CN209227581U - Prefabricated Concrete Pyramid Foundation and Column Steel Connection Structure - Google Patents
Prefabricated Concrete Pyramid Foundation and Column Steel Connection Structure Download PDFInfo
- Publication number
- CN209227581U CN209227581U CN201821852382.0U CN201821852382U CN209227581U CN 209227581 U CN209227581 U CN 209227581U CN 201821852382 U CN201821852382 U CN 201821852382U CN 209227581 U CN209227581 U CN 209227581U
- Authority
- CN
- China
- Prior art keywords
- prefabricated
- column
- foundation
- truss
- steel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Joining Of Building Structures In Genera (AREA)
Abstract
Description
【技术领域】【Technical field】
本实用新型涉及预制装配式混凝土结构建筑领域,具体为一种装配式混凝土棱台型基础与柱钢连接结构。The utility model relates to the field of prefabricated assembled concrete structure buildings, in particular to an assembled concrete prism foundation and column steel connection structure.
【背景技术】【Background technique】
装配式混凝土结构具有施工速度快、节能环保、现场湿作业量小等优点,近些年在国内得到迅猛发展。目前建筑中常用的基础包括独立基础,条形基础,筏板基础、箱型基础和桩基础。其中,锥型基础是独立基础的一种,在建筑结构领域一直拥有非常广泛的应用。目前,锥型基础主要以现场浇筑为主,并没有用于建筑领域的装配式锥型基础的相关技术发明,施工需要湿作业,施工速度慢。为此,提出装配式混凝土锥型基础与柱钢连接结构及装配方法,该种方法连接处的传力由钢结构构件完成,具有安装速度快,节能环保等优点。The prefabricated concrete structure has the advantages of fast construction speed, energy saving and environmental protection, and small amount of wet work on site. It has developed rapidly in China in recent years. The foundations commonly used in construction include independent foundations, strip foundations, raft foundations, box foundations and pile foundations. Among them, the conical foundation is a kind of independent foundation, which has been widely used in the field of building structures. At present, the conical foundation is mainly cast on site, and there is no related technical invention of the prefabricated conical foundation used in the construction field. The construction requires wet work and the construction speed is slow. For this reason, the connection structure and assembly method of prefabricated concrete conical foundation and column steel are proposed. The force transmission at the connection of this method is completed by steel structural members, which has the advantages of fast installation speed, energy saving and environmental protection.
【实用新型内容】【Content of utility model】
本实用新型的目的在于提供一种装配式混凝土棱台型基础与柱钢连接结构,在保证预制混凝土构件间连接的前提下,尽可能的减少湿作业的工作量,大大提高施工速度及施工质量。The purpose of this utility model is to provide a connection structure between prefabricated concrete prism foundation and column steel, which can reduce the workload of wet work as much as possible and greatly improve the construction speed and construction quality under the premise of ensuring the connection between prefabricated concrete components. .
本实用新型的技术方案:Technical scheme of the utility model:
一种装配式混凝土棱台型基础与柱钢连接结构,包括预制柱和预制棱台型基础,预制柱通过柱下预制件插装于预制棱台型基础顶部,具体如下:A prefabricated concrete truss-type foundation and column steel connection structure, including prefabricated columns and prefabricated truss-type foundations, the prefabricated columns are inserted on the top of the prefabricated truss-shaped foundation through the prefabricated parts under the columns, the details are as follows:
预制柱由柱内纵向受力钢筋、柱箍筋、柱下预制件和混凝土组成,呈方形竖向排布的四个柱内纵向受力钢筋通过柱箍筋连接形成框架结构,框架结构的底面焊接在柱下预制件上,框架结构的内侧和外侧浇筑混凝土,形成预制柱;The prefabricated column is composed of longitudinally stressed steel bars in the column, column stirrups, prefabricated parts under the column and concrete. The four longitudinally stressed steel bars in the columns arranged vertically in a square form a frame structure through column stirrups. The bottom surface of the frame structure Welded on the prefabricated part under the column, concrete is poured on the inside and outside of the frame structure to form a precast column;
预制棱台型基础由预制棱台型基础内的钢筋、棱台型基础内螺栓杆组件、混凝土组成,预制棱台型基础内的钢筋包括棱台型基础内纵向受力钢筋、棱台型基础内箍筋和棱台型基础底部钢筋网,四个呈方形竖向排布的棱台型基础内纵向受力钢筋通过棱台型基础内箍筋连接形成框架结构,框架结构的底部再与棱台型基础底部钢筋网焊接形成整体结构,在棱台型基础内纵向受力钢筋内设置棱台型基础内螺栓杆组件,棱台型基础内螺栓杆组件通过长螺栓杆约束钢板均匀设置长螺栓杆,形成预制棱台型基础骨架,在预制棱台型基础骨架周围浇注混凝土,获得预制棱台型基础。The prefabricated truss foundation is composed of steel bars in the prefabricated truss foundation, bolt rod components in the truss foundation, and concrete. The internal stirrups and the steel mesh at the bottom of the truss-shaped foundation, the four vertically arranged square-shaped vertically-stressed steel bars in the truss-shaped foundation are connected by the internal stirrups of the truss-shaped foundation to form a frame structure, and the bottom of the frame structure is connected with the edge The steel mesh at the bottom of the platform foundation is welded to form an overall structure, and the inner bolt rod assembly of the pyramid foundation is arranged in the longitudinal force-bearing steel bar of the pyramid foundation, and the bolt rod assembly of the pyramid foundation is uniformly arranged with long bolts by constraining the steel plate through the long bolt rod rods to form a prefabricated truss-shaped foundation skeleton, and pour concrete around the prefabricated truss-shaped foundation skeleton to obtain a prefabricated truss-shaped foundation.
所述的装配式混凝土棱台型基础与柱钢连接结构,柱下预制件由带孔底板、四块侧向钢板和四块加劲肋焊接而成,开有预留孔洞的带孔底板上焊接四块侧向钢板围成的框架,框架的每个外侧面分别焊接加劲肋,加劲肋的底面与带孔底板焊接。In the connection structure between the prefabricated concrete prism foundation and the column steel, the prefabricated parts under the column are welded by the perforated bottom plate, four lateral steel plates and four stiffeners, and the perforated bottom plate with reserved holes is welded A frame surrounded by four lateral steel plates, each outer surface of the frame is respectively welded with stiffeners, and the bottom surface of the stiffeners is welded with the bottom plate with holes.
所述的装配式混凝土棱台型基础与柱钢连接结构,长螺栓杆约束钢板由四块长方形带孔钢板焊接而成框架结构,长螺栓杆约束钢板上均布预留孔洞,长螺栓杆约束钢板的外轮廓尺寸和孔尺寸及位置与柱下预制件的带孔底板相同。The prefabricated concrete truss-type foundation and column steel connection structure, the long bolt rod constraining steel plate is welded by four rectangular perforated steel plates to form a frame structure, the long bolt rod constraining steel plates are uniformly reserved holes, the long bolt rod constraining The outer contour size, hole size and position of the steel plate are the same as the perforated bottom plate of the prefabricated part under the column.
所述的装配式混凝土棱台型基础与柱钢连接结构,长螺栓杆穿过长螺栓杆约束钢板上面的预留孔洞,长螺栓杆与长螺栓杆约束钢板通过点焊的方式连接,并保证长螺栓杆与长螺栓杆约束钢板垂直。In the connection structure between the prefabricated concrete truss-type foundation and the column steel, the long bolt rod passes through the reserved hole on the long bolt rod restraint steel plate, and the long bolt rod and the long bolt rod restraint steel plate are connected by spot welding, and ensure The long bolt rod is perpendicular to the long bolt rod constraining steel plate.
所述的装配式混凝土棱台型基础与柱钢连接结构,预制棱台型基础的顶部中间为凹槽形结构,凹槽形结构的底部露出长螺栓杆。In the prefabricated concrete truss-shaped foundation and column steel connection structure, the middle of the top of the prefabricated truss-shaped foundation is a groove-shaped structure, and the bottom of the groove-shaped structure exposes long bolt rods.
本实用新型的优点及有益效果是:Advantage and beneficial effect of the present utility model are:
1.本实用新型的预制构件的现场安装连接,湿作业量很小,安装时,灌浆料仅起保护作用,不起传力作用,因此施工时,不必等灌浆料凝固就可继续施工,大大缩短工地现场施工所需要的时间,能够极大的提高施工速度,节约成本,更加符合节能环保和经济安全的绿色建筑发展要求等装配式混凝土结构的优点。1. The on-site installation and connection of prefabricated components of the utility model requires very little wet work. During installation, the grouting material only plays a protective role and does not serve as a force transmission function. Therefore, during construction, construction can be continued without waiting for the grouting material to solidify, greatly Shortening the time required for on-site construction can greatly increase the construction speed, save costs, and meet the advantages of prefabricated concrete structures such as energy-saving, environmental protection, economical and safe green building development requirements.
2.本实用新型预制柱和预制棱台型基础,通过预埋于预制棱台型基础的长螺栓杆杆穿过柱下预制件底板并用螺帽固定的方式连接,可有效实现预制柱与预制棱台型基础间弯矩、剪力和轴力的传递,保证二者的整体性,满足结构受力的要求。2. The prefabricated column and the prefabricated truss-type foundation of the utility model are connected through the long bolt rod embedded in the prefabricated truss-type foundation through the bottom plate of the prefabricated part under the column and fixed with nuts, which can effectively realize the connection between the prefabricated column and the prefabricated truss. The transmission of bending moment, shear force and axial force between the truss-type foundations ensures the integrity of the two and meets the requirements of the structural force.
3.本实用新型制作精度要求高的部分,包括预制柱、预制棱台型基础的制作,均在工厂内完成。现场拼装的难度要求不高,能够节省施工人员的学习成本,大幅度提高施工效率。3. The parts of the utility model that require high manufacturing precision, including the manufacture of prefabricated columns and prefabricated truss-type foundations, are all completed in the factory. The difficulty of on-site assembly is not high, which can save the learning cost of construction personnel and greatly improve construction efficiency.
附图说明Description of drawings
图1为柱下预制件的三维图。Figure 1 is a three-dimensional view of the prefabricated part under the column.
图2为长螺栓杆约束钢板的三维图。Fig. 2 is a three-dimensional diagram of a steel plate constrained by a long bolt shank.
图3为预制柱内钢筋布置及与图1连接的三维图。Figure 3 is a three-dimensional diagram of the arrangement of steel bars in the prefabricated column and its connection with Figure 1.
图4为预制柱的三维图。Figure 4 is a three-dimensional view of a prefabricated column.
图5为螺栓杆与图2连接的三维图。Fig. 5 is a three-dimensional view of the connection between the bolt rod and Fig. 2 .
图6为预制棱台型基础内的钢筋布置三维图。Fig. 6 is a three-dimensional diagram of the reinforcement arrangement in the prefabricated pyramid-type foundation.
图7为预制棱台型基础的三维图。Fig. 7 is a three-dimensional view of a prefabricated truss-shaped foundation.
图8为预制棱台型基础的剖面三维图。Fig. 8 is a three-dimensional cross-sectional view of the prefabricated truss-shaped foundation.
图9为预制柱与预制棱台型基础安装完成的三维图。Figure 9 is a three-dimensional view of the prefabricated column and the prefabricated truss-shaped foundation after installation.
图10为预制柱与棱台型基础吊装完毕后的剖面三维图。Fig. 10 is a three-dimensional cross-sectional view of the prefabricated column and the truss-type foundation after hoisting.
图11预制柱与预制棱台型基础间灌注灌浆料后的三维图。Fig. 11 The three-dimensional diagram after the grouting material is poured between the prefabricated column and the prefabricated truss foundation.
图中,1柱下预制件;2带孔底板;3预留孔洞;4侧向钢板;5加劲肋;6长螺栓杆约束钢板;7柱内纵向受力钢筋;8柱箍筋;9棱台型基础内纵向受力钢筋;10棱台型基础内箍筋;11棱台型基础底部钢筋网;12长螺栓杆;13灌浆料。In the figure, 1 prefabricated part under the column; 2 bottom plate with holes; 3 reserved holes; 4 lateral steel plates; 5 stiffening ribs; 6 long bolt rod restraint steel plates; Longitudinal stress-bearing steel bars in the platform-type foundation; 10 internal stirrups in the edge-shaped foundation; 11 reinforcement mesh at the bottom of the edge-shaped foundation; 12 long bolt rods; 13 grouting materials.
具体实施方式Detailed ways
如图1-图11所示,本实用新型装配式混凝土棱台型基础与柱钢连接结构,主要包括预制柱和预制棱台型基础,具体如下:As shown in Figures 1-11, the utility model's assembled concrete prism foundation and column steel connection structure mainly includes prefabricated columns and prefabricated prism foundations, as follows:
(一)如图1所示,柱下预制件具体结构及制作过程如下:(1) As shown in Figure 1, the specific structure and manufacturing process of the prefabricated parts under the column are as follows:
柱下预制件1由带孔底板2、四块侧向钢板4和四块加劲肋5焊接而成,开有预留孔洞3的带孔底板2上焊接四块侧向钢板4围成的框架,框架的每个外侧面分别焊接加劲肋5,加劲肋5的底面与带孔底板2焊接。The prefabricated part 1 under the column is welded by a perforated bottom plate 2, four lateral steel plates 4 and four stiffeners 5, and a frame surrounded by four lateral steel plates 4 is welded on the perforated bottom plate 2 with a reserved hole 3 Each outer surface of the frame is welded with a stiffener 5, and the bottom surface of the stiffener 5 is welded with the perforated bottom plate 2.
(二)如图2及图5所示,棱台型基础内螺栓杆组件的具体结构及制作过程如下:(2) As shown in Figure 2 and Figure 5, the specific structure and manufacturing process of the bolt rod assembly in the truss-shaped foundation are as follows:
(1)如图2所示,长螺栓杆约束钢板6由四块长方形带孔钢板焊接而成框架结构,长螺栓杆约束钢板6上均布预留孔洞3,长螺栓杆约束钢板6的外轮廓尺寸和孔尺寸及位置与带孔底板2相同。(1) As shown in Figure 2, the long bolt rod constraining steel plate 6 is welded by four rectangular steel plates with holes to form a frame structure. The outline size and hole size and position are the same as those of the bottom plate with holes 2 .
(2)如图5所示,长螺栓杆12穿过长螺栓杆约束钢板6上面的预留孔洞3,长螺栓杆12与长螺栓杆约束钢板6通过点焊的方式连接,并保证长螺栓杆12与长螺栓杆约束钢板6垂直。(2) As shown in Figure 5, the long bolt rod 12 passes through the reserved hole 3 above the long bolt rod constraining steel plate 6, and the long bolt rod 12 is connected to the long bolt rod constraining steel plate 6 by spot welding, and the long bolt rod is guaranteed to Rod 12 is perpendicular to long bolt rod constraining steel plate 6.
(三)如图3至图4所示,预制柱的具体结构及制作过程分别如下:(3) As shown in Figure 3 to Figure 4, the specific structure and manufacturing process of the prefabricated columns are as follows:
(1)如图3至图4所示,预制柱由柱内纵向受力钢筋7、柱箍筋8、柱下预制件1和混凝土组成,呈方形竖向排布的四个柱内纵向受力钢筋7通过柱箍筋8连接形成框架结构,框架结构的底面焊接在柱下预制件1上,框架结构的内侧和外侧浇筑混凝土,形成预制柱。(1) As shown in Figures 3 to 4, the prefabricated column is composed of longitudinally stressed steel bars 7 in the column, column stirrups 8, prefabricated parts 1 under the column and concrete. The reinforcement bars 7 are connected by column stirrups 8 to form a frame structure, the bottom surface of the frame structure is welded on the prefabricated part 1 under the column, and the inner and outer sides of the frame structure are poured with concrete to form a prefabricated column.
(2)预制柱的制作过程为:首先,将预制柱的柱内纵向受力钢筋7焊接在柱下预制件1上,然后绑扎柱箍筋8,完成预制柱内的钢筋布置。(2) The manufacturing process of the prefabricated column is as follows: firstly, welding the longitudinal steel bars 7 in the column of the precast column to the prefabricated part 1 under the column, and then binding the column stirrups 8 to complete the arrangement of the steel bars in the precast column.
预制柱的四根柱内纵向受力钢筋7呈四边形,分别焊接在柱下预制件1的侧向钢板4顶端的四个顶点处。The longitudinal stress reinforcement bars 7 in the four columns of the prefabricated column are quadrangular, and are respectively welded to the four vertices at the top of the lateral steel plate 4 of the prefabricated part 1 under the column.
在柱内纵向受力钢筋7外支撑模板,浇筑混凝土,混凝土凝固后拆除模板,完成预制柱的制作。其中,柱下预制件1的侧向钢板4内也灌注混凝土。The formwork is supported outside the longitudinally stressed steel bars 7 in the column, concrete is poured, and the formwork is removed after the concrete is solidified to complete the production of the prefabricated column. Wherein, concrete is also poured into the lateral steel plate 4 of the prefabricated part 1 under the column.
(四)如图6到图8所示,预制棱台型基础的具体结构及制作过程分别如下:(4) As shown in Figure 6 to Figure 8, the specific structure and manufacturing process of the prefabricated truss-type foundation are as follows:
(1)如图6所示,预制棱台型基础由预制棱台型基础内的钢筋、棱台型基础内螺栓杆组件、混凝土组成,预制棱台型基础内的钢筋包括棱台型基础内纵向受力钢筋9、棱台型基础内箍筋10和棱台型基础底部钢筋网11,四个呈方形竖向排布的棱台型基础内纵向受力钢筋9通过棱台型基础内箍筋10连接形成框架结构,框架结构的底部(即棱台型基础内纵向受力钢筋的下端)再与棱台型基础底部钢筋网11焊接形成整体结构,在棱台型基础内纵向受力钢筋9内设置棱台型基础内螺栓杆组件,棱台型基础内螺栓杆组件通过长螺栓杆约束钢板6均匀设置长螺栓杆12,形成预制棱台型基础骨架,在预制棱台型基础骨架周围浇注混凝土,获得预制棱台型基础。(1) As shown in Figure 6, the prefabricated truss-type foundation is composed of steel bars in the prefabricated truss-shaped foundation, bolt rod components in the truss-shaped foundation, and concrete. Longitudinal stressed steel bars 9, inner stirrups 10 of the pyramid-shaped foundation and steel mesh 11 at the bottom of the pyramid-shaped foundation, four longitudinally stressed steel bars 9 in the pyramid-shaped foundation arranged vertically in a square pass through the inner hoops of the pyramid-shaped foundation The ribs 10 are connected to form a frame structure, and the bottom of the frame structure (i.e. the lower end of the longitudinally stressed steel bars in the pyramid-shaped foundation) is welded with the steel mesh 11 at the bottom of the pyramid-shaped foundation to form an overall structure, and the longitudinally stressed steel bars in the pyramid-shaped foundation The internal bolt rod assembly of the truss-shaped foundation is arranged in 9, and the long bolt rods 12 are evenly arranged on the steel plate 6 constrained by the long bolt shank to form the prefabricated truss-shaped foundation skeleton. Around the prefabricated truss-shaped foundation skeleton, Concrete is poured to obtain a prefabricated truss-type foundation.
(2)如图7和图8所示,预制棱台型基础的制作过程为:首先,绑扎作为底面的棱台型基础底部钢筋网11,然后绑扎棱台型基础内纵向受力钢筋9和棱台型基础内箍筋10,并焊接到棱台型基础底部钢筋网11上,形成整体钢筋骨架;其次,将图5中长螺栓杆12、长螺栓杆约束钢板6的组合结构,焊接到底层钢筋网11上、棱台型基础内纵向受力钢筋9内;最后,在预制棱台型基础外支撑模板,浇筑混凝土,混凝土凝固后拆除模板,完成预制棱台型基础的预制。其中,预制棱台型基础的顶部中间为凹槽形结构,凹槽形结构的底部露出长螺栓杆12。(2) As shown in Fig. 7 and Fig. 8, the manufacturing process of prefabricated pyramidal foundation is: at first, binding is used as the steel mesh 11 at the bottom of the pyramidal foundation of the bottom surface, and then the longitudinal stressed steel bars 9 and 9 in the vertical pyramidal foundation are bound The inner stirrup 10 of the truss-shaped foundation is welded to the steel mesh 11 at the bottom of the truss-shaped foundation to form an integral steel skeleton; secondly, the combined structure of the long bolt rod 12 and the long bolt rod constraint steel plate 6 in Fig. 5 is welded to the On the bottom reinforcement mesh 11, inside the longitudinally stressed steel bars 9 in the truss-type foundation; finally, support the formwork outside the prefabricated truss-type foundation, pour concrete, remove the formwork after the concrete solidifies, and complete the prefabrication of the prefabricated truss-type foundation. Wherein, the middle of the top of the prefabricated truss-shaped foundation is a groove-shaped structure, and the bottom of the groove-shaped structure exposes a long bolt rod 12 .
(五)如图9-图11所示,上述预制构件在工厂内预制完成,然后运输到施工现场组装,具体吊装过程如下:(5) As shown in Figure 9-11, the above-mentioned prefabricated components are prefabricated in the factory and then transported to the construction site for assembly. The specific hoisting process is as follows:
(1)如图9及图10所示,预制柱与预制棱台型基础的吊装,将预制柱吊装到预制棱台型基础顶部,并下落,下落后保证柱下预制件1的预留孔洞3套装于长螺栓杆12内;(1) As shown in Figure 9 and Figure 10, for the hoisting of the prefabricated column and the prefabricated truss-shaped foundation, the prefabricated column is hoisted to the top of the prefabricated truss-shaped foundation, and it falls. After falling, ensure the reserved hole of the prefabricated part 1 under the column 3 set in the long bolt rod 12;
(2)如图10所示,在预制柱与预制棱台型基础吊装完成后,在穿过柱下预制件预留孔洞3的长螺栓杆12上安装固定螺母,完成预制柱与预制棱台型基础间的固定连接。(2) As shown in Figure 10, after the hoisting of the prefabricated column and the prefabricated truss-type foundation is completed, a fixing nut is installed on the long bolt rod 12 passing through the reserved hole 3 of the prefabricated part under the column to complete the prefabricated column and the prefabricated truss Fixed connections between foundations.
(3)如图11所示,在安装完固定螺母后,在预制柱与预制棱台型基础之间的空隙处浇筑灌浆料13,待灌浆料凝固后,完成装配式棱台型基础的制作。灌浆料主要的作用是保护预制件,辅助传力。(3) As shown in Figure 11, after the fixing nuts are installed, the grouting material 13 is poured in the gap between the prefabricated column and the prefabricated truss-type foundation, and after the grouting material is solidified, the fabrication of the prefabricated truss-type foundation is completed . The main function of the grouting material is to protect the prefabricated parts and assist force transmission.
本实用新型的传力机理为:预制柱受到的弯矩和剪力,通过柱下预制件的侧向钢板传递到带孔底板,带孔底板受到的弯矩和剪力通过与其相连的螺栓杆传递到预制棱台型基础。预制柱的轴力直接通过柱下预制件的带孔钢板传递到预制棱台型基础的凹槽顶面。从而实现预制柱和预制棱台型基础间弯矩、剪力和轴力的传递。The force transmission mechanism of the utility model is: the bending moment and shear force received by the prefabricated column are transmitted to the bottom plate with holes through the lateral steel plate of the prefabricated part under the column, and the bending moment and shear force received by the bottom plate with holes pass through the bolt rods connected to it. Transfer to prefabricated pyramid-type foundations. The axial force of the prefabricated column is directly transmitted to the groove top surface of the prefabricated pyramid foundation through the perforated steel plate of the prefabricated part under the column. In this way, the transmission of bending moment, shear force and axial force between the prefabricated column and the prefabricated truss foundation can be realized.
实施结果表明:本实用新型可有效实现预制柱与预制棱台型基础间弯矩、剪力和轴力的传递,保证二者的整体性,完全满足结构受力的要求。现场安装连接,湿作业量很小,现场施工所需要的时间少,极大的提高施工速度,节约成本,节省施工人员的学习成本,大幅度提高施工效率。符合节能环保和经济安全的绿色建筑发展要求等装配式混凝土结构的优点。The implementation results show that the utility model can effectively realize the transmission of bending moment, shear force and axial force between the prefabricated column and the prefabricated truss foundation, ensure the integrity of the two, and fully meet the requirements of the structural force. On-site installation and connection, the amount of wet work is very small, the time required for on-site construction is less, the construction speed is greatly improved, the cost is saved, the learning cost of construction personnel is saved, and the construction efficiency is greatly improved. The advantages of prefabricated concrete structures that meet the requirements of energy-saving, environmental protection, economical and safe green building development.
Claims (5)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201821852382.0U CN209227581U (en) | 2018-11-09 | 2018-11-09 | Prefabricated Concrete Pyramid Foundation and Column Steel Connection Structure |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201821852382.0U CN209227581U (en) | 2018-11-09 | 2018-11-09 | Prefabricated Concrete Pyramid Foundation and Column Steel Connection Structure |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN209227581U true CN209227581U (en) | 2019-08-09 |
Family
ID=67502597
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201821852382.0U Expired - Fee Related CN209227581U (en) | 2018-11-09 | 2018-11-09 | Prefabricated Concrete Pyramid Foundation and Column Steel Connection Structure |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN209227581U (en) |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109267584A (en) * | 2018-11-09 | 2019-01-25 | 沈阳建筑大学 | Assembly concrete prismoid shaped basis and column steel connection structure and assembly method |
| CN111395382A (en) * | 2020-03-19 | 2020-07-10 | 衡水衡源电力建设有限责任公司 | Prefabricated foundation for power transmission engineering |
| CN116575499A (en) * | 2023-05-23 | 2023-08-11 | 中国十七冶集团有限公司 | A precise controller and construction method for the concrete auxiliary edge angle of the abutment foundation |
-
2018
- 2018-11-09 CN CN201821852382.0U patent/CN209227581U/en not_active Expired - Fee Related
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109267584A (en) * | 2018-11-09 | 2019-01-25 | 沈阳建筑大学 | Assembly concrete prismoid shaped basis and column steel connection structure and assembly method |
| CN111395382A (en) * | 2020-03-19 | 2020-07-10 | 衡水衡源电力建设有限责任公司 | Prefabricated foundation for power transmission engineering |
| CN116575499A (en) * | 2023-05-23 | 2023-08-11 | 中国十七冶集团有限公司 | A precise controller and construction method for the concrete auxiliary edge angle of the abutment foundation |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN107143034A (en) | A kind of assembly concrete frame structure beam column rigid connection node | |
| CN206267422U (en) | A kind of assembly concrete superposed column | |
| CN109267584A (en) | Assembly concrete prismoid shaped basis and column steel connection structure and assembly method | |
| CN103452350B (en) | Assembling electronic workshop and construction method thereof | |
| CN109267585B (en) | Assembled prismatic table type foundation and column structure and assembling method | |
| CN209227581U (en) | Prefabricated Concrete Pyramid Foundation and Column Steel Connection Structure | |
| CN106869386A (en) | A kind of recycled concrete superposed beam of high-strength construction waste and its construction method | |
| CN108130915B (en) | Prefabricated assembled steel frame raft foundation post-casting strip formwork and construction method thereof | |
| CN208105473U (en) | A kind of assembly node of upper and lower self-heat conserving external wall and floor | |
| CN205369295U (en) | Basis precast prestressed beam slab formula wind power generation column foot plinth | |
| CN209227836U (en) | Prefabricated concrete structure wall-column full steel key connection structure | |
| CN207959244U (en) | Prefabricated assembling type reinforced frame raft foundation alter-pouring strips mould plate | |
| CN209227579U (en) | Prefabricated prism foundation and column structure | |
| CN221855263U (en) | Prefabricated UHPC shell-steel plate-common concrete combined bent cap structure | |
| CN211849006U (en) | A modular and rapid assembly of hollow slab beam lateral splicing auxiliary construction device | |
| CN210421568U (en) | Assembled beam and plate structure | |
| CN203603542U (en) | Fabricated electronic workshop | |
| CN208502067U (en) | A kind of partial precast assembly prestress steel reinforced concrete hybrid beam | |
| CN220724829U (en) | Double-sided overlapped assembled bridge pier suitable for construction of high and cold and earthquake active areas | |
| CN110872809A (en) | Precast concrete beam with built-in steel plate and concrete slab combination beam and construction method | |
| CN111719411A (en) | Prefabricated hollow column structure and its forming method | |
| CN207376882U (en) | A kind of assembly concrete variable cross-section newel post type shearing wall member and its making mold | |
| CN109577520A (en) | Concrete filled steel tube is keyed shear wall rod structure and assembly method | |
| CN103243691A (en) | Prefabricated steel formwork for gallery top arch of dam absorption basin | |
| CN211735013U (en) | A self-anchored steel corrugated plate crushed stone composite arch bridge |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20190809 Termination date: 20191109 |