CN104818809B - Construction method for combined plate staircase - Google Patents
Construction method for combined plate staircase Download PDFInfo
- Publication number
- CN104818809B CN104818809B CN201510178530.XA CN201510178530A CN104818809B CN 104818809 B CN104818809 B CN 104818809B CN 201510178530 A CN201510178530 A CN 201510178530A CN 104818809 B CN104818809 B CN 104818809B
- Authority
- CN
- China
- Prior art keywords
- template
- stair
- time
- plate
- marking time
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Abstract
The invention relates to a construction method for a combined plate staircase. The construction method comprises the following steps that: a corresponding number of steel templates with the corresponding dimensions are manufactured according to the dimension of the staircase, wherein the steel templates comprise a bottom integral steel plate (1), middle standard pedaling templates (2) with the same number as the staircase steps, an upper pedaling template (3) and a lower pedaling template (4); the bottom integral steel plate (1) is manufactured according to the dimension of the staircase; the two ends of the bottom integral steel plate are bent; the bent upper end is used for being connected with an upper platform plate, and the bent lower end is used for being connected with a lower platform plate; the length of the bent upper end is identical to the width of the upper pedaling template (3), and the length of the bent lower end is identical to the width of the lower pedaling template (4); the staircase template is installed; a hoisting ring (6) is fixed; hanging to proper positions are performed, the upper pedaling template (3) is fixed on an upper platform beam through screw bolts, and the lower pedaling template (4) is fixed on a lower platform beam through screw bolts; and concrete is cast. The construction method has the advantages that the staircase construction operation can be simple; the staircase quality is improved; and the cost is reduced.
Description
Art
The invention belongs to building engineering field, and in particular to a kind of stair construction method.
Background technology
Stair are the vertical transportation facilities in building, its quality for it is normal use and emergency case process have to
Close important effect.At present stair are generally dissipated using wooden template and spell construction, and formwork rigidity stability is poor, Jing often occur race mould,
The phenomenons such as displacement, affect construction quality;And the formwork time is long, installation and removal inconvenience may make when concrete strength is inadequate
Into destruction, construction is complicated, and efficiency is low;It is less that plank sheathing makes material source, welding and relatively costly.Therefore, wooden template is used
The method that scattered spelling carries out stair construction has much room for improvement.
The content of the invention
The present invention provides a kind of stair construction method to solve the above-mentioned problems in the prior art.This can make
Obtain stair constructing operation simply and stair quality and reduces cost can be improved.The technical solution used in the present invention is:
A kind of construction method of compoboard stair, comprises the following steps:
1) size of stair is determined, main width including stair, length, step number of marking time, the width marked time.
2) steel form of corresponding size and quantity is made, including bottom integral plate (1), stair exponent number Central Standard are stepped on
Step template (2), template (3) of marking time on, template (4) of marking time under;The bottom overall steel is made according to stair size
Plate (1), the bottom integral plate two ends bending, the upper end after bending is used to be connected with upper mounting plate plate, and lower end is used for flat with lower
Platen is connected, the top and bottom length after bending respectively with mark time the width phase of template (4) under template of above marking time (3) and one
When;
3) stair template is installed:Each adjacent Central Standard is marked time between template (2), Central Standard template (2) with
Be fixedly connected between the bottom integral plate (1), template of marking time by (3) and under mark time template (4) respectively with it is corresponding in
Ministerial standard template (2) of marking time is fixedly connected;The mark time both sides of template (2) of each Central Standard are right-angled trapezium, and trapezoidal is oblique
The slope on side is consistent with stair slope, and the slope of bottom integral plate (1) is consistent with stair slope;
4) guarantee stair template during lifting can fixed hoisting ring (6) in place of held stationary, lift by crane ring diameter
Lifting load requirement must be met.
5) the stair template lifting for connecting step (3) is in place, template of above marking time (3) and under mark time template (4) and bottom
The anchor hole of portion integral plate junction should reserve anchor hole aligned in position with upper mounting plate beam and lower platform beam respectively, use crab-bolt
Template of marking time by (3) and under template (4) of marking time be separately fixed on upper mounting plate beam and lower platform beam, cut away after the completion of lifting
Suspension ring;
6) casting concrete:Mark time template penetration concrete from the intermediate standard of stair template the top, upper level is marked time
After template is poured completely, under gravity, concrete automatically flows into next stage and marks time in template, until whole stair template is poured
Till full.
The present invention has the advantages and positive effects that:
(1) punching block panel stiffness stability is strong, and concrete is unlikely to deform, and presentation quality is good, it is ensured that construction quality;
(2) steel form can be mounted directly in place, simple to operate without the need for dismounting, saving work as permanent formwork during construction
When, construction safety;
(3) timber, environmental protection are saved;
(4) steel form and concrete can bond integral cooperation, so as to effectively increase the bearing capacity of stair.
Description of the drawings
Fig. 1 is the structural representation of this combined staircase;
Fig. 2 is that standard is marked time template schematic diagram;
Fig. 3 is template schematic diagram of marking time up and down;
In figure:1- integral plates, 2- standards mark time mark time on template, 3- mark time under template, 4- template, 5a, high-strength bolt,
5b- crab-bolts, 6- hoisting rings, 7- bolts hole, 8- anchor holes.
Specific embodiment
Embodiments of the invention are described in detail below in conjunction with the accompanying drawings.
Referring to Fig. 1, the stair process of the present invention is as follows:
(1) size of stair is measured and is checked, main width including stair, length, step number of marking time, marked time
Width etc..
(2) template is made.According to data make corresponding size and the steel form of quantity, the steel form includes integral plate
1st, stair exponent number Central Standard being marked time template 4, high-strength bolt 5a, the crab-bolt of mark time under template 3, of mark time in template 2,
5b and hoisting ring 6.
Template concrete construction method is as follows:
First the bottom integral plate 1 is made according to stair size, the integral plate two ends are marked time up and down template width
Degree carries out bending at position, and bending angle is consistent with the slope of stairs, and in the bolt position being connected with the template 2,3,4 of marking time
Open bolt hole in place;
Make respectively the standard mark time template 2, on mark time template 3 and under mark time template 4, and open spiral shell in relevant position
Keyhole, as shown in Figures 2 and 3;
To be connected with the high-strength bolt 5a between the standard form 2, between standard form 2 and the bottom steel plate 1,
The template 3,4 of marking time up and down is connected respectively with the standard form 2, is now not connected to mark time up and down template 3,4 and bottom steel
Plate 1;
Hoisting ring 6 is welded in relevant position, lifting ring diameter must meet lifting load requirement, and welding position must carry out moment of flexure
Mechanics Calculation, it is ensured that stair template being capable of held stationary during lifting.
(3) installation form.Steel form is lifted it is in place, template of marking time up and down and the anchor hole of steel plate junction should with it is upper and lower
Anchor hole aligned in position is reserved on landing beam, template of marking time up and down is separately fixed on upper and lower landing beam with crab-bolt 5b, lifted
After the completion of cut away hoisting ring.Note fitting stair step absolute altitude, original position and levelness in model sheetinstallat work progress
When adjustment.
(4) casting concrete.From the template penetration concrete of marking time of stair template the top, upper level template of marking time is poured
Man Hou, under gravity, concrete automatically flows into next stage and marks time in template, till whole steel form is poured completely.Pour
After the completion of building, concrete surface is automatically smooth, and outward appearance is good.
(5) concrete curing.Note the destruction artificial to concrete, until can normally use, without the need for dismantling template, steel
Template is stayed in stair as permanent template, the arrangement of reinforcement in the steel plate of concrete base can replace concrete, is effectively improved
The bearing capacity of concrete.
The present invention has the advantages and positive effects that:Punching block panel stiffness stability is strong, and concrete is unlikely to deform, outward appearance matter
Measure, it is ensured that construction quality;Steel form can be mounted directly as permanent formwork, during construction it is in place, without the need for dismounting, operation letter
It is single, save man-hour, construction safety;Save timber, environmental protection;Steel form and concrete can bond integral cooperation,
So as to effectively increase the bearing capacity of stair.
Although being described to the preferred embodiments of the present invention above in conjunction with accompanying drawing, the invention is not limited in
The specific embodiment stated, above-mentioned specific embodiment is only schematic, be not it is restricted, this area it is common
Technical staff in the case of without departing from present inventive concept and scope of the claimed protection, may be used also under the enlightenment of the present invention
To make many forms, these are belonged within protection scope of the present invention.
Claims (1)
1. a kind of construction method of compoboard stair, comprises the following steps:
1) size of stair is determined, main width including stair, length, step number of marking time, the width marked time;
2) steel form of corresponding size and quantity is made, including bottom integral plate (1), stair exponent number Central Standard are marked time mould
Plate (2), template (3) of marking time on, template (4) of marking time under;The bottom integral plate is made according to stair size
(1), the bottom integral plate two ends bending, the upper end after bending is used to be connected with upper mounting plate plate, and lower end is used for and lower platform
Plate is connected, the top and bottom length after bending respectively with mark time the width phase of template (4) under template of above marking time (3) and one
When;
3) stair template is installed:Each adjacent Central Standard is marked time between template (2), Central Standard mark time template (2) with
Be fixedly connected between the bottom integral plate (1), template of marking time by (3) and under mark time template (4) respectively with it is corresponding in
Ministerial standard template (2) of marking time is fixedly connected;The mark time both sides of template (2) of each Central Standard are right-angled trapezium, and trapezoidal is oblique
The slope on side is consistent with stair slope, and the slope of bottom integral plate (1) is consistent with stair slope;
4) guarantee stair template during lifting can fixed hoisting ring (6) in place of held stationary, lifting ring diameter must expire
Foot lifting load requirement;
5) the stair template lifting for connecting step (3) is in place, template of above marking time (3) and under template (4) of marking time it is whole with bottom
The anchor hole of body steel plate junction should reserve anchor hole aligned in position with upper mounting plate beam and lower platform beam respectively, will be upper with crab-bolt
Template of marking time (3) and under template (4) of marking time be separately fixed on upper mounting plate beam and lower platform beam, lifting is cut away after the completion of lifting
Ring;
6) casting concrete:Mark time template penetration concrete from the Central Standard of stair template the top, upper level is marked time template
After pouring completely, under gravity, concrete automatically flows into next stage and marks time in template, until whole stair template pours and is completely
Only.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510178530.XA CN104818809B (en) | 2015-04-15 | 2015-04-15 | Construction method for combined plate staircase |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510178530.XA CN104818809B (en) | 2015-04-15 | 2015-04-15 | Construction method for combined plate staircase |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104818809A CN104818809A (en) | 2015-08-05 |
CN104818809B true CN104818809B (en) | 2017-04-19 |
Family
ID=53729270
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510178530.XA Expired - Fee Related CN104818809B (en) | 2015-04-15 | 2015-04-15 | Construction method for combined plate staircase |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104818809B (en) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108505747A (en) * | 2017-02-27 | 2018-09-07 | 五冶集团上海有限公司 | A kind of stair concreting steel form |
CN107283606A (en) * | 2017-08-22 | 2017-10-24 | 程丹松 | Stair pour mould and stair |
CN109763647A (en) * | 2019-03-13 | 2019-05-17 | 中国五冶集团有限公司 | Adjustable entirety stair tread formwork and construction method |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2345624Y (en) * | 1998-12-01 | 1999-10-27 | 黑龙江省第一建筑工程公司 | Shaping formwork for cast-in-place concrete stairs |
CN102251664A (en) * | 2011-04-26 | 2011-11-23 | 湖南省沙坪建筑有限公司 | One-time forming construction method for cast-in-place stair tread template |
CN202220439U (en) * | 2011-08-26 | 2012-05-16 | 河南省大成建设工程有限公司 | Combined steel template of integral stair plate |
CN102747837A (en) * | 2012-07-06 | 2012-10-24 | 中国十七冶集团有限公司 | Cleaning method for cast-in-place reinforced concrete stair segment timber template |
CN103195215A (en) * | 2013-04-11 | 2013-07-10 | 北京工业大学 | Reinforced concrete stringer stairway with slidable end structures and method for constructing reinforced concrete stringer stairway |
JP5378877B2 (en) * | 2009-05-20 | 2013-12-25 | 寛 石川 | Steel frame stair tread manufacturing method |
CN103669840A (en) * | 2013-11-29 | 2014-03-26 | 重庆智锐德科技有限公司 | Stair tread for building construction reinforcement |
-
2015
- 2015-04-15 CN CN201510178530.XA patent/CN104818809B/en not_active Expired - Fee Related
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2345624Y (en) * | 1998-12-01 | 1999-10-27 | 黑龙江省第一建筑工程公司 | Shaping formwork for cast-in-place concrete stairs |
JP5378877B2 (en) * | 2009-05-20 | 2013-12-25 | 寛 石川 | Steel frame stair tread manufacturing method |
CN102251664A (en) * | 2011-04-26 | 2011-11-23 | 湖南省沙坪建筑有限公司 | One-time forming construction method for cast-in-place stair tread template |
CN202220439U (en) * | 2011-08-26 | 2012-05-16 | 河南省大成建设工程有限公司 | Combined steel template of integral stair plate |
CN102747837A (en) * | 2012-07-06 | 2012-10-24 | 中国十七冶集团有限公司 | Cleaning method for cast-in-place reinforced concrete stair segment timber template |
CN103195215A (en) * | 2013-04-11 | 2013-07-10 | 北京工业大学 | Reinforced concrete stringer stairway with slidable end structures and method for constructing reinforced concrete stringer stairway |
CN103669840A (en) * | 2013-11-29 | 2014-03-26 | 重庆智锐德科技有限公司 | Stair tread for building construction reinforcement |
Also Published As
Publication number | Publication date |
---|---|
CN104818809A (en) | 2015-08-05 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103938796B (en) | Cast-in-situ reinforced concrete column construction | |
CN104141383B (en) | A kind of Bailey beam pendent form support system and construction thereof | |
CN204266590U (en) | Sump, hoistway formwork bed die anti-floating system | |
CN104818809B (en) | Construction method for combined plate staircase | |
CN109025291A (en) | A kind of construction method of separate type precast stair | |
CN105464216B (en) | Construction method based on integral lifting formwork-strengthening system superelevation super-section batter post | |
CN205476467U (en) | Prefabricated steel stair template with adjustable | |
CN107806019A (en) | Large-span suspension bridge gate Sarasota construction method | |
CN105804395A (en) | Staircase one-step continuous casting forming construction method based on integral shaped formwork | |
CN102900024A (en) | Overturning die plate for large-scale concrete structure and using method for overturning die plate | |
CN201738250U (en) | Arch culvert and arch ring steel die trolley | |
CN202064281U (en) | Slip form frame | |
CN109025275A (en) | A kind of shear wall side regularization stair punching block and installation method | |
CN208456122U (en) | A kind of stair, which pour, uses steel form | |
CN104499706A (en) | Elevator well template platform and construction method thereof | |
CN111663455A (en) | Trackless light hydraulic creeping formwork | |
CN206189607U (en) | Rag bolt location structure | |
CN216551573U (en) | Built-in steel tower column splicing construction assembly structure | |
CN203113515U (en) | Slip form jacking integrated device | |
CN105480842B (en) | Equipment support beam and its construction method are poured after one kind | |
CN205742982U (en) | A kind of printing opacity template for building | |
CN212359061U (en) | PC staircase safety protection operation platform | |
CN205314539U (en) | Large -scale cantilever type combination steel form | |
CN114856195A (en) | Post-pouring construction method for floor slab at building pipe well | |
CN212836352U (en) | Be applicable to subway station Z type stair structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
EXSB | Decision made by sipo to initiate substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CP02 | Change in the address of a patent holder | ||
CP02 | Change in the address of a patent holder |
Address after: 300350 District, Jinnan District, Tianjin Haihe Education Park, 135 beautiful road, Beiyang campus of Tianjin University Patentee after: Tianjin University Address before: 300072 Tianjin City, Nankai District Wei Jin Road No. 92 Patentee before: Tianjin University |
|
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20170419 Termination date: 20210415 |