CN106436689A - Bearing platform steel plate pile support and steel plate pile serving bearing platform template construction method - Google Patents

Bearing platform steel plate pile support and steel plate pile serving bearing platform template construction method Download PDF

Info

Publication number
CN106436689A
CN106436689A CN201610870183.1A CN201610870183A CN106436689A CN 106436689 A CN106436689 A CN 106436689A CN 201610870183 A CN201610870183 A CN 201610870183A CN 106436689 A CN106436689 A CN 106436689A
Authority
CN
China
Prior art keywords
cushion cap
steel sheet
sheet pile
pile
bearing platform
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610870183.1A
Other languages
Chinese (zh)
Other versions
CN106436689B (en
Inventor
黄坤坤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Huazheng Construction Engineering Co ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201610870183.1A priority Critical patent/CN106436689B/en
Publication of CN106436689A publication Critical patent/CN106436689A/en
Application granted granted Critical
Publication of CN106436689B publication Critical patent/CN106436689B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/02Sheet piles or sheet pile bulkheads
    • E02D5/03Prefabricated parts, e.g. composite sheet piles
    • E02D5/04Prefabricated parts, e.g. composite sheet piles made of steel
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • E02D27/14Pile framings, i.e. piles assembled to form the substructure

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Paleontology (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Architecture (AREA)
  • Chemical & Material Sciences (AREA)
  • Composite Materials (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The invention discloses a bearing platform steel plate pile support and steel plate pile serving bearing platform template. A method comprises the steps of: 1) staking out in survey; 2) old road excavation; 3) arrangement of a guide frame; 4) insertion of steel plate piles; 5) excavation of bearing platform soil for the first time; 6) arrangement of surrounding purlins and supports; 7) excavation of the bearing platform soil for the second time; 8) drilling away of pile heads and detection of pile foundations; 9) casting of concrete cushion layers; 10) building of bearing platform templates; 11) binding of bearing platform reinforcements and arrangement of pier column reinforcements; 12) arrangement of isolation layers; 13) casting of bearing platform pier column concrete; 14) dismounting of the supports, the surrounding purlins and the steel plate piles; and 15) treatment of the drawing places of the steel plate piles. The bearing platform steel plate pile support and steel plate pile serving bearing platform template guarantees the structural and personal safety in construction, guarantees normal use and safety of buildings, underground pipelines and roads around foundation pits, accelerates the construction progress, guarantees the construction period target realization, reduces the workload of soil excavation, accumulation and transportation, protects surrounding environments, and reduces the fly dust influence.

Description

Cushion cap steel sheet pile supporting and steel sheet pile double as cushion cap template construction method
Technical field
The present invention relates to a kind of overpass construction method, more particularly, to a kind of cushion cap steel sheet pile supporting and steel sheet pile are simultaneous Make cushion cap template.
Background technology
In elevated bridge construction, the construction quality of cushion cap often cannot be guaranteed, and often destroy periphery construction and build Thing, underground utilities, the normal of road use and safety, and the road that is connected with it can be subject to the inconvenience of moving traffic;In cushion cap During construction, the workload of earth excavation, stacking and transport, protection and the dust controlling of surrounding enviroment can be affected, also can be because of mistake The hidden danger of quality of heavy excavation backfill uses the impact of quality to recovering old road;Conventional arrangement and method for construction digging up and filling in roll less than Position, can lead to the uneven sedimentation in road surface, delay construction speed, thus have impact on the realization of constructing aims;In sum, pin To disadvantages mentioned above present in prior art, invention proposes a kind of cushion cap steel sheet pile supporting and steel sheet pile doubles as cushion cap template.
Content of the invention
The present invention employed technical scheme comprise that a kind of cushion cap steel sheet pile supporting of offer and steel for solving above-mentioned technical problem Sheet pile doubles as cushion cap template, wherein,
(One)Surveying and locating
According to the four angular coordinate calculating cushion cap side and adding 10cm, released with total powerstation and mark the steel sheet pile position line behind four angle point positions;
(Two)The old road of steel sheet pile insert division is excavated
Routing at steel sheet pile position, then abolishes old road face with cutting machine along after wire cutting;
(Three)Set up steel sheet pile insertion leading truck
Prevent the bending deformation of steel sheet pile and the penetration capability improving stake, certain rigidity, firm leading truck are set;
(Four)Inserting piling steel sheet pile is to designed elevation
Vibration hammer injection is joined using digging machine;
(Five)First time cushion cap earth excavation
Cut the earth in steel sheet pile to enclosing at the absolute altitude of purlin bottom with digging machine;
(Six)Set up and enclose purlin and support
In earth excavation to after enclose purlin bottom absolute altitude, steel sheet pile is then hung in crane by design quantity welding bracket and encloses purlin and put Put on bracket and weld;Purlin welding consolidation, last welding reinforcement angle steel in the angle of cut at the angle of cut then will be enclosed;
(Seven)Second cushion cap earth excavation
Enclosing after the completion of purlin supports and set up, after being excavated at substrate 20cm absolute altitude with digging machine, finally using manually digging clearly to setting Meter foundation ditch bottom absolute altitude;
(Eight)Cut pile crown, pile measurement
Cushion cap excavation of foundation pit put in place after in time establishment officer carry out pile crown with equipment and abolish, pile crown concrete is cut using air compressor machine;
(Nine)Pour concrete bed course
Cushion cap bed course adopts 10cm thickness C15 concreting, and the every hem width of bed course goes out cushion cap 10cm;
(Ten)Cushion cap template is set up
Size according to cushion cap is previously placed in the surrounding of foundation ditch using bamboo slab rubber;
(11)Cushion cap reinforcing bar binding and pier stud reinforcing bar are set up
After cushion cap blinding concrete reaches the 70% of design strength, you can carry out cushion cap reinforcing bar binding;
(12)Template adjustment is reinforced
Reinforcement installation puts in place, colligation protective layer cushion block outside cushion cap facade reinforcing bar, then by mobile for the bamboo slab rubber of reinforcing bar surrounding patch To cushion block of concrete bar protective layer;Outside bamboo slab rubber, backfill medium coarse sand is at cushion cap 2/3;Reinforced using the lumps of wood on top;
(13)Set up sealing coat
Inside steel sheet pile, cushion cap position disposes division board;
(14)Pour cushion cap pier stud concrete
Placement layer by layer, thickness is less than 30cm, is vibrated using immersion vibrator, 5~10 in vibrator insertion lower-layer concrete Cm is it is ensured that the good combination of levels concrete;
(15)Remove and support, enclose purlin and steel sheet pile
After cushion cap concrete placings, after pier stud pours and completes form removal, carry out foundation ditch backfill, pull out steel sheet pile;
(16)Steel sheet pile pulls out the process at place
Backfilled using medium coarse sand, that is, pier stud concrete placings complete, after Pier Formwork, pier stud construction scaffolding are removed, by steel plate Space medium coarse sand between stake and cushion cap fills up;Pull out the principle of vibration by layer of sand vibration compacting using steel sheet pile, adopt simultaneously With the mode of water filling it is ensured that sand moistening, by sand surface, hydrops are not defined;Cushion cap is backfilled using plain soil, using digging machine Layering leveling compacting.
Above-mentioned automatically controls track wheel type mobile job platform construction method, and wherein, in described step 3, leading truck is adopted Use single-layer double-side form, by nose girder with enclose purlin stake etc. and form.
Above-mentioned automatically controls track wheel type mobile job platform construction method, wherein, enclose the spacing generally 2.5 of purlin stake~ 3.5 meters, the two-sided spacing enclosed between purlin is unsuitable excessive, from the point of view of protective layer thickness big 8 slightly than sheet pile wall thickness~ 10mm.
Above-mentioned automatically controls track wheel type mobile job platform construction method, wherein, in described step 4, before piling, Grease in the fore shaft of sheet pile, is squeezed into facilitating and extracts.
Above-mentioned automatically controls track wheel type mobile job platform construction method, wherein, in described step 6, encloses purlin and props up Support is all using H400 shaped steel.
Above-mentioned automatically controls track wheel type mobile job platform construction method, wherein, in described step 8, controls foundation pile stake top Elevation exceeds cushion cap bottom surface 10cm, when pile crown will dig and put in place, reduces broken pile dynamics, it is to avoid the coming off of mass concrete, with Prevent from destroying protective layer and pile body.
Above-mentioned automatically controls track wheel type mobile job platform construction method, wherein, in described step 12, cushion block number Amount is no less than 5 pieces of settings by every square meter;The lumps of wood a size of 100*50mm.
Above-mentioned automatically controls track wheel type mobile job platform construction method, wherein, in described step 13, division board Thick for 12mm.
The present invention has the advantages that with respect to prior art:
1)Structure in guaranteeing to construct and personal safety;
2)Ensure that foundation ditch periphery construction of structures, underground utilities, the normal of road use and safety;
3)Be conducive to maintaining 204 national highway moving traffics and builder's road traffic, it is to avoid because slope excavates the traffic causing and construction The scope of operation is not enough;
4)Be conducive to by science organization's parallel line production, accelerating construction progress is it is ensured that the realization of constructing aims;
5)The workload of earth excavation, stacking and transport, protection surrounding enviroment, minimizing airborne dust impact can be reduced;
6)Excavated surface can be reduced to greatest extent, avoid the hidden danger of quality of excessive digging up and filling in the use product recovering old road The impact of matter, can also avoid conventional construction scheme to roll using digging up and filling in simultaneously and not in place lead to uneven heavy in road surface Fall.
Specific embodiment
(One)Surveying and locating
According to the four angular coordinate calculating cushion cap side and adding 10cm, released with total powerstation and mark the steel sheet pile position line behind four angle point positions;
(Two)The old road of steel sheet pile insert division is excavated
Routing at steel sheet pile position, then abolishes old road face with cutting machine along after wire cutting;
(Three)Set up steel sheet pile insertion leading truck
For ensureing vertical, the bending deformation squeezed into precision, prevent steel sheet pile of control stake of the correct of pile sinking axial location and stake With the penetration capability improving stake, certain rigidity, firm leading truck are set;
Leading truck adopts single-layer double-side form, by nose girder with enclose purlin stake etc. and form, encloses generally 2.5~3.5 meters of the spacing of purlin stake, The two-sided spacing enclosed between purlin is unsuitable excessive, from the point of view of protective layer thickness slightly than sheet pile wall thickness big 8~10mm;
Install leading truck when it should be noted that following some:Controlled using total powerstation and level indicator and adjust the position of nose girder;Nose girder Highly suitable, to be conducive to controlling the construction height of steel sheet pile and improve construction efficiency;Nose girder can not beating with steel sheet pile And if producing sinking and deform;The position of nose girder should accurately can not be collided with steel sheet pile;
(Four)Inserting piling steel sheet pile is to designed elevation
Vibration hammer injection is joined using digging machine, the situation of underground utilities, underground structure before injection, must be found out, it is to avoid damage;
Before piling, to steel sheet pile by root inspection, reject and connect fore shaft corrosion, deform serious steel sheet pile, failure is to be trimmed After can use;
Before piling, grease in the fore shaft of sheet pile, squeezed into facilitating and extract;
During inserting piling, measurement at any time monitors the gradient of every pile less than 0.3%, can not be adjusted with pulling together method when deflection is excessive Timing, pulls up and beats again;
(Five)First time cushion cap earth excavation
Foundation ditch shoveling replaces cooperation with the setting enclosing purlin support and carries out:First step digging machine cut the earth in steel sheet pile to enclose purlin bottom mark Eminence;
(Six)Set up and enclose purlin and support
Enclose purlin and support all using H400 shaped steel.Construction plan according to Design of Construction Organization and this special scheme and equipment investment And the model size of cushion cap outside the venue patterning process support bracket, enclose purlin, angle brace;
In earth excavation to after enclose purlin bottom absolute altitude, steel sheet pile is then hung in crane by design quantity welding bracket and encloses purlin and put Put on bracket and weld;Purlin welding consolidation, last welding reinforcement angle steel in the angle of cut at the angle of cut then will be enclosed;
(Seven)Second cushion cap earth excavation
Enclosing after the completion of purlin supports and set up, after being excavated at substrate 20cm absolute altitude with digging machine, finally using manually digging clearly to setting Meter foundation ditch bottom absolute altitude;With closed muck haulage car with digging with transporting outside construction site during earth excavation;
(Eight)Cut pile crown, pile measurement
Cushion cap excavation of foundation pit put in place after in time establishment officer carry out pile crown with equipment and abolish, pile crown coagulation is cut using air compressor machine Soil.In work progress, note controlling foundation pile height of pile top to exceed cushion cap bottom surface 10cm;When pile crown will dig and put in place, reduce broken Stake dynamics, it is to avoid the coming off of mass concrete, to prevent from destroying protective layer and pile body;
Pile crown cuts after putting in place, stake top loose concrete is all cut, removing surface is clean;As stake top absolute altitude is less than design mark Gao Shi, must be connected to designed elevation with ad eundem concrete;
By design requirement, pile quality is detected, carries out the setting-out of stake position, measure deflected file amount, qualified after can carry out Next procedure is constructed;
(Nine)Pour concrete bed course
Cushion cap bed course adopts 10cm thickness C15 concreting, and the every hem width of bed course goes out cushion cap 10cm;Carry out setting-out before construction, determine Bed course plan-position and absolute altitude, prevent from exceeding cushion cap bottom absolute altitude and enter inside cushion cap;
After the leveling compacting of foundation ditch bottom, pour 10cm thickness C15 concrete cushion, vibration compacting, control bed course top mark high and smooth Degree;
(Ten)Cushion cap template is set up
After cushion cap pit earthwork excavates, soil on labor cleaning's steel sheet pile, the size according to cushion cap adopts 12cm bamboo slab rubber It is previously placed in the surrounding of foundation ditch;Adopt batten by piece fixation outside bamboo slab rubber, make the template of unilateral cushion cap form entirety;
(11)Cushion cap reinforcing bar binding and pier stud reinforcing bar are set up
After cushion cap blinding concrete reaches the 70% of design strength, you can carry out cushion cap reinforcing bar binding;Clean mat surface, in pad On layer, four angle points of cushion cap are released in measurement, recover cushion cap sideline;By pile crown reinforcing bar eliminate rust, conditioning straight and curved to design angle, Ensure that pile crown reinforcement location is accurate;
Cushion cap reinforcing bar is concentrated in processing space and is made, and is tied up according to design drawing and relevant code requirement after being transported to job site Prick;Reinforcement construction order is:Cushion cap bottom layer of the reinforcing steel → cushion cap cableway → cushion cap side reinforcing bar → cushion cap top layer reinforcing bar → pier Body embedded bar;
(12)Template adjustment is reinforced
Reinforcement installation puts in place, colligation protective layer cushion block outside cushion cap facade reinforcing bar, and cushion block quantity is set no less than 5 pieces by every square meter Put, the then bamboo slab rubber movement of just reinforcing bar surrounding is labelled on cushion block of concrete bar protective layer;Outside bamboo slab rubber, backfill medium coarse sand arrives At cushion cap 2/3, i.e. 1.2m position;Reinforced it is ensured that the physical dimension of cushion cap and reinforcing bar using the 100*50mm lumps of wood on top Protective layer cushion block liner is firm;
(13)Set up sealing coat
Inside steel sheet pile, cushion cap position disposes 12mm thickness division board;
(14)Pour cushion cap pier stud concrete
Concrete, by blending station centralized mixing, strictly controls match ratio, carries out mix-proportion adjustment according to sandstone water content, when temperature is low The slump take off value, temperature high when the slump take value;
Concrete is transported to scene, concrete mixer cloth, placement layer by layer by agitator truck, and thickness is less than 30cm;Using Immersion vibrator vibrates, and in vibrator insertion lower-layer concrete, 5~10 cm are it is ensured that the good combination of levels concrete;Mixed The mark of solidifying soil vibration compacting is that concrete stops sinking, effervescent, bleeding, surface be not flat;
After concreting is complete, cushion cap top of concrete is carried out repair, floating, smear again second time after due-in slurry and press polish at Reason, is processed with pier stud binding site dabbing;
(15)Remove and support, enclose purlin and steel sheet pile
After cushion cap concrete placings, after pier stud pours and completes form removal, carry out foundation ditch backfill, pull out steel sheet pile;Before pulling out sheet pile, clearly The process in native hole after the method for pile pulling, order and pile pulling;Can not be because of the vibration effect of pile pulling, and pile pulling band soil excessively causes ground Face, the sedimentation closing on inhering architecture, structures or beneath pipeline and displacement;
(16)Steel sheet pile pulls out the process at place
1st, the relevant process during pile pulling
Steel sheet pile beat pull out during disturbance can be produced to the periphery soil body, according to engineering characteristic, structural relation and postorder construction will Ask, make considered below:
1. cushion cap occupies the part road surface of existing road, for ensureing that can recover original path after bearing platform construction uses function;
2. original path has still maintained traffic, and steel sheet pile pulls out about 1.5 meters of upright high slopes of rear cushion cap foundation ditch under Vehicular vibration Stability requirement;
3. need to recover at cushion cap foundation ditch banket to planting technique and bridge capping construction support stability requirement;
2nd, pile extracting method
This technology pile pulling adopts vibration hammer pile pulling:The forced vibration being produced using vibration hammer, disturbance soil property, destroy soil around sheet pile Cohesive strength to overcome pile extraction resistance, rely on the effect of additional lifting force to pull out stake;
3rd, cushion cap Foundation treatment
1. the following Foundation treatment of cushion cap top surface
Backfilled using medium coarse sand, that is, pier stud concrete placings complete, after Pier Formwork, pier stud construction scaffolding are removed, by steel plate Space medium coarse sand between stake and cushion cap fills up;Pull out the principle of vibration by layer of sand vibration compacting using steel sheet pile, adopt simultaneously With the mode of water filling it is ensured that sand moistening, by sand surface, hydrops are not defined;
2. the above foundation ditch of cushion cap top surface
Because cushion cap above upright slope height is 1.0~1.5m, outside has traffic to pass through, and traffic load is larger, in order to ensure side Slope is stablized and traffic safety, according to construction period and construction needs, after steel sheet pile is pulled out, cushion cap is carried out back using plain soil Fill out, using digging machine layering leveling compacting.After the completion of Coping Construction, further according to design drawing, foundation ditch is carried out with anti-excavation process.
Although the present invention is disclosed as above with preferred embodiment, so it is not limited to the present invention, any people in the art Member, without departing from the spirit and scope of the present invention, when making a little modification and perfect, therefore protection scope of the present invention is worked as By being defined that claims are defined.

Claims (8)

1. a kind of cushion cap steel sheet pile supporting and steel sheet pile double as cushion cap template construction method it is characterised in that:Comprise the following steps:
(One)Surveying and locating
According to the four angular coordinate calculating cushion cap side and adding 10cm, released with total powerstation and mark the steel sheet pile position line behind four angle point positions;
(Two)The old road of steel sheet pile insert division is excavated
Routing at steel sheet pile position, then abolishes old road face with cutting machine along after wire cutting;
(Three)Set up steel sheet pile insertion leading truck
Prevent the bending deformation of steel sheet pile and the penetration capability improving stake, certain rigidity, firm leading truck are set;
(Four)Inserting piling steel sheet pile is to designed elevation
Vibration hammer injection is joined using digging machine;
(Five)First time cushion cap earth excavation
Cut the earth in steel sheet pile to enclosing at the absolute altitude of purlin bottom with digging machine;
(Six)Set up and enclose purlin and support
In earth excavation to after enclose purlin bottom absolute altitude, steel sheet pile is then hung in crane by design quantity welding bracket and encloses purlin and put Put on bracket and weld;Purlin welding consolidation, last welding reinforcement angle steel in the angle of cut at the angle of cut then will be enclosed;
(Seven)Second cushion cap earth excavation
Enclosing after the completion of purlin supports and set up, after being excavated at substrate 20cm absolute altitude with digging machine, finally using manually digging clearly to setting Meter foundation ditch bottom absolute altitude;
(Eight)Cut pile crown, pile measurement
Cushion cap excavation of foundation pit put in place after in time establishment officer carry out pile crown with equipment and abolish, pile crown concrete is cut using air compressor machine;
(Nine)Pour concrete bed course
Cushion cap bed course adopts 10cm thickness C15 concreting, and the every hem width of bed course goes out cushion cap 10cm;
(Ten)Cushion cap template is set up
Size according to cushion cap is previously placed in the surrounding of foundation ditch using bamboo slab rubber;
(11)Cushion cap reinforcing bar binding and pier stud reinforcing bar are set up
After cushion cap blinding concrete reaches the 70% of design strength, you can carry out cushion cap reinforcing bar binding;
(12)Template adjustment is reinforced
Reinforcement installation puts in place, colligation protective layer cushion block outside cushion cap facade reinforcing bar, then by mobile for the bamboo slab rubber of reinforcing bar surrounding patch To cushion block of concrete bar protective layer;Outside bamboo slab rubber, backfill medium coarse sand is at cushion cap 2/3;Reinforced using the lumps of wood on top;
(13)Set up sealing coat
Inside steel sheet pile, cushion cap position disposes division board;
(14)Pour cushion cap pier stud concrete
Placement layer by layer, thickness is less than 30cm, is vibrated using immersion vibrator, 5~10 in vibrator insertion lower-layer concrete Cm is it is ensured that the good combination of levels concrete;
(15)Remove and support, enclose purlin and steel sheet pile
After cushion cap concrete placings, after pier stud pours and completes form removal, carry out foundation ditch backfill, pull out steel sheet pile;
(16)Steel sheet pile pulls out the process at place
Backfilled using medium coarse sand, that is, pier stud concrete placings complete, after Pier Formwork, pier stud construction scaffolding are removed, by steel plate Space medium coarse sand between stake and cushion cap fills up;Pull out the principle of vibration by layer of sand vibration compacting using steel sheet pile, adopt simultaneously With the mode of water filling it is ensured that sand moistening, by sand surface, hydrops are not defined;Cushion cap is backfilled using plain soil, using digging machine Layering leveling compacting.
2. a kind of cushion cap steel sheet pile supporting and steel sheet pile double as cushion cap template construction method, its feature as claimed in claim 1 It is:In described step 3, leading truck adopts single-layer double-side form, by nose girder with enclose purlin stake etc. and form.
3. a kind of cushion cap steel sheet pile supporting and steel sheet pile double as cushion cap template construction method, its feature as claimed in claim 2 It is:Enclose generally 2.5~3.5 meters of the spacing of purlin stake, the two-sided spacing enclosed between purlin is unsuitable excessive, from the angle of protective layer thickness Consider slightly than sheet pile wall thickness big 8~10mm.
4. a kind of cushion cap steel sheet pile supporting and steel sheet pile double as cushion cap template construction method, its feature as claimed in claim 1 It is:In described step 4, before piling, grease in the fore shaft of sheet pile, squeezed into facilitating and extract.
5. a kind of cushion cap steel sheet pile supporting and steel sheet pile double as cushion cap template construction method, its feature as claimed in claim 1 It is:In described step 6, enclose purlin and support all using H400 shaped steel.
6. a kind of cushion cap steel sheet pile supporting and steel sheet pile double as cushion cap template construction method, its feature as claimed in claim 1 It is:In described step 8, control foundation pile height of pile top to exceed cushion cap bottom surface 10cm, when pile crown will dig and put in place, reduce broken Stake dynamics, it is to avoid the coming off of mass concrete, to prevent from destroying protective layer and pile body.
7. a kind of cushion cap steel sheet pile supporting and steel sheet pile double as cushion cap template construction method, its feature as claimed in claim 1 It is:In described step 12, cushion block quantity is pressed every square meter and is no less than 5 pieces of settings;The lumps of wood a size of 100*50mm.
8. a kind of cushion cap steel sheet pile supporting and steel sheet pile double as cushion cap template construction method, its feature as claimed in claim 1 It is:In described step 13, division board is that 12mm is thick.
CN201610870183.1A 2016-10-05 2016-10-05 The supporting of cushion cap steel sheet pile and steel sheet pile double as cushion cap template construction method Active CN106436689B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610870183.1A CN106436689B (en) 2016-10-05 2016-10-05 The supporting of cushion cap steel sheet pile and steel sheet pile double as cushion cap template construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610870183.1A CN106436689B (en) 2016-10-05 2016-10-05 The supporting of cushion cap steel sheet pile and steel sheet pile double as cushion cap template construction method

Publications (2)

Publication Number Publication Date
CN106436689A true CN106436689A (en) 2017-02-22
CN106436689B CN106436689B (en) 2018-10-09

Family

ID=58171384

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610870183.1A Active CN106436689B (en) 2016-10-05 2016-10-05 The supporting of cushion cap steel sheet pile and steel sheet pile double as cushion cap template construction method

Country Status (1)

Country Link
CN (1) CN106436689B (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107012792A (en) * 2017-05-23 2017-08-04 温州市隆尚建设有限公司 A kind of construction method of bridge substructure
CN108166395A (en) * 2017-12-26 2018-06-15 中铁四局集团路桥工程有限公司 A kind of construction method that beam bridge is built across Business Line
CN109322320A (en) * 2018-11-13 2019-02-12 中国二十冶集团有限公司 The construction method of Deep Thick Soft Ground Area cushion cap and basement bottom board
CN109680706A (en) * 2018-12-11 2019-04-26 中交一公局土木工程建筑研究院有限公司 Assembled bearing platform pier pile full scale model and crack pouring construction process using same
CN110258607A (en) * 2019-06-28 2019-09-20 王义东 A kind of convenient construction method of bridge construction that mass concrete Pile-supported stand foundation is set
CN112031012A (en) * 2020-07-14 2020-12-04 上海建工集团股份有限公司 Warehouse-dividing excavation construction method and device for bearing platform under limited operation space
CN112681290A (en) * 2020-12-19 2021-04-20 中交二公局萌兴工程有限公司 Larsen steel sheet pile support construction process
CN114482149A (en) * 2022-01-25 2022-05-13 张文元 Municipal construction foundation pile foundation construction method
CN114837088A (en) * 2022-04-27 2022-08-02 中国建筑第七工程局有限公司 Construction method of bearing platform on highway

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20140112718A1 (en) * 2012-10-22 2014-04-24 Vitaly Boris Feygin Universal cellular cofferdam with embedded columnar framing and embedded rock anchor mechanism
CN104196042B (en) * 2014-08-15 2015-12-09 中国建筑第六工程局有限公司 A kind of steel sheet pile cofferdam structure construction method
CN105220703A (en) * 2015-09-11 2016-01-06 安徽省公路桥梁工程有限公司 A kind of sand flat enclosure-type deep water construction method under weighing apparatus method condition based on returning
CN105442623A (en) * 2015-12-17 2016-03-30 中交二航局第四工程有限公司 No-trestle water bridge pile foundation and bearing platform construction method and cofferdam thereof

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20140112718A1 (en) * 2012-10-22 2014-04-24 Vitaly Boris Feygin Universal cellular cofferdam with embedded columnar framing and embedded rock anchor mechanism
CN104196042B (en) * 2014-08-15 2015-12-09 中国建筑第六工程局有限公司 A kind of steel sheet pile cofferdam structure construction method
CN105220703A (en) * 2015-09-11 2016-01-06 安徽省公路桥梁工程有限公司 A kind of sand flat enclosure-type deep water construction method under weighing apparatus method condition based on returning
CN105442623A (en) * 2015-12-17 2016-03-30 中交二航局第四工程有限公司 No-trestle water bridge pile foundation and bearing platform construction method and cofferdam thereof

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
魏加友: "混凝土结构桥梁承台施工技术分析", 《山东工业技术》 *

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107012792A (en) * 2017-05-23 2017-08-04 温州市隆尚建设有限公司 A kind of construction method of bridge substructure
CN108166395A (en) * 2017-12-26 2018-06-15 中铁四局集团路桥工程有限公司 A kind of construction method that beam bridge is built across Business Line
CN109322320A (en) * 2018-11-13 2019-02-12 中国二十冶集团有限公司 The construction method of Deep Thick Soft Ground Area cushion cap and basement bottom board
CN109680706A (en) * 2018-12-11 2019-04-26 中交一公局土木工程建筑研究院有限公司 Assembled bearing platform pier pile full scale model and crack pouring construction process using same
CN110258607A (en) * 2019-06-28 2019-09-20 王义东 A kind of convenient construction method of bridge construction that mass concrete Pile-supported stand foundation is set
CN112031012A (en) * 2020-07-14 2020-12-04 上海建工集团股份有限公司 Warehouse-dividing excavation construction method and device for bearing platform under limited operation space
CN112681290A (en) * 2020-12-19 2021-04-20 中交二公局萌兴工程有限公司 Larsen steel sheet pile support construction process
CN114482149A (en) * 2022-01-25 2022-05-13 张文元 Municipal construction foundation pile foundation construction method
CN114482149B (en) * 2022-01-25 2024-06-04 广东玄城建设工程有限公司 Municipal construction foundation pile foundation construction method
CN114837088A (en) * 2022-04-27 2022-08-02 中国建筑第七工程局有限公司 Construction method of bearing platform on highway

Also Published As

Publication number Publication date
CN106436689B (en) 2018-10-09

Similar Documents

Publication Publication Date Title
CN106436689B (en) The supporting of cushion cap steel sheet pile and steel sheet pile double as cushion cap template construction method
CN106958256B (en) A kind of placement layer by layer, the open caisson construction technique repeatedly sunk
CN104074199B (en) Underwater bearing platform construction method
CN102505695B (en) Construction method for deep foundation pit of three-dimensional garage
CN108060683A (en) A kind of middle weathering geology top-down construction method
CN105064397B (en) Open excavation construction method for expanding excavation of station on metro interzone shield tunnel foundation
CN102444142B (en) Pile group column replacement expanded basement and construction method of same
CN106049505B (en) A kind of construction method of deep pit support supporting system
CN106088127A (en) Open caisson construction method
CN103696784B (en) Large-diameter long pipe curtain construction method for shallowly-buried large-span under-tunnel-passing architectural structure
CN106930319A (en) A kind of high slope framed revetment and its construction method
CN108678000A (en) A kind of U-shaped retaining structure of roadbed Xia Chuan highways and its construction method
CN101245602A (en) Construction technique for pits in foundation-pit support system
CN106836238A (en) A kind of construction method and its structure for falling the vertical floor support replacement of grade formula deep basal pit
CN109505229A (en) Highway high gradient slope stress equilibrium and vibration damping are taken precautions against natural calamities high bridge pier structure and construction method
CN107447778A (en) The heightening and consolidation structure and method of a kind of in-service reinforced concrete retaining wall
CN105350526B (en) Method for setting up steel platform
CN107724401A (en) The construction method of bridge pier foundation ditch
CN109778869A (en) Foundation ditch construction method
CN106869151A (en) A kind of bridge construction method of deep foundation ditch
CN112281857A (en) Deep foundation pit excavation construction method
CN208088288U (en) The big areas grain size shiver stone Gao Tian pile foundation fast pore-creating structure
CN106760620A (en) A kind of utilization open caisson increases the construction method for building the underground space under existing building
CN109706952A (en) Large-scale well-sinking construction method
CN107100164A (en) A kind of long auger guncreting pile construction method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20180829

Address after: 523000 Dongcheng Street, Dongsha Road, Dongsha Road, Dongling Road, Dongling Road, Dongsha Road, Dongguan, Guangdong, 401-402

Applicant after: Guangdong Huang Ye Construction Engineering Co., Ltd.

Address before: 226019 Zhongnan department store, No. 27 Zhongnan Century City, Chongchuan District, Nantong, Jiangsu 3301

Applicant before: Huang Kunkun

TA01 Transfer of patent application right
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address

Address after: Unit 401-402, Dongjun building, Dongke Road, HENGLING Industrial Park, Tongsha Science Park, Dongcheng Street, Dongcheng District, Dongguan City, Guangdong Province, 523000

Patentee after: Guangdong Huazheng Construction Engineering Co.,Ltd.

Address before: 523000 Dongcheng Street, Dongsha Road, Dongsha Road, Dongling Road, Dongling Road, Dongsha Road, Dongguan, Guangdong, 401-402

Patentee before: Guangdong Huang Ye construction engineering corporation, Ltds

CP03 Change of name, title or address