CN106761913B - A kind of method and its structure that the drop shaft drop section effectively improving stability blocks - Google Patents

A kind of method and its structure that the drop shaft drop section effectively improving stability blocks Download PDF

Info

Publication number
CN106761913B
CN106761913B CN201611173012.XA CN201611173012A CN106761913B CN 106761913 B CN106761913 B CN 106761913B CN 201611173012 A CN201611173012 A CN 201611173012A CN 106761913 B CN106761913 B CN 106761913B
Authority
CN
China
Prior art keywords
drop shaft
layer
drop
ore
anchor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201611173012.XA
Other languages
Chinese (zh)
Other versions
CN106761913A (en
Inventor
郎啟富
李雪明
包继锋
吴锡煌
余正方
胡远
徐万寿
麦宗华
张涛
石绪红
杨小平
程传钊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yuxi Dahongshan Mining Co Ltd
Original Assignee
Yuxi Dahongshan Mining Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yuxi Dahongshan Mining Co Ltd filed Critical Yuxi Dahongshan Mining Co Ltd
Priority to CN201611173012.XA priority Critical patent/CN106761913B/en
Publication of CN106761913A publication Critical patent/CN106761913A/en
Application granted granted Critical
Publication of CN106761913B publication Critical patent/CN106761913B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F15/00Methods or devices for placing filling-up materials in underground workings
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • E21D20/02Setting anchoring-bolts with provisions for grouting
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F15/00Methods or devices for placing filling-up materials in underground workings
    • E21F15/005Methods or devices for placing filling-up materials in underground workings characterised by the kind or composition of the backfilling material

Abstract

The invention discloses a kind of methods and its structure that the drop shaft drop section for effectively improving stability blocks, the following steps are included: 1) prize hair: all around carrying out sled hair to drop shaft mouth and drop shaft first, rock is tapped with crowbar, the not clear and melodious rock of sound oppressiveness is prized down with crowbar, float stone is cleared up, guarantees construction environment safety without hidden danger;2) drop shaft fills out mine: filling drop shaft with ore, by filling ore leveling, spreads barrier layer;3) anchor pole is set: opening anchor hole on the drop shaft side wall between barrier layer and drop shaft mouth, Anchor Agent is inserted into anchor hole together with anchor pole, anchor pole horizontal annular on the side wall of drop shaft is provided with two layers, and insertion is in the reinforcing steel that groined type is arranged on two layers of anchor pole;4) drop shaft blocks: the casting concrete into drop shaft, pours range and covers geotextiles for barrier layer to drop shaft mouth, after concreting and conserved, the ore plate of drop shaft mouth is finally completely covered in the capping of drop shaft mouth, completes drop shaft closure.

Description

A kind of method and its structure that the drop shaft drop section effectively improving stability blocks
Technical field
The invention belongs to mining technology and equipment technical fields, and in particular to a kind of drop shaft drop section for effectively improving stability The method and its structure of closure.
Background technique
Since mine is mostly very high, ore transport frequently, for improve transport efficiency save the cost, can mine from top to bottom The pipeline for getting through a similar well, from top to bottom directly topples over ore, referred to as drop shaft.Drop shaft refers to be slipped from top to bottom using self weight On the one hand transport efficiency can be improved in the pit shaft of ore drawing stone or barren rock, on the other hand, can play certain powder ore and make With.Stope box is predominantly located in inside ore body, using rectilinear arrangement, is arranged in by through-vein transporting drift, several layerings The same nugget shares a drop shaft and first carries out kerve when mining engineering carries out back production, then move back from cutting groove toward thing both sides It adopts.Due to a segmentation only cutting groove (as soon as part increases section cutting groove), from east westerly back production when must pass through it Its through-vein transporting drift after a upper substoping has passed through through-vein transporting drift, is worn in order to ensure next segmentation continues to use this Arteries and veins drop shaft it is necessary to back production will by stope box block, abbreviation drop shaft drop section block.
Drop shaft closure should be secured, cannot be impacted and damage by pressure by upper segmentation blasted ore-rock, and next point after cannot influencing The ore removal of section.In the prior art drop shaft drop section plugging structure some beat anchor pole in pit shaft using the equipment such as skip bucket and poured again It builds, often stability is poor, and severe bends modification easily occurs by the ore-rock impact of upper segmentation slump, cannot play safety catch Effect, hardly possible ensure safety completely;Also the drop shaft drop section plugging structure having first reuses fine sand, plastic coat etc. with ore filling Filling, but this method there are the problem of it is also very much, it is many firstly because since the height of ore filling is generally all in several hundred rice The granularity of well known ore is larger, thus gap is larger, and fine sand filling not only needs a large amount of fine sands to be even filled into drop shaft Lower section just can be more smooth, and considerably increases the ore dressing difficulty and preparation equipment for being used for this part ore of filling later Pressure;In addition it is mostly single layer anchor pole that previous drop section, which blocks, and endurance is weaker, is easy to happen entirety and falls, in addition single layer anchor pole Hidden danger is larger when construction, has certain gap after ore filling, and slightly accidentally, when construction construction personnel, which is easy to slip, falls.It is right The drop shaft relatively more long using the time in some, well head is caving deformation, safety is lower, and stability is worse, it is therefore necessary to Develop the drop section blocking technology of a kind of raising drop shaft drop section closure stability and safety.
Summary of the invention
The first object of the present invention is to provide a kind of method that the drop shaft drop section for effectively improving stability blocks, the second mesh Be provide it is a kind of effectively improve stability drop shaft drop section plugging structure.
The first object of the present invention be achieved in that the following steps are included:
1) it prizes hair: sled hair all around being carried out to drop shaft mouth and drop shaft first, tap rock with crowbar, sound oppressiveness is not clear and melodious Rock prized down with crowbar, to clear up float stone, guarantee construction environment safety without hidden danger;
2) drop shaft fills out mine: being filled under drop shaft to well head at 1.5 ~ 5m with ore, by filling ore leveling, spreads 0.1 ~ 0.3m Barrier layer;
3) anchor pole is set: anchor hole is opened on the drop shaft side wall between barrier layer and drop shaft mouth, by anchor pole together with Anchor Agent It is inserted into anchor hole, anchor pole horizontal annular on the side wall of drop shaft is provided with two layers, and insertion is arranged in groined type on two layers of anchor pole Reinforcing steel;
4) drop shaft blocks: the casting concrete into drop shaft, and pouring range is barrier layer to drop shaft mouth, covers after concreting It lid geotextiles and is conserved, curing period is 8 ~ 10 days, finally covers in drop shaft mouth and the ore plate of drop shaft mouth is completely covered, complete Drop shaft blocks.
The second object of the present invention is achieved in that the drop shaft is by filling including drop shaft, filled layer and concrete component Layer and the filling of concrete component block, it is characterised in that the filled layer includes ore layer and the barrier that is arranged on ore layer Layer;The concrete that the concrete component includes structural framework and pours, the structural framework includes anchor pole and reinforces steel, described Anchor pole by the way that, to be arranged on the side wall of drop shaft, the anchor pole is in drop shaft in the anchor hole that is provided on drop shaft side wall of insertion Side wall on horizontal annular be provided with two layers, respectively upper bolt layer and lower bolt layer, well of the upper bolt layer close to drop shaft Mouthful, steel, the reinforcing are reinforced in insertion to the lower bolt layer on barrier layer, the upper bolt layer and lower bolt layer Steel is arranged in groined type on upper bolt layer and lower bolt layer;The top of the drop shaft, which covers, the mine that well head is completely covered Slabstone.
Beneficial effects of the present invention:
1, method for blocking of the present invention is simple, effectively shortens the construction time, improves the fastness and safety of block section, It ensures closure quality, has ensured that personnel, equipment safety and production continue.
2, drop shaft of the present invention blocks securely, can neither be impacted and damage by pressure by upper segmentation blasted ore-rock, and is easy to remove, not shadow The ore removal for ringing next segmentation, can prevent drop shaft bending deformation under impact, effectively play the effect of safety catch.
3, the present invention uses the ore screening of small particle, further improves the firm of ore layer filling, between ore between Gap is small, and endurance is high, directly uses cotton as barrier layer, leaks into ore layer when on the one hand obstructing concreting, another Aspect is avoided using fine sand, convenient and easy, and cotton can take out recycling after removing closure.
4, the present invention uses two layers of anchor pole, and steel is reinforced in insertion, is effectively improved the endurance of stability and anchor pole, is avoided The case where entirety is fallen or collapsed, has the drop shaft for being caving deformation especially suitable at of long duration, well head;The setting of lower bolt layer Subsequent construction can be carried out as workbench later, thus construction personnel easily slips caused by avoiding no workbench The problem of falling;The present invention is provided with the ore plate for covering all drop shaft mouth in drop shaft mouth, increases forced area, further increases Safety coefficient reduces security risk.
Detailed description of the invention
Fig. 1 is the structural diagram of the present invention;
Fig. 2 is the top view of Fig. 1;
Fig. 3 is the top view of upper bolt layer in Fig. 1;
Fig. 4 is the top view of lower bolt layer in Fig. 1;
In figure: 1- drop shaft, 2- ore layer, 3- barrier layer, 4- concrete component, 5- anchor pole, 6- reinforce steel, 7- ore plate, 8- point Duan Liandao.
Specific embodiment
Below with reference to embodiment and attached drawing, the present invention is further illustrated, but is not subject in any way to the present invention Limitation, based on present invention teach that it is made it is any transform or replace, all belong to the scope of protection of the present invention.
The method that the drop shaft drop section for effectively improving stability as described in the embodiment of the present invention and attached drawing blocks, including it is following Step:
1) it prizes hair: sled hair all around being carried out to drop shaft mouth and drop shaft first, tap rock with crowbar, sound oppressiveness is not clear and melodious Rock prized down with crowbar, to clear up float stone, guarantee construction environment safety without hidden danger;
2) drop shaft fills out mine: being filled under drop shaft to well head at 1.5 ~ 5m with ore, by filling ore leveling, spreads 0.1 ~ 0.3m Barrier layer;
3) anchor pole is set: anchor hole is opened on the drop shaft side wall between barrier layer and drop shaft mouth, by anchor pole together with Anchor Agent It is inserted into anchor hole, anchor pole horizontal annular on the side wall of drop shaft is provided with two layers, and insertion is arranged in groined type on two layers of anchor pole Reinforcing steel;
4) drop shaft blocks: the casting concrete into drop shaft, and pouring range is barrier layer to drop shaft mouth, covers after concreting It lid geotextiles and is conserved, curing period is 8 ~ 10 days, finally covers in drop shaft mouth and the ore plate of drop shaft mouth is completely covered, complete Drop shaft blocks.
Maintenance described in step 4) is to sprinkle water to be conserved twice daily on concrete.
A kind of drop shaft drop section plugging structure effectively improving stability, including drop shaft 1, filled layer and concrete component 4, it is described Drop shaft 1 is blocked by filled layer and the filling of concrete component 4, and the filled layer includes ore layer 2 and the resistance that is arranged on ore layer 2 Interlayer 3;The concrete component 4 includes structural framework and the concrete poured, and the structural framework includes anchor pole 5 and reinforcing steel 6, the anchor hole that the anchor pole 5 is provided on 1 side wall of drop shaft by insertion is interior to be arranged on the side wall of drop shaft 1, described The horizontal annular on the side wall of drop shaft 1 of anchor pole 5 is provided with two layers, respectively upper bolt layer and lower bolt layer, the upper bolt layer Close to the well head of drop shaft 1, insertion adds the lower bolt layer on barrier layer 3, the upper bolt layer and lower bolt layer Gu steel 6, the reinforcing steel 6 is arranged in groined type on upper bolt layer and lower bolt layer;The top of the drop shaft 1 covers There is the ore plate 7 that well head is completely covered.
The ore layer 2 is filled by the ore that particle size is no more than 1 diameter 1/8 of drop shaft.
The barrier layer 3 is filled by cotton.
The depth of the anchor hole is 0.7 ~ 1.5m.
The length of the anchor pole 5 is 1.5 ~ 3m, diameter 20mm.
The distance between described upper bolt layer and lower bolt layer are 0.9 ~ 3.2m, and the upper bolt layer and lower bolt Layer is provided with 4 ~ 20 anchor poles 5.
The upper bolt layer and lower bolt layer is provided with 6 ~ 16 anchor poles 5.
The upper bolt layer and lower bolt layer is provided with 9 ~ 11 anchor poles 5.
The lower bolt layer is that 22.5o setting is rotated horizontally relative to upper bolt layer.
The reinforcing steel 6 has 4, and is the screw-thread steel of diameter 20mm.
The working principle of the invention and the course of work: the drop shaft 1 that section to be dropped is blocked is carried out using the ore by screening Then filling adds cotton as barrier layer 3, beats anchor hole in the side wall of drop shaft 1 and then add Anchor Agent by anchor pole 5 to suitable position Insertion is laid with lower bolt layer, reinforcing steel 6 is embedded in lower bolt layer, embedding grammar is to clamp using more anchor poles 5 by steel 6 is reinforced Rather than directly reinforcing steel is placed on above lower bolt layer, 4 reinforcing steel 6 are laid to groined type, then with lower bolt layer work It is laid with upper bolt layer for workbench, then is embedded in and reinforces steel 6, last cast-in-place C20 concrete drop section is blocked to the well head of drop shaft 1, maintenance 8 ~ 10 days, finally cover ore plate 7.
Embodiment 1
1) prize hair: the drop shaft mouth and drop shaft for treating drop section closure first all around carry out sled hair, rock are tapped with crowbar, by sound The not clear and melodious rock of sound oppressiveness is prized down with crowbar, to clear up float stone, guarantees construction environment safety without hidden danger;2) drop shaft fills out mine: It is no more than under the ore filling drop shaft to well head of drop shaft diameter 1/8 with particle size at 1.5m, filling ore leveling is spread The cotton barrier layer of 0.1m;3) anchor pole is set: opening the anchor that depth is 0.7m on the drop shaft side wall between barrier layer and drop shaft mouth Anchor Agent is inserted into anchor hole by hole together with anchor pole, and the length of anchor pole is 1.5m, diameter 20mm, side wall of the anchor pole in drop shaft Upper horizontal annular is provided with two layers, and two layers of anchor pole is provided with 4, and the distance between two layers of anchor pole is 0.9m, on two layers of anchor pole Insertion is in the reinforcing steel that groined type is arranged;4) drop shaft blocks: C20 concrete is poured into drop shaft, pouring range is barrier layer Geotextiles are covered to drop shaft mouth, after concreting and are sprinkled water on concrete daily is conserved twice, curing period is 8 days, The ore plate of drop shaft mouth is finally completely covered in the capping of drop shaft mouth, completes drop shaft and blocks.
The method for blocking of embodiment 1 is simple, effectively shortens the construction time, improves the fastness and safety of block section Property, it is ensured that quality is blocked, has ensured that personnel, equipment safety and production continue.
Embodiment 2
1) prize hair: the drop shaft mouth and drop shaft for treating drop section closure first all around carry out sled hair, rock are tapped with crowbar, by sound The not clear and melodious rock of sound oppressiveness is prized down with crowbar, to clear up float stone, guarantees construction environment safety without hidden danger;2) drop shaft fills out mine: It is no more than under the ore filling drop shaft to well head of drop shaft diameter 1/8 with particle size at 5m, by filling ore leveling, spreads 0.3m Cotton barrier layer;3) anchor pole is set: opening the anchor hole that depth is 1.5m on the drop shaft side wall between barrier layer and drop shaft mouth, it will Anchor Agent is inserted into anchor hole together with anchor pole, and the length of anchor pole is 3m, diameter 20mm, anchor pole horizontal loops on the side wall of drop shaft Shape is provided with two layers, and two layers of anchor pole is provided with 20, and the distance between two layers of anchor pole is 3.2m, on two layers of anchor pole insertion be in The reinforcing steel of groined type setting;4) drop shaft blocks: pouring C20 concrete into drop shaft, pours range as barrier layer to drop shaft Mouthful, geotextiles and sprinkling water on concrete daily are covered after concreting and are conserved twice, and curing period is 10 days, is finally existed Drop shaft mouth covers the ore plate that drop shaft mouth is completely covered, and completes drop shaft and blocks.
The method for blocking of embodiment 2 is simple, effectively shortens the construction time, improves the fastness and safety of block section Property, it is ensured that quality is blocked, has ensured that personnel, equipment safety and production continue.
Embodiment 3
1) prize hair: the drop shaft mouth and drop shaft for treating drop section closure first all around carry out sled hair, rock are tapped with crowbar, by sound The not clear and melodious rock of sound oppressiveness is prized down with crowbar, to clear up float stone, guarantees construction environment safety without hidden danger;2) drop shaft fills out mine: It is no more than under the ore filling drop shaft to well head of drop shaft diameter 1/8 with particle size at 3m, by filling ore leveling, spreads 0.2m Cotton barrier layer;3) anchor pole is set: the anchor hole that depth is 1m is opened on the drop shaft side wall between barrier layer and drop shaft mouth, by anchor Gu agent is inserted into anchor hole together with anchor pole, the length of anchor pole is 2m, diameter 20mm, anchor pole horizontal annular on the side wall of drop shaft It is provided with two layers, two layers of anchor pole is provided with 12, and the distance between two layers of anchor pole is 1.2m, and insertion is in well on two layers of anchor pole The reinforcing steel of font setting;4) drop shaft blocks: C20 concrete is poured into drop shaft, pouring range is barrier layer to drop shaft mouth, Geotextiles are covered after concreting and are sprinkled water on concrete daily and are conserved twice, and curing period is 9 days, finally in drop shaft Mouth covers the ore plate that drop shaft mouth is completely covered, and completes drop shaft and blocks.
The method for blocking of embodiment 3 is simple, effectively shortens the construction time, improves the fastness and safety of block section Property, it is ensured that quality is blocked, has ensured that personnel, equipment safety and production continue.
Embodiment 4
It is blocked using Dahongshan 400m segmentation K402 and K605 drop shaft drop section as embodiment: bis- drop shafts of K402 and K605 Well head is caving deformation, and 400m segmentation 8# nugget in deep mining falls mine to K402 drop shaft, and 9# nugget falls mine to K605 drop shaft.Two Drop shaft parameter is essentially identical, drop shaft mouth approximate ellipsoidal, and long and short side average diameter is respectively 8m, 7m, oval perimeters 23.55m, About 43.96 ㎡ of area, blocking height is 3m, and single drop shaft blocks volume about 130m3, uses cast-in-place C20 concrete plug, anchor bolt construction Two layers, 1.9m is spent between single layer anchor pole, construct 24 Ф 20, L=2.5m anchor pole, it is put into the 7m long screw-thread steel of 8 Ф 20 in work progress, Skeleton is used as in intersecting parallels arrangement.

Claims (8)

1. a kind of method that the drop shaft drop section for effectively improving stability blocks, it is characterised in that the described method comprises the following steps:
1) it prizes hair: sled hair all around being carried out to drop shaft mouth and drop shaft first, rock is tapped with crowbar, by the not clear and melodious rock of sound oppressiveness Stone is prized down with crowbar, to clear up float stone, guarantees construction environment safety without hidden danger;
2) drop shaft fills out mine: being filled under drop shaft to well head at 1.5 ~ 5m with ore, the particle size of ore is no more than drop shaft diameter 1/ 8, by filling ore leveling, the barrier layer of 0.1 ~ 0.3m is spread, barrier layer is filled by cotton;
3) anchor pole is set: opening anchor hole on the drop shaft side wall between barrier layer and drop shaft mouth, anchor pole is inserted into together with Anchor Agent In anchor hole, anchor pole horizontal annular on the side wall of drop shaft is provided with two layers, and insertion adds in what groined type was arranged on two layers of anchor pole Gu steel, embedding grammar is to be lived using more anchor poles by steel clamp is reinforced;
4) drop shaft blocks: the casting concrete into drop shaft, and pouring range is barrier layer to drop shaft mouth, overburden soil after concreting It work cloth and is conserved, curing period is 8 ~ 10 days, finally covers in drop shaft mouth and the ore plate of drop shaft mouth is completely covered, complete drop shaft It blocks.
2. according to the method described in claim 1, it is characterized in that maintenance described in step 4) is to sprinkle water on concrete daily It is conserved twice.
3. the drop shaft drop section plugging structure that one kind obtains method according to claim 1, including drop shaft (1), filled layer and concrete Component (4), the drop shaft (1) are blocked by filled layer and concrete component (4) filling, it is characterised in that the filled layer includes mine Rock layers (2) and the barrier layer (3) being arranged on ore layer (2), ore layer (2) are no more than drop shaft (1) diameter by particle size 1/8 ore is filled, and barrier layer (3) is filled by cotton;The concrete component (4) includes structural framework and pours Concrete, the structural framework include anchor pole (5) and reinforce steel (6), and the anchor pole (5) is provided with drop shaft by insertion (1) to be arranged on the side wall of drop shaft (1) in the anchor hole on side wall, the anchor pole (5) is horizontal on the side wall of drop shaft (1) Annular is provided with two layers, respectively upper bolt layer and lower bolt layer, the upper bolt layer close to drop shaft (1) well head, it is described Steel (6) are reinforced in insertion to lower bolt layer on barrier layer (3), the upper bolt layer and lower bolt layer, the reinforcing steel (6) it is arranged in groined type on upper bolt layer and lower bolt layer;The top of the drop shaft (1) covers and well head is completely covered Ore plate (7).
4. section plugging structure drops in drop shaft according to claim 3, it is characterised in that the depth of the anchor hole is 0.7 ~ 1.5m.
5. section plugging structure drops in drop shaft according to claim 3, it is characterised in that the length of the anchor pole (5) is 1.5 ~ 3m, diameter 20mm.
6. section plugging structure drops in drop shaft according to claim 3, it is characterised in that the upper bolt layer and lower bolt layer it Between distance be 0.9 ~ 3.2m, and the upper bolt layer and lower bolt layer are provided with 4 ~ 20 anchor poles (5).
7. section plugging structure drops in drop shaft according to claim 3, it is characterised in that the lower bolt layer is relative to upper anchor Bar layer rotates horizontally 22.5o setting.
8. section plugging structure drops in drop shaft according to claim 3, it is characterised in that the reinforcing steel (6) has 4, and is straight The screw-thread steel of diameter 20mm.
CN201611173012.XA 2016-12-18 2016-12-18 A kind of method and its structure that the drop shaft drop section effectively improving stability blocks Active CN106761913B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611173012.XA CN106761913B (en) 2016-12-18 2016-12-18 A kind of method and its structure that the drop shaft drop section effectively improving stability blocks

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611173012.XA CN106761913B (en) 2016-12-18 2016-12-18 A kind of method and its structure that the drop shaft drop section effectively improving stability blocks

Publications (2)

Publication Number Publication Date
CN106761913A CN106761913A (en) 2017-05-31
CN106761913B true CN106761913B (en) 2019-06-07

Family

ID=58889640

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611173012.XA Active CN106761913B (en) 2016-12-18 2016-12-18 A kind of method and its structure that the drop shaft drop section effectively improving stability blocks

Country Status (1)

Country Link
CN (1) CN106761913B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108678806A (en) * 2018-05-07 2018-10-19 宝钢集团新疆八钢铁有限公司 A kind of method for blocking of Underground drop shaft
CN108843389B (en) * 2018-05-21 2020-11-06 金川集团股份有限公司 Stope drop shaft collapse treatment method
CN110159339A (en) * 2019-06-04 2019-08-23 甘肃酒钢集团宏兴钢铁股份有限公司 A kind of underground drop shaft enclosed construction and its enclosure method
CN111928744A (en) * 2020-07-24 2020-11-13 甘肃酒钢集团宏兴钢铁股份有限公司 Rapid full-descending method for open mine support drop shaft

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103032045A (en) * 2012-12-19 2013-04-10 玉溪大红山矿业有限公司 Plugging method and plugging device for high sub-level open draw shaft mouth
CN203441376U (en) * 2013-05-10 2014-02-19 玉溪大红山矿业有限公司 Plugging structure for drop shaft
CN205712130U (en) * 2016-05-23 2016-11-23 郑州大学 A kind of thick miscellaneous fill foundation pit slope protection pilework

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103032045A (en) * 2012-12-19 2013-04-10 玉溪大红山矿业有限公司 Plugging method and plugging device for high sub-level open draw shaft mouth
CN203441376U (en) * 2013-05-10 2014-02-19 玉溪大红山矿业有限公司 Plugging structure for drop shaft
CN205712130U (en) * 2016-05-23 2016-11-23 郑州大学 A kind of thick miscellaneous fill foundation pit slope protection pilework

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
无底柱分段崩落采矿法中溜矿井封堵方法的探讨;王宁等;《矿业工程》;20110815;第9卷(第4期);第44-45页
高深溜井在大红山无底柱分段崩落采矿法中的应用与改进;范有才等;《采矿技术》;20111115;第11卷(第6期);第6-8页

Also Published As

Publication number Publication date
CN106761913A (en) 2017-05-31

Similar Documents

Publication Publication Date Title
CN106761913B (en) A kind of method and its structure that the drop shaft drop section effectively improving stability blocks
CN105697033B (en) A kind of construction method of Tunnel Engineering without template punishment rock mass cavity
CN105041333B (en) It is a kind of first to fill out the method for digging method processing Tunnel Landslide afterwards
CN104278993B (en) A kind of bias voltage Skew Tunnel enters the constructional method in hole
CN103696784B (en) Large-diameter long pipe curtain construction method for shallowly-buried large-span under-tunnel-passing architectural structure
CN108150187A (en) A kind of huge loose talus shield encircles the method into hole
CN107761584A (en) A kind of freeway tunnel mouth Dangerous Rock Body Treatment Methods
CN204371354U (en) The compound supporting and protection structure of a kind of Karst Tunnel
CN108625879A (en) Mountain Tunnels half-open and half-hidden structure and its construction method
CN104895118A (en) Underground diaphragm wall internal corner position piping plug structure and grouting processing method thereof
CN108049395A (en) A kind of anti-collapse impact holing construction method in complex karst place
CN109441479A (en) A kind of bored tunnel sump remedy method
CN104196014A (en) Combined rock-embedded anchor cable slide-resistant pile where round steel is implanted and construction method thereof
CN105951712A (en) Underground diaphragm wall construction method for cutting through underground structure under ground limitation condition
CN106761814A (en) A kind of pipe curtain and bamboo reinforcement grouted anchor bar combined retaining structure and method
CN105625420B (en) A kind of extension type support with manually dug piles construction and its construction method
CN105544508A (en) Cast-in-place pile applicable to karst region having communicating channels
CN107620600A (en) A kind of MJS engineering methods and pipe-roof method combined supporting big cross section small interval tunneling engineering method
CN202730778U (en) Well sealing structure of relief well in foundation pit
CN108166395A (en) A kind of construction method that beam bridge is built across Business Line
CN105241320B (en) A kind of both sides, Gao Dou valley, scenic spot bridge abutment controlled blasting and means of defence
CN204753654U (en) Underground continuous wall reentrant corner position piping block structure
CN105041318B (en) A kind of closed barnyard mining afterwards filling method
CN107780418A (en) The rapid constructing method cheated in Deep Foundation Pit
CN106948350A (en) The rapid constructing method of deep basal pit accessory structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant