CN109973122A - A Tunnel Reinforcement Control Method for Loose Surrounding Rock or Large Deformation of Soft Rock - Google Patents

A Tunnel Reinforcement Control Method for Loose Surrounding Rock or Large Deformation of Soft Rock Download PDF

Info

Publication number
CN109973122A
CN109973122A CN201910398527.7A CN201910398527A CN109973122A CN 109973122 A CN109973122 A CN 109973122A CN 201910398527 A CN201910398527 A CN 201910398527A CN 109973122 A CN109973122 A CN 109973122A
Authority
CN
China
Prior art keywords
rock
tunnel
large deformation
reinforcement
plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910398527.7A
Other languages
Chinese (zh)
Inventor
姚志雄
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujian University of Technology
Original Assignee
Fujian University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujian University of Technology filed Critical Fujian University of Technology
Priority to CN201910398527.7A priority Critical patent/CN109973122A/en
Publication of CN109973122A publication Critical patent/CN109973122A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/107Reinforcing elements therefor; Holders for the reinforcing elements
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/15Plate linings; Laggings, i.e. linings designed for holding back formation material or for transmitting the load to main supporting members
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/18Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/40Devices or apparatus specially adapted for handling or placing units of linings or supporting units for tunnels or galleries
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F17/00Methods or devices for use in mines or tunnels, not covered elsewhere
    • E21F17/18Special adaptations of signalling or alarm devices

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

本发明公开了一种围岩松动或软岩大变形的隧道加固控制方法,包括以下步骤:步骤一、在围岩四周施作初期支护层,在初期支护层上表面设置传感器件,用于监测围岩应力或变形状态;步骤二、制作可移动的加固模架体系;根据地质雷达或传感器件的监测结果确定已成初支段围岩松动或大变形范围,移动加固模架体系至待加固段进行加固。本发明能够对隧道已成初支段由于扰动或勘察设计不周或施做不当而产生的大变形区域进行充分的二次加固,能给予隧道薄弱段一个全面的支撑力,保障注浆加固质量;另外,针对富水破碎浅埋隧道从地面二次注浆时,该方法能从洞内起到整体的稳定作用,防止围岩坍落影响施工作业及结构安全。

The invention discloses a tunnel reinforcement control method for loose surrounding rock or large deformation of soft rock. To monitor the stress or deformation state of the surrounding rock; step 2, make a movable reinforcement formwork system; according to the monitoring results of the geological radar or sensor devices, determine the loose or large deformation range of the surrounding rock in the primary support section, and move the reinforcement formwork system to The section to be reinforced is reinforced. The invention can carry out sufficient secondary reinforcement for the large deformation area of the primary branch section of the tunnel due to disturbance or improper investigation and design or improper implementation, and can give a comprehensive support force to the weak section of the tunnel to ensure the quality of grouting reinforcement. In addition, for the secondary grouting of water-rich broken shallow buried tunnels from the ground, this method can play an overall stabilizing role from the inside of the tunnel, preventing the surrounding rock from slumping and affecting the construction operation and structural safety.

Description

一种围岩松动或软岩大变形的隧道加固控制方法A tunnel reinforcement control method for loose surrounding rock or large deformation of soft rock

技术领域technical field

本发明涉及一种复杂地质环境条件下隧洞隧道围岩加固方法,尤其涉及一种围岩松动或软岩大变形的隧道加固控制方法。The invention relates to a method for strengthening the surrounding rock of a tunnel under complex geological environment conditions, in particular to a method for controlling the reinforcement of the surrounding rock for loose surrounding rock or large deformation of soft rock.

背景技术Background technique

当前我国隧道工程多用新奥法施工,其施工要点是在隧道开挖后尽快施做柔性的喷锚支护,使得支护结构与围岩共同产生适量变形以充分发挥围岩自稳定能力,二衬在合适时机再进行施做。如在地质复杂多变的地层进行隧道施工,往往由于前期勘察不够精细化导致设计施工考虑不周、施工不到位或由于外界不可控扰动因素如临近工程爆破施工,暴雨、台风及地震自然力等因素导致已成初支段围岩松动、恶化产生大变形。在这种工况下,如在没采取充分保护措施的情况下进行注浆加固施工,极可能由于围岩受到进一步扰动,在注浆体未充分硬化前便引起洞内收敛变形过大或拱顶下沉,甚至酿成塌方事故,对洞内作业人员及结构安全造成严重威胁。如是浅埋段从地表进行注浆加固,也极易导致隧道上方地表开裂,甚至出现山体滑坡现象;洞内也可能出现坍落而影响结构稳定性。如何安全有效地对恶化围岩进行二次加固,提升加固质量,对于当前隧道施工具有非常重要的现实意义。At present, the new Austrian method is mostly used in the construction of tunnel projects in our country. The key point of the construction is to implement flexible spray-bolt support as soon as possible after the excavation of the tunnel, so that the support structure and the surrounding rock can produce an appropriate amount of deformation to give full play to the self-stabilizing ability of the surrounding rock. The lining will be applied at the right time. For example, tunnel construction in geologically complex and changeable strata is often due to insufficient preliminary investigation, resulting in poor consideration of design and construction, inadequate construction, or due to external uncontrollable disturbance factors such as blasting construction of adjacent projects, heavy rain, typhoon and natural earthquake forces, etc. As a result, the surrounding rocks in the primary branch segment became loose and deteriorated, resulting in large deformation. Under such working conditions, if the grouting reinforcement construction is carried out without adequate protection measures, it is very likely that the surrounding rock will be further disturbed, causing excessive convergence deformation or arching in the cave before the grouting body is fully hardened. The roof sinks and even leads to a landslide accident, which poses a serious threat to the safety of workers and structures in the cave. If the shallow buried section is reinforced by grouting from the surface, it will easily lead to cracks on the surface above the tunnel, and even landslides; the cave may also collapse and affect the structural stability. How to safely and effectively carry out secondary reinforcement of deteriorated surrounding rock and improve the quality of reinforcement has very important practical significance for current tunnel construction.

发明内容Contents of the invention

本发明的目的是提供一种围岩松动或软岩大变形的隧道加固控制方法,该方法能有效控制围岩变形,降低隧道施工时发生坍落、山体滑坡、突泥涌水,隧道运营期间发生渗漏等事故发生的概率,全面保护环境及人员安全。The purpose of the present invention is to provide a tunnel reinforcement control method for loose surrounding rock or large deformation of soft rock. The probability of accidents such as leakage, comprehensive protection of the environment and personnel safety.

为实现上述发明目的,本发明的技术方案是:一种围岩松动或软岩大变形的隧道加固控制方法,包括以下步骤:In order to achieve the purpose of the above invention, the technical solution of the present invention is: a tunnel reinforcement control method for loose surrounding rock or large deformation of soft rock, comprising the following steps:

步骤一、在围岩四周施作初期支护层,在初期支护层上表面设置传感器件,用于监测围岩应力或变形状态;Step 1. An initial support layer is installed around the surrounding rock, and a sensor device is arranged on the upper surface of the initial support layer to monitor the stress or deformation state of the surrounding rock;

步骤二、制作可移动的加固模架体系;根据地质雷达或传感器件的监测结果确定已成初支段围岩松动或大变形范围,移动加固模架体系至待加固段进行加固。Step 2: Make a movable reinforcement formwork system; determine the looseness or large deformation range of the surrounding rock in the primary support section according to the monitoring results of the geological radar or sensor devices, and move the reinforcement formwork system to the to-be-reinforced section for reinforcement.

进一步的,所述步骤一中,初期支护层包括铺设在围岩四周的钢筋网,以及喷射在钢筋网上的混凝土层。Further, in the first step, the initial support layer includes a reinforcement mesh laid around the surrounding rock, and a concrete layer sprayed on the reinforcement mesh.

进一步的,所述步骤二中,加固模架体系的制作及加固方法为:Further, in the step 2, the production and reinforcement methods of the reinforcement formwork system are:

在隧道底面上设置两个平行的小车,小车车体沿隧道延伸方向设置且小车沿隧道延伸方向移动;在小车车体前后端分别安装竖向伸缩杆,以及驱动竖向伸缩杆伸缩的液压缸,在同一小车上的竖向伸缩杆顶端安装通长的支撑梁;在支撑梁间安装若干与隧道拱顶弧度相匹配的拱梁,在拱梁外表面设置若干通长的支撑杆,在支撑杆上铺设上部支护板;在小车外侧安装可收放的侧壁支护板;在上部支护板、侧壁支护板上分别设置注浆孔,得到能给予围岩全面支撑力的加固模架体系;根据地质雷达或传感器件的监测结果确定已成初支段围岩松动或大变形范围,移动加固模架体系至待加固段,通过液压缸调节上部支护板的支护高度,使其贴紧混凝土层,利用注浆孔对松动或大变形围岩区域进行注浆加固,形成注浆加固土体;待围岩达到稳定状态,在初期支护层表面铺设防水层并移开加固模架体系,进行二衬混凝土及隧道底板浇筑,形成封闭的受力结构。Two parallel trolleys are arranged on the bottom surface of the tunnel. The trolley body is arranged along the tunnel extension direction and the trolley moves along the tunnel extension direction. Vertical telescopic rods are installed at the front and rear ends of the trolley body respectively, as well as the hydraulic cylinders that drive the vertical extension rods to expand and contract. , install a full-length support beam at the top of the vertical telescopic rod on the same trolley; install a number of arch beams matching the curvature of the tunnel vault between the support beams, and set a number of full-length support rods on the outer surface of the arch beam to support The upper support plate is laid on the pole; the retractable side wall support plate is installed on the outside of the trolley; the grouting holes are respectively set on the upper support plate and the side wall support plate to obtain the reinforcement that can give the surrounding rock a comprehensive support force. Formwork system: According to the monitoring results of geological radar or sensor devices, determine the looseness or large deformation range of the surrounding rock in the primary support section, move the reinforcement formwork system to the section to be strengthened, and adjust the support height of the upper support plate through the hydraulic cylinder. Make it close to the concrete layer, and use grouting holes to grouting and reinforce the loose or large deformation surrounding rock area to form grouting reinforcement soil; when the surrounding rock reaches a stable state, lay a waterproof layer on the surface of the initial support layer and remove it. The formwork system is reinforced, and the secondary lining concrete and the tunnel floor are poured to form a closed stress structure.

进一步的,所述侧壁支护板、上部支护板均为韧性钢板。Further, the side wall support plate and the upper support plate are both ductile steel plates.

进一步的,所述侧壁支护板与小车外侧面连接有加固杆,加固杆两端分别与小车、侧壁支护板铰接。Further, a reinforcement rod is connected to the side wall support plate and the outer side of the trolley, and both ends of the reinforcement rod are hinged with the trolley and the side wall support plate respectively.

本发明的有益效果是:The beneficial effects of the present invention are:

1、本发明能够对隧道已成初支段由于扰动或勘察设计不周或施做不当而产生的大变形区域进行充分的二次加固,能给予隧道薄弱段一个全面的支撑力,保障注浆加固质量;另外,针对富水破碎浅埋隧道从地面二次注浆时,该方法能从洞内起到整体的稳定作用,防止围岩坍落影响施工作业及结构安全。1. The present invention can fully reinforce the large deformation area of the primary section of the tunnel due to disturbance, poor investigation and design, or improper construction, and can give a comprehensive supporting force to the weak section of the tunnel to ensure grouting Reinforcement quality; In addition, when secondary grouting is performed from the ground for water-rich broken shallow tunnels, this method can play an overall stabilizing role from the inside of the tunnel, preventing the collapse of surrounding rocks from affecting construction operations and structural safety.

2、本发明适用于各种复杂地质条件下由于各种扰动因素导致围岩恶化的二次加固,安全可靠,控制变形效果好,隧道稳定性好,且对环境影响小,施工风险小,适用性强。2. The present invention is suitable for the secondary reinforcement of the deterioration of surrounding rock due to various disturbance factors under various complex geological conditions. Strong sex.

附图说明Description of drawings

图1为本发明隧道的结构示意图;Fig. 1 is the structural representation of the tunnel of the present invention;

图2为本发明加固状态示意图;FIG. 2 is a schematic diagram of the reinforcement state of the present invention;

图3为本发明加固模架体系的装配示意图;Fig. 3 is the assembling schematic diagram of reinforcing formwork system of the present invention;

图4为本发明加固模架体系的结构示意图。FIG. 4 is a schematic structural diagram of the reinforcement formwork system of the present invention.

具体实施方式Detailed ways

下面将结合附图对本发明实施例中的技术方案进行清楚、完整地描述。The technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the accompanying drawings.

如图1-4所示,一种围岩松动或软岩大变形的隧道加固控制方法,包括以下步骤:As shown in Figure 1-4, a tunnel reinforcement control method for loose surrounding rock or large deformation of soft rock includes the following steps:

步骤一、如图1-2所示,在围岩四周施作初期支护层,在初期支护层上表面设置传感器件3,用于监测围岩应力或变形状态。Step 1. As shown in Figure 1-2, an initial support layer is installed around the surrounding rock, and a sensor device 3 is installed on the upper surface of the initial support layer to monitor the stress or deformation state of the surrounding rock.

初期支护层包括铺设在围岩四周的钢筋网1,以及喷射在钢筋网1上的混凝土层2。The initial support layer includes a steel mesh 1 laid around the surrounding rock, and a concrete layer 2 sprayed on the steel mesh 1 .

步骤二、如图2-4所示,制作可移动的加固模架体系;根据地质雷达或传感器件3的监测结果确定已成初支段围岩松动或大变形范围,移动加固模架体系至待加固段进行加固。Step 2, as shown in Figure 2-4, make a movable reinforcement formwork system; determine the looseness or large deformation range of the surrounding rock in the primary support section according to the monitoring results of the ground radar or sensor device 3, and move the reinforcement formwork system to The section to be reinforced is reinforced.

所述加固模架体系的制作及加固方法为:The making and reinforcing method of described reinforced formwork system are:

在隧道底面上设置两个平行的小车7,小车7车体沿隧道延伸方向设置且小车7沿隧道延伸方向移动;在小车7车体前后端分别安装竖向伸缩杆8,以及驱动竖向伸缩杆8伸缩的液压缸9,在同一小车7上的竖向伸缩杆8顶端安装通长的支撑梁10。Two parallel trolleys 7 are arranged on the bottom surface of the tunnel, and the trolley 7 car bodies are arranged along the extension direction of the tunnel and the trolley 7 moves along the tunnel extension direction; vertical telescopic rods 8 are respectively installed at the front and rear ends of the trolley 7 car bodies, and drive vertical telescopic The telescopic hydraulic cylinder 9 of rod 8 installs a long support beam 10 at the top of the vertical telescopic rod 8 on the same dolly 7.

在支撑梁10间安装若干与隧道拱顶弧度相匹配的拱梁11,在拱梁11外表面设置若干通长的支撑杆12,在支撑杆12上铺设上部支护板13;通过液压缸9可以调节上部支护板13的支护高度,对围岩进行竖向支护。A number of arch beams 11 matching the arc of the tunnel vault are installed between the support beams 10, several long support rods 12 are arranged on the outer surface of the arch beams 11, and upper support plates 13 are laid on the support rods 12; through the hydraulic cylinder 9 The support height of the upper support plate 13 can be adjusted to vertically support the surrounding rock.

在小车7外侧安装可收放的侧壁支护板14;侧壁支护板14与小车7外侧面连接有加固杆16,加固杆16两端分别与小车7、侧壁支护板14铰接,加固杆16向上转动,可以收起侧壁支护板14,反之可以放下侧壁支护板14,对围岩进行横向支护。A retractable side wall support plate 14 is installed on the outside of the trolley 7; the side wall support plate 14 is connected with the outer surface of the trolley 7 with a reinforcement rod 16, and the two ends of the reinforcement rod 16 are respectively hinged with the trolley 7 and the side wall support plate 14 , the reinforcement bar 16 rotates upwards, can pack up the side wall support plate 14, can put down the side wall support plate 14 otherwise, the surrounding rock is carried out lateral support.

在上部支护板13、侧壁支护板14上分别设置注浆孔15,得到能给予围岩全面支撑力的加固模架体系。Grouting holes 15 are respectively set on the upper supporting plate 13 and the side wall supporting plate 14 to obtain a reinforced formwork system capable of giving the surrounding rock a comprehensive supporting force.

根据地质雷达或传感器件3的监测结果确定已成初支段围岩松动或大变形范围,移动加固模架体系至待加固段,通过液压缸9调节上部支护板13的支护高度,使其贴紧混凝土层,利用注浆孔15对松动或大变形围岩区域进行注浆加固,形成注浆加固土体17。According to the monitoring results of geological radar or sensor device 3, it is determined that the surrounding rock of the initial support section is loose or has a large deformation range, and the reinforcement formwork system is moved to the section to be reinforced, and the support height of the upper support plate 13 is adjusted by the hydraulic cylinder 9, so that It sticks to the concrete layer, and uses the grouting hole 15 to perform grouting reinforcement on the loose or large deformed surrounding rock area to form a grouting reinforcement soil mass 17 .

待围岩达到稳定状态,在初期支护层表面铺设防水层4并移开加固模架体系,进行二衬混凝土5及隧道底板6浇筑,形成封闭的受力结构。When the surrounding rock reaches a stable state, a waterproof layer 4 is laid on the surface of the primary support layer and the reinforcement formwork system is removed, and the secondary lining concrete 5 and the tunnel floor 6 are poured to form a closed stress-bearing structure.

所述侧壁支护板14、上部支护板13均为韧性钢板。Both the side wall support plate 14 and the upper support plate 13 are tough steel plates.

本发明能够对隧道已成初支段由于扰动或勘察设计不周或施做不当而产生的大变形区域进行充分的二次加固,能给予隧道薄弱段一个全面的支撑力,保障注浆加固质量;另外,针对富水破碎浅埋隧道从地面二次注浆时,该方法能从洞内起到整体的稳定作用,防止围岩坍落影响施工作业及结构安全。The invention can fully reinforce the large deformation area of the primary support section of the tunnel due to disturbance, poor investigation and design, or improper construction, and can give a comprehensive supporting force to the weak section of the tunnel, ensuring the quality of grouting reinforcement ; In addition, when secondary grouting from the ground for water-rich broken shallow tunnels, this method can play an overall stabilizing role from the inside of the tunnel, preventing the collapse of surrounding rocks from affecting construction operations and structural safety.

所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明的范围。The described embodiments are only some, but not all, embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative efforts shall fall within the scope of the present invention.

Claims (5)

1. the tunnel reinforcement control method of a kind of wall rock loosening or soft rock large deformation, which comprises the following steps:
Step 1: applying preliminary bracing layer in country rock surrounding, senser element is arranged in branch sheath upper surface in the early stage, encloses for monitoring Rock stress or deformation state;
Step 2: production is moveable to reinforce formwork system;It is had become according to the determination of the monitoring result of geological radar or senser element First branch section wall rock loosening or large deformation range, mobile formwork system to section to be reinforced of reinforcing are reinforced.
2. the tunnel reinforcement control method of a kind of wall rock loosening as described in claim 1 or soft rock large deformation, which is characterized in that In the step 1, preliminary bracing layer includes the steel mesh for being laid on country rock surrounding, and the concrete being injected on steel mesh Layer.
3. the tunnel reinforcement control method of a kind of wall rock loosening as described in claim 1 or soft rock large deformation, which is characterized in that In the step 2, production and the reinforcement means of formwork system are reinforced are as follows:
Two parallel trolleies are set on tunnel bottom surface, and trolley is arranged along tunnel extending direction and trolley extends along tunnel Direction is mobile;Vertical telescopic rod, and the hydraulic cylinder that the vertical telescopic rod of driving is flexible are installed respectively in trolley front and back end, Vertical telescopic rod top end on same trolley installs elongated supporting beam;It is installed between supporting beam several with tunnel vault radian phase Several elongated support rods are arranged in arched girder outer surface in matched arched girder, and top retaining-plate is laid on support rod;Outside trolley Side is installed by retractable side wall retaining-plate;Injected hole is respectively set on top retaining-plate, side wall retaining-plate, obtains to give and enclose The reinforcing formwork system of rock comprehensive support power;It is determined according to the monitoring result of geological radar or senser element and has become just branch section country rock It loosens or large deformation range, mobile reinforcing formwork system to section to be reinforced, the supporting for adjusting top retaining-plate by hydraulic cylinder is high Degree, makes it be adjacent to concrete layer, carries out grouting and reinforcing to loosening or large deformation country rock region using injected hole, forms grouting and reinforcing The soil body;Reach stable state to country rock, supporting layer surface is laid with waterproof layer and removes reinforcing formwork system in the early stage, carries out two linings Concrete and tunnel floor pour, and form closed force structure.
4. the tunnel reinforcement control method of a kind of wall rock loosening as claimed in claim 3 or soft rock large deformation, which is characterized in that The side wall retaining-plate, top retaining-plate are flexible steel plate.
5. the tunnel reinforcement control method of a kind of wall rock loosening as claimed in claim 3 or soft rock large deformation, which is characterized in that The side wall retaining-plate and trolley lateral surface are connected with reinforcing bar, and reinforcing bar both ends are hinged with trolley, side wall retaining-plate respectively.
CN201910398527.7A 2019-05-14 2019-05-14 A Tunnel Reinforcement Control Method for Loose Surrounding Rock or Large Deformation of Soft Rock Pending CN109973122A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910398527.7A CN109973122A (en) 2019-05-14 2019-05-14 A Tunnel Reinforcement Control Method for Loose Surrounding Rock or Large Deformation of Soft Rock

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910398527.7A CN109973122A (en) 2019-05-14 2019-05-14 A Tunnel Reinforcement Control Method for Loose Surrounding Rock or Large Deformation of Soft Rock

Publications (1)

Publication Number Publication Date
CN109973122A true CN109973122A (en) 2019-07-05

Family

ID=67073607

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910398527.7A Pending CN109973122A (en) 2019-05-14 2019-05-14 A Tunnel Reinforcement Control Method for Loose Surrounding Rock or Large Deformation of Soft Rock

Country Status (1)

Country Link
CN (1) CN109973122A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110792478A (en) * 2019-11-13 2020-02-14 中铁十局集团有限公司 Omnibearing monitoring method for various mixed harmful gases in non-coal measure stratum tunnel
CN114060066A (en) * 2021-11-25 2022-02-18 中铁第四勘察设计院集团有限公司 Assembled stratum stress compensation servo steel frame system for controlling large deformation of tunnel
CN114673521A (en) * 2021-07-07 2022-06-28 西华大学 Preliminary bracing device of big deformation of red clay tunnel country rock of control
CN114704287A (en) * 2022-04-01 2022-07-05 山东省公路桥梁建设集团有限公司 Tunnel surrounding rock reinforcing apparatus
CN119041935A (en) * 2024-10-31 2024-11-29 中交第一航务工程局有限公司 Supporting method for construction of underground excavation tunnel

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104196546A (en) * 2014-08-06 2014-12-10 山东大学 Treatment method for fault fracture zone collapse in tunnel construction process
CN105863677A (en) * 2016-04-12 2016-08-17 中国电建集团成都勘测设计研究院有限公司 Strengthening method for preliminary tunnel support
CN205618172U (en) * 2016-03-28 2016-10-05 兰州市轨道交通有限公司 Tunnel country rock slip casting reinforcerment system
CN106089258A (en) * 2016-08-24 2016-11-09 重庆工商职业学院 Tunnel device and construction method
CN205840897U (en) * 2016-06-30 2016-12-28 北京城建七建设工程有限公司 A kind of bored tunnel vault caves in emergency set
CN206830213U (en) * 2017-04-13 2018-01-02 中铁二院工程集团有限责任公司 A kind of soft rock tunnel anti-collapse monitoring device
CN107725068A (en) * 2017-11-06 2018-02-23 山东建筑大学 A kind of assembled supporting construction and its construction method based on outside steel arch-shelf and inner side concrete slab
CN109057820A (en) * 2018-08-20 2018-12-21 福建工程学院 A kind of rich water weak broken formation tunnel method for protecting support
CN109268033A (en) * 2018-07-31 2019-01-25 杭州江润科技有限公司 Pushing out ring arch reinforces Large Deformation Support and its construction method in soft rock tunnel regularization
CN109441479A (en) * 2018-10-23 2019-03-08 北京市城远市政工程有限责任公司 A kind of bored tunnel sump remedy method

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104196546A (en) * 2014-08-06 2014-12-10 山东大学 Treatment method for fault fracture zone collapse in tunnel construction process
CN205618172U (en) * 2016-03-28 2016-10-05 兰州市轨道交通有限公司 Tunnel country rock slip casting reinforcerment system
CN105863677A (en) * 2016-04-12 2016-08-17 中国电建集团成都勘测设计研究院有限公司 Strengthening method for preliminary tunnel support
CN205840897U (en) * 2016-06-30 2016-12-28 北京城建七建设工程有限公司 A kind of bored tunnel vault caves in emergency set
CN106089258A (en) * 2016-08-24 2016-11-09 重庆工商职业学院 Tunnel device and construction method
CN206830213U (en) * 2017-04-13 2018-01-02 中铁二院工程集团有限责任公司 A kind of soft rock tunnel anti-collapse monitoring device
CN107725068A (en) * 2017-11-06 2018-02-23 山东建筑大学 A kind of assembled supporting construction and its construction method based on outside steel arch-shelf and inner side concrete slab
CN109268033A (en) * 2018-07-31 2019-01-25 杭州江润科技有限公司 Pushing out ring arch reinforces Large Deformation Support and its construction method in soft rock tunnel regularization
CN109057820A (en) * 2018-08-20 2018-12-21 福建工程学院 A kind of rich water weak broken formation tunnel method for protecting support
CN109441479A (en) * 2018-10-23 2019-03-08 北京市城远市政工程有限责任公司 A kind of bored tunnel sump remedy method

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110792478A (en) * 2019-11-13 2020-02-14 中铁十局集团有限公司 Omnibearing monitoring method for various mixed harmful gases in non-coal measure stratum tunnel
CN114673521A (en) * 2021-07-07 2022-06-28 西华大学 Preliminary bracing device of big deformation of red clay tunnel country rock of control
CN114060066A (en) * 2021-11-25 2022-02-18 中铁第四勘察设计院集团有限公司 Assembled stratum stress compensation servo steel frame system for controlling large deformation of tunnel
CN114704287A (en) * 2022-04-01 2022-07-05 山东省公路桥梁建设集团有限公司 Tunnel surrounding rock reinforcing apparatus
CN119041935A (en) * 2024-10-31 2024-11-29 中交第一航务工程局有限公司 Supporting method for construction of underground excavation tunnel

Similar Documents

Publication Publication Date Title
CN109973122A (en) A Tunnel Reinforcement Control Method for Loose Surrounding Rock or Large Deformation of Soft Rock
CN108412542B (en) A kind of wide lane digging gangue paste body filling of high seam is at lane method
CN106337686B (en) Three layers of subway station canopy structure of rocky stratum tunneling and construction method
CN101864987B (en) Building method of filled wall body for gob-side entry retaining of large-inclination coal seam
CN104847374B (en) Large-deformation tunnel in soft rock support system and its construction method
CN103510959B (en) A kind of Shallow-buried Large-span small interval loess tunnel excavation technology
CN106567718B (en) A kind of construction method of compound stratum list arch super-span subway station kerve support replacement
CN104612698A (en) Method for constructing upper step middle partition wall of shallow-buried excavation tunnel
CN110821513B (en) Construction method for performing advanced grouting and supporting on tunnel local collapse
CN105781571A (en) Construction method for soft rock deformation tunnel lining support dismantling-replacing arch
CN102061923B (en) Tunnel construction method capable of protecting existing building
CN105443132A (en) Construction method of shallow-buried subsurface-excavated cross-shaped cross-strut tunnel
CN204729099U (en) Rock quality layer tunneling three layers of subway station canopy structure
CN103821167A (en) Construction method for subway station body
CN103982188A (en) Supporting structure system of rock stratum large-section deep vertical shaft and construction method of supporting structure system
CN108561151A (en) The micro- step construction method of the big arch springing of loess tunnel
CN103089270B (en) Excavating method suitable for large section loess tunnels
CN107725064A (en) Tunnel partition wall structure and the method that tunnel step excavation is realized using middle-wall method
CN108266209A (en) A kind of big ledge method in large section subway station excavates the rapid constructing method of lower part
CN106930321A (en) Underground structure novel construction method is built in a kind of pipe-jacking with large diameter combination hole stake
CN111322090A (en) Support method for controlling deformation of surrounding rock of high-geostress hard rock tunnel
CN103321234A (en) Load-bearing structure built on high slope or geological complex area and constructing method thereof
CN104453915A (en) Large-section vertical shaft pre-grouting reinforcement quick excavation method
CN109339800A (en) A rapid construction method of tunnel in the connecting section of bridge and tunnel
CN107191206B (en) A six-step construction method for two units of shallow buried long-span tunnels

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190705

RJ01 Rejection of invention patent application after publication