CN109322320A - The construction method of Deep Thick Soft Ground Area cushion cap and basement bottom board - Google Patents
The construction method of Deep Thick Soft Ground Area cushion cap and basement bottom board Download PDFInfo
- Publication number
- CN109322320A CN109322320A CN201811346409.3A CN201811346409A CN109322320A CN 109322320 A CN109322320 A CN 109322320A CN 201811346409 A CN201811346409 A CN 201811346409A CN 109322320 A CN109322320 A CN 109322320A
- Authority
- CN
- China
- Prior art keywords
- cushion cap
- construction
- bottom board
- basement bottom
- waterproof
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/10—Deep foundations
- E02D27/12—Pile foundations
- E02D27/14—Pile framings, i.e. piles assembled to form the substructure
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/045—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D31/00—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
- E02D31/02—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/02—Sheet piles or sheet pile bulkheads
- E02D5/03—Prefabricated parts, e.g. composite sheet piles
- E02D5/04—Prefabricated parts, e.g. composite sheet piles made of steel
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Composite Materials (AREA)
- Chemical & Material Sciences (AREA)
- Hydrology & Water Resources (AREA)
- Bulkheads Adapted To Foundation Construction (AREA)
Abstract
The invention discloses the construction methods of a kind of Deep Thick Soft Ground Area cushion cap and basement bottom board, this method carries out cushion cap excavation by the way of steel sheet pile supporting, waist rail is set in steel sheet pile by calculating according to cushion cap depth, angle brace and to support, after the completion of excavation, pour bed course, construction waterproof and waterproof protective layer, cushion cap reinforcing bar is bound in waterproof protective layer, then in cushion cap reinforcing bar surrounding supporting module, cushion cap concrete is poured to basement bottom board bottom absolute altitude, construction bearing platform side waterproof and waterproof protective layer, steel sheet pile is extracted after the backfill earthwork and compacting, after the construction section bearing platform construction of delimitation, pour basement bottom board bed course, construction waterproof slab and waterproof protective layer, bind baseplate reinforcing bar, pour underplate concrete, complete basement bottom board construction.This method can it is simple, efficiently, the completion soft clay area cushion cap excavation supporting of safety and basement bottom board construction, it is ensured that construction operation steel sheet pile safe and convenient recycles after extracting, save the cost.
Description
Technical field
The present invention relates to the construction methods of a kind of Deep Thick Soft Ground Area cushion cap and basement bottom board.
Background technique
Cushion cap refers to bearing, being distributed the load transmitted by pier shaft, the steel for each stake top of connection being arranged at the top of pile foundation
Reinforced concrete platform.In the area that Deep Thick Soft Ground Area, especially mud are deep, in order to guarantee deep pit monitor, the soil of cushion cap
Side, which is excavated, to be generally required to carry out pattern foundation pit supporting structure, not only can guarantee speed of application using the method for steel sheet pile supporting, but also can guarantee in hole
The safety in hole.But according to conventional way, cushion cap and basement bottom board pour simultaneously, using steel sheet pile supporting,
As by the way of pouring simultaneously, steel sheet pile will be unable to extract, and cushion cap side waterproof construction is difficult, will definitely increase cost,
Speed of application is slow.
Summary of the invention
Technical problem to be solved by the invention is to provide the constructions of a kind of Deep Thick Soft Ground Area cushion cap and basement bottom board
Method, the defect that this method overcomes traditional cushion cap and basement bottom board to construct can be simple, efficient, safety complete using this method
It constructs at soft clay area cushion cap excavation supporting and basement bottom board, it is ensured that construction operation steel sheet pile safe and convenient recycles after extracting
It utilizes, save the cost.
In order to solve the above technical problems, the construction method of Deep Thick Soft Ground Area cushion cap of the present invention and basement bottom board includes such as
Lower step:
Step 1:, according to bearing platform construction drawing surveying setting-out, cushion cap edge positions are determined in the construction segment limit of division,
Certain distance construction steel sheet pile on the outside of cushion cap sideline;
Step 2: waist rail is arranged along steel sheet pile by calculating according to the depth of foundation pit, angle brace, length direction are set at waist rail angle
Waist rail between be arranged to support;
Step 3: cushion cap earth excavation to cushion cap cheats bottom absolute altitude, in cushion cap hole, bottom pour mold builds cushion cap bed course;
Step 4: removing angle brace, to support and waist rail, cushion cap position is released on cushion cap bed course, according to cushion cap position in cushion cap pad
Laying water-proof coiled material on layer, waterproof roll periphery has more cushion cap position certain length, and carries out protection, pours on waterproof roll
Waterproof protective layer;
Step 5: binding cushion cap reinforcing bar in waterproof protective layer, and in cushion cap position surrounding supporting module, installation template adds
Solid system pours cushion cap concrete to basement bottom board bottom absolute altitude;
Step 6: removing cushion cap surrounding template, the waterproof roll that cushion cap bottom has more certain length is translated into cushion cap side and fixation,
It lays waterproof roll in cushion cap side and rolls up the waterproof roll overlap joint come with cushion cap bottom and fix, pasted on the outside of waterproof roll anti-
Steel sheet pile is extracted after water conservation extruded sheet, cushion cap side backfill and compacting;
Step 7: this is constructed after all cushion caps press step 1 to step 6 construction in the construction segment limit of division
Section levelling of the land, raft contact face dabbing cleaning, pours basement bottom board bed course in cushion cap top surface, then in basement bottom board pad
It successively constructs on layer base plate waterproofing and waterproof slab protective layer;
Step 8: binding baseplate reinforcing bar on waterproof slab protective layer, baseplate reinforcing bar anchors into or penetrates through cushion cap reinforcing bar, pouring construction
Basement bottom board concrete in section completes basement bottom board construction.
Further, in step 1, apart from steel sheet pile 800mm on the outside of the cushion cap sideline.
Further, in step 4, the length that the waterproof roll periphery has more cushion cap position is 500mm.
It is since the construction method of Deep Thick Soft Ground Area cushion cap of the present invention and basement bottom board uses above-mentioned technical proposal, i.e., our
Method carries out cushion cap excavation by the way of steel sheet pile supporting, and waist rail, angle brace is arranged in steel sheet pile by calculating according to cushion cap depth
With to support, after the completion of excavation, bed course, construction waterproof and waterproof protective layer are poured, cushion cap reinforcing bar is bound in waterproof protective layer, so
Afterwards in cushion cap reinforcing bar surrounding supporting module, pour cushion cap concrete to basement bottom board bottom absolute altitude, construction bearing platform side waterproof and
Waterproof protective layer backfills the earthwork and extracts steel sheet pile after being compacted, after the construction section bearing platform construction of delimitation, pours basement
Bottom cushion, construct waterproof slab and waterproof protective layer, binds baseplate reinforcing bar, pours underplate concrete, completes basement bottom board
Construction.The defect that this method overcomes traditional cushion cap and basement bottom board to construct, can be simple, efficient, safety complete using this method
It constructs at soft clay area cushion cap excavation supporting and basement bottom board, it is ensured that construction operation steel sheet pile safe and convenient recycles after extracting
It utilizes, save the cost.
Detailed description of the invention
The present invention will be further described in detail below with reference to the accompanying drawings and embodiments:
Fig. 1 is this method Steel Sheet Pile, waist rail, angle brace and schematic diagram is arranged to support;
Fig. 2 is bearing platform construction schematic diagram in this method;
Fig. 3 is cushion cap side waterproof and waterproof protective layer construction schematic diagram in this method;
Fig. 4 is basement bottom board construction schematic diagram in this method.
Specific embodiment
Embodiment is as shown in Figures 1 to 4, and the construction method of Deep Thick Soft Ground Area cushion cap and basement bottom board of the present invention includes
Following steps:
Step 1:, according to bearing platform construction drawing surveying setting-out, 1 edge positions of cushion cap are determined in the construction segment limit of division,
Certain distance construction steel sheet pile 2 on the outside of 1 sideline of cushion cap;
Step 2: waist rail 3 is arranged along steel sheet pile 2 by calculating, in 3 jiaos of setting angle braces 4 of waist rail, length according to the depth of foundation pit
Setting is to support 5 between the waist rail 3 in direction;
Step 3: 1 earth excavation of cushion cap to cushion cap 1 cheats bottom absolute altitude, bottom pour mold is cheated in cushion cap 1 and builds cushion cap bed course 11;
Step 4: removing angle brace 4, to support 5 and waist rail 3,1 position of cushion cap is released on cushion cap bed course 11, is existed according to 1 position of cushion cap
Laying water-proof coiled material 12 on cushion cap bed course 11,12 periphery of waterproof roll has more 1 position certain length of cushion cap, and carries out protection,
Waterproof protective layer 13 is poured on waterproof roll 12;
Step 5: binding cushion cap reinforcing bar 14 in waterproof protective layer 13, and in 1 position surrounding supporting module 6 of cushion cap, mould is installed
The reinforcement system 61 of plate 6 pours cushion cap concrete 15 to basement bottom board bottom absolute altitude;
Step 6: removing 1 surrounding template 6 of cushion cap, the waterproof roll 12 that 1 bottom of cushion cap has more certain length is translated into 1 side of cushion cap
And it is fixed, it lays waterproof roll 7 in 1 side of cushion cap and rolls up the overlap joint of waterproof roll 12 come with cushion cap bottom and fix, in waterproof roll
Waterproofing protection extruded sheet 8 is pasted in 7,12 outside of material, extracts steel sheet pile 2 after 1 side backfill 16 of cushion cap and compacting;
Step 7: this is constructed after all cushion caps press step 1 to step 6 construction in the construction segment limit of division
Section levelling of the land, 1 contact surface dabbing of cushion cap cleaning, pours 9 bed course 91 of basement bottom board in 1 top surface of cushion cap, then in basement
It successively constructs on 9 bed course 91 of bottom plate base plate waterproofing 92 and waterproof slab protective layer 93;
Step 8: binding baseplate reinforcing bar 94 on waterproof slab protective layer 93, baseplate reinforcing bar 94 anchors into or penetrates through cushion cap reinforcing bar 14,
9 concrete of basement bottom board in pouring construction section completes basement bottom board 9 and constructs.
Preferably, in step 1, apart from steel sheet pile 800mm on the outside of 1 sideline of cushion cap.
Preferably, in step 4, the length that 12 periphery of waterproof roll has more 1 position of cushion cap is 500mm.
For this method compared with traditional construction mode, the Construction Principle of this method is simple, constructs easy to implement, that cheats in hole opens
It digs securely and reliably, and steel sheet pile recoverable, saves construction cost, it can simple, efficient, safety completion soft clay area cushion cap
Excavation supporting and basement bottom board construction, improve construction quality.
Claims (3)
1. the construction method of a kind of Deep Thick Soft Ground Area cushion cap and basement bottom board, it is characterised in that this method includes following step
It is rapid:
Step 1:, according to bearing platform construction drawing surveying setting-out, cushion cap edge positions are determined in the construction segment limit of division,
Certain distance construction steel sheet pile on the outside of cushion cap sideline;
Step 2: waist rail is arranged along steel sheet pile by calculating according to the depth of foundation pit, angle brace, length direction are set at waist rail angle
Waist rail between be arranged to support;
Step 3: cushion cap earth excavation to cushion cap cheats bottom absolute altitude, in cushion cap hole, bottom pour mold builds cushion cap bed course;
Step 4: removing angle brace, to support and waist rail, cushion cap position is released on cushion cap bed course, according to cushion cap position in cushion cap pad
Laying water-proof coiled material on layer, waterproof roll periphery has more cushion cap position certain length, and carries out protection, pours on waterproof roll
Waterproof protective layer;
Step 5: binding cushion cap reinforcing bar in waterproof protective layer, and in cushion cap position surrounding supporting module, installation template adds
Solid system pours cushion cap concrete to basement bottom board bottom absolute altitude;
Step 6: removing cushion cap surrounding template, the waterproof roll that cushion cap bottom has more certain length is translated into cushion cap side and fixation,
It lays waterproof roll in cushion cap side and rolls up the waterproof roll overlap joint come with cushion cap bottom and fix, pasted on the outside of waterproof roll anti-
Steel sheet pile is extracted after water conservation extruded sheet, cushion cap side backfill and compacting;
Step 7: this is constructed after all cushion caps press step 1 to step 6 construction in the construction segment limit of division
Section levelling of the land, raft contact face dabbing cleaning, pours basement bottom board bed course in cushion cap top surface, then in basement bottom board pad
It successively constructs on layer base plate waterproofing and waterproof slab protective layer;
Step 8: binding baseplate reinforcing bar on waterproof slab protective layer, baseplate reinforcing bar anchors into or penetrates through cushion cap reinforcing bar, pouring construction
Basement bottom board concrete in section completes basement bottom board construction.
2. the construction method of Deep Thick Soft Ground Area cushion cap according to claim 1 and basement bottom board, it is characterised in that: step
In rapid one, apart from steel sheet pile 800mm on the outside of the cushion cap sideline.
3. the construction method of Deep Thick Soft Ground Area cushion cap according to claim 1 and basement bottom board, it is characterised in that: step
In rapid four, the length that the waterproof roll periphery has more cushion cap position is 500mm.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811346409.3A CN109322320A (en) | 2018-11-13 | 2018-11-13 | The construction method of Deep Thick Soft Ground Area cushion cap and basement bottom board |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811346409.3A CN109322320A (en) | 2018-11-13 | 2018-11-13 | The construction method of Deep Thick Soft Ground Area cushion cap and basement bottom board |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109322320A true CN109322320A (en) | 2019-02-12 |
Family
ID=65260757
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811346409.3A Pending CN109322320A (en) | 2018-11-13 | 2018-11-13 | The construction method of Deep Thick Soft Ground Area cushion cap and basement bottom board |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109322320A (en) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110130356A (en) * | 2019-06-05 | 2019-08-16 | 汕头市建筑工程总公司 | A kind of muddy soft soil area basement cheats bottom monoblock type back cover construction method |
CN110206305A (en) * | 2019-05-18 | 2019-09-06 | 陕西建工第五建设集团有限公司 | A kind of steel reinforcement cage and the whole straight anchoring bit architecture of steel form |
CN112195953A (en) * | 2020-09-30 | 2021-01-08 | 中冶建工集团有限公司 | Construction method of basement foundation |
CN113566019A (en) * | 2021-06-29 | 2021-10-29 | 中国二十冶集团有限公司 | Construction method for laying drainage pipe network without excavating upper part of ground reservoir |
CN114108671A (en) * | 2021-10-29 | 2022-03-01 | 上海建工七建集团有限公司 | Construction method of shallow foundation |
CN114277807A (en) * | 2022-01-20 | 2022-04-05 | 中国建筑第八工程局有限公司 | Construction method for underground large-section transfer beam serving as pit-in-pit support |
CN115233743A (en) * | 2022-09-02 | 2022-10-25 | 中建八局发展建设有限公司 | Construction method of brick-free base plate waterproof coiled material with base film |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2005076438A (en) * | 2003-08-31 | 2005-03-24 | Eskandari M | Moisture-proof structure of basement |
CN203475456U (en) * | 2013-08-09 | 2014-03-12 | 中建一局集团第三建筑有限公司 | GRC forming die plate system |
CN105350559A (en) * | 2015-11-27 | 2016-02-24 | 中国一冶集团有限公司 | Construction method suitable for emery structural ground of large factory building |
CN106436689A (en) * | 2016-10-05 | 2017-02-22 | 黄坤坤 | Bearing platform steel plate pile support and steel plate pile serving bearing platform template construction method |
-
2018
- 2018-11-13 CN CN201811346409.3A patent/CN109322320A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2005076438A (en) * | 2003-08-31 | 2005-03-24 | Eskandari M | Moisture-proof structure of basement |
CN203475456U (en) * | 2013-08-09 | 2014-03-12 | 中建一局集团第三建筑有限公司 | GRC forming die plate system |
CN105350559A (en) * | 2015-11-27 | 2016-02-24 | 中国一冶集团有限公司 | Construction method suitable for emery structural ground of large factory building |
CN106436689A (en) * | 2016-10-05 | 2017-02-22 | 黄坤坤 | Bearing platform steel plate pile support and steel plate pile serving bearing platform template construction method |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110206305A (en) * | 2019-05-18 | 2019-09-06 | 陕西建工第五建设集团有限公司 | A kind of steel reinforcement cage and the whole straight anchoring bit architecture of steel form |
CN110130356A (en) * | 2019-06-05 | 2019-08-16 | 汕头市建筑工程总公司 | A kind of muddy soft soil area basement cheats bottom monoblock type back cover construction method |
