CN105220703B - Enclosing type deepwater platform construction method based on condition of sand backfilling balance method - Google Patents

Enclosing type deepwater platform construction method based on condition of sand backfilling balance method Download PDF

Info

Publication number
CN105220703B
CN105220703B CN201510582372.4A CN201510582372A CN105220703B CN 105220703 B CN105220703 B CN 105220703B CN 201510582372 A CN201510582372 A CN 201510582372A CN 105220703 B CN105220703 B CN 105220703B
Authority
CN
China
Prior art keywords
cushion cap
concrete
steel
steel sheet
cofferdam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510582372.4A
Other languages
Chinese (zh)
Other versions
CN105220703A (en
Inventor
孙学军
沈维成
石怀远
刘向前
徐大振
王其见
陈小虎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Road and Bridge Engineering Co Ltd
Original Assignee
Anhui Road and Bridge Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Road and Bridge Engineering Co Ltd filed Critical Anhui Road and Bridge Engineering Co Ltd
Priority to CN201510582372.4A priority Critical patent/CN105220703B/en
Publication of CN105220703A publication Critical patent/CN105220703A/en
Application granted granted Critical
Publication of CN105220703B publication Critical patent/CN105220703B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Revetment (AREA)

Abstract

The invention discloses an enclosing type deepwater platform construction method base on the condition of a sand backfilling balance method. The enclosing type deepwater platform construction method is characterized in that firstly, cofferdams of construction steel sheet piles are formed on the river bed surface, back covering concrete layers are formed in the cofferdams through underwater pouring, and sandy soil of which the height is greater than that of the back covering concrete layers of the outer sides of the cofferdams is sucked to the interior of the steel sheet cofferdams through dredging tubes so that height difference of sandy soil of the inner side of the steel sheet cofferdams and the outer side of the steel sheet cofferdams is reduced; water is extracted gradually in the steel sheet cofferdams and inner supports are installed sequentially, and temporarily stored sandy soil is hoisted out of the cofferdams so that surface layers of the back covering concrete layers are exposed; platform templates are arranged on the back covering concrete layers, and a platform template supporting system is formed by installing I-shaped steel between the steel sheet piles and the platform templates; and first layer platform concrete, concrete top beams and second layer platform concrete are poured in the platform templates in sequence, and sandy soil is backfilled between the steel sheet piles and the platform templates at the same time and the construction of platform concrete is completed. According to the enclosing type deepwater platform construction method, cofferdam platform is easy to construct on abrupt slope or deepwater sandy riverbed.

Description

One kind is based on back and sands flat enclosure-type deep water construction method under the conditions of weighing apparatus method
Technical field
The present invention relates to Construction of Civil Engineering is and in particular to the construction method of deep water cushion cap.
Background technology
At present, when steel sheet-pile cofferdam is constructed on chiltern deepwater riverbed, because cofferdam implantation, bury sinking, fixation, back cover Quite big etc. difficulty of construction, when channel gradient is larger, cofferdam size limited conditions lower cushion cap difficulty of construction is very big.Therefore, exist Steel cofferdam that in engineering design, generally setting rigidity doubles or avoid as far as possible the unfavorable geology such as deep water, abrupt slope, rock matter riverbed, The position that shape, hydrologic condition coexist.However, because being limited by factors such as bridge line position, bridge type, across footpath, costs, above-mentioned situation has Shi Wufa avoids, that is, inevitably needs sometimes to arrange cofferdam in deep water layer of sand.And it is reliable in prior art Effectively construction method can be constructed with this understanding.
Content of the invention
The present invention is for avoiding the deficiency existing for above-mentioned prior art, provides and a kind of simple and reliable sands flat weighing apparatus based on returning Enclosure-type deep water construction method under the conditions of method, so that the cofferdam bearing platform construction on abrupt slope, deep water sandy bed river is easy to real Apply.
The present invention is to solve technical problem to adopt the following technical scheme that
The present invention is based on back and sands flat enclosure-type deep water construction method under the conditions of weighing apparatus method, it is characterized in that entering as follows OK:
Step 1: on riverbed face, be in the construction of hammering inserting piling and steel sheet pile that complete steel sheet pile at cushion cap position The welding mounting construction of top layer inner support, formed steel cofferdam structure, carry out in described steel cofferdam underwater casting formed with Pile foundation and steel sheet pile consolidate the bottom concrete layer being integrated, and now outside steel cofferdam, the height of sandy soils is more than steel cofferdam The height of inner side sandy soils;
Step 2: the bottom mouth of pipe of dredging tube is sunk down in the sandy soils outside steel cofferdam, using gas lift method by steel plate Cofferdam outer periphery is higher than that the sand of bottom concrete layer is drawn in steel cofferdam, reduces sand height inside and outside steel cofferdam Difference;
Step 3: progressively draw water in steel cofferdam and install the inner support at corresponding water level in steel cofferdam therewith, draw water With inner support is installed alternately, until completing remaining all of inner support in steel cofferdam, steel cofferdam internal water now Body is evacuated the dummy status that reveals, and handling goes out the sand sucking in cofferdam and deposited temporarily, until making the table of bottom concrete layer Layer exposes;
Step 4: cushion cap template is set on bottom concrete layer, is in that level is pacified between described steel sheet pile and cushion cap template Dress I-steel is supported, and one end of described I-steel is welded on the inner side of steel sheet pile, and the other end is butted on the outside of cushion cap template Vertical floor;Described I-steel is embarked on journey and arranged for interval in column between steel sheet pile and cushion cap template, forms stable cap mold Plate support system;
Step 5: pour in described cushion cap template and complete ground floor cushion cap concrete, using the sand temporarily deposited as return Back-up sand backfills in the space between the steel sheet pile on the height and position of ground floor cushion cap concrete place and cushion cap template;Described The top of ground floor cushion cap concrete pours one concrete Guan Liang, forms the enclosure-type stress strong point;
Step 6: pour second layer cushion cap concrete on described ground floor cushion cap concrete, and in described second layer cushion cap After the completion of concreting, sand is backfilling into steel sheet pile and the cushion cap template on the height and position of second layer cushion cap concrete place Between space, complete the construction of cushion cap concrete.
The present invention is based on back and sands flat enclosure-type deep water construction method under the conditions of weighing apparatus method, it is characterized in that: in described step 2 Reduce sand difference in height inside and outside cofferdam until being equivalent in level.
The present invention is based on back and sands flat enclosure-type deep water construction method under the conditions of weighing apparatus method, it is characterized in that: described I-steel The spacing of adjacent a line, and adjacent one row spacing be disposed as 1m.
The present invention is based on back and sands flat enclosure-type deep water construction method under the conditions of weighing apparatus method, it is characterized in that: described concrete Guan Liang flushes the top surface of ground floor cushion cap concrete, and along ground floor cushion cap concrete surrounding space closely knit pour, formation is bowed Depending on being shaped as closed rectangular, enclosure-type is collectively forming with described steel sheet pile, concrete Guan Liang and ground floor cushion cap concrete steady Surely support stress surface.
The present invention is based on back and sands flat enclosure-type deep water cushion cap formwork support structure under the conditions of weighing apparatus method, and it is structurally characterized in that: On riverbed face, it is in construction steel sheet pile formation steel cofferdam at cushion cap position, in described steel cofferdam, be respectively mounted top Layer inner support and each road inner support being in above cushion cap template;Cap mold is arranged on the bottom concrete layer in steel cofferdam Plate, is in be horizontally mounted I-steel to be supported, one end of described I-steel is welded between described steel sheet pile and cushion cap template The inner side of steel sheet pile, the other end is butted on the vertical floor in outside of cushion cap template;Described I-steel steel sheet pile and cushion cap template it Between embark on journey and arranged for interval in column, form stable cushion cap form bracing system.
The present invention is based on back and sands flat enclosure-type deep water cushion cap formwork support structure under the conditions of weighing apparatus method, and its design feature also exists In the spacing of the adjacent a line of described I-steel, and the spacing of adjacent row is disposed as 1m.
Compared with the prior art, the present invention has the beneficial effect that:
1st, the present invention is to be drawn into outside cofferdam by gas lift method using cofferdam periphery chiltern soil layer, reduces soil pressure inside and outside cofferdam Difference, forms the soil pressure active balance inside and outside cofferdam, reduces elongated shaped steel plate pile and itself bears moment of flexure and out-of-balance force, in construction no Riverbed need to be pre-processed, the construction in especially suitable deep water cofferdam.
2nd, to reduce soil layer inside and outside cofferdam in construction poor for the inventive method, it is possible to increase steel sheet pile inner support level interval, subtracts Support the number of plies less, both reduced the cost, and ensured working security again.
3rd, the inventive method makes full use of steel sheet pile enclosing structure as cushion cap external mold Bracing Systems, by arranging work Word steel power transmission connection external mold floor, can effectively reduce cofferdam area.At cushion cap, the Guan Liang of setting effectively assume responsibility for simultaneously The steel sheet pile bottom strong point, fine complete system transform, serve as cofferdam bottom and support.
3rd, the inventive method, simple and reliable, equipment that need not be complicated, construction cost is low, construction feasibility is high.
Brief description
Fig. 1 is the elevational schematic view that the present invention returns in sand balancing method work progress;
Fig. 2 is cofferdam of the present invention overlooking the structure diagram;
Fig. 3 is enclosure-type structural system elevational schematic view of the present invention;
Fig. 4 is the cushion cap concrete overlooking the structure diagram of the present invention;
In figure label: 1 pile foundation, 2 bottom concrete layers, 3 steel sheet piles, 4 dredging tubes, 5 Cast-in-situ Piles in Sand-fillings, 6a top layer inner support, 6b Inner support, 7 I-steel, 8 cushion cap templates, 9 concrete Guan Liangs, 10 ground floor cushion cap concrete, 11 second layer cushion cap concrete, 12 Cushion cap concrete.
Specific embodiment
The present embodiment is the cushion cap foundation that constructs a bridge in environment as shown in Figure 1, as shown in figure 1, steel sheet pile 3 is located at water Riverbed under plane is sandy bed river or other abrupt slope soil property riverbeds, and the embedded inserting piling of steel sheet pile 3 is to riverbed depths, and riverbed face Chiltern surface be in great slope, so being not suitable for fluting or other method fixation steel plate stake.
Referring to Fig. 1, Fig. 2, Fig. 3 and Fig. 4, it is based on back in the present embodiment and sands flat enclosure-type deep water bearing platform construction under the conditions of weighing apparatus method Method is to carry out as follows:
Step 1: on riverbed face, be in the hammering inserting piling construction completing steel sheet pile 3 at cushion cap position and steel sheet pile 3 The welding mounting construction of middle top layer inner support 6a, forms steel cofferdam structure, carries out underwater casting shape in described steel cofferdam Become the bottom concrete layer 2 being integrated with pile foundation 1 and steel sheet pile 3 consolidation, now outside steel cofferdam, the height of sandy soils is more than The height of sandy soils inside steel cofferdam.
Step 2: the bottom mouth of pipe of dredging tube 4 is sunk down in the sandy soils outside steel cofferdam, using gas lift method by steel Plate cofferdam outer periphery is higher than that the sand of bottom concrete layer 2 is drawn in steel cofferdam, reduces sand inside and outside steel cofferdam high Degree is poor, until being equivalent in level, stops inhaling mud operation.
Step 3: progressively draw water in steel cofferdam and install inner support 6b at corresponding water level in steel cofferdam therewith, take out Water with inner support is installed alternately, until completing remaining all of inner support 6b in steel cofferdam, in steel cofferdam now Portion's water body is evacuated the dummy status that reveals, and handling goes out the sand sucking in cofferdam and deposited temporarily, until making bottom concrete layer 2 Top layer expose.
Step 4: cushion cap template 8 is set on bottom concrete layer 2, is in water between described steel sheet pile 3 and cushion cap template 8 Safety dress I-steel 7 is supported, and one end of described I-steel 7 is welded on the inner side of steel sheet pile 3, and the other end is butted on cushion cap template The 8 vertical floor in outside;Described I-steel 7 is embarked on journey and arranged for interval in column between steel sheet pile 3 and cushion cap template, is formed stable Cushion cap form bracing system;The spacing of the adjacent a line of I-steel 7, and adjacent one row spacing be disposed as 1m.
Step 5: pour in described cushion cap template 8 and complete ground floor cushion cap concrete 10, the sand temporarily deposited is made Backfill the space between the steel sheet pile 3 on ground floor cushion cap concrete 10 place height and position and cushion cap template 8 for Cast-in-situ Piles in Sand-filling 5 In;Pour one concrete Guan Liang 9 on the top of described ground floor cushion cap concrete 10, form the enclosure-type stress strong point;Tool During body is implemented, concrete Guan Liang 9 flushes the top surface of ground floor cushion cap concrete 10, and the surrounding along ground floor cushion cap concrete 10 Space is closely knit to be poured, and forming plan view shape is closed rectangular, is mixed with described steel sheet pile 3, concrete Guan Liang 9 and ground floor cushion cap Solidifying soil 10 is collectively forming enclosure-type and stably supports stress surface.
Step 6: pour second layer cushion cap concrete 11 on described ground floor cushion cap concrete 10, and in the described second layer Cushion cap concrete 11 pour after the completion of by sand be backfilling into steel sheet pile on second layer cushion cap concrete 11 place height and position and Space between cushion cap template 8, completes the construction of cushion cap concrete 12.
In being embodied as, the global shape in cofferdam can be different according to construction needs, including cylindrical shape and square tube shape, As shown in Fig. 2 it overlooks as rectangle in this enforcement, for this reason, it is closure collar tie beam that concrete Guan Liang 9 forms plan view shape.
As shown in Figure 1, Figure 2, Figure 3 and Figure 4, it is based on back in the present embodiment and sand flat enclosure-type deep water cap mold under the conditions of weighing apparatus method Board supporting structure is on riverbed face, is in construction steel sheet pile 3 formation steel cofferdam at cushion cap position, encloses in described steel plate It is respectively mounted top layer inner support 6a in weir and be in each road inner support 6b above cushion cap template;Back cover in steel cofferdam mixes On solidifying soil layer 2, cushion cap template 8 is set, is in be horizontally mounted I-steel 7 to be supported between described steel sheet pile 3 and cushion cap template 8, One end of described I-steel 7 is welded on the inner side of steel sheet pile 3, and the other end is butted on the vertical floor in outside of cushion cap template 8;Described work Word steel 7 is embarked on journey and arranged for interval in column between steel sheet pile 3 and cushion cap template, forms stable cushion cap form bracing system, work The spacing of the adjacent a line of word steel 7, and adjacent one row spacing be disposed as 1m.

Claims (4)

1. one kind is based on back and sands flat enclosure-type deep water construction method under the conditions of weighing apparatus method, it is characterized in that carrying out as follows:
Step 1: on riverbed face, be in the hammering inserting piling construction completing steel sheet pile (3) at cushion cap position and steel sheet pile (3) The welding mounting construction of middle top layer inner support (6a), forms steel cofferdam structure, carries out underwater casting in described steel cofferdam Form the bottom concrete layer (2) being integrated with pile foundation (1) and steel sheet pile (3) consolidation, now sandy soils outside steel cofferdam Highly it is more than the height of sandy soils inside steel cofferdam;
Step 2: the bottom mouth of pipe of dredging tube (4) is sunk down in the sandy soils outside steel cofferdam, using gas lift method by steel plate Cofferdam outer periphery is higher than that the sand of bottom concrete layer (2) is drawn in steel cofferdam, reduces sand inside and outside steel cofferdam high Degree is poor;
Step 3: progressively draw water in steel cofferdam and install the inner support (6b) at corresponding water level in steel cofferdam therewith, draw water With installation inner support alternately, until completing remaining all of inner support (6b) in steel cofferdam, in steel cofferdam now Portion's water body is evacuated the dummy status that reveals, and handling goes out the sand sucking in cofferdam and deposited temporarily, until making bottom concrete layer (2) top layer is exposed;
Step 4: in bottom concrete layer (2) upper setting cushion cap template (8), between described steel sheet pile (3) and cushion cap template (8) It is supported in being horizontally mounted I-steel (7), one end of described I-steel (7) is welded on the inner side of steel sheet pile (3), and the other end supports The vertical floor in outside in cushion cap template (8);Described I-steel (7) is embarked on journey and in column between steel sheet pile (3) and cushion cap template Arranged for interval, forms stable cushion cap form bracing system;
Step 5: pour in described cushion cap template (8) and complete ground floor cushion cap concrete (10), the sand temporarily deposited is made For Cast-in-situ Piles in Sand-filling (5) steel sheet pile (3) on the height and position of ground floor cushion cap concrete (10) place for the backfill and cushion cap template (8) it Between space in;Pour one concrete Guan Liang (9) on the top of described ground floor cushion cap concrete (10), form enclosure-type and be subject to The power strong point;
Step 6: pour second layer cushion cap concrete (11) on described ground floor cushion cap concrete (10), and in the described second layer Sand is backfilling into the steel plate on the height and position of second layer cushion cap concrete (11) place by cushion cap concrete (11) after the completion of pouring Space between stake and cushion cap template (8), completes the construction of cushion cap concrete (12).
2. according to claim 1 sand flat enclosure-type deep water construction method under the conditions of weighing apparatus method based on returning, it is characterized in that: Reduce sand difference in height inside and outside cofferdam until being equivalent in level in described step 2.
3. according to claim 1 sand flat enclosure-type deep water construction method under the conditions of weighing apparatus method based on returning, it is characterized in that: The spacing of the adjacent a line of described I-steel, and the spacing of adjacent row is disposed as 1m.
4. according to claim 1 sand flat enclosure-type deep water construction method under the conditions of weighing apparatus method based on returning, it is characterized in that: Described concrete Guan Liang (9) flushes the top surface of ground floor cushion cap concrete (10), and four along ground floor cushion cap concrete (10) All spaces are closely knit to be poured, and forming plan view shape is closed rectangular, with described steel sheet pile (3), concrete Guan Liang (9) and ground floor Cushion cap concrete (10) is collectively forming enclosure-type and stably supports stress surface.
CN201510582372.4A 2015-09-11 2015-09-11 Enclosing type deepwater platform construction method based on condition of sand backfilling balance method Active CN105220703B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510582372.4A CN105220703B (en) 2015-09-11 2015-09-11 Enclosing type deepwater platform construction method based on condition of sand backfilling balance method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510582372.4A CN105220703B (en) 2015-09-11 2015-09-11 Enclosing type deepwater platform construction method based on condition of sand backfilling balance method

Publications (2)

Publication Number Publication Date
CN105220703A CN105220703A (en) 2016-01-06
CN105220703B true CN105220703B (en) 2017-01-18

Family

ID=54989935

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510582372.4A Active CN105220703B (en) 2015-09-11 2015-09-11 Enclosing type deepwater platform construction method based on condition of sand backfilling balance method

Country Status (1)

Country Link
CN (1) CN105220703B (en)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105887910B (en) * 2016-04-22 2020-03-31 广州比艾莫信息科技有限公司 Formwork supporting and stripping system for foundation bearing platform and working process of formwork supporting and stripping system
CN106436689B (en) * 2016-10-05 2018-10-09 广东煌烨建设工程有限公司 The supporting of cushion cap steel sheet pile and steel sheet pile double as cushion cap template construction method
CN106958254A (en) * 2017-05-08 2017-07-18 中铁七局集团第四工程有限公司 Latch steel pipe and reinforced concrete combination pile cofferdam and its construction method
CN109339065B (en) * 2018-12-11 2022-04-12 中国建筑一局(集团)有限公司 Method for deep water exposed bedrock close-packed pile supporting construction bearing platform
CN110184923A (en) * 2019-05-04 2019-08-30 湖北省路桥集团有限公司 A kind of main bearing platform construction technique of bridge
CN111042164B (en) * 2019-12-31 2021-12-07 湖北省路桥集团有限公司 Composite special-shaped cofferdam and construction method
CN113684849B (en) * 2021-09-28 2022-11-29 中交一公局第一工程有限公司 Steel sheet pile cofferdam supporting and anti-collision conversion structure and construction method
CN113863355B (en) * 2021-10-18 2023-02-24 中电建十一局工程有限公司 Waterproof construction method for large-volume bearing platform in water

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007205077A (en) * 2006-02-03 2007-08-16 Shimizu Corp Temporary coffering method
CN202401462U (en) * 2011-11-11 2012-08-29 中交四航局第一工程有限公司 Deep-water single-wall steel sheet pile cofferdam structure with small soil penetration depth
CN103015446A (en) * 2012-08-10 2013-04-03 中铁大桥局股份有限公司 Method for constructing bearing platform on deepwater and rigid impermeable layer
CN203977417U (en) * 2014-08-14 2014-12-03 安徽省公路桥梁工程有限公司 Ribs built-in steel casing for a kind of pile of deep water pile foundation

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007205077A (en) * 2006-02-03 2007-08-16 Shimizu Corp Temporary coffering method
CN202401462U (en) * 2011-11-11 2012-08-29 中交四航局第一工程有限公司 Deep-water single-wall steel sheet pile cofferdam structure with small soil penetration depth
CN103015446A (en) * 2012-08-10 2013-04-03 中铁大桥局股份有限公司 Method for constructing bearing platform on deepwater and rigid impermeable layer
CN203977417U (en) * 2014-08-14 2014-12-03 安徽省公路桥梁工程有限公司 Ribs built-in steel casing for a kind of pile of deep water pile foundation

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
临近建筑物深基坑承台施工钢板桩支护方案探讨;宁镇;《科技致富向导》;20130120;第234、304页 *
浅谈水下承台施工技术;李瑛;《科技信息(科学教研)》;20080501(第13期);第102-103页 *
济祁高速淮河特大桥深水钢板桩围堰施工技术;沈维成;《公路交通科技(引用技术板)》;20150331;第243-245页 *
顺德支流特大桥深埋式承台钢板桩围堰设计与施工;张荣光等;《广东公路交通》;20100630;第41-44页 *

Also Published As

Publication number Publication date
CN105220703A (en) 2016-01-06

Similar Documents

Publication Publication Date Title
CN105220703B (en) Enclosing type deepwater platform construction method based on condition of sand backfilling balance method
CN106638640B (en) Construction method without bottom concrete combined type cofferdam under the conditions of formation geology
CN103195076B (en) Muddy Bottoms deep-excavation tower crane foundation construction method
CN102767189B (en) Set bearing platform foundations and construction method thereof
CN105544575B (en) A kind of bottom concrete construction method under water of use steel truss reinforcement
CN104264688A (en) Manual hole digging non-uniform pile support construction technology
CN105756091B (en) A kind of Metro station excavation construction method of control adjacent building composition deformation
CN102363961A (en) Deepwater single-wall steel plate pile cofferdam structure with low buried depth and construction method thereof
CN101768924B (en) Overhead method for existing railway in area with soft foundation and high water level
CN106884433A (en) Control vibrations pile pulling causes the structure of underground structure depression and control depression method
CN105926672B (en) A kind of Underground Subway Station steel pipe column construction method
CN112982481B (en) Structure construction method for crossing subway intersection node on pipe gallery
CN102619206A (en) Foundation platform structure of bare rock and karst pile in deep water
CN108442370A (en) The broken pile connector processing method of prestressed concrete pipe pile
CN110847207A (en) Structure and construction method for newly-built bridge with subway tunnel passing through existing bridge piles
CN104775439B (en) A kind of pattern foundation pit supporting structure sealing integral structure and its construction method
CN202401462U (en) Deep-water single-wall steel sheet pile cofferdam structure with small soil penetration depth
CN104264683A (en) Concave ultra-deep foundation pit zoned supporting method for three-side surrounded cultural protection building
CN110093927B (en) Method for controlling deformation of tunnel outside foundation pit
CN109577322A (en) A kind of constructing device for inside soil body existing pile foundation pile extension
CN111810185B (en) Tunnel bottom pre-reinforcement construction method
CN206448285U (en) Without bottom concrete combined type cofferdam under the conditions of formation geology
CN108978680A (en) A kind of muck soil elevator foundation pit supporting construction device and method
CN105155421B (en) Complete embedding circular construction method in a kind of single pile Single column pier river course shallow water
CN106120853B (en) A kind of inverted construction method of frame bridge

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant