CN106812213B - The quick construction method in place of column muscle at PC Structure Beam-column node - Google Patents
The quick construction method in place of column muscle at PC Structure Beam-column node Download PDFInfo
- Publication number
- CN106812213B CN106812213B CN201710130448.9A CN201710130448A CN106812213B CN 106812213 B CN106812213 B CN 106812213B CN 201710130448 A CN201710130448 A CN 201710130448A CN 106812213 B CN106812213 B CN 106812213B
- Authority
- CN
- China
- Prior art keywords
- column
- place
- lifting
- control
- muscle
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/18—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
- E04B1/20—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of concrete, e.g. reinforced concrete, or other stonelike material
- E04B1/21—Connections specially adapted therefor
Abstract
The invention discloses a kind of quick construction methods in place of column muscle at PC Structure Beam-column node, include the following steps: prefabricated post lifting front pillar muscle position adjustment;The lifting of prefabricated post;The lifting of precast beam;Bullet controls mold control line in place;It controls mold installation, fix;Bean column node template construction;Bean column node concreting and maintenance;Mold is controlled to remove, have enough to meet the need;Upper segmented column lifting is in place.The present invention lifts quickly auxiliary tool in place as prefabricated post using control mold during PC Structure Beam-column node construction, column muscle position after being poured by control mold to column muscle position and node concrete at bean column node before the lifting of upper segmented column is in place carries out repeatedly adjustment and controls, ensure that column muscle can be quick, accurate in place when construction in later period, effectively increase lifting efficiency, a large amount of mounting cost is saved, the duration is greatly shortened.
Description
Technical field
The present invention relates to a kind of column muscle control methods in place, and in particular to column muscle is quickly at a kind of PC Structure Beam-column node
Position construction method.
Background technique
At home and abroad development speed is very fast for prefabricated construction, and in China, prefabricated construction construction technology is mature
Degree be not also it is very high, especially PC structural elements connecting node tectonic sieving and component be accurate, quick aspect in place, reinforce
It is a major issue for being currently badly in need of capturing to component connecting node tectonic sieving, construction and quick location control, to subtract
Few cost.
Summary of the invention
Goal of the invention: the present invention aiming at the shortcomings in the prior art, uses control during PC Structure Beam-column node construction
Molding jig lifts quickly auxiliary tool in place as prefabricated post, by control mold to bean column node before the lifting of upper segmented column is in place
Column muscle position after place column muscle position and node concrete pour carries out repeatedly adjustment and control, it is ensured that column muscle energy when construction in later period
It is enough quick, accurate in place, lifting efficiency is effectively increased, a large amount of mounting cost is saved, greatly shortens a kind of PC knot of duration
The quick construction method in place of column muscle at structure bean column node.
Technical solution: the quick construction method in place of column muscle at a kind of PC Structure Beam-column node of the present invention, including such as
Lower step:
(1) prefabricated post site acceptance: can be pre- by control mold auxiliary when prefabricated post is transported from factory to engineering site
The checking and accepting of column processed is more than the component of code requirement to column muscle design position deviation, forbids to march into the arena;
(2) prefabricated post lifting front pillar muscle position adjustment: prefabricated post is secondary prefabricated using control mold inspection before lifting
The deviation situation of column column muscle, and just successive step appropriate is carried out, column muscle excessive error as caused by the human factors such as lifting
Component, when construction also forbids to lift, be lifted after to be adjusted;
(3) lifting of prefabricated post: the precast column unit of control mould secondary passed examination has been passed through to column muscle, can carry out
Lifting construction, when lifting, will reinforce the protection work to component, and the especially protection to column muscle avoids the factors such as lifting collision from leading
Column muscle position is caused to generate biggish deviation.It therefore, also will be by code requirement to the column muscle error in place and to prefabricated post in place
It tightens control;
(4) lifting of precast beam: before hoisting beam, the Hoisting Position of check column and adjustment, the good beam of bullet is in place on shaft
The lifting of the laggard cross girders of control line, and the lifting error of beam is rationally controlled, while avoiding interference pre- in precast beam hoisting process
Column column muscle processed;
(5) bullet controls mold control line in place: after prefabricated beam column lifting is in place, will control mold in the top surface of precast beam
Position line pop-up pops up control mold control line in place, again based on the position line for controlling mold again preferably in order to the later period
Check work in work progress;
(6) bean column node template construction;Template uses aluminum dipping form at bean column node, guarantees node concrete presentation quality,
During formwork, the protection of column muscle at Ying Jiaqiang node;
(7) bean column node concreting with vibrate;It carries out bean column node concreting according to design requirement and vibrates,
Column muscle is avoided in work progress crosses large disturbances;
(8) control mold installation, fixed: bean column node concreting is finished with vibrating, before concrete initial set, according to
The control die location line and control line of prefabricated top surface of the beam carry out the installation of control mold immediately and fix, and are passed through and are fixed using steel wire
U-loop is fixed in beam body, is checked again for, is adjusted to column muscle position after fixed;
(9) control mold is removed, is had enough to meet the need: with regard to dismountable control after bean column node concrete actual strength, which reaches certain, to be required
Molding jig, and control mold is used in turn, the column muscle position after control mold is removed substantially has met lifting in place
It is required that the best position of check column muscle again;
(10) segmented column lifting is in place on: by having carried out adjustment control to column muscle position using control mold, in lifting
When segmented column can quickly, accurate contraposition, the lifting of segmented column works in place in completion.
Further, single column muscle position alignment error must not exceed 2mm before the prefabricated post in the step (2) lifts, always
Scapus muscle error must not exceed 5mm.
Further, the prefabricated post in the step (3) lifts control errors: plane error is no more than 2mm, and absolute altitude error is not
More than 3mm, the error of perpendicularity is no more than 0.4%.
Further, the error after the beam installation in the step (4) is fixed is no more than 2mm.
Further, the error of position line of control mold is no more than 3mm in the step (5), controls the control in place of mold
Linear distance position line 100-200mm, in order to carry out control and adjustment in place to control mold.
Further, being fixed temporarily for mold is fixed in beam body using steel wire across fixed U-loop in the step (8),
Wherein steel wire uses the high tensile steel wire of diameter 3-6mm, and the absolute altitude in place for controlling die top should be bigger than PC structure top surface of the beam absolute altitude
150-200mm, so that slot milling carries out the Local treatment etc. of node concrete.
Further, node concrete intensity when control mold is removed in the step (9) must reach design strength
85% or more.
The utility model has the advantages that the present invention is fast as prefabricated post lifting using control mold during PC Structure Beam-column node construction
Speed auxiliary tool in place, by control mold to column muscle position and node concrete at bean column node before the lifting of upper segmented column is in place
Column muscle position progress repeatedly adjustment and control after pouring, it is ensured that column muscle can be quick, accurate in place when construction in later period, effectively mentions
High lifting efficiency, saves a large amount of mounting cost, greatly shortens the duration.
Specific embodiment
The present invention is further explained in the light of specific embodiments:
Embodiment 1
The quick construction method in place of column muscle, includes the following steps: at a kind of PC Structure Beam-column node
(1) prefabricated post site acceptance: can be pre- by control mold auxiliary when prefabricated post is transported from factory to engineering site
The checking and accepting of column processed is more than the component of code requirement to column muscle design position deviation, forbids to march into the arena;
(2) prefabricated post lifting front pillar muscle position adjustment: prefabricated post is secondary prefabricated using control mold inspection before lifting
The deviation situation of column column muscle, and just successive step appropriate is carried out, column muscle excessive error as caused by the human factors such as lifting
Component, when construction also forbids to lift, be lifted after to be adjusted, and single column muscle position alignment error must not before prefabricated post lifts
More than 2mm, total scapus muscle error must not exceed 5mm;
(3) lifting of prefabricated post: the precast column unit of control mould secondary passed examination has been passed through to column muscle, can carry out
Lifting construction, when lifting, will reinforce the protection work to component, and the especially protection to column muscle avoids the factors such as lifting collision from leading
Column muscle position is caused to generate biggish deviation.It therefore, also will be by code requirement to the column muscle error in place and to prefabricated post in place
It tightens control, prefabricated post lifts control errors: plane error is no more than 2mm, and absolute altitude error is no more than 3mm, and the error of perpendicularity is not
More than 0.4%;
(4) lifting of precast beam: before hoisting beam, the Hoisting Position of check column and adjustment, the good beam of bullet is in place on shaft
The lifting of the laggard cross girders of control line, and the lifting error of beam is rationally controlled, while avoiding interference pre- in precast beam hoisting process
Column column muscle processed, the error after beam installation is fixed are no more than 2mm;
(5) bullet controls mold control line in place: after prefabricated beam column lifting is in place, will control mold in the top surface of precast beam
Position line pop-up pops up control mold control line in place, again based on the position line for controlling mold again preferably in order to the later period
Check work in work progress, the error of position line for controlling mold are no more than 3mm, control the control line in place of mold apart from position
Line 100mm is set, in order to carry out control and adjustment in place to control mold;
(6) bean column node template construction;Template uses aluminum dipping form at bean column node, guarantees node concrete presentation quality,
During formwork, the protection of column muscle at Ying Jiaqiang node;
(7) bean column node concreting with vibrate;It carries out bean column node concreting according to design requirement and vibrates,
Column muscle is avoided in work progress crosses large disturbances;
(8) control mold installation, fixed: bean column node concreting is finished with vibrating, before concrete initial set, according to
The control die location line and control line of prefabricated top surface of the beam carry out the installation of control mold immediately and fix, and are passed through and are fixed using steel wire
