CN104947677A - Rapid cofferdam filling construction method for pit in pit - Google Patents

Rapid cofferdam filling construction method for pit in pit Download PDF

Info

Publication number
CN104947677A
CN104947677A CN201410121611.1A CN201410121611A CN104947677A CN 104947677 A CN104947677 A CN 104947677A CN 201410121611 A CN201410121611 A CN 201410121611A CN 104947677 A CN104947677 A CN 104947677A
Authority
CN
China
Prior art keywords
pit
cofferdam
hole
cofferdam device
excavation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410121611.1A
Other languages
Chinese (zh)
Other versions
CN104947677B (en
Inventor
杨前
王新
陶荣江
陈凯
张永峰
丁丽祯
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Original Assignee
China MCC20 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC20 Group Corp Ltd filed Critical China MCC20 Group Corp Ltd
Priority to CN201410121611.1A priority Critical patent/CN104947677B/en
Publication of CN104947677A publication Critical patent/CN104947677A/en
Application granted granted Critical
Publication of CN104947677B publication Critical patent/CN104947677B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Foundations (AREA)
  • Revetment (AREA)

Abstract

The invention relates to cofferdam filling construction, and discloses a rapid cofferdam filling construction method for a pit in a pit. The rapid cofferdam filling construction method includes the steps that a cofferdam device is manufactured; a frame is welded through reinforcements to be in the specification slightly larger than that of the pit in the pit; then a dense-mesh steel plate mesh and a connecting water collecting well are paved on the periphery of the frame, and a steel tube or a structural steel support is used inside the frame; the pit in the pit is excavated, wherein the pit in the pit is excavated at the place where the elevation needs to be adjusted; the cofferdam device is installed and adjusted, after excavation of the pit in the pit is finished, the cofferdam device is instantly placed into the excavated pit, and the cofferdam device is adjusted along with resetting of soil flow or drift sand; after adjustment is finished, concrete is poured on the periphery of the cofferdam device, a water pump is installed in the water collecting well for water pumping after the concrete solidifies, a water isolation mold, a pouring pad layer, the assembling reinforcements, a formwork and the pouring concert are paved to the bottom of the cofferdam device after the water level falls, and then construction can be completed. By means of the rapid cofferdam filling construction method, the containment effect is stable, and the overall schedule of construction of the pit in the pit is guaranteed; influences on the peripheral construction environment of the pit in the pit are avoided.

Description

Cheat quick cofferdam in hole and fill construction method
Technical field
The present invention relates to cofferdam and fill construction, particularly relate to Zhong Keng cofferdam, hole and fill construction method.
Background technology
Along with the development of China's building cause, engineering land used day is becoming tight, many construction lands are had to be in and soft region or shoal area, when all kinds of foundation pit construction is carried out in this region, there will be the phenomenon that foundation ditch elevation of bottom height is different, i.e. hole in secondary excavation hole, cheats excavation and can cause excavation slope stream soil and drift sand, bring difficulty to foundation pit construction in this region is cheated.
Summary of the invention
The present invention is intended to the defect overcoming prior art, provides in a kind of hole and cheats quick cofferdam filling construction method.The present invention goes along with sb. to guard him effect stability, can ensure construction overall progress in hole in hole; Avoid cheating periphery construction environment in hole to be affected.
In order to solve the problems of the technologies described above, the invention provides in a kind of hole and cheat quick cofferdam filling construction method, it comprises:
Cofferdam device making step: employing steel bar welding is connected into the framework slightly larger than cheating specification in hole; Then lay close order expanded metal lath at frame peripheral, connect collecting well, lower portion uses steel pipe or type steel support;
Cheat excavation step in hole: after cofferdam device is made, hole excavation in needing the place adjusting absolute altitude to cheat, the size of excavation and the degree of depth are slightly larger than cofferdam device;
Cofferdam device mounting and adjusting step, in hole after the excavation of hole, puts in the hole of excavation by cofferdam device immediately, along with the reset of stream soil or drift sand adjusts cofferdam device;
Concreting step: at the peripheral concreting of cofferdam device after adjusting, the peripheral soil body and entirety is made to go along with sb. to guard him stable, water pump is installed after concrete setting in collecting well draw water, after water level decreasing, lay water-separating film in the bottom of cofferdam device, build bed course, assembling reinforcement, formwork, concreting, can complete in hole and cheat inner concrete structure construction.
Cheat quick cofferdam in described hole and fill construction method, in described cofferdam device making step, described reinforcing bar uses reinforcing bar residue waste material in engineering.
The present invention adopts in engineering and remains reinforcing bar waste material and be welded into and cheat the framework of specification slightly larger than in hole, then close order expanded metal lath is laid at frame peripheral, connect collecting well, lower portion uses steel pipe or type steel support, the size of excavation and the degree of depth is cheated slightly larger than cofferdam device in hole, after excavation, immediately cofferdam device is put in the hole of excavation, along with the reset of stream soil or drift sand adjusts cofferdam device, at peripheral concreting after adjusting, water pump is installed after concrete setting in collecting well draw water, water-separating film is laid in the bottom of cofferdam device after water level decreasing, build bed course, assembling reinforcement, formwork, concreting, can complete in hole and cheat inner concrete structure construction.The principle of the invention is simple, convenient operation; Cofferdam device entirety goes along with sb. to guard him effect stability; Construction overall progress in hole in hole can be ensured; Can prevent from cheating periphery construction environment in hole to be affected.
Accompanying drawing illustrates:
Below in conjunction with accompanying drawing, invention is further described:
Fig. 1 is elevational schematic view of the present invention;
Fig. 2 is top view of the present invention.
Detailed description of the invention
As shown in Figure 1, cheat quick cofferdam in a kind of hole and fill construction method, it comprises:
Cofferdam device 11 making step: employing reinforcing bar 1 is welded into the framework slightly larger than cheating specification in hole; Then lay close order expanded metal lath 5 at frame peripheral, connect collecting well 6, lower portion uses steel pipe or type steel support 4;
Cheat excavation step in hole: after cofferdam device is made, hole excavation in needing the place adjusting absolute altitude to cheat, the size of excavation and the degree of depth are slightly larger than cofferdam device;
Cofferdam device mounting and adjusting step, in hole after the excavation of hole, puts in the hole of excavation by cofferdam device immediately, along with the reset of stream soil or drift sand adjusts cofferdam device;
Concreting step: at the peripheral concreting 2 of cofferdam device after adjusting, the peripheral soil body and entirety is made to go along with sb. to guard him stable, water pump is installed after concrete setting in collecting well draw water, after water level decreasing, lay water-separating film 3 in the bottom of cofferdam device, build bed course, assembling reinforcement, formwork, concreting, can complete in hole and cheat inner concrete structure construction.
Cheat quick cofferdam in described hole and fill construction method, in described cofferdam device making step, described reinforcing bar uses reinforcing bar residue waste material in engineering.

Claims (2)

1. cheat quick cofferdam in hole and fill a construction method, it is characterized in that, it comprises:
Cofferdam device making step: employing steel bar welding is connected into the framework slightly larger than cheating specification in hole; Then lay close order expanded metal lath at frame peripheral, connect collecting well, lower portion uses steel pipe or type steel support;
Cheat excavation step in hole: after cofferdam device is made, hole excavation in needing the place adjusting absolute altitude to cheat, the size of excavation and the degree of depth are slightly larger than cofferdam device;
Cofferdam device mounting and adjusting step, in hole after the excavation of hole, puts in the hole of excavation by cofferdam device immediately, along with the reset of stream soil or drift sand adjusts cofferdam device;
Concreting step: at the peripheral concreting of cofferdam device after adjusting, the peripheral soil body and entirety is made to go along with sb. to guard him stable, water pump is installed after concrete setting in collecting well draw water, after water level decreasing, lay water-separating film in the bottom of cofferdam device, build bed course, assembling reinforcement, formwork, concreting, can complete in hole and cheat inner concrete structure construction.
2. cheat quick cofferdam in hole according to claim 1 and fill construction method, it is characterized in that, in described cofferdam device making step, described reinforcing bar uses reinforcing bar residue waste material in engineering.
CN201410121611.1A 2014-03-28 2014-03-28 Rapid cofferdam filling construction method for pit in pit Active CN104947677B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410121611.1A CN104947677B (en) 2014-03-28 2014-03-28 Rapid cofferdam filling construction method for pit in pit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410121611.1A CN104947677B (en) 2014-03-28 2014-03-28 Rapid cofferdam filling construction method for pit in pit

Publications (2)

Publication Number Publication Date
CN104947677A true CN104947677A (en) 2015-09-30
CN104947677B CN104947677B (en) 2017-04-19

Family

ID=54162695

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410121611.1A Active CN104947677B (en) 2014-03-28 2014-03-28 Rapid cofferdam filling construction method for pit in pit

Country Status (1)

Country Link
CN (1) CN104947677B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107542157A (en) * 2016-06-28 2018-01-05 五冶集团上海有限公司 A kind of rapid shaping construction method of underground catch pit
CN107780418A (en) * 2016-08-29 2018-03-09 中国二十冶集团有限公司 The rapid constructing method cheated in Deep Foundation Pit
CN108343066A (en) * 2018-04-24 2018-07-31 中铁二局第工程有限公司 Hole support construction and excavation method in a kind of subway transfer station interconnection hole
CN112878332A (en) * 2020-10-11 2021-06-01 安徽中擎建设发展有限公司 Basement elevator shaft sump construction structure and method thereof
CN113202119A (en) * 2021-05-20 2021-08-03 中国水利水电第十一工程局有限公司 Combined cofferdam for strong-flow sand-ground layer gabion construction of linear river channel and construction method thereof
CN116180761A (en) * 2023-04-06 2023-05-30 中国十七冶集团有限公司 Excavation method of fire elevator foundation pit in building basement in coastal area

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0220720A (en) * 1988-07-07 1990-01-24 Taisei Corp Underground construction method by muddy water excavation
CN101245602A (en) * 2008-03-13 2008-08-20 王形 Construction technique for pits in foundation-pit support system
CN101545260A (en) * 2008-03-27 2009-09-30 中国二十冶建设有限公司 Method for supporting bored filling pile driven by stirring pile in foundation pit, group pit and middle pit
CN102162250A (en) * 2010-02-24 2011-08-24 中国二十冶集团有限公司 Protective construction method of excavating large area deep foundation pit in running sand confined water soil layer
CN103015456A (en) * 2011-09-21 2013-04-03 五冶集团上海有限公司 Rapid pit-in-pit form erecting method in foundation slab of buried concrete structure

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0220720A (en) * 1988-07-07 1990-01-24 Taisei Corp Underground construction method by muddy water excavation
CN101245602A (en) * 2008-03-13 2008-08-20 王形 Construction technique for pits in foundation-pit support system
CN101545260A (en) * 2008-03-27 2009-09-30 中国二十冶建设有限公司 Method for supporting bored filling pile driven by stirring pile in foundation pit, group pit and middle pit
CN102162250A (en) * 2010-02-24 2011-08-24 中国二十冶集团有限公司 Protective construction method of excavating large area deep foundation pit in running sand confined water soil layer
CN103015456A (en) * 2011-09-21 2013-04-03 五冶集团上海有限公司 Rapid pit-in-pit form erecting method in foundation slab of buried concrete structure

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107542157A (en) * 2016-06-28 2018-01-05 五冶集团上海有限公司 A kind of rapid shaping construction method of underground catch pit
CN107780418A (en) * 2016-08-29 2018-03-09 中国二十冶集团有限公司 The rapid constructing method cheated in Deep Foundation Pit
CN108343066A (en) * 2018-04-24 2018-07-31 中铁二局第工程有限公司 Hole support construction and excavation method in a kind of subway transfer station interconnection hole
CN108343066B (en) * 2018-04-24 2023-11-17 中铁二局第一工程有限公司 Subway transfer station tie line pit in pit supporting structure and excavation method
CN112878332A (en) * 2020-10-11 2021-06-01 安徽中擎建设发展有限公司 Basement elevator shaft sump construction structure and method thereof
CN113202119A (en) * 2021-05-20 2021-08-03 中国水利水电第十一工程局有限公司 Combined cofferdam for strong-flow sand-ground layer gabion construction of linear river channel and construction method thereof
CN116180761A (en) * 2023-04-06 2023-05-30 中国十七冶集团有限公司 Excavation method of fire elevator foundation pit in building basement in coastal area

Also Published As

Publication number Publication date
CN104947677B (en) 2017-04-19

Similar Documents

Publication Publication Date Title
CN104947677B (en) Rapid cofferdam filling construction method for pit in pit
CN104213565B (en) A kind of formwork system that is applicable to large-scale deep trouth hole sty bed course and formwork thereof water smashes construction method
CN105220703B (en) Enclosing type deepwater platform construction method based on condition of sand backfilling balance method
CN104372799B (en) Rigid unearthing platform foundation pit inner support structure and construction method
CN104895324B (en) A kind of construction method of the huge plug-in type suspension column structure of reinforced concrete composite structure
CN106759439A (en) For the tower crane and its construction method of foundation ditch
CN106930277A (en) A kind of construction of manual-excavation cast-in-place pile method
CN108824240A (en) A kind of pipe culvert construction method and auxiliary device
CN110056000B (en) Construction method and structure of counter weight type retaining wall
CN100476142C (en) Construction Method of Combined "V" Shape Steel Tube Concrete Column
CN206298900U (en) A kind of diaphram wall built-in type steel encloses purlin plug system
CN106836240A (en) Basement annular brace construction method for supporting
CN102493446B (en) Steel tube column capable of preventing concrete spillover and method for mounting steel tube column
CN106087991B (en) Stake top absolute altitude is in natural ground dug pile construction method below
CN108867723A (en) The method of frame structure building rectification and underground increasing layer
CN103122642A (en) Construction method of vertical post support change
CN108316328A (en) A kind of pressurization sinking device and its construction method for open caisson construction
CN111197317A (en) Construction method and structure of foundation cushion under condition of flowing plastic silt soil
CN205242441U (en) Oval contrary shaft of doing of suspension type
CN110318403A (en) A kind of deep basal pit inner support assembled support replacement construction tool and construction method
CN205975637U (en) A template reinforcing apparatus for concrete placement in circular well
CN108978697B (en) Terrace template system and construction method
CN203960878U (en) A kind of construction formwork of retaining engineering
CN106917396B (en) A kind of taper foundation reinforcement method
CN103821149A (en) Large-scale deep foundation pit slope remaining soil digging and pit-in-pit concrete post casting construction method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant