids to march into the arena;
(2) prefabricated post lifting front pillar muscle position adjustment: prefabricated post is secondary prefabricated using control mold inspection before lifting The deviation situation of column column muscle, and just successive step appropriate is carried out, column muscle excessive error as caused by the human factors such as lifting Component, when construction also forbids to lift, be lifted after to be adjusted, and single column muscle position alignment error must not before prefabricated post lifts More than 2mm, total scapus muscle error must not exceed 5mm;
(3) lifting of prefabricated post: the precast column unit of control mould secondary passed examination has been passed through to column muscle, can carry out Lifting construction, when lifting, will reinforce the protection work to component, and the especially protection to column muscle avoids the factors such as lifting collision from leading Column muscle position is caused to generate biggish deviation.It therefore, also will be by code requirement to the column muscle error in place and to prefabricated post in place It tightens control, prefabricated post lifts control errors: plane error is no more than 2mm, and absolute altitude error is no more than 3mm, and the error of perpendicularity is not More than 0.4%;
(4) lifting of precast beam: before hoisting beam, the Hoisting Position of check column and adjustment, the good beam of bullet is in place on shaft The lifting of the laggard cross girders of control line, and the lifting error of beam is rationally controlled, while avoiding interference pre- in precast beam hoisting process Column column muscle processed, the error after beam installation is fixed are no more than 2mm;
(5) bullet controls mold control line in place: after prefabricated beam column lifting is in place, will control mold in the top surface of precast beam Position line pop-up pops up control mold control line in place, again based on the position line for controlling mold again preferably in order to the later period Check work in work progress, the error of position line for controlling mold are no more than 3mm, control the control line in place of mold apart from position Line 150mm is set, in order to carry out control and adjustment in place to control mold;
(6) bean column node template construction;Template uses aluminum dipping form at bean column node, guarantees node concrete presentation quality, During formwork, the protection of column muscle at Ying Jiaqiang node;
(7) bean column node concreting with vibrate;It carries out bean column node concreting according to design requirement and vibrates, Column muscle is avoided in work progress crosses large disturbances;
(8) control mold installation, fixed: bean column node concreting is finished with vibrating, before concrete initial set, according to The control die location line and control line of prefabricated top surface of the beam carry out the installation of control mold immediately and fix, and are passed through and are fixed using steel wire U-loop is fixed in beam body, and wherein steel wire uses the high tensile steel wire of diameter 5mm, and the absolute altitude in place for controlling die top should compare PC The big 200mm of structure top surface of the beam absolute altitude, so that slot milling carries out the Local treatment etc. of node concrete;
(9) control mold is removed, is had enough to meet the need: with regard to dismountable control after bean column node concrete actual strength, which reaches certain, to be required Molding jig, and control mold is used in turn, the column muscle position after control mold is removed substantially has met lifting in place It is required that preferably the position of check column muscle, node concrete intensity when control mold is removed must reach design strength again 85% or more.
(10) segmented column lifting is in place on: by having carried out adjustment control to column muscle position using control mold, in lifting When segmented column can quickly, accurate contraposition, the lifting of segmented column works in place in completion.
Embodiment 3
The quick construction method in place of column muscle, includes the following steps: at a kind of PC Structure Beam-column node
(1) prefabricated post site acceptance: can be pre- by control mold auxiliary when prefabricated post is transported from factory to engineering site The checking and accepting of column processed is more than the component of code requirement to column muscle design position deviation, forbids to march into the arena;
(2) prefabricated post lifting front pillar muscle position adjustment: prefabricated post is secondary prefabricated using control mold inspection before lifting The deviation situation of column column muscle, and just successive step appropriate is carried out, column muscle excessive error as caused by the human factors such as lifting Component, when construction also forbids to lift, be lifted after to be adjusted, and single column muscle position alignment error must not before prefabricated post lifts More than 2mm, total scapus muscle error must not exceed 5mm;
(3) lifting of prefabricated post: the precast column unit of control mould secondary passed examination has been passed through to column muscle, can carry out Lifting construction, when lifting, will reinforce the protection work to component, and the especially protection to column muscle avoids the factors such as lifting collision from leading Column muscle position is caused to generate biggish deviation.It therefore, also will be by code requirement to the column muscle error in place and to prefabricated post in place It tightens control, prefabricated post lifts control errors: plane error is no more than 2mm, and absolute altitude error is no more than 3mm, and the error of perpendicularity is not More than 0.4%;
(4) lifting of precast beam: before hoisting beam, the Hoisting Position of check column and adjustment, the good beam of bullet is in place on shaft The lifting of the laggard cross girders of control line, and the lifting error of beam is rationally controlled, while avoiding interference pre- in precast beam hoisting process Column column muscle processed, the error after beam installation is fixed are no more than 2mm;
(5) bullet controls mold control line in place: after prefabricated beam column lifting is in place, will control mold in the top surface of precast beam Position line pop-up pops up control mold control line in place, again based on the position line for controlling mold again preferably in order to the later period Check work in work progress, the error of position line for controlling mold are no more than 3mm, control the control line in place of mold apart from position Line 200mm is set, in order to carry out control and adjustment in place to control mold;
(6) bean column node template construction;Template uses aluminum dipping form at bean column node, guarantees node concrete presentation quality, During formwork, the protection of column muscle at Ying Jiaqiang node;
(7) bean column node concreting with vibrate;It carries out bean column node concreting according to design requirement and vibrates, Column muscle is avoided in work progress crosses large disturbances;
(8) control mold installation, fixed: bean column node concreting is finished with vibrating, before concrete initial set, according to The control die location line and control line of prefabricated top surface of the beam carry out the installation of control mold immediately and fix, and are passed through and are fixed using steel wire U-loop is fixed in beam body, and wherein steel wire uses the high tensile steel wire of diameter 6mm, and the absolute altitude in place for controlling die top should compare PC The big 200mm of structure top surface of the beam absolute altitude, so that slot milling carries out the Local treatment etc. of node concrete;
(9) control mold is removed, is had enough to meet the need: with regard to dismountable control after bean column node concrete actual strength, which reaches certain, to be required Molding jig, and control mold is used in turn, the column muscle position after control mold is removed substantially has met lifting in place It is required that preferably the position of check column muscle, node concrete intensity when control mold is removed must reach design strength again 85% or more.
(10) segmented column lifting is in place on: by having carried out adjustment control to column muscle position using control mold, in lifting When segmented column can quickly, accurate contraposition, the lifting of segmented column works in place in completion.
This hair is during PC Structure Beam-column node construction using control mold as the quick auxiliary in place of prefabricated post lifting Tool, the column after being poured by control mold to column muscle position and node concrete at bean column node before the lifting of upper segmented column is in place Muscle position progress repeatedly adjustment and control, it is ensured that column muscle can be quick, accurate in place when construction in later period, effectively increases lifting effect Rate saves a large amount of mounting cost, greatly shortens the duration.
The above described is only a preferred embodiment of the present invention, be not intended to limit the present invention in any form, though So the present invention has been disclosed as a preferred embodiment, and however, it is not intended to limit the invention, any technology people for being familiar with this profession Member, without departing from the scope of the present invention, when the technology contents using the disclosure above make a little change or modification For the equivalent embodiment of equivalent variations, but anything that does not depart from the technical scheme of the invention content, according to the technical essence of the invention Any simple modification, equivalent change and modification to the above embodiments, all of which are still within the scope of the technical scheme of the invention.

Claims (4)

1. the quick construction method in place of column muscle at a kind of PC Structure Beam-column node, characterized by the following steps:
(1) testing for prefabricated post prefabricated post site acceptance: is assisted by control mold when prefabricated post is transported from factory to engineering site Knock off work, is more than the component of code requirement to column muscle design position deviation, forbids to march into the arena;
(2) prefabricated post lifting front pillar muscle position adjustment: prefabricated post is secondary to check prefabricated post column using control mold before lifting The deviation situation of muscle, and just successive step appropriate is carried out, to the component of column muscle excessive error as caused by lifting, when construction, is answered Forbid to lift, be lifted after to be adjusted;
(3) lifting of prefabricated post: having passed through the precast column unit of control mould secondary passed examination to column muscle, carries out lifting and applies Work, when lifting, will reinforce the protection work to component, avoid lifting collision that column muscle position is caused to generate biggish deviation;Therefore, It also to tighten control by code requirement to the column muscle error in place and to prefabricated post in place;
(4) lifting of precast beam: before hoisting beam, the Hoisting Position of check column and adjustment, the good beam of bullet controls in place on shaft The lifting of the laggard cross girders of line, and the lifting error of beam is rationally controlled, while interference prefabricated post is avoided in precast beam hoisting process Column muscle;
(5) bullet controls mold control line in place: after prefabricated beam column lifting is in place, will control the position of mold in the top surface of precast beam Line pop-up, it should pop up control mold control line in place, again based on the position line for controlling mold again in order to construction in later period Check work in the process;
(6) bean column node template construction;Template uses aluminum dipping form at bean column node, guarantees node concrete presentation quality, in formwork In the process, at Ying Jiaqiang node column muscle protection;
(7) bean column node concreting with vibrate;It carries out bean column node concreting according to design requirement and vibrates, construct Avoid column muscle in the process crosses large disturbances;
(8) control mold installation, fixed: bean column node concreting is finished with vibrating, before concrete initial set, according to prefabricated The control die location line and control line of top surface of the beam carry out the installation of control mold immediately and fix, and pass through fixed U-shaped using steel wire Ring is fixed in beam body, is checked again for, is adjusted to column muscle position after fixed;
(9) control mold is removed, is had enough to meet the need: with regard to dismountable control mould after bean column node concrete actual strength, which reaches certain, to be required Tool, and be used in turn mold is controlled, the column muscle position after control mold is removed substantially has met lifting requirement in place, Should check column muscle again position;
(10) segmented column lifting is in place on: by having carried out adjustment control to column muscle position using control mold, lifting upper segmented column When can quickly, accurate contraposition, the lifting of segmented column works in place in completion;
Single column muscle position alignment error must not exceed 2mm before prefabricated post in the step (2) lifts, and total scapus muscle error is not It obtains more than 5mm;
The error of position line of control mold is no more than 3mm in the step (5), controls the control line position line by distance in place of mold 100-200mm, in order to carry out control and adjustment in place to control mold;
Being fixed temporarily for mold is fixed in beam body using steel wire across fixed U-loop in the step (8), and wherein steel wire uses The high tensile steel wire of diameter 3-6mm, the absolute altitude in place for controlling die top should be 150-200mm bigger than PC structure top surface of the beam absolute altitude, with Just slot milling carries out the Local treatment of node concrete.
2. the quick construction method in place of column muscle at a kind of PC Structure Beam-column node according to claim 1, it is characterised in that: Prefabricated post in the step (3) lifts control errors: plane error is no more than 2mm, and absolute altitude error is no more than 3mm, verticality Error is no more than 0.4%.
3. the quick construction method in place of column muscle at a kind of PC Structure Beam-column node according to claim 1, it is characterised in that: Error after beam installation in the step (4) is fixed is no more than 2mm.
4. the quick construction method in place of column muscle at a kind of PC Structure Beam-column node according to claim 1, it is characterised in that: Node concrete intensity when control mold is removed in the step (9) must reach 85% of design strength or more.
CN201710130448.9A 2017-03-07 2017-03-07 The quick construction method in place of column muscle at PC Structure Beam-column node Active CN106812213B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710130448.9A CN106812213B (en) 2017-03-07 2017-03-07 The quick construction method in place of column muscle at PC Structure Beam-column node

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710130448.9A CN106812213B (en) 2017-03-07 2017-03-07 The quick construction method in place of column muscle at PC Structure Beam-column node

Publications (2)

Publication Number Publication Date
CN106812213A CN106812213A (en) 2017-06-09
CN106812213B true CN106812213B (en) 2019-06-14

Family

ID=59114636

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710130448.9A Active CN106812213B (en) 2017-03-07 2017-03-07 The quick construction method in place of column muscle at PC Structure Beam-column node

Country Status (1)

Country Link
CN (1) CN106812213B (en)

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6192238A (en) * 1984-10-08 1986-05-10 清水建設株式会社 Anchoring of pc pillar
JPH0754397A (en) * 1993-08-16 1995-02-28 Fujita Corp Erection construction method of precast concrete column
CN105625730A (en) * 2015-12-25 2016-06-01 中民筑友有限公司 Method for assembling precast column
CN205444945U (en) * 2015-12-25 2016-08-10 中民筑友有限公司 Bar reinforcement positioning device
CN205369939U (en) * 2015-12-25 2016-07-06 中民筑友有限公司 Bar reinforcement positioning device
CN106013434B (en) * 2016-07-18 2019-01-08 江苏工程职业技术学院 Bean column node fixed structure and installation method among a kind of prefabricated construction

Also Published As

Publication number Publication date
CN106812213A (en) 2017-06-09

Similar Documents

Publication Publication Date Title
CN208310140U (en) A kind of precast stair accurate assembly accessory part
CN104895279B (en) The cladding attachment structure and its construction method of precast wall panel and precast beam
CN102767288A (en) Method and structure for mounting precast reinforced concrete stairs
CN104631837A (en) Method for installing and constructing special-shaped large-tonnage steel castings
CN104389268B (en) A kind of steel tower column with location structure and construction method for hanging thereof
CN105464216B (en) Construction method based on integral lifting formwork-strengthening system superelevation super-section batter post
CN208965714U (en) A kind of prefabricated piping lane main frame structure of assembly concrete
CN106759947A (en) Assembly concrete-filled steel tube post post connected mode
CN105780995A (en) Curved surface space pipe truss structure and mounting method thereof
CN103485574A (en) Method for constructing reinforced concrete structure of tower top of prilling tower
CN103104090A (en) Silo house concrete whole sliding and ascending module
CN106812213B (en) The quick construction method in place of column muscle at PC Structure Beam-column node
CN104675112A (en) Steel stair formwork and constructing method for once pouring forming of building staircase
CN104912231A (en) Dry-hanging connecting structure of precast outer wall panel and shear wall and construction method of same
CN102561196A (en) Turnover construction process of high-pier forms
CN205063248U (en) Prefabricated exterior wall board and precast beam hang connection structure futilely
CN104131635B (en) Method and platform for constructing peripheral shear wall of prefabricated staircase
CN215889394U (en) Device for controlling elevation of cast large-area floor slab
CN202831621U (en) Integrated slipform for silo concrete
CN215104696U (en) Template system for construction of thin-wall hollow pier of bridge
CN115126254A (en) Construction method of assembled composite floor slab support
CN205310501U (en) Apparatus for producing of precast concrete decking
CN204626965U (en) For the steel stair template of poured up at a time between architectural stair
CN205712473U (en) A kind of PC beam column node connection device
CN107542164A (en) Build the suspension column terrace crack resistence construction method of pillar

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant