CN106958348A - A kind of prefabricated post bean column node is constructed using plastic formwork - Google Patents

A kind of prefabricated post bean column node is constructed using plastic formwork Download PDF

Info

Publication number
CN106958348A
CN106958348A CN201710243301.0A CN201710243301A CN106958348A CN 106958348 A CN106958348 A CN 106958348A CN 201710243301 A CN201710243301 A CN 201710243301A CN 106958348 A CN106958348 A CN 106958348A
Authority
CN
China
Prior art keywords
prefabricated post
prefabricated
column node
bean column
post
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710243301.0A
Other languages
Chinese (zh)
Inventor
马树军
张广鹏
张涛
王帅鹏
马祥瑜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qingdao No 1 Construction Group Co Ltd
Original Assignee
Qingdao No 1 Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qingdao No 1 Construction Group Co Ltd filed Critical Qingdao No 1 Construction Group Co Ltd
Priority to CN201710243301.0A priority Critical patent/CN106958348A/en
Publication of CN106958348A publication Critical patent/CN106958348A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G13/00Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

Constructed the invention discloses a kind of prefabricated post bean column node using plastic formwork, include prefabricated post and precast beam, prefabricated post is vertically arranged with the prefabricated post reinforcing bar stretched out, and precast beam includes prefabricated beam arm and prefabricated bean column node;The styletable of prefabricated post is preset with split bolt hole, four corners of prefabricated post are respectively arranged with the external angle template being fixedly connected by lock pin with prefabricated post, the top of two adjacent outer corner templates is erected with bean column node situation template, transfer block is respectively arranged with one end of the bean column node situation template of prefabricated post both sides, plank sheathing is equipped with transfer block, plastic formwork is assemblied with prefabricated post, steel column hoop is arranged in prefabricated post by the mutual cooperation of split bolt and split bolt hole.The prefabricated post bean column node of the present invention is constructed using plastic formwork, and it is smaller to solve at bean column node template overlap joint plate face well, overlap it is improper easily causes the problems such as mould that rises, dew are starched, accelerate construction speed, improve economic benefit.

Description

A kind of prefabricated post bean column node is constructed using plastic formwork
Technical field
The present invention relates to technical field of building construction, more particularly to a kind of prefabricated post bean column node uses plastic formwork structure Make.
Background technology
In recent years, prefabrication is prefabricated assembled with the continuous progress and development of new building technology and material Building is widely applied.Country advocates prefabrication energetically at this stage, compared with traditional construction technology, in advance Assembled architecture processed has that speed of application is fast, the construction period is short, production efficiency is high, good product quality, production cost are low in itself Feature.In the country that many building industrializations are flourishing, prefabrication experienced long-term experiment and application, modernization Prefabrication product can high speed integrated building various functions, and building form and component it is very smart Cause.In prefabricated assembled concrete frame construction, the correctness that template is set up at bean column node directly influences concrete Forming Quality after pouring.The most frequently used mode is to carry out setting up at bean column node using common plank sheathing, this mode Advantage is can to facilitate blanking according to bean column node size, be disadvantageous in that due at bean column node template overlap joint plate face compared with Small, overlap joint is improper to easily cause the problems such as mould that rises, dew are starched, the impression quality having influence on after concreting.
The content of the invention
For defect present in prior art or deficiency, the present invention innovatively proposes a kind of prefabricated post bean column node Constructed using plastic formwork, it is smaller to solve at bean column node template overlap joint plate face well, overlap it is improper easily cause the mould that rises, The problems such as dew slurry, construction speed is accelerated, economic benefit is improved.
The technical proposal of the invention is realized in this way:
A kind of prefabricated post bean column node is constructed using plastic formwork, includes prefabricated post and precast beam, and the prefabricated post is indulged The prefabricated post reinforcing bar stretched out to being provided with, the precast beam includes prefabricated beam arm and prefabricated bean column node, described prefabricated The upper and lower ends of bean column node are provided with prefabricated post reinforcing bar hole, and the prefabricated post reinforcing bar hole is used to install pre- in prefabricated post Post reinforcing bar processed, the end of the prefabricated beam arm is provided with precast beam muscle, the precast beam of the precast beam muscle and contiguous prefabricated beam arm Muscle is fixedly connected;The styletable of the prefabricated post is preset with split bolt hole, and four corners of the prefabricated post are respectively arranged with The external angle template being fixedly connected by lock pin with prefabricated post, the top of described two adjacent outer corner templates is erected with bean column node position Template is put, the both sides of prefabricated post are fixedly arranged on respectively, is set respectively in one end of the bean column node situation template of the prefabricated post both sides It is equipped with transfer block, the transfer block and is equipped with plank sheathing, plastic formwork is assemblied with the prefabricated post, passes through described pair of drawing spiral shell Steel column hoop is arranged in prefabricated post by the mutual cooperation of bolt and split bolt hole.
It is preferred that, the precast beam muscle of the prefabricated beam arm is connected by the precast beam muscle of mechanical sleeves and contiguous prefabricated beam arm Connect, and precast beam muscle is fixed by high-strength concrete.
It is preferred that, the quantity of the prefabricated post reinforcing bar hole is adapted with the quantity of prefabricated post reinforcing bar.
It is preferred that, the quantity of the split bolt hole is set to three.
Compared with prior art, the beneficial effects of the present invention are:
Constructed, solved well at bean column node using plastic formwork the invention discloses a kind of prefabricated post bean column node Template overlap joint plate face is smaller, and overlap joint is improper to easily cause the problems such as mould that rises, dew are starched, and accelerates construction speed, improves economic effect Benefit;Meanwhile, it can save circulation material, reduce assembling recruitment, lifting construction speed and presentation quality is good, for response country number Call together, promote energy-conservation green material, with obvious society and environmental benefit.
Brief description of the drawings
Fig. 1 is the structural representation of prefabricated post of the present invention;
Fig. 2 is the assembled schematic diagram of plastic formwork of the present invention;
Fig. 3 is that plastic formwork of the present invention reinforces schematic diagram;
Fig. 4 is the attachment structure schematic diagram of prefabricated beam arm of the invention and prefabricated bean column node;
Reference:1st, prefabricated post;2nd, precast beam;3rd, prefabricated post reinforcing bar;4th, prefabricated beam arm;5th, prefabricated bean column node; 6、 Prefabricated post reinforcing bar hole;7th, precast beam muscle;8th, mechanical sleeves;9th, split bolt hole;10th, lock pin;11st, external angle template;12nd, beam Column border node situation template;13rd, transfer block;14th, plank sheathing;15th, plastic formwork;16th, steel column hoop.
Embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete Site preparation is described, it is clear that described embodiment is only a part of embodiment of the invention, rather than whole embodiments.It is based on Embodiment in the present invention, it is every other that those of ordinary skill in the art are obtained under the premise of creative work is not made Embodiment, belongs to the scope of protection of the invention.
As shown in Figure 1, constructed, included prefabricated using plastic formwork the invention provides a kind of prefabricated post bean column node Post 1 and precast beam 2, the prefabricated post 1 are vertically arranged with the prefabricated post reinforcing bar 3 stretched out, and the precast beam 2 includes pre- Beam arm 4 and prefabricated bean column node 5 processed, the upper and lower ends of the prefabricated bean column node 5 are provided with prefabricated post reinforcing bar hole 6, described Prefabricated post reinforcing bar hole 6 is used to installing prefabricated post reinforcing bar 3 in prefabricated post 1, the quantity of the prefabricated post reinforcing bar hole 6 with it is prefabricated The quantity of post reinforcing bar 3 is adapted;The end of the prefabricated beam arm 4 is provided with precast beam muscle 7, the precast beam muscle 7 with it is adjacent pre- The precast beam muscle 7 of beam arm 4 processed is fixedly connected, and the precast beam muscle 7 of the prefabricated beam arm 4 passes through mechanical sleeves 8 and contiguous prefabricated beam The precast beam muscle 7 of arm 4 is connected, and precast beam muscle 7 is fixed by high-strength concrete;The styletable of the prefabricated post 1 is preset There is split bolt hole 9, the quantity of the split bolt hole 9 is set to three, and four corners of the prefabricated post 1 are set respectively The external angle template 11 being fixedly connected by lock pin 10 with prefabricated post 1 is equipped with, the top of described two adjacent outer corner templates 11 is set up There is bean column node situation template 12, the both sides of prefabricated post 1 are fixedly arranged on respectively, the bean column node position in the both sides of prefabricated post 1 One end of template 12, which is respectively arranged with transfer block 13, the transfer block 13, is equipped with plank sheathing 14, is spelled in the prefabricated post 1 Equipped with plastic formwork 15, steel column hoop 16 is arranged on prefabricated by the mutual cooperation of the split bolt and split bolt hole 9 On post 1.
Prefabricated post 1 is that batch production is prefabricated, and is linked up in advance with producer in the reserved 3 split bolt holes 9 in styletable position, is made Steel column hoop 16 can be installed by split bolt hole 9 for later stage split bolt and reinforced.During construction, spelled in prefabricated post 1 Equipped with plastic formwork 15, the lighter weight of plastic formwork 15 itself, and closely splicing is constituted by the plate face of different moduluses, can be very Good solution rise mould, dew slurry the problems such as.In assembled plastic formwork 15, bean column node situation template 12 assembled first, in beam column Node location template 12 sets transfer block 13 close to the position at floor bottom, and plank sheathing 14 is laid in transfer block 13, plastics After the completion of template 15 is installed, assembling reinforcement, using the mutual cooperation of reserved three split bolt holes 9 and split bolt, by steel Tie 16 is reinforced, it is to avoid overlap joint, reinforce improper the problems such as easily cause the mould that rises, dew slurry;Prefabricated beam arm 4 is lifted, when When 5 points of prefabricated post beam column section is moved to prefabricated post 3 surface of reinforcing bar, prefabricated beam arm 4 is moved down, passes through prefabricated post reinforcing bar 3 prefabricated After prefabricated post reinforcing bar hole 6 on bean column node 5, both sides rigging out, using mechanical sleeves 8 by the precast beam of prefabricated beam arm 4 The scene of precast beam muscle 7 of muscle 7 and adjacent prefabricated beam arm 4 is fixed, the prefabricated beam arm 4 of both sides is connected as into an entirety, and lead to High-strength concrete is crossed precast beam muscle 7 is fixed.
Upper described is only the preferred embodiment of invention, is not intended to limit the invention, all spirit in the present invention and Within principle, any modifications, equivalent substitutions and improvements made etc. should be included within the scope of the present invention.

Claims (4)

1. a kind of prefabricated post bean column node is constructed using plastic formwork, include prefabricated post and precast beam, the prefabricated post longitudinal direction It is provided with the prefabricated post reinforcing bar stretched out, it is characterised in that:The precast beam includes prefabricated beam arm and prefabricated bean column node, The upper and lower ends of the prefabricated bean column node are provided with prefabricated post reinforcing bar hole, and the prefabricated post reinforcing bar hole is used to install prefabricated Prefabricated post reinforcing bar on post, the end of the prefabricated beam arm is provided with precast beam muscle, the precast beam muscle and contiguous prefabricated beam arm Precast beam muscle be fixedly connected;The styletable of the prefabricated post is preset with split bolt hole, four corners point of the prefabricated post The external angle template that lock pin is fixedly connected with prefabricated post is not provided with, and the top of described two adjacent outer corner templates is erected with beam Column border node situation template, is fixedly arranged on the both sides of prefabricated post respectively, the one of the bean column node situation template of the prefabricated post both sides End, which is respectively arranged with transfer block, the transfer block, is equipped with plank sheathing, is assemblied with plastic formwork in the prefabricated post, passes through institute Steel column hoop is arranged in prefabricated post by the mutual cooperation for stating split bolt and split bolt hole.
2. prefabricated post bean column node according to claim 1 is constructed using plastic formwork, it is characterised in that:The precast beam The precast beam muscle of arm is connected by mechanical sleeves with the precast beam muscle of contiguous prefabricated beam arm, and by high-strength concrete to precast beam Muscle is fixed.
3. prefabricated post bean column node according to claim 1 is constructed using plastic formwork, it is characterised in that:The prefabricated post The quantity of reinforcing bar hole is adapted with the quantity of prefabricated post reinforcing bar.
4. prefabricated post bean column node according to claim 1 is constructed using plastic formwork, it is characterised in that:Described pair of drawing spiral shell The quantity in keyhole hole is set to three.
CN201710243301.0A 2017-04-14 2017-04-14 A kind of prefabricated post bean column node is constructed using plastic formwork Pending CN106958348A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710243301.0A CN106958348A (en) 2017-04-14 2017-04-14 A kind of prefabricated post bean column node is constructed using plastic formwork

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710243301.0A CN106958348A (en) 2017-04-14 2017-04-14 A kind of prefabricated post bean column node is constructed using plastic formwork

Publications (1)

Publication Number Publication Date
CN106958348A true CN106958348A (en) 2017-07-18

Family

ID=59484429

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710243301.0A Pending CN106958348A (en) 2017-04-14 2017-04-14 A kind of prefabricated post bean column node is constructed using plastic formwork

Country Status (1)

Country Link
CN (1) CN106958348A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0237874A2 (en) * 1986-03-21 1987-09-23 Maier, Josef Panel-shuttering for columns
CN202441060U (en) * 2012-03-22 2012-09-19 广东中城建设集团有限公司 Construction structure of reinforced concrete frame beam columns
CN104975714A (en) * 2015-07-08 2015-10-14 中国葛洲坝集团第六工程有限公司 Factory building concrete floor reserved hidden bracket template device and construction method
CN106013434A (en) * 2016-07-18 2016-10-12 江苏工程职业技术学院 Prefabricated assembled structural intermediate beam column node fixing structure and installation method
CN205777491U (en) * 2016-05-29 2016-12-07 青岛一建集团有限公司 A kind of building body beam-column joint connecting structure
KR101683641B1 (en) * 2016-04-28 2016-12-08 주식회사 엔알씨구조 Prefabricated column structure with concrete form
CN206655472U (en) * 2017-04-14 2017-11-21 青岛一建集团有限公司 A kind of prefabricated post bean column node is constructed using plastic formwork

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0237874A2 (en) * 1986-03-21 1987-09-23 Maier, Josef Panel-shuttering for columns
CN202441060U (en) * 2012-03-22 2012-09-19 广东中城建设集团有限公司 Construction structure of reinforced concrete frame beam columns
CN104975714A (en) * 2015-07-08 2015-10-14 中国葛洲坝集团第六工程有限公司 Factory building concrete floor reserved hidden bracket template device and construction method
KR101683641B1 (en) * 2016-04-28 2016-12-08 주식회사 엔알씨구조 Prefabricated column structure with concrete form
CN205777491U (en) * 2016-05-29 2016-12-07 青岛一建集团有限公司 A kind of building body beam-column joint connecting structure
CN106013434A (en) * 2016-07-18 2016-10-12 江苏工程职业技术学院 Prefabricated assembled structural intermediate beam column node fixing structure and installation method
CN206655472U (en) * 2017-04-14 2017-11-21 青岛一建集团有限公司 A kind of prefabricated post bean column node is constructed using plastic formwork

Similar Documents

Publication Publication Date Title
CN106193282B (en) Assembling frame girder construction based on 3D printing
CN105926804A (en) Reinforcement method of 3D printed reinforced masonry shear wall
CN103452350B (en) Assembling electronic workshop and construction method thereof
CN103470040A (en) Splicing method of composite floor slab and beam
CN108360678A (en) A kind of assembled beam-column node tenon connection structure
CN101597920A (en) Assembled type building construction and method thereof
CN205976072U (en) Assembly type structure wall body and prefabricated concrete structure
CN105839784B (en) Assembled jacking type construction techniques
CN114263275B (en) Construction method for same-layer construction of high-rise assembled steel structure-core tube
CN206570955U (en) A kind of prefabricated post single hole provisions for grouting
CN206655472U (en) A kind of prefabricated post bean column node is constructed using plastic formwork
CN112853983A (en) Manufacturing and on-site assembling process of light segment prefabricated bridge pier
CN208347063U (en) The prefabricated double board wall units of one kind, shear-wall element and assembly concrete shear wall
CN202401667U (en) Prefabricated column with reserved embedded column porous channel and embedded column type full-assembly anti-seismic building
CN107116676A (en) Superelevation blower fan prestressed concrete tower tube construction method
CN102213032A (en) Construction method for connecting reinforcing bars of structural columns
CN209227581U (en) Assembly concrete prismoid shaped basis and column steel connection structure
CN104797762B (en) Building and construction method thereof
CN216305369U (en) Box template of pouring of preassembleing
CN106958348A (en) A kind of prefabricated post bean column node is constructed using plastic formwork
CN207110035U (en) Assembled steel tendon concrete frame structure based on steel plate connection joint
CN206512923U (en) Multilayer prefabricated post of the one-shot forming with bracket
CN216552513U (en) Fabricated batten wall constructional column prefabricated part based on straight tenon
CN206233359U (en) A kind of assembled architecture reinforced concrete member
CN210552011U (en) Take precast stair mould of concrete maintenance function

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination