CN106760466B - Pylon multilayer lifts linkage construction method at light shaft - Google Patents

Pylon multilayer lifts linkage construction method at light shaft Download PDF

Info

Publication number
CN106760466B
CN106760466B CN201611023020.6A CN201611023020A CN106760466B CN 106760466 B CN106760466 B CN 106760466B CN 201611023020 A CN201611023020 A CN 201611023020A CN 106760466 B CN106760466 B CN 106760466B
Authority
CN
China
Prior art keywords
pylon
layer
nut
wall
screw arbor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201611023020.6A
Other languages
Chinese (zh)
Other versions
CN106760466A (en
Inventor
傅宇
陈刚
都毅
唐静
刘宇宏
王炳
高昌权
张宇
徐建虎
秦红
陈舸
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chengdu Construction Engineering No 7 Construction Engineering Co Ltd
Chengdu Construction Industry Group Co Ltd
Original Assignee
Chengdu Construction Engineering No 7 Construction Engineering Co Ltd
Chengdu Construction Industry Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chengdu Construction Engineering No 7 Construction Engineering Co Ltd, Chengdu Construction Industry Group Co Ltd filed Critical Chengdu Construction Engineering No 7 Construction Engineering Co Ltd
Priority to CN201611023020.6A priority Critical patent/CN106760466B/en
Publication of CN106760466A publication Critical patent/CN106760466A/en
Application granted granted Critical
Publication of CN106760466B publication Critical patent/CN106760466B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/28Mobile scaffolds; Scaffolds with mobile platforms
    • E04G3/30Mobile scaffolds; Scaffolds with mobile platforms suspended by flexible supporting elements, e.g. cables
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/04Means for fastening, supporting, or bracing scaffolds on or against building constructions
    • E04G5/046Means for fastening, supporting, or bracing scaffolds on or against building constructions for fastening scaffoldings on walls

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Electric Cable Installation (AREA)

Abstract

The invention discloses pylon multilayers at light shaft to lift linkage construction method, the pylon includes operating platform and the Screw arbor with nut at both-ends for being symmetricly set on two side lower part of operating platform, the construction method specifically: will at least two layers of pylon be linked together by steel cable, adjacent two layers pylon is parallel to each other, each layer pylon is corresponding with the installation position that wall is reserved respectively, when at least two layers of pylon is lifted by tower crane to when corresponding to installation position, each layer pylon is fixed by Screw arbor with nut at both-ends and the wall connecting of its two sides, the pylon and the wall of two sides collectively form construction channel.The present invention is mainly suitable under long and narrow channel-type environment, pass through the form of construction work for lifting the pylon linkage of multilayer, simultaneously make pylon two sides respectively with the mode of corresponding wall connecting, construction channel is collectively formed using pylon and wall, relative to the form of construction work using traditional structure pylon, difficulty of construction of the invention is lower, can greatly save the construction period.

Description

Pylon multilayer lifts linkage construction method at light shaft
Technical field
The invention belongs to technical field of building construction, in particular to pylon multilayer lifting linkage construction at a kind of light shaft Method.
Background technique
In traditional construction, external wall usually pass through setting pylon as operating space, it is existing plug-in Frame is connect by the connector of one side with external wall.However, it was found that the light shaft built mostly in practice of construction Place is usually a long and narrow channel-type structure, is gone forward side by side so that the pylon form of construction work of existing structure be caused to install in the present context The difficulty of row construction is larger, seriously affects the duration of construction.
Summary of the invention
It is an object of the invention to: in view of the above problems, providing one kind can be effectively applicable to lead in long and narrow Road formula architectural lighting well location installs pylon multilayer at the light shaft of pylon and lifts linkage construction method.
The technical scheme of the present invention is realized as follows: pylon multilayer lifts linkage construction method at light shaft, it is special Sign is: the pylon includes operating platform and the Screw arbor with nut at both-ends for being symmetricly set on two side lower part of operating platform, described to apply Work method specifically: will at least two layers of pylon be linked together by steel cable, adjacent two layers pylon is parallel to each other, outside each layer Hanger is corresponding with the installation position that wall is reserved respectively, when at least two layers of pylon is lifted by tower crane to corresponding installation position When, each layer pylon is fixed by Screw arbor with nut at both-ends and the wall connecting of its two sides, the common structure of the wall of the pylon and two sides At construction channel.
Pylon multilayer lifts linkage construction method at light shaft of the present invention, close on the operating platform End is respectively arranged with hanging ring at angle, and in adjacent two layers pylon, the pylon of lower layer is connected by steel cable and the pylon on upper layer It being connected together, the steel cable of the tower crane is connect with the hanging ring of upper layer pylon, and tower crane hook is exceptionally straight by steel cable, after lifting, each layer Pylon is held in horizontal position.
Pylon multilayer lifts linkage construction method at light shaft of the present invention, close on the operating platform End is respectively arranged with reservation operations hole at angle, what the position at the reservation operations hole was connect with Screw arbor with nut at both-ends biconditional operation platform Position is corresponding, when needing to remove pylon, installation personnel station on the operational platform, by reservation operations hole by respective layer The Screw arbor with nut at both-ends fixing bolt of pylon is unlocked, and Screw arbor with nut at both-ends is withdrawn;When the Screw arbor with nut at both-ends dismounting of each layer pylon finishes Afterwards, tower crane continues up lifting, and pylon is made to start to climb, and when pylon rises to next predetermined mounting height, tower crane stops It is promoted, installation personnel guidance pylon enters installation point and corrected, then pre- on wall by passing through Screw arbor with nut at both-ends The wall-through hole stayed, fixes pylon with wall connecting.
Pylon multilayer lifts linkage construction method at light shaft of the present invention, in multilayer pylon installation process In, successively installed from lower to upper since bottom pylon first, bottom pylon after the installation is completed, remove bottom with thereon The pylon of the steel cable connected between one layer of pylon, upper layer leads into installation position while the pylon correction of lower layer It sets, after the installation is completed to bottom pylon, installation personnel enters the Screw arbor with nut at both-ends in bottom pylon to upper one layer of pylon Carry out installation fixation.
The present invention is mainly suitable under long and narrow channel-type environment, pass through the construction party for lifting the pylon linkage of multilayer Formula, while pylon two sides being made with the mode of corresponding wall connecting, to collectively form construction channel using pylon and wall respectively, Relative to the form of construction work using traditional structure pylon, difficulty of construction of the invention is lower, can greatly save the construction period.
Detailed description of the invention
Fig. 1 is the construction schematic diagram of pylon in the present invention.
Fig. 2 is the structural schematic diagram of pylon in the present invention.
Fig. 3 is the top view of pylon in the present invention.
Marked in the figure: 1 is pylon, 2 be operating platform, and 3 be Screw arbor with nut at both-ends, and 4 be steel cable, and 5 be wall, and 6 be hanging ring, 7 For reservation operations hole.
Specific embodiment
With reference to the accompanying drawing, the present invention is described in detail.
In order to make the objectives, technical solutions, and advantages of the present invention clearer, with reference to the accompanying drawings and embodiments, right The present invention is further elaborated.It should be appreciated that the specific embodiments described herein are merely illustrative of the present invention, and It is not used in the restriction present invention.
As shown in Figure 1, pylon multilayer lifts linkage construction method at a kind of light shaft, the pylon 1 includes operation Platform 2 and the Screw arbor with nut at both-ends 3 for being symmetricly set on 2 liang of side lower parts of operating platform, the construction method specifically: will at least two layers Pylon 1 is linked together by steel cable 4, and adjacent two layers pylon 1 is parallel to each other, and each layer pylon 1 is reserved with wall 5 respectively Installation position it is corresponding, when at least two layers of pylon 1 is lifted by tower crane to correspondence installation position, each layer pylon 1 passes through Screw arbor with nut at both-ends 3 and the wall 5 of its two sides are connected and fixed, and the wall 5 of the pylon 1 and two sides collectively forms construction channel.
As shown in Figures 2 and 3, it is respectively arranged with hanging ring 6 by proximal end Jiao Chu on the operating platform 2, outside adjacent two layers In hanger 1, the pylon 1 of lower layer is linked together by steel cable 4 and the pylon 1 on upper layer, the steel cable of the tower crane and upper layer The hanging ring 6 of pylon 1 connects, and tower crane hook is exceptionally straight by steel cable, and after lifting, each layer pylon 1 is held in horizontal position.
Wherein, reservation operations hole 7, the reservation operations are respectively arranged with by proximal end Jiao Chu on the operating platform 2 The position at hole 7 is corresponding with the position that 3 biconditional operation platform 2 of Screw arbor with nut at both-ends connects, and when needing to remove pylon 1, installs people 3 fixing bolt of Screw arbor with nut at both-ends of respective layer pylon 1 is unlocked by reservation operations hole 7 on operating platform 2 in member station, receives Return Screw arbor with nut at both-ends 3;After the Screw arbor with nut at both-ends 3 of each layer pylon 1 is removed, tower crane continues up lifting, makes pylon 1 Start to climb, when pylon 1 rises to next predetermined mounting height, tower crane stops being promoted, and installation personnel guides pylon 1 to enter Installation point is simultaneously corrected, and then by the way that Screw arbor with nut at both-ends 3 is passed through the wall-through hole reserved on wall 5, makes pylon 1 and wall 5 are connected and fixed.
In 1 installation process of multilayer pylon, successively installed from lower to upper since bottom pylon 1 first, in bottom After the installation is completed, the steel cable removing bottom and connecting between one layer of pylon 1 thereon, the pylon on upper layer is in lower layer for pylon 1 Pylon correction while lead into installation site, after the installation is completed to bottom pylon 1, installation personnel enters bottom Installation fixation is carried out to the Screw arbor with nut at both-ends 3 of upper one layer of pylon 1 in pylon 1.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all in essence of the invention Made any modifications, equivalent replacements, and improvements etc., should all be included in the protection scope of the present invention within mind and principle.

Claims (2)

1. pylon multilayer lifts linkage construction method at light shaft, it is characterised in that: the pylon (1) includes operating platform (2) Screw arbor with nut at both-ends (3) of (2) two side lower part of operating platform, the construction method are symmetricly set on and specifically: will at least two Layer pylon (1) is linked together by steel cable (4), and adjacent two layers pylon (1) is parallel to each other, and each layer pylon (1) is respectively With wall (5) reserve installation position it is corresponding, when at least two layers of pylon (1) by tower crane lift to correspondence installation position when, Each layer pylon (1) is connected and fixed by Screw arbor with nut at both-ends (3) and the wall (5) of its two sides, the wall of pylon (1) and two sides Body (5) collectively forms construction channel;
It is respectively arranged with reservation operations hole (7) on the operating platform (2) by proximal end Jiao Chu, the reservation operations hole (7) position is corresponding with the position that Screw arbor with nut at both-ends (3) biconditional operation platform (2) connects, when needing to remove pylon (1), peace Dress personnel stand on operating platform (2), by reservation operations hole (7) that the Screw arbor with nut at both-ends (3) of respective layer pylon (1) is fixed Bolt is unlocked, and is withdrawn Screw arbor with nut at both-ends (3);After the Screw arbor with nut at both-ends (3) of each layer pylon (1) is removed, tower crane continues Lifting upwards, makes pylon (1) start to climb, and when pylon (1) rises to next predetermined mounting height, tower crane stops being promoted, Installation personnel guidance pylon (1) enters installation point and is corrected, then by the way that Screw arbor with nut at both-ends (3) are passed through wall (5) Upper reserved wall-through hole, is connected and fixed pylon (1) with wall (5);
In multilayer pylon (1) installation process, successively installed from lower to upper since bottom pylon (1) first, in bottom After the installation is completed, the steel cable removing bottom and connecting between one layer of pylon (1) thereon, the pylon on upper layer exists pylon (1) Installation site is led into while the pylon correction of lower layer, after the installation is completed to bottom pylon (1), installation personnel enters Installation fixation is carried out to the Screw arbor with nut at both-ends (3) of upper one layer of pylon (1) in bottom pylon (1).
2. pylon multilayer lifts linkage construction method at light shaft according to claim 1, it is characterised in that: described Hanging ring (6) are respectively arranged with by proximal end Jiao Chu on operating platform (2), in adjacent two layers pylon (1), the pylon of lower layer (1) it is linked together by steel cable (4) and the pylon (1) on upper layer, the steel cable of the tower crane and the hanging ring of upper layer pylon (1) (6) it connects, tower crane hook is exceptionally straight by steel cable, and after lifting, each layer pylon (1) is held in horizontal position.
CN201611023020.6A 2016-11-21 2016-11-21 Pylon multilayer lifts linkage construction method at light shaft Active CN106760466B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611023020.6A CN106760466B (en) 2016-11-21 2016-11-21 Pylon multilayer lifts linkage construction method at light shaft

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611023020.6A CN106760466B (en) 2016-11-21 2016-11-21 Pylon multilayer lifts linkage construction method at light shaft

Publications (2)

Publication Number Publication Date
CN106760466A CN106760466A (en) 2017-05-31
CN106760466B true CN106760466B (en) 2019-02-05

Family

ID=58969841

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611023020.6A Active CN106760466B (en) 2016-11-21 2016-11-21 Pylon multilayer lifts linkage construction method at light shaft

Country Status (1)

Country Link
CN (1) CN106760466B (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8141683B1 (en) * 2009-04-30 2012-03-27 Wurtec Elevator Products & Services Expandable platform
CN203640248U (en) * 2013-11-15 2014-06-11 重庆华龄软汇科技有限公司 Fast construction device for external wall of light well
CN204326489U (en) * 2014-12-01 2015-05-13 江苏邗建集团有限公司 Construction of lift well operating platform
CN204456816U (en) * 2015-02-10 2015-07-08 中建四局第三建筑工程有限公司 One can promote supporting leg type elevator hoistway construction platform
CN204492137U (en) * 2015-01-22 2015-07-22 中建三局第二建设工程有限责任公司 The elevated regularization operating platform of elevator shaft
CN204826659U (en) * 2015-05-21 2015-12-02 中建三局第三建设工程有限责任公司 Light well steel platform of unloading
CN205224567U (en) * 2015-11-19 2016-05-11 中国葛洲坝集团第六工程有限公司 Collapsible foldable elevartor shaft construction platform

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8141683B1 (en) * 2009-04-30 2012-03-27 Wurtec Elevator Products & Services Expandable platform
CN203640248U (en) * 2013-11-15 2014-06-11 重庆华龄软汇科技有限公司 Fast construction device for external wall of light well
CN204326489U (en) * 2014-12-01 2015-05-13 江苏邗建集团有限公司 Construction of lift well operating platform
CN204492137U (en) * 2015-01-22 2015-07-22 中建三局第二建设工程有限责任公司 The elevated regularization operating platform of elevator shaft
CN204456816U (en) * 2015-02-10 2015-07-08 中建四局第三建筑工程有限公司 One can promote supporting leg type elevator hoistway construction platform
CN204826659U (en) * 2015-05-21 2015-12-02 中建三局第三建设工程有限责任公司 Light well steel platform of unloading
CN205224567U (en) * 2015-11-19 2016-05-11 中国葛洲坝集团第六工程有限公司 Collapsible foldable elevartor shaft construction platform

Also Published As

Publication number Publication date
CN106760466A (en) 2017-05-31

Similar Documents

Publication Publication Date Title
WO2020052291A1 (en) Construction elevator wall-attaching frame mounting platform attached to steel platform formwork and method therefor
CN108033367B (en) Synchronous lifting device and lifting method for steel column and cylinder frame alternately supported steel platform and tower crane
CN103979383A (en) Multi-layer lifting platform for building construction
CN103711308A (en) Tool type steel-column supporting steel platform climbing system and using method thereof
CN104895337B (en) The installation method of large-size horizontal equipment in concrete frame
CN103318768A (en) Assembling method of quayside with low posture
CN104929353A (en) Detachable stepwise automatic climbing operating platform for elevator shafts
CN104153586B (en) A kind of suspension cable hangs the construction method of mounting purlines
CN105888229A (en) All-steel attached scaffold mounting method
CN104989111A (en) Construction method for steel structure high-rise hoisting
CN106760466B (en) Pylon multilayer lifts linkage construction method at light shaft
CN202380721U (en) Hydraulic self-elevating climbing system
CN105625732B (en) Superelevation overhanging steel structure truss support free construction method
CN107724643A (en) One kind installs elevator hoistways structure and installation method additional
CN209145256U (en) The dedicated climbing frame of assembled architecture
CN203640291U (en) Height-difference adjustable double-layer operating platform for construction of building body and external ornaments
CN103669867B (en) Building body and outer decoration construction discrepancy in elevation adjustable double-layer operating platform and installation method
CN113323368A (en) Lifting construction method for external protection hanging frame of assembled building
CN205662189U (en) Mounting structure of elevator guide rail and elevator
CN204754150U (en) Dish -type node formula scaffold
CN104328748B (en) The bracket end ruggedized construction of a kind of cantilever glider bridge and installation method thereof
CN103741939B (en) The outside climbing type CONSTRUCTION OPERATIONS platform of building and mounting method
CN103225390B (en) Hollow facade pulley guide attached-type lifting scaffold
CN207228604U (en) A kind of unilateral suspension type aerial movement steel platform
CN103899078A (en) Mounting method of attached automatic lifting protection shield

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 610031 No. 111 Babao Street, Qingyang District, Chengdu City, Sichuan Province

Applicant after: Chengdu Construction Industry Group Co., Ltd.

Applicant after: Chengdu Construction Engineering No. 7 Construction Engineering Co., Ltd.

Address before: 610031 No. 111 Babao Street, Qingyang District, Chengdu City, Sichuan Province

Applicant before: Chengdu Construction Engineering Group Corp.

Applicant before: Chengdu No.7 Construction Engineering Co., Ltd.

CB02 Change of applicant information
GR01 Patent grant