CN106436689B - The supporting of cushion cap steel sheet pile and steel sheet pile double as cushion cap template construction method - Google Patents

The supporting of cushion cap steel sheet pile and steel sheet pile double as cushion cap template construction method Download PDF

Info

Publication number
CN106436689B
CN106436689B CN201610870183.1A CN201610870183A CN106436689B CN 106436689 B CN106436689 B CN 106436689B CN 201610870183 A CN201610870183 A CN 201610870183A CN 106436689 B CN106436689 B CN 106436689B
Authority
CN
China
Prior art keywords
cushion cap
steel sheet
sheet pile
pile
purlin
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610870183.1A
Other languages
Chinese (zh)
Other versions
CN106436689A (en
Inventor
黄坤坤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Huazheng Construction Engineering Co.,Ltd.
Original Assignee
Guangdong Huang Ye Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Huang Ye Construction Engineering Co Ltd filed Critical Guangdong Huang Ye Construction Engineering Co Ltd
Priority to CN201610870183.1A priority Critical patent/CN106436689B/en
Publication of CN106436689A publication Critical patent/CN106436689A/en
Application granted granted Critical
Publication of CN106436689B publication Critical patent/CN106436689B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/02Sheet piles or sheet pile bulkheads
    • E02D5/03Prefabricated parts, e.g. composite sheet piles
    • E02D5/04Prefabricated parts, e.g. composite sheet piles made of steel
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • E02D27/14Pile framings, i.e. piles assembled to form the substructure

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Paleontology (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Architecture (AREA)
  • Chemical & Material Sciences (AREA)
  • Composite Materials (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

Cushion cap template is doubled as the invention discloses a kind of cushion cap steel sheet pile supporting and steel sheet pile, 1)Surveying and locating;2)It excavates on old road;3) leading truck is set up;4)Inserting piling steel sheet pile;5)First time cushion cap earth excavation;6)Set up purlin and support;7)Second of cushion cap earth excavation;8)Cut pile crown, pile measurement;9)Pour concrete bed course;10)Set up cushion cap template;11)Cushion cap reinforcing bar is bound and pier stud reinforcing bar is set up;12)Set up separation layer;13)Pour cushion cap pier stud concrete;14)Remove support, purlin and steel sheet pile;15)Steel sheet pile pulls out the processing at place.Cushion cap steel sheet pile supporting provided by the invention and steel sheet pile double as cushion cap template, it is ensured that the structure in construction and personal safety;Ensure foundation pit periphery construction of structures, underground utilities, road normal use and safety, accelerate construction speed, it is ensured that the realization of constructing aims reduces earth excavation, stacking and the workload of transport, protects surrounding enviroment, reduces airborne dust influence.

Description

The supporting of cushion cap steel sheet pile and steel sheet pile double as cushion cap template construction method
Technical field
The present invention relates to a kind of overpass construction method more particularly to a kind of cushion cap steel sheet pile supporting and steel sheet pile are simultaneous Make cushion cap template.
Background technology
In elevated bridge construction, the construction quality of cushion cap often cannot be guaranteed, and often destroys periphery construction and build The normal use and safety of object, underground utilities, road, and being connected road with it can be by the inconvenience of moving traffic;In cushion cap When construction, earth excavation, stacking and the workload of transport can influence protection and the dust controlling of surrounding enviroment, can also be because of mistake The hidden danger of quality of heavy excavation backfill uses restoring old road the influence of quality;Conventional arrangement and method for construction digging up and filling in roll less than Position, can lead to the non-uniform sedimentation in road surface, delay construction speed, to affect the realization of constructing aims;In conclusion needle To disadvantages mentioned above existing in the prior art, invention proposes a kind of cushion cap steel sheet pile supporting and steel sheet pile doubles as cushion cap template.
Invention content
The present invention the technical solution adopted is that provides a kind of cushion cap steel sheet pile supporting and steel to solve above-mentioned technical problem Sheet pile doubles as cushion cap template, wherein
(One)Surveying and locating
According to the four angular coordinate for calculating cushion cap side and adding 10cm, steel sheet pile is marked after releasing quadrangle point with total powerstation The position line;
(Two)It excavates on the old road of steel sheet pile insert division
Then the routing at steel sheet pile position abolishes old road face with cutting machine after wire cutting;
(Three)It sets up steel sheet pile and is inserted into leading truck
It prevents the bending deformation of steel sheet pile and improves the penetration capability of stake, certain rigidity, firm leading truck is set;
(Four)Inserting piling steel sheet pile is to designed elevation
Vibration hammer injection is matched using digging machine;
(Five)First time cushion cap earth excavation
It is cut the earth to the absolute altitude of purlin bottom in steel sheet pile with digging machine;
(Six)Set up purlin and support
After earth excavation to purlin bottom absolute altitude, is then hung in and enclosed with crane by design quantity welding bracket on steel sheet pile Purlin is shelved on bracket and is welded;Then by purlin, welding consolidates at the angle of cut, finally angle steel is reinforced in welding in the angle of cut;
(Seven)Second of cushion cap earth excavation
It after the completion of purlin support is set up, is excavated to away from after at substrate 20cm absolute altitudes with digging machine, finally clear is dug using artificial To design foundation pit bottom absolute altitude;
(Eight)Cut pile crown, pile measurement
Rear establishment officer in time abolishes cushion cap excavation of foundation pit with equipment progress pile crown in place, and it is mixed to cut pile crown using air compressor machine Solidifying soil;
(Nine)Pour concrete bed course
Cushion cap bed course uses 10cm thickness C15 concretings, bed course to go out cushion cap 10cm per hem width;
(Ten)Cushion cap template is set up
The surrounding of foundation pit is previously placed in using bamboo slab rubber according to the size of cushion cap;
(11)Cushion cap reinforcing bar is bound and pier stud reinforcing bar is set up
After cushion cap blinding concrete reaches the 70% of design strength, you can carry out cushion cap reinforcing bar binding;
(12)Template adjustment is reinforced
Reinforcement installation in place, binds protective layer cushion block, then by the bamboo slab rubber of reinforcing bar surrounding on the outside of cushion cap facade reinforcing bar Movement is labelled on cushion block of concrete bar protective layer;Medium coarse sand is backfilled on the outside of bamboo slab rubber at cushion cap 2/3;It is carried out using the lumps of wood on top It reinforces;
(13)Set up separation layer
Cushion cap position disposes isolation board on the inside of steel sheet pile;
(14)Pour cushion cap pier stud concrete
Placement layer by layer, thickness are no more than 30cm, are vibrated using immersion vibrator, and vibrator is inserted into 5 in lower-layer concrete ~10 cm ensure the good combination of levels concrete;
(15)Remove support, purlin and steel sheet pile
After cushion cap concrete placings, after pier stud pours completion form removal, foundation pit backfill is carried out, steel sheet pile is pulled out;
(16)Steel sheet pile pulls out the processing at place
It is backfilled using medium coarse sand, i.e., pier stud concrete placings are completed, will after Pier Formwork, pier stud construction scaffolding are removed Gap between steel sheet pile and cushion cap is filled up with medium coarse sand;The principle of vibration is pulled out using steel sheet pile by layer of sand vibration compacting, together The mode of Shi Caiyong water fillings ensures the moistening of sand, is subject to sand surface not ponding;Cushion cap is backfilled using plain soil, is used Digging machine layering leveling compacting.
Above-mentioned automatically controls track wheel type mobile job platform construction method, wherein in the step 3, leading truck is adopted With single-layer double-side form, it is made of nose girder and purlin stake etc..
Above-mentioned automatically controls track wheel type mobile job platform construction method, wherein the spacing of purlin stake is generally 2.5 ~3.5 meters, the spacing between two-sided purlin should not be too large, slightly bigger than sheet pile wall thickness by 8 from the point of view of protective layer thickness~ 10mm。
Above-mentioned automatically controls track wheel type mobile job platform construction method, wherein in the step 4, before piling, The grease in the fore shaft of sheet pile is squeezed into and is extracted to facilitate.
Above-mentioned automatically controls track wheel type mobile job platform construction method, wherein in the step 6, purlin and branch Support is all made of H400 shaped steel.
Above-mentioned automatically controls track wheel type mobile job platform construction method, wherein in the step 8, controls foundation pile Height of pile top is higher by cushion cap bottom surface 10cm, when pile crown will be dug in place, reduces broken pile dynamics, avoids the de- of mass concrete It falls, to prevent from destroying protective layer and pile body.
Above-mentioned automatically controls track wheel type mobile job platform construction method, wherein in the step 12, cushion block number Amount is no less than 5 pieces of settings by every square meter;Lumps of wood size is 100*50mm.
Above-mentioned automatically controls track wheel type mobile job platform construction method, wherein in the step 13, isolation board For 12mm thickness.
The present invention has the advantages that compared with the existing technology:
1)Ensure the structure in construction and personal safety;
2)Ensure foundation pit periphery construction of structures, underground utilities, road normal use and safety;
3)Be conducive to maintain 204 national highway moving traffics and builder's road traffic, avoid caused by slope is excavated traffic and Operation side is insufficient;
4)Be conducive to, by science organization's parallel line production, accelerate construction progress, it is ensured that the realization of constructing aims;
5)Earth excavation, stacking and the workload of transport can be reduced, protection surrounding enviroment reduce airborne dust influence;
6)Excavated surface can be reduced to greatest extent, the hidden danger of quality of excessive digging up and filling in is avoided to make to restoring old road With the influence of quality, while conventional construction scheme can also be avoided, which to be rolled using digging up and filling in, not in place causes road surface non-uniform Sedimentation.
Specific implementation mode
(One)Surveying and locating
According to the four angular coordinate for calculating cushion cap side and adding 10cm, steel sheet pile is marked after releasing quadrangle point with total powerstation The position line;
(Two)It excavates on the old road of steel sheet pile insert division
Then the routing at steel sheet pile position abolishes old road face with cutting machine after wire cutting;
(Three)It sets up steel sheet pile and is inserted into leading truck
For ensure pile sinking axial location correct and stake it is vertical, control stake squeezes into precision, prevents the buckling of steel sheet pile Deformation and the penetration capability for improving stake, are arranged certain rigidity, firm leading truck;
Leading truck uses single-layer double-side form, is made of nose girder and purlin stake etc., and the spacing of purlin stake is generally 2.5~ 3.5 meters, the spacing between two-sided purlin should not be too large, slightly bigger than sheet pile wall thickness by 8 from the point of view of protective layer thickness~ 10mm;
The following is should be noted that when leading truck is installed:Using the position of total powerstation and level meter control and adjustment nose girder;It leads Depth of beam is suitable, to be conducive to the construction height for controlling steel sheet pile and improve construction efficiency;Nose girder cannot be with steel sheet pile Set and generate sinking and deformation;The position of nose girder should be accurate, can not be collided with steel sheet pile;
(Four)Inserting piling steel sheet pile is to designed elevation
It the case where matching vibration hammer injection using digging machine, underground utilities, underground structure must be found out before injection, avoids damaging;
Before piling, to steel sheet pile by root inspection, the corrosion of connection fore shaft, the serious steel sheet pile of deformation are rejected, failure waits for Rear is modified to can be used;
Before piling, the grease in the fore shaft of sheet pile is squeezed into and is extracted to facilitate;
It measures gradient of the monitoring per pile at any time during inserting piling and is no more than 0.3%, the side of pulling together cannot be used when deflection is excessive When method is aligned, pulls up and beat again;
(Five)First time cushion cap earth excavation
Foundation pit shoveling replaces cooperation with the setting that purlin supports and carries out:First step digging machine is cut the earth in steel sheet pile to purlin At the absolute altitude of bottom;
(Six)Set up purlin and support
Purlin and support are all made of H400 shaped steel.According to the construction plan and equipment of Design of Construction Organization and this special scheme The model size of input and cushion cap supports bracket, purlin, angle brace in over-the-counter patterning process;
After earth excavation to purlin bottom absolute altitude, is then hung in and enclosed with crane by design quantity welding bracket on steel sheet pile Purlin is shelved on bracket and is welded;Then by purlin, welding consolidates at the angle of cut, finally angle steel is reinforced in welding in the angle of cut;
(Seven)Second of cushion cap earth excavation
It after the completion of purlin support is set up, is excavated to away from after at substrate 20cm absolute altitudes with digging machine, finally clear is dug using artificial To design foundation pit bottom absolute altitude;With closed muck haulage vehicle with digging with transporting outside construction site when earth excavation;
(Eight)Cut pile crown, pile measurement
Rear establishment officer in time abolishes cushion cap excavation of foundation pit with equipment progress pile crown in place, and it is mixed to cut pile crown using air compressor machine Solidifying soil.In work progress, notice that controlling foundation pile height of pile top is higher by cushion cap bottom surface 10cm;When pile crown will be dug in place, reduce Broken pile dynamics avoids falling off for mass concrete, to prevent from destroying protective layer and pile body;
After pile crown is cut in place, stake top loose concrete is all cut, removing surface is clean;It is set as stake top absolute altitude is less than When counting absolute altitude, designed elevation must be connected to ad eundem concrete;
Pile quality is detected by design requirement, carries out stake position setting-out, measures deflected file amount, it can after qualified Carry out next procedure construction;
(Nine)Pour concrete bed course
Cushion cap bed course uses 10cm thickness C15 concretings, bed course to go out cushion cap 10cm per hem width;Setting-out is carried out before construction, It determines bed course plan-position and absolute altitude, prevents from entering inside cushion cap more than cushion cap bottom absolute altitude;
After the leveling compacting of foundation pit bottom, pour 10cm thickness C15 concrete cushions, vibration compacting, control bed course top mark height and Flatness;
(Ten)Cushion cap template is set up
After cushion cap pit earthwork excavates, the soil on manual cleaning steel sheet pile uses 12cm bamboos according to the size of cushion cap Offset plate is previously placed in the surrounding of foundation pit;The template of unilateral cushion cap is set to be formed piece fixation using batten on the outside of bamboo slab rubber It is whole;
(11)Cushion cap reinforcing bar is bound and pier stud reinforcing bar is set up
After cushion cap blinding concrete reaches the 70% of design strength, you can carry out cushion cap reinforcing bar binding;Mat surface is cleaned, It is measured on bed course and releases four angle points of cushion cap, restore cushion cap sideline;Pile crown reinforcing bar is derusted, conditioning is straight and curved to design angle Degree ensures that pile crown reinforcement location is accurate;
Cushion cap reinforcing bar is concentrated in processing space and is made, and is carried out according to design drawing and related code requirement after being transported to construction site Binding;Reinforcement construction sequence be:Cushion cap bottom layer of the reinforcing steel → cushion cap cableway → cushion cap side reinforcing bar → cushion cap top layer reinforcing bar → Pier shaft embedded bar;
(12)Template adjustment is reinforced
Reinforcement installation in place, binds protective layer cushion block on the outside of cushion cap facade reinforcing bar, and cushion block quantity is no less than 5 by every square meter Block is arranged, and then the movement of the bamboo slab rubber of reinforcing bar surrounding will be labelled on cushion block of concrete bar protective layer;It is thick in being backfilled on the outside of bamboo slab rubber Sand is at cushion cap 2/3, i.e. positions 1.2m;Reinforced using the 100*50mm lumps of wood on top, ensure cushion cap geometric dimension and Cushion block of concrete bar protective layer liner is secured;
(13)Set up separation layer
Cushion cap position disposes 12mm thickness isolation boards on the inside of steel sheet pile;
(14)Pour cushion cap pier stud concrete
Concrete strictly controls match ratio by blending station centralized mixing, and mix-proportion adjustment, temperature are carried out according to sandstone water content When low the slump remove value, temperature it is high when the slump take upper value;
Concrete is transported by agitator truck to scene, concrete mixer cloth, placement layer by layer, and thickness is no more than 30cm; It is vibrated using immersion vibrator, vibrator is inserted into 5~10 cm in lower-layer concrete, ensures the good knot of levels concrete It closes;The closely knit mark of concrete vibrating is that concrete stops sinking, effervescent, bleeding, surface be not flat;
After concreting is complete, cushion cap top of concrete is modified, is smoothed out, smears second time and press polish after due-in slurry again Processing, with the processing of pier stud binding site dabbing;
(15)Remove support, purlin and steel sheet pile
After cushion cap concrete placings, after pier stud pours completion form removal, foundation pit backfill is carried out, steel sheet pile is pulled out;Before pulling out sheet pile, Specify the processing in native hole after the method, sequence and pile pulling of pile pulling;Can not excessively it draw because of the vibration effect and pile pulling band soil of pile pulling The sedimentation and displacement for playing ground, closing on inhering architecture, structures or beneath pipeline;
(16)Steel sheet pile pulls out the processing at place
1, the related processing during pile pulling
Steel sheet pile will produce disturbance beating the during of pulling out to the periphery soil body, be applied according to engineering characteristic, structural relation and postorder Work requirement, makees considered below:
1. cushion cap occupies the part road surface of existing road, function is used for original path can be restored after guarantee bearing platform construction;
2. original path has still maintained traffic, steel sheet pile to pull out about 1.5 meters of upright high slopes of rear cushion cap foundation pit and shake in vehicle Stability requirement under dynamic;
3. what need to be restored at cushion cap foundation pit bankets to planting technique and bridge capping construction support stability requirement;
2, pile extracting method
This technology pile pulling uses vibration hammer pile pulling:The forced vibration generated using vibration hammer disturbs soil property, destroys sheet pile week The cohesive strength of soil is enclosed to overcome pile extraction resistance, pulls out stake by the effect of additional lifting force;
3, cushion cap Foundation treatment
1. the following Foundation treatment in cushion cap top surface
It is backfilled using medium coarse sand, i.e., pier stud concrete placings are completed, will after Pier Formwork, pier stud construction scaffolding are removed Gap between steel sheet pile and cushion cap is filled up with medium coarse sand;The principle of vibration is pulled out using steel sheet pile by layer of sand vibration compacting, together The mode of Shi Caiyong water fillings ensures the moistening of sand, is subject to sand surface not ponding;
2. the above foundation pit in cushion cap top surface
Since the above upright slope height of cushion cap is 1.0~1.5m, there is traffic passage in outside, and traffic load is larger, in order to protect Stability of slope and traffic safety are demonstrate,proved, according to construction period and construction needs, after steel sheet pile is pulled out, i.e., cushion cap is carried out using element soil Backfill is layered leveling compacting using digging machine.After the completion of equal Coping Constructions, foundation pit is carried out at anti-excavation further according to design drawing Reason.
Although the present invention is disclosed as above with preferred embodiment, however, it is not to limit the invention, any this field skill Art personnel, without departing from the spirit and scope of the present invention, when can make a little modification and it is perfect, therefore the present invention protection model It encloses to work as and is subject to what claims were defined.

Claims (8)

1. a kind of cushion cap steel sheet pile supporting and steel sheet pile double as cushion cap template construction method, it is characterised in that:Include the following steps:
(One)Surveying and locating
According to the four angular coordinate for calculating cushion cap side and adding 10cm, steel sheet pile position is marked after releasing quadrangle point with total powerstation Line;
(Two)It excavates on the old road of steel sheet pile insert division
Then the routing at steel sheet pile position abolishes old road face with cutting machine after wire cutting;
(Three)It sets up steel sheet pile and is inserted into leading truck
It prevents the bending deformation of steel sheet pile and improves the penetration capability of stake, certain rigidity, firm leading truck is set;
(Four)Inserting piling steel sheet pile is to designed elevation
Vibration hammer injection is matched using digging machine;
(Five)First time cushion cap earth excavation
It is cut the earth to the absolute altitude of purlin bottom in steel sheet pile with digging machine;
(Six)Set up purlin and support
After earth excavation to purlin bottom absolute altitude, then purlin is hung in crane and put on steel sheet pile by design quantity welding bracket It sets on bracket and welds;Then by purlin, welding consolidates at the angle of cut, finally angle steel is reinforced in welding in the angle of cut;
(Seven)Second of cushion cap earth excavation
It after the completion of purlin support is set up, is excavated to away from after at substrate 20cm absolute altitudes with digging machine, finally clear is dug to setting using artificial Count foundation pit bottom absolute altitude;
(Eight)Cut pile crown, pile measurement
Rear establishment officer in time abolishes cushion cap excavation of foundation pit with equipment progress pile crown in place, and pile crown coagulation is cut using air compressor machine Soil;
(Nine)Pour concrete bed course
Cushion cap bed course uses 10cm thickness C15 concretings, bed course to go out cushion cap 10cm per hem width;
(Ten)Cushion cap template is set up
The surrounding of foundation pit is previously placed in using bamboo slab rubber according to the size of cushion cap;
(11)Cushion cap reinforcing bar is bound and pier stud reinforcing bar is set up
After cushion cap blinding concrete reaches the 70% of design strength, you can carry out cushion cap reinforcing bar binding;
(12)Template adjustment is reinforced
Reinforcement installation in place, binds protective layer cushion block on the outside of cushion cap facade reinforcing bar, then moves the bamboo slab rubber of reinforcing bar surrounding It is labelled on cushion block of concrete bar protective layer;Medium coarse sand is backfilled on the outside of bamboo slab rubber at cushion cap 2/3;Added using the lumps of wood on top Gu;
(13)Set up separation layer
Cushion cap position disposes isolation board on the inside of steel sheet pile;
(14)Pour cushion cap pier stud concrete
Placement layer by layer, thickness are no more than 30cm, are vibrated using immersion vibrator, and vibrator is inserted into 5~10 in lower-layer concrete Cm ensures the good combination of levels concrete;
(15)Remove support, purlin and steel sheet pile
After cushion cap concrete placings, after pier stud pours completion form removal, foundation pit backfill is carried out, steel sheet pile is pulled out;
(16)Steel sheet pile pulls out the processing at place
It is backfilled using medium coarse sand, i.e., pier stud concrete placings are completed, after Pier Formwork, pier stud construction scaffolding are removed, by steel plate Gap between stake and cushion cap is filled up with medium coarse sand;The principle for pulling out vibration using steel sheet pile adopts layer of sand vibration compacting simultaneously With the mode of water filling, ensure the moistening of sand, is subject to sand surface not ponding;Cushion cap is backfilled using plain soil, using digging machine Layering leveling compacting.
2. a kind of cushion cap steel sheet pile supporting as described in claim 1 and steel sheet pile double as cushion cap template construction method, feature It is:In the step 3, leading truck uses single-layer double-side form, is made of nose girder and purlin stake.
3. a kind of cushion cap steel sheet pile supporting as claimed in claim 2 and steel sheet pile double as cushion cap template construction method, feature It is:The spacing of purlin stake is 2.5~3.5 meters, and the spacing between two-sided purlin should not be too large, from the point of view of protective layer thickness It is bigger 8~10mm than sheet pile wall thickness.
4. a kind of cushion cap steel sheet pile supporting as described in claim 1 and steel sheet pile double as cushion cap template construction method, feature It is:In the step 4, before piling, the grease in the fore shaft of sheet pile is squeezed into and is extracted to facilitate.
5. a kind of cushion cap steel sheet pile supporting as described in claim 1 and steel sheet pile double as cushion cap template construction method, feature It is:In the step 6, purlin and support are all made of H400 shaped steel.
6. a kind of cushion cap steel sheet pile supporting as described in claim 1 and steel sheet pile double as cushion cap template construction method, feature It is:In the step 8, control foundation pile height of pile top is higher by cushion cap bottom surface 10cm, when pile crown will be dug in place, reduces broken Stake dynamics, avoids falling off for mass concrete, to prevent from destroying protective layer and pile body.
7. a kind of cushion cap steel sheet pile supporting as described in claim 1 and steel sheet pile double as cushion cap template construction method, feature It is:In the step 12, cushion block quantity is no less than 5 pieces of settings by every square meter;Lumps of wood size is 100*50mm.
8. a kind of cushion cap steel sheet pile supporting as described in claim 1 and steel sheet pile double as cushion cap template construction method, feature It is:In the step 13, isolation board is 12mm thick.
CN201610870183.1A 2016-10-05 2016-10-05 The supporting of cushion cap steel sheet pile and steel sheet pile double as cushion cap template construction method Active CN106436689B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610870183.1A CN106436689B (en) 2016-10-05 2016-10-05 The supporting of cushion cap steel sheet pile and steel sheet pile double as cushion cap template construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610870183.1A CN106436689B (en) 2016-10-05 2016-10-05 The supporting of cushion cap steel sheet pile and steel sheet pile double as cushion cap template construction method

Publications (2)

Publication Number Publication Date
CN106436689A CN106436689A (en) 2017-02-22
CN106436689B true CN106436689B (en) 2018-10-09

Family

ID=58171384

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610870183.1A Active CN106436689B (en) 2016-10-05 2016-10-05 The supporting of cushion cap steel sheet pile and steel sheet pile double as cushion cap template construction method

Country Status (1)

Country Link
CN (1) CN106436689B (en)

Families Citing this family (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107012792B (en) * 2017-05-23 2018-11-02 温州市隆尚建设有限公司 A kind of construction method of bridge substructure
CN108166395B (en) * 2017-12-26 2019-05-10 中铁四局集团路桥工程有限公司 A kind of construction method for building beam bridge across Business Line
CN109322320A (en) * 2018-11-13 2019-02-12 中国二十冶集团有限公司 The construction method of Deep Thick Soft Ground Area cushion cap and basement bottom board
CN109680706A (en) * 2018-12-11 2019-04-26 中交一公局土木工程建筑研究院有限公司 Assembled bearing platform pier pile full scale model and crack pouring construction process using same
CN110258607A (en) * 2019-06-28 2019-09-20 王义东 A kind of convenient construction method of bridge construction that mass concrete Pile-supported stand foundation is set
CN112031012B (en) * 2020-07-14 2022-03-15 上海建工集团股份有限公司 Warehouse-dividing excavation construction method and device for bearing platform under limited operation space
CN111894006A (en) * 2020-07-24 2020-11-06 保利长大工程有限公司 Steel sheet pile supporting structure serving as cushion cap formwork support and construction method
CN112681290A (en) * 2020-12-19 2021-04-20 中交二公局萌兴工程有限公司 Larsen steel sheet pile support construction process
CN114482149B (en) * 2022-01-25 2024-06-04 广东玄城建设工程有限公司 Municipal construction foundation pile foundation construction method
CN114837088A (en) * 2022-04-27 2022-08-02 中国建筑第七工程局有限公司 Construction method of bearing platform on highway

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104196042B (en) * 2014-08-15 2015-12-09 中国建筑第六工程局有限公司 A kind of steel sheet pile cofferdam structure construction method
CN105220703A (en) * 2015-09-11 2016-01-06 安徽省公路桥梁工程有限公司 A kind of sand flat enclosure-type deep water construction method under weighing apparatus method condition based on returning
CN105442623A (en) * 2015-12-17 2016-03-30 中交二航局第四工程有限公司 No-trestle water bridge pile foundation and bearing platform construction method and cofferdam thereof

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20140112718A1 (en) * 2012-10-22 2014-04-24 Vitaly Boris Feygin Universal cellular cofferdam with embedded columnar framing and embedded rock anchor mechanism

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104196042B (en) * 2014-08-15 2015-12-09 中国建筑第六工程局有限公司 A kind of steel sheet pile cofferdam structure construction method
CN105220703A (en) * 2015-09-11 2016-01-06 安徽省公路桥梁工程有限公司 A kind of sand flat enclosure-type deep water construction method under weighing apparatus method condition based on returning
CN105442623A (en) * 2015-12-17 2016-03-30 中交二航局第四工程有限公司 No-trestle water bridge pile foundation and bearing platform construction method and cofferdam thereof

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
混凝土结构桥梁承台施工技术分析;魏加友;《山东工业技术》;20150801(第15期);52-53页 *

Also Published As

Publication number Publication date
CN106436689A (en) 2017-02-22

Similar Documents

Publication Publication Date Title
CN106436689B (en) The supporting of cushion cap steel sheet pile and steel sheet pile double as cushion cap template construction method
CN106958256B (en) A kind of placement layer by layer, the open caisson construction technique repeatedly sunk
CN104074199B (en) Underwater bearing platform construction method
CN102505695B (en) Construction method for deep foundation pit of three-dimensional garage
CN102444142B (en) Pile group column replacement expanded basement and construction method of same
CN100572686C (en) The construction technology of hole support system in the hole
CN106930319A (en) A kind of high slope framed revetment and its construction method
CN103590602B (en) The construction method of cast-in-place concrete hollow building roof
CN103696784B (en) Large-diameter long pipe curtain construction method for shallowly-buried large-span under-tunnel-passing architectural structure
KR20140075767A (en) Retaining wall construction using site compaction and excavation
CN106088127A (en) Open caisson construction method
CN106320377A (en) Water-rich soft soil area deep foundation pit cover and excavation top-down construction method
CN109505229A (en) Highway high gradient slope stress equilibrium and vibration damping are taken precautions against natural calamities high bridge pier structure and construction method
CN107447778A (en) The heightening and consolidation structure and method of a kind of in-service reinforced concrete retaining wall
CN111910679B (en) Construction method of overlong and ultrahigh-weight retaining wall under complex terrain
CN106836238A (en) A kind of construction method and its structure for falling the vertical floor support replacement of grade formula deep basal pit
CN106436788A (en) Foundation reinforcement and inclination correction method for friction piles of high-rise building
CN107489164A (en) The heightening and consolidation structure and method of a kind of in-service reinforced concrete retaining wall
CN102071698B (en) Construction method of beddings of foundation downward overturn beam and pile cap
CN106869151A (en) A kind of bridge construction method of deep foundation ditch
CN112281857A (en) Deep foundation pit excavation construction method
CN109706952A (en) Large-scale well-sinking construction method
CN207331740U (en) A kind of heightening and consolidation structure of in-service reinforced concrete retaining wall
CN207331739U (en) A kind of heightening and consolidation structure of in-service reinforced concrete retaining wall
CN102235007B (en) Method for supporting deep foundation with upper nail-lower pile combination

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20180829

Address after: 523000 Dongcheng Street, Dongsha Road, Dongsha Road, Dongling Road, Dongling Road, Dongsha Road, Dongguan, Guangdong, 401-402

Applicant after: Guangdong Huang Ye Construction Engineering Co., Ltd.

Address before: 226019 Zhongnan department store, No. 27 Zhongnan Century City, Chongchuan District, Nantong, Jiangsu 3301

Applicant before: Huang Kunkun

GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: Unit 401-402, Dongjun building, Dongke Road, HENGLING Industrial Park, Tongsha Science Park, Dongcheng Street, Dongcheng District, Dongguan City, Guangdong Province, 523000

Patentee after: Guangdong Huazheng Construction Engineering Co.,Ltd.

Address before: 523000 Dongcheng Street, Dongsha Road, Dongsha Road, Dongling Road, Dongling Road, Dongsha Road, Dongguan, Guangdong, 401-402

Patentee before: Guangdong Huang Ye construction engineering corporation, Ltds