CN106758845B - Concrete structure falls beam joist device and falls beam construction method using it - Google Patents

Concrete structure falls beam joist device and falls beam construction method using it Download PDF

Info

Publication number
CN106758845B
CN106758845B CN201710014933.XA CN201710014933A CN106758845B CN 106758845 B CN106758845 B CN 106758845B CN 201710014933 A CN201710014933 A CN 201710014933A CN 106758845 B CN106758845 B CN 106758845B
Authority
CN
China
Prior art keywords
top plate
jack
joist device
corbel
box beam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710014933.XA
Other languages
Chinese (zh)
Other versions
CN106758845A (en
Inventor
郭玉鹏
孙延琳
王爱平
杨成达
黄峻峻
赵坤
张学飞
常春章
张海霞
曾来仕
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 10 Engineering Group Co Ltd
Original Assignee
China Railway No 10 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway No 10 Engineering Group Co Ltd filed Critical China Railway No 10 Engineering Group Co Ltd
Priority to CN201710014933.XA priority Critical patent/CN106758845B/en
Publication of CN106758845A publication Critical patent/CN106758845A/en
Application granted granted Critical
Publication of CN106758845B publication Critical patent/CN106758845B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Abstract

Beam joist device is fallen the invention discloses a kind of concrete structure and falls beam construction method using it.It is a kind of to fall beam joist device for falling the concrete structure under the conditions of beam headroom deficiency, it is characterized in that:It includes the corbel (1) of the shape of a saddle, the outside of the both sides of the corbel (1) is fixedly installed the top plate (2) of one piece of jacking load respectively, and the top of every piece of top plate (2) is equipped with stiffened steel plates (3) and is fixedly connected with the side of the top plate (2) and corbel (1).The joist device of the present invention is when in use, works is held up in the bottom of works using joist device, and pass through joist device and the Lifting Equipments hard point such as jack is provided so that jack working space becomes larger, and ensures to can continue to carry out falling beam operation in the case that headroom is insufficient.Easy to operate, construction safety of the invention, it can be ensured that engineering construction safety and quality.

Description

Concrete structure falls beam joist device and falls beam construction method using it
Technical field
The present invention relates to a kind of concrete structures to fall beam joist device, more particularly to falls between beam works before in place Headroom is insufficient, can not normal construction when the joist device that uses, belong to technical field of bridge construction.It should the invention further relates to utilizing Joist device carries out the method for falling beam construction.
Background technology
Bridge falls beam construction and is widely used in all kinds of engineerings such as railway, highway, municipal administration.It (or is constructed in concrete structure Object) prestressed structure fall that beam is in place or works side position applies and moves beam work progress in place after tensioning using upper pour In, it will usually in place, influence the safety and matter of engineering because headroom is insufficient or other reasons lead to not normally between up-down structure object Amount.Especially realize that bridge is in place bridging equipment (such as Bridge Erector, large-scale hoisting machinery) can not be used, and scene is not It satisfies the requirements when realizing the molding concrete structure of cast-in-situ (or structures), or in existing bridge or similar structures body When maintaining (such as bearing replacement), construction operation difficulty is big, and security risk is high, and construction quality is difficult to ensure.
Invention content
For the above-mentioned problems in the prior art, the present invention provides one kind in headroom deficiency, construction operation Concrete structure under the conditions of narrow space falls beam joist device, using its construction safety, efficiently.
The technical solution adopted by the present invention to solve the technical problems is:It is a kind of mixed under the conditions of beam headroom deficiency for falling Xtah Crude Clay structure object falls beam joist device, it is characterized in that:It includes the corbel of the shape of a saddle, the outside point of the both sides of the corbel Be not fixedly installed the top plate of one piece of jacking load, the top of every piece of top plate be equipped with stiffened steel plates and the top plate and The side of corbel is fixedly connected.
Joist device in the present invention is when in use holding up concrete structure and provide the Lifting Equipments such as jack Hard point, wherein corbel is used to hold up concrete structure when in use, and the top plate of both sides is as jack jacking load Fulcrum.Stiffened steel plates are used for the intensity of Strengthening Roof.
The present invention also provides the methods for falling beam construction using above-mentioned joist device progress box beam, it is characterized in that:First press More solito falls beam construction method and fulcrum is arranged in box beam bottom using jack and box beam is fallen beam to because of headroom deficiency jack Can not normal operation height, the joist device then is installed in the corresponding position in the bottom of box beam, and ensure the beam of box beam Bottom and corbel are in close contact, in box beam bottom that box beam support pad is good using sleeper, then by original position in the jack of beam bottom move to Then the ceiling location of the both sides of joist device continues to fall using top plate as the new fulcrum of jack using jack Beam operation by box beam until drop down onto commitment positions.
The beneficial effects of the invention are as follows:The present invention utilizes the joist device of special construction design, in the insufficient condition of headroom Under, it can hold up works by joist device is arranged in structure bottom using joist device and the jackings such as jack be provided Equipment hard point makes fulcrum move to the both sides of joist device by the bottom of works by the position of the fulcrum of change jack, from And so that jack working space becomes larger, ensure to can continue to carry out falling beam operation in the case that headroom is insufficient.The present invention grasps Make simple, construction safety, and construction efficiency is high, can effectively solving the works under the confined conditions such as headroom deficiency, to fall beam difficult in place Topic, especially suitable for newly-built structure object it is upper it is cast-in-place, fall that beam is in place or the maintenance of the similar structures object such as existing bridge, Jacking when bearing replacement and beam operation is fallen, resource input is few, easy to operate, and method is practical, is easy to draw materials, it can be ensured that engineering Construction safety and quality.
Description of the drawings
Fig. 1 is the structural schematic diagram of the joist device in the specific embodiment of the invention;
Fig. 2 is the left view of Fig. 1;
Fig. 3 is the cooperation schematic diagram of joist device and box beam in the specific embodiment of the invention;
Fig. 4 is the side view of Fig. 3;
Fig. 5 is that box beam falls beam jack operation schematic diagram before in place in the specific embodiment of the invention;
Fig. 6 be in the specific embodiment of the invention box beam fall beam it is in place when jack operation schematic diagram;
1, corbel in figure, 2, top plate, 3, stiffened steel plates, 4, box beam, 5, joist device, 6, jack, 7, buttress, 8, steel pad Plate, 9, sleeper.
Specific implementation mode
Below by specific embodiment and in conjunction with attached drawing, the present invention is further illustrated:
It is as shown in the picture, a kind of to fall beam joist device for falling the concrete structure under the conditions of beam headroom deficiency, Corbel 1 including the shape of a saddle, is made by steel plate, and the outside of the both sides of the corbel 1 is fixedly installed one piece respectively The top plate 2 of load is jacked, the top of every piece of top plate 2 is equipped with the side of stiffened steel plates 3 and the top plate 2 and corbel 1 It is fixedly connected.To ensure the integral strength of device, corbel 1, top plate 2, stiffened steel plates 3 should have enough intensity and thickness, add Strength steel plate 3 should securely be welded with top plate 2 and corbel 1.
The method that box beam falls beam construction is carried out using above-mentioned joist device:First thousand are utilized according to the conventional beam construction method that falls After jin top 6 is arranged fulcrum in 4 bottom of box beam and box beam is fallen beam to certain altitude, because headroom deficiency jack can not normal operation When, the joist device 5 then is installed in the corresponding position in the bottom of box beam 4, and ensure beam bottom and 1 inside of corbel of box beam 4 Face is in close contact, and will be changed at the ceiling location of joist device 5 positioned at the former position of the fulcrum of beam bottom, using sleeper at box beam bottom Portion is good by box beam support pad, then moves to 2 position of top plate of the both sides of joist device original position in the jack of beam bottom, top plate is made For the new fulcrum of jack, start jack operation after ready, continues to fall beam operation until box beam is dropped down onto both Positioning is set, and is located on mounted bearing.
Other parts in the present embodiment use known technology, and details are not described herein.
The present invention can effectively solve the works under the confined conditions such as headroom deficiency and fall beam problem in place, easy to operate, side Just, construction safety, it can be ensured that engineering construction safety and quality.

Claims (2)

1. a kind of falling beam joist device for falling the concrete structure under the conditions of beam headroom deficiency, it is characterized in that:It includes The corbel (1) of the shape of a saddle, the outside of the both sides of the corbel (1) are fixedly installed the top plate of one piece of jacking load respectively (2), the top of every piece of top plate (2) is equipped with stiffened steel plates (3) and is fixed with the side of the top plate (2) and corbel (1) and connected It connects.
2. a kind of carrying out the method that box beam falls beam construction using joist device described in claim 1, it is characterized in that:First according to normal Rule fall beam construction method and fulcrum are arranged in box beam bottom using jack and box beam is fallen beam to because headroom deficiency jack can not Then the height of normal operation installs the joist device in the corresponding position in the bottom of box beam, and ensure the beam bottom of box beam with Corbel (1) medial surface is in close contact, in box beam bottom that box beam support pad is good using sleeper, then by original position in the jack of beam bottom It moves to the top plate of the both sides of joist device (2) position, using top plate as the new fulcrum of jack, then jack is utilized to continue It carries out falling beam operation until box beam is dropped down onto commitment positions.
CN201710014933.XA 2017-01-09 2017-01-09 Concrete structure falls beam joist device and falls beam construction method using it Active CN106758845B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710014933.XA CN106758845B (en) 2017-01-09 2017-01-09 Concrete structure falls beam joist device and falls beam construction method using it

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710014933.XA CN106758845B (en) 2017-01-09 2017-01-09 Concrete structure falls beam joist device and falls beam construction method using it

Publications (2)

Publication Number Publication Date
CN106758845A CN106758845A (en) 2017-05-31
CN106758845B true CN106758845B (en) 2018-08-17

Family

ID=58948584

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710014933.XA Active CN106758845B (en) 2017-01-09 2017-01-09 Concrete structure falls beam joist device and falls beam construction method using it

Country Status (1)

Country Link
CN (1) CN106758845B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112144327A (en) * 2019-06-28 2020-12-29 比亚迪股份有限公司 Track support assembly, assembly method thereof, track and track traffic system

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2617926Y (en) * 2003-05-16 2004-05-26 邹城市鲍矿大帅工贸有限公司 Joist of rockbolt
CN201990947U (en) * 2011-01-28 2011-09-28 龙建路桥股份有限公司 Overall bracket for capping beam
CN104343087B (en) * 2014-11-14 2016-01-27 山东恒堃机械有限公司 A kind of joist transporting device
CN106087757B (en) * 2016-08-01 2017-12-05 中铁十七局集团第三工程有限公司 A high position in box beam erection falls beam construction method
CN206408536U (en) * 2017-01-09 2017-08-15 中铁十局集团有限公司 For fall beam headroom it is not enough under the conditions of concrete structure fall beam joist device

Also Published As

Publication number Publication date
CN106758845A (en) 2017-05-31

Similar Documents

Publication Publication Date Title
CN106087757B (en) A high position in box beam erection falls beam construction method
CN201635410U (en) Temporary reinforcing device for concrete structure for bearing hoisting construction load
CN106758845B (en) Concrete structure falls beam joist device and falls beam construction method using it
CN206408536U (en) For fall beam headroom it is not enough under the conditions of concrete structure fall beam joist device
CN103952979A (en) Bracket-free construction device and construction method for steel-concrete superposed beam top plate
CN206800220U (en) One kind is used for across highway old bridge removal Fast Installation adjustable support
WO2024055709A1 (en) Transverse movement device for replacement of track beam anchor bolt
CN104818809B (en) Construction method for combined plate staircase
CN207862778U (en) Wedge shape drops bridle iron
CN201915420U (en) Foundation of temporary gate building
CN202298465U (en) Bridge jacking system
CN105480842B (en) Equipment support beam and its construction method are poured after one kind
TW201437457A (en) Jack stand for bridge lifting
CN202671575U (en) Converter lifting in-place protection pad device
CN202670986U (en) Safety lifting lug for lifting blast furnace downcomer
CN204212071U (en) A kind of pier stud anchor structure
CN208280154U (en) A kind of outdoor construction elevator strengthening of foundation device
CN105603883A (en) Bridge capping beam or tie beam formwork support adjusting device and application
CN205421021U (en) Integral hoisting roof beam sand box that falls
CN218884931U (en) Head sheave aligning device
CN205116211U (en) Be applied to construction elevator base apparatus that basement roof subsides post -cast strip department
CN104818730A (en) Equipment base top embedded part and mounting method thereof
CN202688903U (en) Cast-in-situ beam false work dismantling device
CN216949557U (en) Secondary structure concrete member pours device
CN218438418U (en) Preformed hole plugging device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant