CN109441479A - A kind of bored tunnel sump remedy method - Google Patents
A kind of bored tunnel sump remedy method Download PDFInfo
- Publication number
- CN109441479A CN109441479A CN201811240133.0A CN201811240133A CN109441479A CN 109441479 A CN109441479 A CN 109441479A CN 201811240133 A CN201811240133 A CN 201811240133A CN 109441479 A CN109441479 A CN 109441479A
- Authority
- CN
- China
- Prior art keywords
- tunnel
- stainless steel
- hole
- arc panel
- steel arc
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/006—Lining anchored in the rock
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
- E21D11/105—Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/14—Lining predominantly with metal
- E21D11/18—Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D20/00—Setting anchoring-bolts
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Structural Engineering (AREA)
- Architecture (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Civil Engineering (AREA)
- Lining And Supports For Tunnels (AREA)
Abstract
The present invention relates to a kind of bored tunnel sump remedy methods, including following construction procedure: step A: preliminary bracing is carried out before construction;Step B: the collapsing hole of tunnel top is closed;Step C: backfill processing is carried out in hole to collapsing;Step D: material spray filling is carried out in hole to collapsing;Step E: injecting treatment is carried out in hole to collapsing.It is an advantage of the invention that it is safe and reliable, at low cost, timely and effectively the tunnel after landslide can be handled, and make treated to cave in area with higher stability.
Description
Technical field
The present invention relates to bored tunnel technical field of construction, during bored tunnel, after caving in, such as
A kind of bored tunnel sump remedy method where reason landslide section and vault sinking section propose.
Background technique
In tunnel construction, landslide is one of most common geology harm.Once caving in, not only the duration is caused to prolong
Accidentally, engineering cost is significantly increased, and the life security of construction, technical staff can be jeopardized, also will cause construction quality
Hidden danger carrys out extreme difficulties to maintenance work belt, or even makes tunnel can not normal use.
The short and small tunnel that especially those height above sea level are not high, buried depth is shallower using New Austrian Tunneling Method when being excavated, due to up/down steps
Too long for gap, inverted arch arch is installed not in time, the reasons such as arch ring cannot be closed as early as possible, and secondary lining is not caught up with, then meets rainy season
Construction, rainwater are largely assembled in massif, and vault load-bearing increases severely, and are likely to result in tunnel and cave in, tunnel caves in
The direct result presented afterwards is that mountain upper ground surface huge pitfall occurs, and a large amount of soil bodys pour in hole, and landslide Duan Chuzhi steelframe is almost complete
Portion collapses, and cave in section front and rear sides vault sinking.
Currently, Tunnel Engineering Treatment for collapse mainly has the methods of poling board method, pipe shed method, freezing process, anchor pole method, cut and cover method,
But treatment effect is very different, cannot definitely guarantee safely.For standard construction, improve treatment effect, improves operation effect
Rate increases safety guarantee, and research and probe one kind is safe and effective, practicable Tunnel Landslide processing method is for reducing tunneling tunnel
The construction risk in road has very important meaning.
Summary of the invention
The object of the present invention is to provide a kind of bored tunnel sump remedy methods, its advantage is that securely and reliably, at low cost, energy
It is enough that timely and effectively the tunnel after landslide is handled, and make treated to cave in area with higher stability.
Above-mentioned technical purpose of the invention has the technical scheme that a kind of bored tunnel sump remedy
Method, including following construction procedure:
Step A: preliminary bracing is carried out before construction;
Step B: the collapsing hole of tunnel top is closed;
Step C: backfill processing is carried out in hole to collapsing;
Step D: material spray filling is carried out in hole to collapsing;
Step E: injecting treatment is carried out in hole to collapsing.
Through the above technical solutions, the construction method is safe and reliable, at low cost, it can be timely and effectively to the tunnel after landslide
Road is handled, and makes treated to cave in area with higher stability.It is by preliminary bracing, to guarantee staff
Then safety during subsequent construction is closed the collapsing hole of tunnel top, prevent the soil body from occurring further
It collapses, then first passes through backfill processing, be filled to collapsing in hole, form it into the new soil body, then filled out again by material spray
It fills, makes to combine closely between the soil body around the soil body newly formed and tunnel, finally by slip casting operation, be sufficient filling with slurries
The gap location between the soil body around to the soil body and tunnel newly formed, plays the role of bonding, and form final reinforcing body,
Compared to direct slip casting, cost is lower, while stability is more preferably.
The present invention is further arranged to: the step A includes:
Step A1: prospecting massif original ground collapses range, sets up a cordon around massif pitfall, and protective net is arranged;
Step A2: the earthwork in tunnel is fallen into after cleaning landslide;
Step A3: the tunnel inner wall at landslide is carried out just to spray supporting.
Through the above technical solutions, prospecting massif original ground collapses range, the pull-up around massif pitfall before construction
Warning line, and protective net is arranged causes security risk for preventing people on mountain or poultry from crashing into pitfall;It will be collapsed by trolley
The earthwork transportation to be fallen to tunnel behind side to tunnel outside, in order to the progress of subsequent construction operation;It is right after cleaning out
Tunnel inner wall concrete spraying support at landslide, while according to the needs of practice of construction, selective carry out humidification process, with
It can quickly condense, harden convenient for concrete, preliminary bracing is formed to the inner wall in tunnel, improves the safety of staff's operation
Property.
The present invention is further arranged to: the step B includes:
Prefabricated stainless steel arc panel: being fixed at the landslide of tunnel top by step B1 by more root posts, forms vertical branch
Support;
Step B2: a pillow extended along length of tunnel direction is fixed in the position in tunnel and below stainless steel arc panel
Wood, make to be fixed on sleeper two sides in advance and internal whorl be connected with screw rod steel pipe and tunnel center line it is perpendicular, then turn
Dynamic screw rod, the one end for making screw rod be connected with top hold out against position in stainless steel arc panel close to bottom end, form cross-brace.
Through the above technical solutions, then passing through at prefabricated stainless steel curved board transportation tension to the landslide of tunnel top
Equipment is held out against to hold out against more columns arranged side by side in the concave surface of stainless steel arc panel formation vertical supporting, wherein holding out against equipment
Jack or oil cylinder etc. can be used;Then by rotation screw rod, the one end for making screw rod be connected with top is held out against in stainless steel arc
Plate forms cross-brace close to the position of bottom end, cooperates with vertical supporting, has stainless steel arc panel after mounting
The length of higher stability, screw rod and steel pipe is designed according to the internal diameter in tunnel.
The present invention is further arranged to: the step B includes:
Step B3: the hole reserved on stainless steel arc panel is reinforced by anchor pole.
Through the above technical solutions, the setting of anchor pole, fixes for stainless steel arc panel to be close to the inner wall in tunnel, makes
It reduces the gap between stainless steel arc panel and the inner wall in tunnel, prevents while increasing stainless steel arc panel stability
In step D in material spray or step E when slip casting, liquid outflow influences further to construct.
The present invention is further arranged to: the step B3 further include:
Step B3-1: in the surrounding gunite concrete of stainless steel arc panel, seal the inner wall in itself and tunnel.
Through the above technical solutions, in the surrounding gunite concrete of stainless steel arc panel, for making its inner wall with tunnel
Further sealing.
The present invention is further arranged to: in the step C, by the earthwork of bulk by backfill reserved on stainless steel arc panel
To collapsing in hole, a layer concrete is sprayed in every one layer of backfill for mouth filling, is then blocked by welded plate by mouth is backfilled.
Through the above technical solutions, filling by the earthwork, it is made to collapse the soil body that formation is new in hole, then every backfill one
Layer, one layer concrete of injection are successively reinforced, and keep the new soil body more firm.
The present invention is further arranged to: in the step D, passing through the prefabricated interface in material spray equipment and stainless steel arc panel
It is connected, and carries out roughstuff towards collapse gunite concrete and the stone in hole formed after landslide and fill.
It is filled through the above technical solutions, carrying out roughstuff by gunite concrete and stone, and hole will be collapsed as far as possible and filled out
It is full, to reduce the dosage of slurries in step E, reduce construction cost.
The present invention is further arranged to: the step E includes:
Step E1: it is connected by grouting equipment with another prefabricated interface on stainless steel arc panel, and carries out injecting treatment, made not
It is come into full contact between rust steel arc panel and the soil body of surrounding close;
Step E2: cross-brace and vertical supporting are removed.
Through the above technical solutions, making to come into full contact between stainless steel arc panel and the soil body of surrounding by slip casting operation
The gap location between the soil body that is close, being sufficiently filled to slurries around the soil body newly formed and tunnel, plays the role of bonding.
In conclusion advantageous effects of the invention are as follows:
1, the construction method in the application, by preliminary bracing, to guarantee safety of staff during subsequent construction
Property, then the collapsing hole of tunnel top is closed, prevents the soil body from further collapsing occurs, is then first passed through at backfill
Reason, is filled to collapsing in hole, forms it into the new soil body, is then filled again by material spray, makes the soil body newly formed and tunnel
It combines closely between the soil body around road, finally by slip casting operation, slurries is made to be sufficiently filled to the soil body newly formed and tunnel
Gap location between the soil body of surrounding, plays the role of bonding, and form final reinforcing body, compared to direct slip casting, cost
It is lower, while there is higher stability;
2, stainless steel arc panel is reinforced by vertical supporting, cross-brace and anchor pole, substantially increases stainless steel arc
Stability after the installation of shape plate, while improving the safety of staff's operation;
3, it is prevented by the surrounding gunite concrete in stainless steel arc panel for sealing the inner wall of itself and tunnel further
When slip casting, slurries are flowed out out of stainless steel arc panel and tunnel inner wall gap.
Detailed description of the invention
Fig. 1 is overall flow schematic diagram of the invention;
Fig. 2 is the overall structure diagram for embodying construction;
Fig. 3 is the structural schematic diagram for embodying stainless steel arc panel.
In figure, 1, tunnel;2, hole is collapsed;3, stainless steel arc panel;31, hole;32, mouth is backfilled;33, prefabricated interface;4,
Column;5, sleeper;6, screw rod;61, it comes directly towards;7, steel pipe;8, anchor pole;9, welded plate.
Specific embodiment
Referring to Figures 1 and 2, it is a kind of bored tunnel sump remedy method disclosed by the invention, including following construction procedure:
Step A: preliminary bracing is carried out before construction;
Step B: the collapsing hole 2 at 1 top of closing tunnel;
Step C: backfill processing is carried out in hole 2 to collapsing;
Step D: material spray filling is carried out in hole 2 to collapsing;
Step E: slip casting operation is carried out in hole 2 to collapsing.
The construction method is safe and reliable, at low cost, can timely and effectively handle the tunnel 1 after landslide, and
Make treated to cave in area with higher stability.It is by preliminary bracing, to guarantee staff in subsequent construction process
In safety, then the collapsing hole 2 at the top of tunnel 1 is closed, prevent the soil body occur it is further collapse, then first lead to
Backfill processing is crossed, is filled to collapsing in hole 2, forms it into the new soil body, then makes newly to be formed by material spray filling again
It combines closely between the soil body around the soil body and tunnel 1, finally by slip casting operation, the soil for making slurries be sufficiently filled to newly be formed
The gap location between the soil body around body and tunnel 1, plays the role of bonding, and form final reinforcing body, compared to direct
Slip casting, cost is lower, while stability is more preferably.
Include: referring to Fig. 2, step A
Step A1: before construction, prospecting massif original ground collapses range, sets up a cordon around massif pitfall, and be arranged
Protective net prevents people or poultry on mountain from crashing into pitfall, causes security risk.
Step A2: the outside that will be fallen after landslide to the earthwork transportation in tunnel 1 to tunnel 1 by trolley, in order to rear
The progress of continuous construction operation.
Step A3: after cleaning out, to the 1 inner wall concrete spraying support of tunnel at landslide, while according to practice of construction
Needs, selective carry out humidification process formed the inner wall in tunnel 1 in order to which concrete can quickly condense, harden
Preliminary bracing.
Include: referring to Fig. 2 and Fig. 3, step B
Step B1:, then will be more by holding out against equipment at the landslide of the prefabricated transport of stainless steel arc panel 3 to 1 top of tunnel
Root column 4 arranged side by side, which is held out against, forms vertical supporting in the concave surface of stainless steel arc panel 3, wherein hold out against equipment can be used it is very heavy
Top or oil cylinder etc..
Step B2: the position in tunnel 1 and below stainless steel arc panel 3 is placed one and is prolonged along 1 length direction of tunnel
The sleeper 5 stretched, can be fixed by spike, at this point, being fixed on 5 two sides of sleeper and internal whorl is connected with screw rod 6 in advance
Steel pipe 7 and the center line in tunnel 1 it is perpendicular, then rotate screw rod 6, make screw rod 6 be connected with top 61 one end hold out against not
Steel arc panel 3 become rusty close to the position of bottom end, forms cross-brace, cooperates with vertical supporting, stainless steel arc panel 3 is made to exist
The length of stability with higher after installation, screw rod 6 and steel pipe 7 is designed according to the internal diameter in tunnel 1.
Step B3: after the completion of cross-brace, by anchor pole 8 pass through stainless steel arc panel 3 on reserve hole 31, by its with
The inner wall in tunnel 1 is close to fix, and makes it while increasing by 3 stability of stainless steel arc panel, reduces stainless steel arc panel 3 and tunnel
Gap between the inner wall in road 1, when preventing in step D slip casting in material spray or step E, liquid outflow influences further to construct.
Step B3-1: after the completion of anchor pole 8 is fixed, in the surrounding gunite concrete of stainless steel arc panel 3, make itself and tunnel 1
Inner wall further seal.
In reference Fig. 2 and Fig. 3, step C, by manually by the earthwork of bulk by backfill reserved on stainless steel arc panel 3
32 filling of mouth forms it into the new soil body, every one layer of backfill to collapsing in hole 2, and one layer concrete of injection is reinforced, the operation
After the completion, it is blocked by welded plate 9 by mouth 32 is backfilled.
In step D, it is connected by material spray equipment with the prefabricated interface 33 on stainless steel arc panel 3, then towards shape after landslide
At collapse gunite concrete and stone in hole 2 carry out roughstuff and fill, and hole 2 will be collapsed as far as possible and filled up, to reduce step E
The dosage of middle slurries reduces construction cost.
Step E includes:
Step E1: being connected with another prefabricated interface 33 on stainless steel arc panel 3 by grouting equipment, and carry out slip casting operation,
Make to come into full contact between stainless steel arc panel 3 and the soil body of surrounding close, slurries is made to be sufficiently filled to the soil body newly formed and tunnel 1
Gap location between the soil body of surrounding, plays the role of bonding.
Step E2: removing and hold out against equipment, then removes column 4;Screw rod 6 is rotated, its top 61 and stainless steel arc are made
Plate 3 separates, and releases cross-brace.
The embodiment of present embodiment is presently preferred embodiments of the present invention, not limits protection of the invention according to this
Range, therefore: the equivalence changes that all structures under this invention, shape, principle are done, should all be covered by protection scope of the present invention it
It is interior.
Claims (8)
1. a kind of bored tunnel sump remedy method, it is characterised in that: including following construction procedure:
Step A: preliminary bracing is carried out before construction;
Step B: the collapsing hole (2) at the top of closing tunnel (1);
Step C: backfill processing is carried out to collapsing in hole (2);
Step D: material spray filling is carried out in hole (2) to collapsing;
Step E: slip casting operation is carried out in hole (2) to collapsing.
2. a kind of bored tunnel sump remedy method according to claim 1, it is characterised in that: the step A includes:
Step A1: prospecting massif original ground collapses range, sets up a cordon around massif pitfall, and protective net is arranged;
Step A2: the earthwork in tunnel (1) is fallen into after cleaning landslide;
Step A3: tunnel (1) inner wall at landslide is carried out just to spray supporting.
3. a kind of bored tunnel sump remedy method according to claim 1, it is characterised in that: the step B includes:
Step B1: at the landslide that prefabricated stainless steel arc panel (3) is fixed at the top of tunnel (1) by more root posts (4), shape
At vertical supporting;
Step B2: the position in tunnel (1) and below stainless steel arc panel (3) fixes one along tunnel (1) length direction
The sleeper (5) of extension, makes to be fixed on sleeper (5) two sides in advance and internal whorl is connected with the steel pipe (7) and tunnel of screw rod (6)
(1) center line is perpendicular, then rotates screw rod (6), the one end for making screw rod (6) be connected with top (61) is held out against in stainless steel arc
Shape plate (3) forms cross-brace close to the position of bottom end.
4. a kind of bored tunnel sump remedy method according to claim 1, it is characterised in that: the step B further include:
Step B3: the hole (31) reserved on stainless steel arc panel (3) is reinforced by anchor pole (8).
5. a kind of bored tunnel sump remedy method according to claim 4, it is characterised in that: the step B3 is also wrapped
It includes:
Step B3-1: in the surrounding gunite concrete of stainless steel arc panel (3), seal the inner wall of itself and tunnel (1).
6. a kind of bored tunnel sump remedy method according to claim 1, it is characterised in that:, will be big in the step C
The earthwork of block is interior to hole (2) is collapsed by backfill mouth (32) filling reserved on stainless steel arc panel (3), every one layer of backfill, injection
Then one layer concrete will backfill mouth (32) by welded plate (9) and block.
7. a kind of bored tunnel sump remedy method according to claim 1, it is characterised in that: in the step D, pass through
Material spray equipment is connected with the prefabricated interface (33) on stainless steel arc panel (3), and collapses injection in hole (2) towards what is formed after landslide
Concrete and stone carry out roughstuff and fill.
8. a kind of bored tunnel sump remedy method according to claim 1, it is characterised in that: the step E includes:
Step E1: it is connected by grouting equipment with another prefabricated interface (33) on stainless steel arc panel (3), and carries out slip casting work
Industry makes to come into full contact between stainless steel arc panel (3) and the soil body of surrounding close;
Step E2: cross-brace and vertical supporting are removed.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811240133.0A CN109441479B (en) | 2018-10-23 | 2018-10-23 | Collapse treatment method for underground excavation tunnel |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811240133.0A CN109441479B (en) | 2018-10-23 | 2018-10-23 | Collapse treatment method for underground excavation tunnel |
Publications (2)
Publication Number | Publication Date |
---|---|
CN109441479A true CN109441479A (en) | 2019-03-08 |
CN109441479B CN109441479B (en) | 2021-03-09 |
Family
ID=65547171
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811240133.0A Active CN109441479B (en) | 2018-10-23 | 2018-10-23 | Collapse treatment method for underground excavation tunnel |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109441479B (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109973122A (en) * | 2019-05-14 | 2019-07-05 | 福建工程学院 | A kind of tunnel reinforcement control method of wall rock loosening or soft rock large deformation |
CN110397458A (en) * | 2019-07-03 | 2019-11-01 | 中铁四局集团第五工程有限公司 | A kind of three-dimensional reinforced construction method suitable for the tunnel enlarging that caves in |
CN111365042A (en) * | 2020-03-13 | 2020-07-03 | 重庆工程职业技术学院 | Large-section tunnel supporting device |
CN111365044A (en) * | 2020-03-11 | 2020-07-03 | 山东科技大学 | Method for treating tunnel collapse by using roof-contacted shield support |
CN113187498A (en) * | 2021-05-13 | 2021-07-30 | 中铁十六局集团第二工程有限公司 | TBM tunnel collapsed cavity backfilling and advanced pipe shed construction method |
CN115162408A (en) * | 2022-06-14 | 2022-10-11 | 长江勘测规划设计研究有限责任公司 | Construction method for repairing collapsed tunnel |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2001355394A (en) * | 2000-06-13 | 2001-12-26 | Mitsubishi Heavy Ind Ltd | Tunnel-collapse preventive structure |
US7731453B2 (en) * | 2003-11-28 | 2010-06-08 | Stein & Partner Gmbh | Method and device for trenchless laying of pipelines |
CN105257301A (en) * | 2015-10-16 | 2016-01-20 | 中铁十局集团济南铁路工程有限公司 | Method for reinforcing collapse of weak surrounding rock of shallow embedded and mining tunnel |
CN205063972U (en) * | 2015-10-28 | 2016-03-02 | 中铁建大桥工程局集团第五工程有限公司 | A fill formula strutting arrangement for controlling tunnel landslide |
CN106545351A (en) * | 2016-11-02 | 2017-03-29 | 山东科技大学 | A kind of tunnel front landslide emergency processing method |
CN106837419A (en) * | 2017-04-07 | 2017-06-13 | 兖州煤业股份有限公司 | Face sky old working compound closure wall and its method of construction |
CN106894826A (en) * | 2017-05-08 | 2017-06-27 | 中国水利水电建设工程咨询中南有限公司 | The supporting construction and method for protecting support of section of being caved in a kind of hole |
CN108005695A (en) * | 2018-01-31 | 2018-05-08 | 中铁北京工程局集团第工程有限公司 | The fast-supporting device and method of branch large deformation at the beginning of for punishing tunnel weak surrounding rock |
CN108561165A (en) * | 2018-06-15 | 2018-09-21 | 贵州大学 | A kind of tunnel supporting apparatus convenient for deployment and dismounting |
-
2018
- 2018-10-23 CN CN201811240133.0A patent/CN109441479B/en active Active
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2001355394A (en) * | 2000-06-13 | 2001-12-26 | Mitsubishi Heavy Ind Ltd | Tunnel-collapse preventive structure |
US7731453B2 (en) * | 2003-11-28 | 2010-06-08 | Stein & Partner Gmbh | Method and device for trenchless laying of pipelines |
CN105257301A (en) * | 2015-10-16 | 2016-01-20 | 中铁十局集团济南铁路工程有限公司 | Method for reinforcing collapse of weak surrounding rock of shallow embedded and mining tunnel |
CN205063972U (en) * | 2015-10-28 | 2016-03-02 | 中铁建大桥工程局集团第五工程有限公司 | A fill formula strutting arrangement for controlling tunnel landslide |
CN106545351A (en) * | 2016-11-02 | 2017-03-29 | 山东科技大学 | A kind of tunnel front landslide emergency processing method |
CN106837419A (en) * | 2017-04-07 | 2017-06-13 | 兖州煤业股份有限公司 | Face sky old working compound closure wall and its method of construction |
CN106894826A (en) * | 2017-05-08 | 2017-06-27 | 中国水利水电建设工程咨询中南有限公司 | The supporting construction and method for protecting support of section of being caved in a kind of hole |
CN108005695A (en) * | 2018-01-31 | 2018-05-08 | 中铁北京工程局集团第工程有限公司 | The fast-supporting device and method of branch large deformation at the beginning of for punishing tunnel weak surrounding rock |
CN108561165A (en) * | 2018-06-15 | 2018-09-21 | 贵州大学 | A kind of tunnel supporting apparatus convenient for deployment and dismounting |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109973122A (en) * | 2019-05-14 | 2019-07-05 | 福建工程学院 | A kind of tunnel reinforcement control method of wall rock loosening or soft rock large deformation |
CN110397458A (en) * | 2019-07-03 | 2019-11-01 | 中铁四局集团第五工程有限公司 | A kind of three-dimensional reinforced construction method suitable for the tunnel enlarging that caves in |
CN111365044A (en) * | 2020-03-11 | 2020-07-03 | 山东科技大学 | Method for treating tunnel collapse by using roof-contacted shield support |
CN111365042A (en) * | 2020-03-13 | 2020-07-03 | 重庆工程职业技术学院 | Large-section tunnel supporting device |
CN113187498A (en) * | 2021-05-13 | 2021-07-30 | 中铁十六局集团第二工程有限公司 | TBM tunnel collapsed cavity backfilling and advanced pipe shed construction method |
CN115162408A (en) * | 2022-06-14 | 2022-10-11 | 长江勘测规划设计研究有限责任公司 | Construction method for repairing collapsed tunnel |
CN115162408B (en) * | 2022-06-14 | 2024-02-02 | 长江勘测规划设计研究有限责任公司 | Construction method for repairing collapse tunnel |
Also Published As
Publication number | Publication date |
---|---|
CN109441479B (en) | 2021-03-09 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109441479A (en) | A kind of bored tunnel sump remedy method | |
CN104746517B (en) | A kind of suspension roof support system of total length below artesian head | |
CN104278993B (en) | A kind of bias voltage Skew Tunnel enters the constructional method in hole | |
CN106437726B (en) | Shallow-depth-excavation tunnel crosses ground fissure crushed zone construction method | |
CN202969392U (en) | Complex geology deep excavation pit combined support | |
CN102979535B (en) | Draining type section of jurisdiction is used in a kind of tunnel lining | |
CN104612713B (en) | Buried section of method for tunnel construction of an ultra shallow | |
CN206189425U (en) | Combined type side slope treatment protector | |
CN104453913A (en) | Vertical shaft working face ahead pre-grouting method | |
CN206174963U (en) | Cross shallow undercut tunnel supporting construction of burying of ground fissure crushed zone | |
CN108547643B (en) | A kind of construction method encircleed for handling tunnel top large size cavity solution cavity shield | |
CN106703044A (en) | Flow-plastic-shaped flushing and filling soil weak stratum sloping combination support method | |
CN103696787B (en) | Deformed steel bar high-pressure grouting anchor rod and support method for reinforcing roadway by deformed steel bar high-pressure grouting anchor rod | |
CN106522248A (en) | Method for reinforcing soil slope and slope reinforcing device | |
CN108678753B (en) | Reverse-slope tunnel construction method | |
CN109812269A (en) | It is a kind of suitable for second mining working face without pillar mining method | |
CN211898463U (en) | Reinforcing device combining micro-steel pipe pile and anchor rod | |
CN205712143U (en) | Concrete spraying floating platform structure for mine environment recovery treatment | |
CN106761913A (en) | A kind of method and its structure of the drop shaft drop section closure for effectively improving steadiness | |
CN108999196A (en) | In-network processing construction method for supporting between a kind of stake | |
CN205712171U (en) | A kind of retaining wall reinforcement structure | |
CN209669718U (en) | A kind of existing hangar tunnel combination stone cut off wall structure of rockfall protection | |
CN207143961U (en) | With reference to the pattern foundation pit supporting structure water-retaining structure of High-pressure Spiral Spray Technology | |
CN103590407B (en) | A kind of tomb of falling crown form hole restoration construction method | |
CN205152981U (en) | Disease treatment structure is kept off to existing of light -duty flexibility |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |