CN107780418A - The rapid constructing method cheated in Deep Foundation Pit - Google Patents

The rapid constructing method cheated in Deep Foundation Pit Download PDF

Info

Publication number
CN107780418A
CN107780418A CN201610744185.6A CN201610744185A CN107780418A CN 107780418 A CN107780418 A CN 107780418A CN 201610744185 A CN201610744185 A CN 201610744185A CN 107780418 A CN107780418 A CN 107780418A
Authority
CN
China
Prior art keywords
hole
cheated
deep
foundation pit
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610744185.6A
Other languages
Chinese (zh)
Inventor
杨光
郑岩
秦永康
高申
张健
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Original Assignee
China MCC20 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC20 Group Corp Ltd filed Critical China MCC20 Group Corp Ltd
Priority to CN201610744185.6A priority Critical patent/CN107780418A/en
Publication of CN107780418A publication Critical patent/CN107780418A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/10Restraining of underground water by lowering level of ground water

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses the rapid constructing method cheated in a kind of Deep Foundation Pit, this method is reinforced below hole Zhong Keng regions and deep basal pit bottom using high-pressure rotary jet grouting pile first;When earth excavation is cheated in hole, prefabricated steel supporting construction is installed as earthwork Bian Kaibian is dug, after the completion of earth excavation, steel supporting construction is installed in place, and then pours hole foot mat closing;Precipitation is cheated in hole and uses deep-well precipitation, and is integrally formed with peripheral deep foundation pit precipitation;Wall body structure construction is cheated in hole, for steel supporting construction as foundation ditch exterior sheathing, casting concrete completes wall body structure construction.This method carries out supporting while earth excavation is cheated in hole, avoids the security risk that hole earth excavation is brought to deep basal pit in hole, improves efficiency of construction.

Description

The rapid constructing method cheated in Deep Foundation Pit
Technical field
The present invention relates to the rapid constructing method cheated in a kind of Deep Foundation Pit.
Background technology
Industrial equipment foundation usually occurs cheating in hole, due to cheating in the hole of deep basal pit due to technological requirement in deep basal pit It can not once construct and complete together with outside foundation ditch main body building enclosure, conventional construction method is in deep foundation pit earthwork digging to hole After middle hole absolute altitude suitable for reading, then carry out concrete concealed beam Construction of Supporting.Due to factors such as concrete curing cycle length, cause to cheat in hole Open-assembly time is long, can not quick closure bottom plate, bring security risk to deep basal pit, the danger that possibility is caved in be present.
The content of the invention
The technical problems to be solved by the invention are to provide the rapid constructing method cheated in a kind of Deep Foundation Pit, and this method exists Supporting is carried out while earth excavation is cheated in hole, the security risk that hole earth excavation is brought to deep basal pit in hole is avoided, improves Efficiency of construction.
In order to solve the above technical problems, the rapid constructing method cheated in Deep Foundation Pit of the present invention comprises the following steps:
Step 1: reinforced below hole Zhong Keng regions and deep basal pit bottom using high-pressure rotary jet grouting pile;
Step 2: when cheating earth excavation in hole, prefabricated steel supporting construction is installed as earthwork Bian Kaibian is dug, earth excavation After the completion of, steel supporting construction is installed in place, and then pours hole foot mat closing;
Step 3: hole precipitation uses deep-well precipitation in hole, and it is integrally formed with peripheral deep foundation pit precipitation;
Step 4: cheating wall body structure construction in hole, steel supporting construction completes wall knot as foundation ditch exterior sheathing, casting concrete Structure is constructed.
Further, steel supporting construction includes the support template being made up of longitudinal channel-section steel and transverse channel steels, support template table Face sets steel plate, and right-angle connecting plate is respectively welded in transverse channel steels both ends, and support template cheats surrounding, adjacent support template in hole Connected by right-angle connecting plate, supported between opposite support template using cross support bar, cross support bar and support template it Between be encased inside flitch.
Further, cross support bar front end is respectively equipped with adjustable bracketing.
Further, before support template cheats surrounding in hole, the surface of steel plate of support template is coated using releasing agent.
Because the rapid constructing method cheated in Deep Foundation Pit of the present invention employs above-mentioned technical proposal, i.e., this method is first in hole Reinforced below hole region and deep basal pit bottom using high-pressure rotary jet grouting pile;When earth excavation is cheated in hole, by prefabricated steel branch Protection structure is installed as earthwork Bian Kaibian is dug, and after the completion of earth excavation, steel supporting construction is installed in place, and then pours hole heelpiece Layer closing;Precipitation is cheated in hole and uses deep-well precipitation, and is integrally formed with peripheral deep foundation pit precipitation;Wall body structure construction is cheated in hole, For steel supporting construction as foundation ditch exterior sheathing, casting concrete completes wall body structure construction.This method cheats earth excavation in hole While carry out supporting, avoid the earth excavation security risk brought to deep basal pit in hole in hole, improve efficiency of construction.
Brief description of the drawings
The present invention is described in further detail with embodiment below in conjunction with the accompanying drawings:
Fig. 1 is the rapid constructing method schematic diagram cheated in Deep Foundation Pit of the present invention;
Fig. 2 is the schematic diagram of steel supporting construction in this method;
Fig. 3 is the cross support bar structural representation for being used to support support template in this method.
Embodiment
Embodiment is as shown in figure 1, the rapid constructing method cheated in Deep Foundation Pit of the present invention comprises the following steps:
Reinforced Step 1: being cheated in hole below 2 regions and the bottom of deep basal pit 1 using high-pressure rotary jet grouting pile;
Step 2: when cheating 2 earth excavation in hole, prefabricated steel supporting construction 3 is installed as earthwork Bian Kaibian is dug, the earthwork is opened After the completion of digging, steel supporting construction 3 is installed in place, and then pours hole foot mat closing;
Step 3: cheating 2 precipitation in hole uses deep-well precipitation, and it is integrally formed with the peripheral precipitation of deep basal pit 1;
Step 4: cheating the construction of 2 wall body structures in hole, steel supporting construction 3 is used as foundation ditch exterior sheathing, and casting concrete completes wall Structure construction, be advantageous to improve the efficiency of wall construction.
As shown in Figure 1, Figure 2 and Figure 3, it is preferred that steel supporting construction 3 is included by longitudinal channel-section steel 31 and the structure of transverse channel steels 32 Into support template, support template surface set steel plate 33, right-angle connecting plate 34, supporting mould is respectively welded in the both ends of transverse channel steels 32 Plate cheats 2 surroundings in hole, and adjacent support template is connected by right-angle connecting plate 34, and cross-shaped is used between opposite support template Strut 35 is supported, and flitch 36 is encased inside between cross support bar 35 and support template.
Preferably, the front end of cross support bar 35 is respectively equipped with adjustable bracketing 37.Adjustable bracketing spacing is adjustable, convenient realization pair Effective support of support template.
As shown in Figure 1, it is preferred that before support template cheats 2 surroundings in hole, support template is coated using releasing agent 4 The surface of steel plate 33.
This method quickly carries out cheating supporting and bottom plate back cover in Deep Foundation Pit, shortens and is cheated the engineering time in Deep Foundation Pit, solves Cheat open-assembly time in certainly cheating and long bring security risk.Steel supporting construction in this method makes simple, convenient material drawing, effectively Improve efficiency of construction, it is ensured that the safety of construction operation.

Claims (4)

1. the rapid constructing method cheated in a kind of Deep Foundation Pit, it is characterised in that this method comprises the following steps:
Step 1: reinforced below hole Zhong Keng regions and deep basal pit bottom using high-pressure rotary jet grouting pile;
Step 2: when cheating earth excavation in hole, prefabricated steel supporting construction is installed as earthwork Bian Kaibian is dug, earth excavation After the completion of, steel supporting construction is installed in place, and then pours hole foot mat closing;
Step 3: hole precipitation uses deep-well precipitation in hole, and it is integrally formed with peripheral deep foundation pit precipitation;
Step 4: cheating wall body structure construction in hole, steel supporting construction completes wall knot as foundation ditch exterior sheathing, casting concrete Structure is constructed.
2. the rapid constructing method cheated in Deep Foundation Pit according to claim 1, it is characterised in that:Steel supporting construction bag The support template being made up of longitudinal channel-section steel and transverse channel steels is included, support template surface sets steel plate, and transverse channel steels both ends are welded respectively Right-angle connecting plate is connect, support template cheats surrounding in hole, and adjacent support template is connected by right-angle connecting plate, opposite supporting mould Supported between plate using cross support bar, flitch is encased inside between cross support bar and support template.
3. the rapid constructing method cheated in Deep Foundation Pit according to claim 2, it is characterised in that:Cross support bar front end It is respectively equipped with adjustable bracketing.
4. the rapid constructing method cheated in Deep Foundation Pit according to claim 1, it is characterised in that:Support template is located at hole Before middle hole surrounding, the surface of steel plate of support template is coated using releasing agent.
CN201610744185.6A 2016-08-29 2016-08-29 The rapid constructing method cheated in Deep Foundation Pit Pending CN107780418A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610744185.6A CN107780418A (en) 2016-08-29 2016-08-29 The rapid constructing method cheated in Deep Foundation Pit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610744185.6A CN107780418A (en) 2016-08-29 2016-08-29 The rapid constructing method cheated in Deep Foundation Pit

Publications (1)

Publication Number Publication Date
CN107780418A true CN107780418A (en) 2018-03-09

Family

ID=61441345

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610744185.6A Pending CN107780418A (en) 2016-08-29 2016-08-29 The rapid constructing method cheated in Deep Foundation Pit

Country Status (1)

Country Link
CN (1) CN107780418A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108951647A (en) * 2018-07-18 2018-12-07 中铁十二局集团第二工程有限公司 Construction method for supporting is excavated in hole in the hole of open trench tunnel
CN111764396A (en) * 2020-07-07 2020-10-13 中建一局集团建设发展有限公司 Construction method for water-rich stratum pit-in-pit
CN112878332A (en) * 2020-10-11 2021-06-01 安徽中擎建设发展有限公司 Basement elevator shaft sump construction structure and method thereof

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201883438U (en) * 2010-12-23 2011-06-29 东南大学 Pit-in-foundation-pit steel sheet pile foundation pit supporting structure
CN103015456A (en) * 2011-09-21 2013-04-03 五冶集团上海有限公司 Rapid pit-in-pit form erecting method in foundation slab of buried concrete structure
CN104947677A (en) * 2014-03-28 2015-09-30 中国二十冶集团有限公司 Rapid cofferdam filling construction method for pit in pit
CN105133620A (en) * 2015-08-19 2015-12-09 中国建筑第八工程局有限公司 Supporting structure for pit-in-pit with local fluidal plastic sludge soil mass and construction method of supporting structure

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201883438U (en) * 2010-12-23 2011-06-29 东南大学 Pit-in-foundation-pit steel sheet pile foundation pit supporting structure
CN103015456A (en) * 2011-09-21 2013-04-03 五冶集团上海有限公司 Rapid pit-in-pit form erecting method in foundation slab of buried concrete structure
CN104947677A (en) * 2014-03-28 2015-09-30 中国二十冶集团有限公司 Rapid cofferdam filling construction method for pit in pit
CN105133620A (en) * 2015-08-19 2015-12-09 中国建筑第八工程局有限公司 Supporting structure for pit-in-pit with local fluidal plastic sludge soil mass and construction method of supporting structure

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
宋国强: "《施工技术入门》", 1 March 2007, 中国电力出版社 *
郭志军: "水泥搅拌桩在地下室坑中坑支护工程中的应用", 《浙江建筑》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108951647A (en) * 2018-07-18 2018-12-07 中铁十二局集团第二工程有限公司 Construction method for supporting is excavated in hole in the hole of open trench tunnel
CN111764396A (en) * 2020-07-07 2020-10-13 中建一局集团建设发展有限公司 Construction method for water-rich stratum pit-in-pit
CN112878332A (en) * 2020-10-11 2021-06-01 安徽中擎建设发展有限公司 Basement elevator shaft sump construction structure and method thereof

Similar Documents

Publication Publication Date Title
CN106499413B (en) A kind of Shallow-buried section tunnel stratum consolidation construction method
CN106703814B (en) Tunneling subway station hole pile construction method
CN105464686B (en) Multi-layer underground space curtain posture excavating construction method and supporting construction under existing facility
CN103758134B (en) A kind of construction method combining Double-row Piles Support system
CN108442943A (en) A kind of branch-cut bridge section tunnel and Double side heading method construction method
CN203320532U (en) Protection device of nearby pile foundation close to deep foundation pit
CN103938634B (en) A kind of deep foundation pit supporting structure and construction method
CN103924987B (en) A kind of SMW engineering method stake tunnel shielding portal seepage-proof structure and construction method thereof
CN105545323B (en) The construction method of cut-and-cover tunnel lining cutting
CN108203983A (en) A kind of deep foundation pit supporting structure and method
CN103898916B (en) Mini stake Composite Braced Retaining Structure and construction method
CN107313431A (en) Close on not contour foundation ditch method for synchronously constructing
CN109083682A (en) A kind of construction method of mine working antiseepage high intensity fire dam
CN108589771A (en) One kind having runed underground station increasing layer transfer node construction method
CN103696784A (en) Large-diameter long pipe curtain construction method for shallowly-buried large-span under-tunnel-passing architectural structure
CN106761918A (en) A kind of tunnel solution cavity and Groundwater Comprehensive administer construction and construction method
CN204590038U (en) A kind of permanent foundation pit supporting construction
CN109209389A (en) Hazy tunnel construction method
CN105625420B (en) A kind of extension type support with manually dug piles construction and its construction method
CN107780418A (en) The rapid constructing method cheated in Deep Foundation Pit
CN107119695A (en) A kind of operation support body and construction method for cancelling outer wall of basement backfill
CN107989620A (en) A kind of construction method of three hole closely-spaced tunnel
CN114483056B (en) Method for treating collapse roof caving hole of high-speed railway shallow-buried tunnel within 15m of height of collapse cavity
CN105350575B (en) A kind of reversed construction method of diaphram wall
CN104963693B (en) Rectangular parallel push pipe connection channel construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180309

RJ01 Rejection of invention patent application after publication