CN112195953A (en) * | 2020-09-30 | 2021-01-08 | 中冶建工集团有限公司 | Construction method of basement foundation |
CN113566019A (en) * | 2021-06-29 | 2021-10-29 | 中国二十冶集团有限公司 | Construction method for laying drainage pipe network without excavating upper part of ground reservoir |
CN114108671A (en) * | 2021-10-29 | 2022-03-01 | 上海建工七建集团有限公司 | Construction method of shallow foundation |
CN114277807A (en) * | 2022-01-20 | 2022-04-05 | 中国建筑第八工程局有限公司 | Construction method for underground large-section transfer beam serving as pit-in-pit support |
CN115233743A (en) * | 2022-09-02 | 2022-10-25 | 中建八局发展建设有限公司 | Construction method of brick-free base plate waterproof coiled material with base film |
CN115233743B (en) * | 2022-09-02 | 2023-09-22 | 中建八局发展建设有限公司 | Construction method of brick-free tire membrane bottom plate waterproof coiled material |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109322320A (en) | The construction method of Deep Thick Soft Ground Area cushion cap and basement bottom board | |
CN105544607B (en) | There is the subway station side wall outsourcing waterproof construction method of boatswain chair beam | |
CN106013172A (en) | Double row pile and diagonal brace combined soft soil deep foundation pit supporting structure and construction method | |
CN108678000B (en) | U-shaped retaining structure for roadbed underpass highway and construction method thereof | |
CN104846841B (en) | Anti-floating construction method for basements without uplift piles | |
CN108166397A (en) | Railway frame bridge construction method | |
CN105350526B (en) | Method for setting up steel platform | |
CN109403340A (en) | A kind of construction method using open caisson as foundation pit enclosure structure | |
CN108589737A (en) | Underground speedy way hands over the construction method that section is built jointly with rail under a kind of major urban arterial highway | |
CN211340827U (en) | Structure for newly building bridge by passing through existing bridge piles in subway tunnel | |
CN108505805A (en) | Large-scale cast-in-place pond and its construction method are split in expansion reinforcing band control | |
CN108301440A (en) | With waterproof, the underground pipe gallery construction method of drain function | |
CN110004991A (en) | Underground structure anti-floating system and construction method based on raised type tangs plate | |
CN109706952A (en) | Large-scale well-sinking construction method | |
CN109371763A (en) | A kind of phreatic high is low to fill out shallow cut subgrade in swelling soil zone construction method | |
CN109236322A (en) | It a kind of artificial bottom plate preventing soft-rock tunnel pucking and its constructs and method for maintaining | |
CN207211188U (en) | Outer wall of underground structure HCMW engineering methods overlap wall | |
CN207228173U (en) | A kind of underground project waterproof structure | |
CN206204954U (en) | Double-row pile combines Deep Foundation Pit Support for Soft Soil structure with diagonal brace | |
CN107326924A (en) | Outer wall of underground structure HCMW engineering methods overlap wall and its construction method | |
CN109610516B (en) | Basement exterior wall post-cast strip retaining wall construction method | |
CN204919566U (en) | Soft soil area tower crane foundation construction supporting construction | |
CN209428870U (en) | A kind of phreatic high is low to fill out shallow cut subgrade in swelling soil zone structure | |
CN110820756A (en) | Shield well and vertical shaft deep foundation pit excavation safety construction method | |
CN207662389U (en) | A kind of sedimentation and deformation observation base point using covered culvert |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190212 |
|
RJ01 | Rejection of invention patent application after publication |