U-loop is fixed in beam body, and wherein steel wire uses the high tensile steel wire of diameter 3mm, and the absolute altitude in place for controlling die top should compare PC
The big 150mm of structure top surface of the beam absolute altitude, so that slot milling carries out the Local treatment etc. of node concrete;
(9) control mold is removed, is had enough to meet the need: with regard to dismountable control after bean column node concrete actual strength, which reaches certain, to be required
Molding jig, and control mold is used in turn, the column muscle position after control mold is removed substantially has met lifting in place
It is required that preferably the position of check column muscle, node concrete intensity when control mold is removed must reach design strength again
85% or more.
(10) segmented column lifting is in place on: by having carried out adjustment control to column muscle position using control mold, in lifting
When segmented column can quickly, accurate contraposition, the lifting of segmented column works in place in completion.
Embodiment 2
The quick construction method in place of column muscle, includes the following steps: at a kind of PC Structure Beam-column node
(1) prefabricated post site acceptance: can be pre- by control mold auxiliary when prefabricated post is transported from factory to engineering site
The checking and accepting of column processed is more than the component of code requirement to column muscle design position deviation, forbids to march into the arena;
(2) prefabricated post lifting front pillar muscle position adjustment: prefabricated post is secondary prefabricated using control mold inspection before lifting
The deviation situation of column column muscle, and just successive step appropriate is carried out, column muscle excessive error as caused by the human factors such as lifting
Component, when construction also forbids to lift, be lifted after to be adjusted, and single column muscle position alignment error must not before prefabricated post lifts
More than 2mm, total scapus muscle error must not exceed 5mm;
(3) lifting of prefabricated post: the precast column unit of control mould secondary passed examination has been passed through to column muscle, can carry out
Lifting construction, when lifting, will reinforce the protection work to component, and the especially protection to column muscle avoids the factors such as lifting collision from leading
Column muscle position is caused to generate biggish deviation.It therefore, also will be by code requirement to the column muscle error in place and to prefabricated post in place
It tightens control, prefabricated post lifts control errors: plane error is no more than 2mm, and absolute altitude error is no more than 3mm, and the error of perpendicularity is not
More than 0.4%;
(4) lifting of precast beam: before hoisting beam, the Hoisting Position of check column and adjustment, the good beam of bullet is in place on shaft
The lifting of the laggard cross girders of control line, and the lifting error of beam is rationally controlled, while avoiding interference pre- in precast beam hoisting process
Column column muscle processed, the error after beam installation is fixed are no more than 2mm;
(5) bullet controls mold control line in place: after prefabricated beam column lifting is in place, will control mold in the top surface of precast beam
Position line pop-up pops up control mold control line in place, again based on the position line for controlling mold again preferably in order to the later period
Check work in work progress, the error of position line for controlling mold are no more than 3mm, control the control line in place of mold apart from position
Line 150mm is set, in order to carry out control and adjustment in place to control mold;
(6) bean column node template construction;Template uses aluminum dipping form at bean column node, guarantees node concrete presentation quality,
During formwork, the protection of column muscle at Ying Jiaqiang node;
(7) bean column node concreting with vibrate;It carries out bean column node concreting according to design requirement and vibrates,
Column muscle is avoided in work progress crosses large disturbances;
(8) control mold installation, fixed: bean column node concreting is finished with vibrating, before concrete initial set, according to
The control die location line and control line of prefabricated top surface of the beam carry out the installation of control mold immediately and fix, and are passed through and are fixed using steel wire
U-loop is fixed in beam body, and wherein steel wire uses the high tensile steel wire of diameter 5mm, and the absolute altitude in place for controlling die top should compare PC
The big 200mm of structure top surface of the beam absolute altitude, so that slot milling carries out the Local treatment etc. of node concrete;
(9) control mold is removed, is had enough to meet the need: with regard to dismountable control after bean column node concrete actual strength, which reaches certain, to be required
Molding jig, and control mold is used in turn, the column muscle position after control mold is removed substantially has met lifting in place
It is required that preferably the position of check column muscle, node concrete intensity when control mold is removed must reach design strength again
85% or more.
(10) segmented column lifting is in place on: by having carried out adjustment control to column muscle position using control mold, in lifting
When segmented column can quickly, accurate contraposition, the lifting of segmented column works in place in completion.
Embodiment 3
The quick construction method in place of column muscle, includes the following steps: at a kind of PC Structure Beam-column node
(1) prefabricated post site acceptance: can be pre- by control mold auxiliary when prefabricated post is transported from factory to engineering site
The checking and accepting of column processed is more than the component of code requirement to column muscle design position deviation, forbids to march into the arena;
(2) prefabricated post lifting front pillar muscle position adjustment: prefabricated post is secondary prefabricated using control mold inspection before lifting
The deviation situation of column column muscle, and just successive step appropriate is carried out, column muscle excessive error as caused by the human factors such as lifting
Component, when construction also forbids to lift, be lifted after to be adjusted, and single column muscle position alignment error must not before prefabricated post lifts
More than 2mm, total scapus muscle error must not exceed 5mm;
(3) lifting of prefabricated post: the precast column unit of control mould secondary passed examination has been passed through to column muscle, can carry out
Lifting construction, when lifting, will reinforce the protection work to component, and the especially protection to column muscle avoids the factors such as lifting collision from leading
Column muscle position is caused to generate biggish deviation.It therefore, also will be by code requirement to the column muscle error in place and to prefabricated post in place
It tightens control, prefabricated post lifts control errors: plane error is no more than 2mm, and absolute altitude error is no more than 3mm, and the error of perpendicularity is not
More than 0.4%;
(4) lifting of precast beam: before hoisting beam, the Hoisting Position of check column and adjustment, the good beam of bullet is in place on shaft
The lifting of the laggard cross girders of control line, and the lifting error of beam is rationally controlled, while avoiding interference pre- in precast beam hoisting process
Column column muscle processed, the error after beam installation is fixed are no more than 2mm;
(5) bullet controls mold control line in place: after prefabricated beam column lifting is in place, will control mold in the top surface of precast beam
Position line pop-up pops up control mold control line in place, again based on the position line for controlling mold again preferably in order to the later period
Check work in work progress, the error of position line for controlling mold are no more than 3mm, control the control line in place of mold apart from position
Line 200mm is set, in order to carry out control and adjustment in place to control mold;
(6) bean column node template construction;Template uses aluminum dipping form at bean column node, guarantees node concrete presentation quality,
During formwork, the protection of column muscle at Ying Jiaqiang node;
(7) bean column node concreting with vibrate;It carries out bean column node concreting according to design requirement and vibrates,
Column muscle is avoided in work progress crosses large disturbances;
(8) control mold installation, fixed: bean column node concreting is finished with vibrating, before concrete initial set, according to
The control die location line and control line of prefabricated top surface of the beam carry out the installation of control mold immediately and fix, and are passed through and are fixed using steel wire
U-loop is fixed in beam body, and wherein steel wire uses the high tensile steel wire of diameter 6mm, and the absolute altitude in place for controlling die top should compare PC
The big 200mm of structure top surface of the beam absolute altitude, so that slot milling carries out the Local treatment etc. of node concrete;
(9) control mold is removed, is had enough to meet the need: with regard to dismountable control after bean column node concrete actual strength, which reaches certain, to be required
Molding jig, and control mold is used in turn, the column muscle position after control mold is removed substantially has met lifting in place
It is required that preferably the position of check column muscle, node concrete intensity when control mold is removed must reach design strength again
85% or more.
(10) segmented column lifting is in place on: by having carried out adjustment control to column muscle position using control mold, in lifting
When segmented column can quickly, accurate contraposition, the lifting of segmented column works in place in completion.
This hair is during PC Structure Beam-column node construction using control mold as the quick auxiliary in place of prefabricated post lifting
Tool, the column after being poured by control mold to column muscle position and node concrete at bean column node before the lifting of upper segmented column is in place
Muscle position progress repeatedly adjustment and control, it is ensured that column muscle can be quick, accurate in place when construction in later period, effectively increases lifting effect
Rate saves a large amount of mounting cost, greatly shortens the duration.
The above described is only a preferred embodiment of the present invention, be not intended to limit the present invention in any form, though
So the present invention has been disclosed as a preferred embodiment, and however, it is not intended to limit the invention, any technology people for being familiar with this profession
Member, without departing from the scope of the present invention, when the technology contents using the disclosure above make a little change or modification
For the equivalent embodiment of equivalent variations, but anything that does not depart from the technical scheme of the invention content, according to the technical essence of the invention
Any simple modification, equivalent change and modification to the above embodiments, all of which are still within the scope of the technical scheme of the invention.
Claims (4)
1. the quick construction method in place of column muscle at a kind of PC Structure Beam-column node, characterized by the following steps:
(1) testing for prefabricated post prefabricated post site acceptance: is assisted by control mold when prefabricated post is transported from factory to engineering site
Knock off work, is more than the component of code requirement to column muscle design position deviation, forbids to march into the arena;
(2) prefabricated post lifting front pillar muscle position adjustment: prefabricated post is secondary to check prefabricated post column using control mold before lifting
The deviation situation of muscle, and just successive step appropriate is carried out, to the component of column muscle excessive error as caused by lifting, when construction, is answered
Forbid to lift, be lifted after to be adjusted;
(3) lifting of prefabricated post: having passed through the precast column unit of control mould secondary passed examination to column muscle, carries out lifting and applies
Work, when lifting, will reinforce the protection work to component, avoid lifting collision that column muscle position is caused to generate biggish deviation;Therefore,
It also to tighten control by code requirement to the column muscle error in place and to prefabricated post in place;
(4) lifting of precast beam: before hoisting beam, the Hoisting Position of check column and adjustment, the good beam of bullet controls in place on shaft
The lifting of the laggard cross girders of line, and the lifting error of beam is rationally controlled, while interference prefabricated post is avoided in precast beam hoisting process
Column muscle;
(5) bullet controls mold control line in place: after prefabricated beam column lifting is in place, will control the position of mold in the top surface of precast beam
Line pop-up, it should pop up control mold control line in place, again based on the position line for controlling mold again in order to construction in later period
Check work in the process;
(6) bean column node template construction;Template uses aluminum dipping form at bean column node, guarantees node concrete presentation quality, in formwork
In the process, at Ying Jiaqiang node column muscle protection;
(7) bean column node concreting with vibrate;It carries out bean column node concreting according to design requirement and vibrates, construct
Avoid column muscle in the process crosses large disturbances;
(8) control mold installation, fixed: bean column node concreting is finished with vibrating, before concrete initial set, according to prefabricated
The control die location line and control line of top surface of the beam carry out the installation of control mold immediately and fix, and pass through fixed U-shaped using steel wire
Ring is fixed in beam body, is checked again for, is adjusted to column muscle position after fixed;
(9) control mold is removed, is had enough to meet the need: with regard to dismountable control mould after bean column node concrete actual strength, which reaches certain, to be required
Tool, and be used in turn mold is controlled, the column muscle position after control mold is removed substantially has met lifting requirement in place,
Should check column muscle again position;
(10) segmented column lifting is in place on: by having carried out adjustment control to column muscle position using control mold, lifting upper segmented column
When can quickly, accurate contraposition, the lifting of segmented column works in place in completion;
Single column muscle position alignment error must not exceed 2mm before prefabricated post in the step (2) lifts, and total scapus muscle error is not
It obtains more than 5mm;
The error of position line of control mold is no more than 3mm in the step (5), controls the control line position line by distance in place of mold
100-200mm, in order to carry out control and adjustment in place to control mold;
Being fixed temporarily for mold is fixed in beam body using steel wire across fixed U-loop in the step (8), and wherein steel wire uses
The high tensile steel wire of diameter 3-6mm, the absolute altitude in place for controlling die top should be 150-200mm bigger than PC structure top surface of the beam absolute altitude, with
Just slot milling carries out the Local treatment of node concrete.
2. the quick construction method in place of column muscle at a kind of PC Structure Beam-column node according to claim 1, it is characterised in that:
Prefabricated post in the step (3) lifts control errors: plane error is no more than 2mm, and absolute altitude error is no more than 3mm, verticality
Error is no more than 0.4%.
3. the quick construction method in place of column muscle at a kind of PC Structure Beam-column node according to claim 1, it is characterised in that:
Error after beam installation in the step (4) is fixed is no more than 2mm.
4. the quick construction method in place of column muscle at a kind of PC Structure Beam-column node according to claim 1, it is characterised in that:
Node concrete intensity when control mold is removed in the step (9) must reach 85% of design strength or more.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710130448.9A CN106812213B (en) | 2017-03-07 | 2017-03-07 | The quick construction method in place of column muscle at PC Structure Beam-column node |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710130448.9A CN106812213B (en) | 2017-03-07 | 2017-03-07 | The quick construction method in place of column muscle at PC Structure Beam-column node |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106812213A CN106812213A (en) | 2017-06-09 |
CN106812213B true CN106812213B (en) | 2019-06-14 |
Family
ID=59114636
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710130448.9A Active CN106812213B (en) | 2017-03-07 | 2017-03-07 | The quick construction method in place of column muscle at PC Structure Beam-column node |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106812213B (en) |
Family Cites Families (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS6192238A (en) * | 1984-10-08 | 1986-05-10 | 清水建設株式会社 | Anchoring of pc pillar |
JPH0754397A (en) * | 1993-08-16 | 1995-02-28 | Fujita Corp | Erection construction method of precast concrete column |
CN105625730A (en) * | 2015-12-25 | 2016-06-01 | 中民筑友有限公司 | Method for assembling precast column |
CN205444945U (en) * | 2015-12-25 | 2016-08-10 | 中民筑友有限公司 | Bar reinforcement positioning device |
CN205369939U (en) * | 2015-12-25 | 2016-07-06 | 中民筑友有限公司 | Bar reinforcement positioning device |
CN106013434B (en) * | 2016-07-18 | 2019-01-08 | 江苏工程职业技术学院 | Bean column node fixed structure and installation method among a kind of prefabricated construction |
-
2017
- 2017-03-07 CN CN201710130448.9A patent/CN106812213B/en active Active
Also Published As
Publication number | Publication date |
---|---|
CN106812213A (en) | 2017-06-09 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN208310140U (en) | A kind of precast stair accurate assembly accessory part | |
CN104895279B (en) | The cladding attachment structure and its construction method of precast wall panel and precast beam | |
CN102767288A (en) | Method and structure for mounting precast reinforced concrete stairs | |
CN104631837A (en) | Method for installing and constructing special-shaped large-tonnage steel castings | |
CN104389268B (en) | A kind of steel tower column with location structure and construction method for hanging thereof | |
CN105464216B (en) | Construction method based on integral lifting formwork-strengthening system superelevation super-section batter post | |
CN208965714U (en) | A kind of prefabricated piping lane main frame structure of assembly concrete | |
CN106759947A (en) | Assembly concrete-filled steel tube post post connected mode | |
CN105780995A (en) | Curved surface space pipe truss structure and mounting method thereof | |
CN103485574A (en) | Method for constructing reinforced concrete structure of tower top of prilling tower | |
CN103104090A (en) | Silo house concrete whole sliding and ascending module | |
CN106812213B (en) | The quick construction method in place of column muscle at PC Structure Beam-column node | |
CN104675112A (en) | Steel stair formwork and constructing method for once pouring forming of building staircase | |
CN104912231A (en) | Dry-hanging connecting structure of precast outer wall panel and shear wall and construction method of same | |
CN102561196A (en) | Turnover construction process of high-pier forms | |
CN205063248U (en) | Prefabricated exterior wall board and precast beam hang connection structure futilely | |
CN104131635B (en) | Method and platform for constructing peripheral shear wall of prefabricated staircase | |
CN215889394U (en) | Device for controlling elevation of cast large-area floor slab | |
CN202831621U (en) | Integrated slipform for silo concrete | |
CN215104696U (en) | Template system for construction of thin-wall hollow pier of bridge | |
CN115126254A (en) | Construction method of assembled composite floor slab support | |
CN205310501U (en) | Apparatus for producing of precast concrete decking | |
CN204626965U (en) | For the steel stair template of poured up at a time between architectural stair | |
CN205712473U (en) | A kind of PC beam column node connection device | |
CN107542164A (en) | Build the suspension column terrace crack resistence construction method of pillar |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |