Bean column node fixed structure and installation method among a kind of prefabricated construction
Technical field
The present invention relates to a kind of bean column node fixed setting methods, and in particular to a kind of prefabricated construction centre beam column
Node fixed setting method.
Background technique
In recent years, prefabricated assembled continuous development and progress with new building technology and material, prefabrication
It is widely used.In the country of many building industrialization prosperities, prefabrication experienced long-term experiment and
Using, the prefabrication product of modernization can highly integrated building various functions, and the form built
It is very exquisite with component.China's construction demand amount is big, construction speed is fast, it is necessary to develop prefabrication, then right
Prefabricated construction joint structure requires and hoisting is also higher and higher.Traditional prefabricated construction hoisting cost compared with
Height, lifting speed is low with precision, this brings very big difficulty to construction, and the adjustment of hoisting process error occupies largely
Duration of a project, therefore, prefabrication lifting also need hanging method further to innovate and grind to realize industry modernization
Study carefully.
Summary of the invention
Goal of the invention: the purpose of the present invention is to solve deficiency in the prior art, provide it is a kind of reasonable in design,
Precast beam installs precision height in place, and construction hoisting speed is fast, and tie support frame can be used in turn, and beam bottom support use compares
Traditional hanging method is many less, save among a kind of prefabricated construction of Construction Cost beam-column node structure and its
Fixed setting method.
Technical solution: a kind of prefabricated construction centre bean column node fixed structure of the present invention, including it is prefabricated
Column and precast beam, longitudinally prefabricated post muscle with outward extension, the precast beam are transversely provided with precast beam muscle, institute to the prefabricated post
It states and is additionally provided with bilateral tie support frame at the node of the handover of prefabricated post and precast beam, the bilateral tie support frame includes connection
The steel angle brace and steel column hoop being structure as a whole, the steel angle brace is two and is separately positioned on the two sides of the steel column hoop, described
Steel angle brace is respectively used to the support in place when support precast beam lifting, and steel column hoop is mounted in prefabricated post, as holding for support frame
Carry fulcrum.
Further, the closed triangular prism that the steel angle brace is made of 5 blocks of steel plates, steel column hoop are by 4 pieces of steel plate groups
At upper and lower opening quadrangular, and steel angle brace and steel column hoop share two blocks of steel plates.
Further, the thickness of the steel plate is not less than 40mm.
Further, in a pre-installation, bullet has got well installation control line to the bilateral tie support frame on shaft.
Further, the bilateral tie support frame can be torn open when node strength reaches the 50% of concrete design strength
It removes.
The invention also discloses a kind of installation method of above-mentioned prefabricated construction centre bean column node fixed structure, packets
Include following steps:
(1) prefabricated post lifts: prefabricated post lifting answers strict control column to lift quality, and Horizontal position errors are no more than 5mm, hangs down
Straight error is no more than 3mm;
(2) play precast beam and lift absolute altitude control line: prefabricated post lifting fixation finishes, and lifts absolute altitude in shaft pop-up precast beam
Control line, under special circumstances it is also contemplated that error transfer factor value;
(3) tie support frame and the installation of beam bottom bracket: precast beam is carried out according to shaft control line, error transfer factor value size and is hung
Dress work in place;
(4) precast beam lifts, is fixed;
(5) precast beam Hoisting Position is reviewed, is adjusted;
(6) bean column node formwork erection;
(7) bean column node concreting, maintenance;
(8) tie support frame is removed, is had enough to meet the need.
The utility model has the advantages that structure of the invention is reasonable, precast beam installs precision height in place, and construction hoisting speed is fast, tie support
Frame can be used in turn, and beam bottom support use traditional hanging method that compares is many less, save Construction Cost, with compared with
Good economic benefit.
Detailed description of the invention
Fig. 1 is the overall schematic of node structure of the present invention;
Fig. 2 is the bilateral tie support frame structure diagram of the present invention.
Specific embodiment
Bean column node fixed structure among a kind of prefabricated construction as depicted in figs. 1 and 2, including 5 He of prefabricated post
Precast beam 3, the longitudinal prefabricated post muscle 6 with outward extension of the prefabricated post 5, the precast beam 3 are transversely provided with precast beam muscle 4,
Bilateral tie support frame is additionally provided at the node of the handover of the prefabricated post 5 and precast beam 3, the bilateral tie support frame includes
The steel angle brace 1 and steel column hoop 2 being connected as one, the steel angle brace 1 are two and are separately positioned on the two of the steel column hoop 2
Side, the steel angle brace 1 are respectively used to the support in place when support precast beam 3 lifts, and steel column hoop 2 is mounted in prefabricated post 5, as
The carrying fulcrum of support frame.
The closed triangular prism that the steel angle brace 1 is made of 5 blocks of steel plates, steel column hoop 2 are made of upper and lower 4 blocks of steel plates
The quadrangular of opening, two arms of angle can freely be unfolded, and steel angle brace 1 and steel column hoop 2 share two blocks of steel plates.
In a pre-installation, bullet has got well installation control line to the bilateral tie support frame on shaft, after guaranteeing beam lifting
Precision in place.
The bilateral tie support frame rigidity is larger, and installation error adjusted value is easy to control, installation error general control
Within 5mm.
The bilateral tie support frame turnaround speed is fast, (generally takes Concrete Design when node strength reaches preset value
The 50% of intensity), it can first retain part conventional steel bracket, bilateral tie support frame, that is, dismountable realizes early removing system mesh
Mark.
The invention also discloses a kind of installation method of above-mentioned prefabricated construction centre bean column node fixed structure, packets
Include following steps:
(1) prefabricated post lifts: prefabricated post lifting answers strict control column to lift quality, and Horizontal position errors are no more than 5mm, hangs down
Straight error is no more than 3mm;
(2) play precast beam and lift absolute altitude control line: prefabricated post lifting fixation finishes, and lifts absolute altitude in shaft pop-up precast beam
Control line, under special circumstances it is also contemplated that error transfer factor value;
(3) tie support frame and the installation of beam bottom bracket: precast beam is carried out according to shaft control line, error transfer factor value size and is hung
Dress work in place;
(4) precast beam lifts, is fixed;
(5) precast beam Hoisting Position is reviewed, is adjusted;
(6) bean column node formwork erection;
(7) bean column node concreting, maintenance;
(8) tie support frame is removed, is had enough to meet the need.
Structure of the invention is reasonable, and precast beam installs precision height in place, and construction hoisting speed is fast, and tie support frame can have enough to meet the need
It uses, beam bottom support use compares, and traditional hanging method is many less, and saving Construction Cost has good economic effect
Benefit.
The above described is only a preferred embodiment of the present invention, be not intended to limit the present invention in any form, though
So the present invention has been disclosed as a preferred embodiment, and however, it is not intended to limit the invention, any technology people for being familiar with this profession
Member, without departing from the scope of the present invention, when the technology contents using the disclosure above make a little change or modification
For the equivalent embodiment of equivalent variations, but anything that does not depart from the technical scheme of the invention content, according to the technical essence of the invention
Any simple modification, equivalent change and modification to the above embodiments, all of which are still within the scope of the technical scheme of the invention.