Disclosure of Invention
The invention provides an intelligent power distribution network engineering auxiliary management system which can automatically coordinate various links such as planning, material, setting value, automatic point table, warehouse debugging, testing, data management and the like.
The technical scheme adopted by the invention is as follows:
an engineering auxiliary management system for an intelligent power distribution network comprises:
the plan management module is used for dividing the intelligent power distribution network project total plan into a plurality of sub projects according to regions and lines, then refining the sub projects into sub projects, wherein the sub projects are divided according to power failure at the same time in principle, and finally are embodied to a single executable installation site;
the material module is used for realizing material management by taking the equipment installation site and the double names of the equipment as root directories, establishing a material in-out management flow, having a material complete set combination function and a warehouse material positioning function;
the test module is used for realizing the test plan management and the test report management of the warehouse material equipment;
the relay protection constant value management module is used for setting fixed value network-hanging release, execution, acceptance and filing processes, and related personnel have respective authority;
the automatic point table management module is used for formulating point table formulation, point table audit, on-site check, acceptance check and filing processes, and related personnel have respective authority;
and the field operation module is used for field investigation, uploading of field investigation records, power failure, field operation, uploading of standardized operation process cards, field acceptance, uploading of field acceptance records and field completion.
The plan management module comprises a plan basic interface, plan attributes, a plan flow and an intelligent alarm;
the plan basic interface comprises a graphic interface and a menu interface, and the graphic takes a geographic map as a base map to display progress and plan; the plan attributes include:
a. and (3) overall planning: completing progress display, completing installation site plan, completing project plan of subsection, and making plan display; importing a geographical location map; correspondingly displaying; the visual management of project plan and progress is realized;
b. the branch project plan, the limiting factor: warehousing materials, testing and debugging, testing reports, setting values and counting tables;
c. project planning, restriction factors: warehousing materials, testing and debugging, testing reports, setting values and counting tables;
d. installation site planning, limiting factors: whether power is off or not, power off numbering, material warehousing, test debugging, test report, value setting and table counting;
the intelligent warning comprises:
a. distinguishing colors;
b. the same power failure numbering equipment of the same project is scheduled at the same time, if the power failure numbering equipment is scheduled respectively, the power failure is regarded as repeated power failure, and automatic statistics is carried out;
c. in the same project, when only 1/3 plans to be impossible, the system should automatically perform a pop-up window early warning and find out the reason for the impossibility.
The material module includes:
1) establishing a menu:
the method comprises the following steps of sequentially improving the subsequent processes after warehousing, namely, a serial number, a material name, an installation place, an equipment double name, a unique serial number, a subsection project, a material model, a unit, a manufacturer, a use quantity, a goods quantity and remarks, wherein the basic machine account is formed by the serial number, the material name, the installation place, the equipment double name, the unique serial number and the remarks;
2) inputting all equipment data:
inputting all materials according to the menu content to form a basic library;
3) and equipment flow:
setting the process as no storage and distinguishing colors; warehousing: color distinction, increased equipment storage places and import accessories; testing and debugging: distinguishing colors; and (3) completing test debugging: the color is distinguished and the storage place of the equipment is increased, and accessories can be introduced; and (4) a delivery area: color distinguishing, equipment storage places, test reports, factory information and factory equipment numbers are added, and accessories can be imported; shipment and field installation power transmission;
4) and (4) intelligent warning:
a. after equipment is put in storage at the same installation place or only 1 piece of equipment is not in stock, the system can remind through a popup window or remind after a button is pressed. Reminding the user to schedule or urge a good;
b, when equipment in the same installation site is debugged or only 1 piece of equipment is not debugged, the system can remind through a popup window or remind after a button, and can schedule or urge goods;
and C, after the same project equipment is put in storage or only 1 installation site equipment is not in stock, the system can remind through a popup window or remind through a button. Reminding the user to schedule or urge a good;
d, when the same project equipment is debugged or only 1 piece of equipment is not debugged, the system can remind through a popup window or after a button is pressed. Reminding the user to schedule or urge a good;
e, after the same subsection engineering equipment is put in storage or only 1 subsection engineering equipment is not in stock, the system can remind through a popup window or remind after a button is pressed. Reminding the user to schedule or urge a good;
f, when the same subsection engineering equipment is debugged or only 1 subsection engineering equipment is not debugged, the system can remind through a popup window or after a button is pressed. Reminding the user to schedule or urge a good;
g, color discrimination: warehousing, testing, planning, ex-warehouse and data;
h, automatically subtracting the using quantity from the inventory quantity of a certain installation site after scheduling;
i, reserving a two-dimension code menu;
j adds the purchasing date and purchasing basis of material purchasing (yes and no);
k replacement of materials, and replacement of the materials with other types of equipment when the materials are not delivered.
The test module comprises:
1) establishing a menu:
the method comprises the following steps of (1) equipment installation place, subsection project, equipment model, manufacturer, fixed value, test report and point table;
2) test week planning and week completion;
3) reporting an auditing process, editing, uploading, sending to an auditor, passing or returning the signature of the auditor, and sending to an installation department;
the test plan flow comprises the following steps:
the relay protection constant value management module comprises:
1) catalog: the installation place of the equipment, the model number of the secondary equipment, the version number and the fixed value list;
2) the process comprises the following steps: fixed value screening and publishing, fixed value execution, fixed value acceptance and verification and fixed value filing;
the automatic point list management module comprises:
1) catalog: the installation place of the equipment, the model number of the secondary equipment, the version number and the point table;
2) the process comprises the following steps: point table formulation, point table audit, point table check, point table acceptance check and point table filing;
the invention discloses an auxiliary management system for intelligent power distribution network engineering, which has the advantages that:
1: the invention decomposes the whole construction plan of the intelligent power distribution network project into partial projects and project projects for management, the implementation scheme is regionalized and modularized, and the power failure plan is formulated for regionalized management, thereby realizing scientific plan formulation and rigid plan implementation. The labor cost and the management cost are reduced.
2: according to the intelligent power distribution network engineering material management system, the intelligent power distribution network engineering material management is innovatively managed by using a material complete set method, all equipment and matched materials needing to be installed in the site are uniformly numbered and managed by taking the equipment installation site as a unit according to the characteristics of multiple distribution network equipment, multiple models, multiple manufacturers, inconsistent arrival periods and the like, the equipment is subjected to ordering, warehousing, testing, debugging and ex-warehouse standard management, intelligent urging for goods is realized, and the conditions of equipment disordering, material mismatching and the like are avoided. Standardize material management level, reduced artifical labour cost and administrative cost.
3: the intelligent power distribution network engineering is innovatively used for warehouse tests, the system is used for standardizing test plans, test flows, test report archiving and the like, the test flows are standardized, and the manual labor cost and the management cost are reduced.
4: the invention standardizes the constant value management and the point table management of the intelligent power distribution network, standardizes the flow, improves the data management level and reduces the labor cost and the management cost.
5: the invention has the function of basic database management. Data can be imported and exported in batches according to a fixed template, documents such as EXCEL, WORD, PDF, pictures and the like can be imported, machine accounts such as relay protection fixed values, automatic point table management machine accounts, subsection project area diagrams and the like are established, and meanwhile systematic management of project data is achieved.
Detailed Description
The utility model provides a supplementary management system of intelligent power distribution network engineering, explains with the intelligent power distribution network engineering in the fulminant urban district of xiao nationality as an example:
1. a plan management module: the method is characterized in that the demonstration engineering characteristics of the intelligent power distribution network are combined, a power distribution network engineering general plan is divided into 40 sub-projects according to regions and lines, the sub-projects are refined into sub-projects, the sub-projects are divided according to simultaneous power failure in principle, and finally the sub-projects are specifically arranged in a single executable installation place. The combined part of the engineering work is too large, and the part of unimportant users have power failure for 2 times.
1) The plan basis interface, the sub-graphical interface and the menu interface, the menu is shown in fig. 1.
2) The attributes are as follows:
a. and (4) overall planning. The regional overall project is firstly decomposed, the project is divided into a plurality of sub projects according to lines and geographical regions, and then the sub projects are decomposed into sub projects according to the conditions of power failure and uninterrupted power supply. And all the branch projects and the project projects are used as basic data input systems.
And the project plan and progress visualization are realized. Firstly, the geographical map is taken as a base map, then installation places in the branch projects and the project are associated with the geographical map, and the unplanned projects, the generated projects and the completed projects are marked by different colors respectively, so that the progress and plan display is realized, and the effect of visualizing the project progress is achieved.
b. And (5) branch engineering planning. The negative link of the generation and formulation of the project plan of the subsection mainly comprises that all materials of the project of the subsection are not put in storage and are not delivered, a warehouse debugging test is not carried out after the materials are delivered, the debugging is unqualified or no test report is given after the debugging, a terminal equipment fixed value list issued by scheduling is not available, an automatic point table which is checked is not available, and the site survey or the site survey before the equipment is installed is not in accordance with the design.
c. And (5) project planning. The negative link of the generation and formulation of the project plan mainly comprises that all materials of the project are not put in storage and are not delivered, after the materials are delivered, warehouse debugging tests are not carried out, after debugging, debugging is unqualified or no test report is provided, terminal equipment fixed value lists issued by scheduling are not provided, an automatic point list is not checked, and field investigation or field investigation and design are not met before equipment installation is not carried out.
d. And planning an installation site. The negative link of plan generation and formulation of the installation site mainly comprises that all materials in the installation site are not put in storage or are not delivered, a warehouse debugging test is not carried out after the materials are delivered, unqualified debugging or no test report is carried out after debugging, a terminal equipment fixed value list issued by scheduling is not available, an automatic point table which is checked is not available, and field investigation or field investigation and design are not met before equipment installation is not carried out.
3) Planning the flow, as shown in fig. 2.
A plan generation flow:
a. and all the branch projects and the project projects are used as basic data input systems.
b. And when all the generation plan conditions of a certain installation site are met, namely no generation plan rejection condition exists, the plan of the installation site meets the generation conditions. And when the plan of the installation site is implemented, the plan is automatically closed and the installation site is filed completely.
c. And when all installation sites in a certain project meet the generation plan condition, the project plan meets the generation condition. And when the project plan is finished, the project plan is automatically closed and the project plan is filed completely.
d. And when all the project items in a certain project item meet the generation plan condition, the project item plan meets the generation condition. And when the project plan is finished, the project plan is automatically closed and the project plan is filed completely.
Planning a negative link:
a. when any rejection link exists in a certain installation place, the plan of the installation place does not meet the generation condition. The negative link mainly comprises that all materials in the installation site are not put in storage and are not delivered, a warehouse debugging test is not carried out after the materials are delivered, a unqualified debugging or no test report is carried out after the debugging, a terminal equipment fixed value list issued by scheduling is not available, an automatic point table which is checked is not available, and field investigation or field investigation and design before the equipment is installed are not met.
b. And when any installation site in a certain project does not meet the plan generation condition, the project does not meet the plan generation condition.
c. And when any project in a certain subsection does not meet the plan generation condition, the subsection does not meet the plan generation condition.
4) And (4) intelligent warning:
a. and (5) color discrimination. The method is used for distinguishing plans in all installation places, project divisions and project divisions from plans in which the generation conditions are met, the generation conditions are not met, the plans are in execution and the finished plans are in different colors, and has a retrieval function.
b. The same power failure numbering equipment in the same project is scheduled at the same time, if the power failure numbering equipment is scheduled respectively, the power failure is regarded as repeated power failure, and automatic statistics is carried out.
c. In the same project, when only 1/3 plans to be impossible, the system should automatically perform a pop-up window early warning and find out the reason for the impossibility.
2. The material module: the system realizes material management by taking the double names of equipment installation places and equipment as root directories, establishes a material warehousing and ex-warehouse management process, has a complete material combination function, and has a warehouse material positioning function.
1) Establishing a menu:
the system comprises a serial number, a material name, an installation place, an equipment double name, a unique number, a subsection project, a material model, a unit (platform, individual type), a manufacturer, a use quantity, a goods quantity and remarks, wherein the serial number, the material name, the installation place, the equipment double name, the unique number, the subsection project, the material model, the unit (platform, individual type), the manufacturer, the. And other subsequent processes after warehousing are successively improved.
2) Input all device data:
and inputting all materials according to the menu content to form a basic library.
3) The equipment flow comprises the following steps:
the process is set as non-warehousing (color differentiation), warehousing (color differentiation, equipment storage places increase and accessories can be introduced), test debugging (color differentiation), test debugging completion (color differentiation increases and accessories can be introduced), a delivery area (color differentiation, equipment storage places increase, test reports, delivery data, equipment delivery serial numbers can be introduced, accessories can be introduced), delivery and field installation power transmission.
4) And (4) intelligent warning:
and a, after equipment is put in storage at the same installation place or only 1 piece of equipment is not in stock, the system can remind through a popup window or remind after a button is pressed. The reminder may schedule or urge the shipment.
b, when the equipment in the same installation place is debugged or only 1 piece of equipment is not debugged, the system can remind through a popup window or after a button is pressed. The reminder may schedule or urge the shipment.
And C, after the same project equipment is put in storage or only 1 installation site equipment is not in stock, the system can remind through a popup window or remind through a button. The reminder may schedule or urge the shipment.
d, when the same project equipment is debugged or only 1 piece of equipment is not debugged, the system can remind through a popup window or after a button is pressed. The reminder may schedule or urge the shipment.
e, after the same subsection engineering equipment is put in storage or only 1 subsection engineering equipment is not in stock, the system can remind through a popup window or remind after a button is pressed. The reminder may schedule or urge the shipment.
f, when the same subsection engineering equipment is debugged or only 1 subsection engineering equipment is not debugged, the system can remind through a popup window or after a button is pressed. The reminder may schedule or urge the shipment.
g color differentiation (warehousing, testing, scheduling, ex-warehouse, data).
h the stock quantity of a certain installation site is automatically subtracted by the use quantity after scheduling.
And i, reserving a two-dimension code menu.
j adds the purchasing date and purchasing basis of material purchasing (yes and no).
k replacement of materials, and replacement of the materials with other types of equipment when the materials are not delivered.
3. Test module
1) Establishing a menu:
firstly, the equipment and materials which are put in storage are taken as basic data, then the equipment which is put in storage is classified into the equipment which needs to be tested and the equipment which does not need to be tested, and the equipment or materials which need to be tested automatically generate a test standing book. The test ledger also needs to set catalogs such as test equipment model, equipment manufacturer, test date, equipment number, whether qualified, test report uploading and the like.
2) Test procedure
And selecting automatically generated equipment or materials with a formulated test plan according to the general primary plan of the monthly project to generate a test week plan. And debugging test work is carried out by the test group according to the test plan, after the test is qualified, a test report is compiled, after the qualified process is passed, the test is completed, and the equipment is brought into tested equipment. This type of equipment is tested within the engineering planning process to overrule condition exclusions.
The test plan flow comprises the following steps:
3) and reporting the audit process, wherein after the test report editor edits the test report, the test report is uploaded to the system, enters the test report process and is sent to the test report auditor, and after the audit is qualified, the signature passes and is sent to the equipment installation department to form data archiving.
4. the relay protection constant value management module:
1) establishing a menu:
and formulating a relay protection fixed value management module menu according to all equipment installation sites in the general project, wherein the menu comprises equipment double names, equipment installation sites, terminal models, terminal versions, fixed value single numbers, setting dates, execution dates and the like.
2) A fixed value planning process: and the fixed value setting personnel perform fixed value setting on all equipment in the schedule by the relay protection fixed value setting personnel according to the general primary schedule of the monthly project, and after the setting is uploaded, the equipment which has finished the fixed value setting is excluded from the set negative condition in the project schedule flow.
3) A fixed value process:
after the relay protection constant value setting personnel complete setting, the relay protection constant value setting personnel uploads the set value to the system, enters a constant value process, sends the set value to a constant value auditor, passes the signature after the audit is qualified, sends the signature to a constant value executive personnel, and jointly checks and accepts with operating personnel after the execution is completed to form data filing.
5. The automatic point table management module:
1) establishing a menu:
and formulating an automatic point table management module menu according to all equipment installation places in the general project, wherein the menu comprises equipment double names, equipment installation places, terminal models, terminal versions, point table numbers, formulated dates, checked dates and the like.
2) And (3) dot table planning flow: and the automatic point table customizing personnel performs point table customizing on all equipment in the plan according to the general primary plan of the monthly project, and after the point table customizing is uploaded, the rejection of the point table rejection conditions of the equipment which finishes the point table customizing in the project plan flow is performed.
3) And (4) point list flow:
after the automatic order list customizing personnel formulate an order list, the order list is uploaded to a system and enters an order list process and is sent to an order list auditor, after the audit is qualified, the signature passes and is sent to an automatic order list checking personnel, and after the execution is finished, the automatic order list customizing personnel check and accept with operating personnel together to form data filing.
6. A field operation module:
1) establishing a menu:
and formulating a field installation menu according to all equipment installation sites in the general project, wherein the menu comprises equipment double names, equipment installation sites, field survey plan uploading, field standardized operation instruction card uploading, field start time, acceptance check, field completion time and filing.
2) And (3) field installation planning process: the on-site survey plan is carried out according to the general primary plan of the lunar project, on-site survey personnel carry out on-site survey on all equipment in the plan, and after on-site survey records or pictures are uploaded, the on-site survey is finished and qualified equipment is rejected in the on-site survey in the project plan flow.
3) And (3) field flow:
after the on-site investigation is finished, uploading the data to a system, after a concrete project plan is made, starting the work on the site, uploading a standardized operation guide card, after the on-site implementation is finished, after the acceptance is qualified, finishing the on-site completion and filing, and simultaneously finishing the project plan.
The intelligent power distribution network engineering auxiliary management system realizes intelligent management of project division of the intelligent power distribution network, complete management of materials and materials, test flow management and data systematization management. The management level is improved, and the labor cost and the management cost are reduced. It has the following characteristics:
(1) the system is not limited to material management, plan management, project management or operation and maintenance management, and is guided to solve the problem in the implementation process of the intelligent power distribution network project, and the system spans distribution network material, plan, project and operation and maintenance management.
(2) The project progress display system is clear by taking the plan management module as a core. The system takes a plan management module as a core, and a material module, a test module, a fixed value module, a point table module and a field installation module are built around the plan management module, so that the implementation of a plan is restricted, and the independence of the modules is not lost.
(3) According to the particularity of power distribution network engineering, the problems of more materials, more types, more manufacturers, long supply period and the like, a material complete management method is initiatively adopted, all equipment and materials in the site are uniquely numbered by taking an equipment installation site as a unit, and unique numbering management is started from equipment warehouse-out. Avoid the situations of incomplete equipment and materials, disorder, fire protection and the like.
(4) According to the general plan of the regional project, the project is divided into a plurality of sub projects, the sub projects are divided according to the principle of the transmission line and the region, the sub projects are divided into sub projects according to the power failure time and the power failure range, and the sub projects comprise a plurality of equipment installation places. And the project plan, progress visualization and graphic display are realized.
(5) The full-data engineering equipment material module overcomes the long-term offline manual recording defect, and is convenient for real-time data sharing and warehouse entry and exit process management.
(6) All module functions are expressed in a list form, related contents can be searched and counted according to specified fields, and the searching is convenient and visual.
(7) The personalized warning function design has a material reminding function, the complete set of materials is automatically combined, color reminding and window reminding are carried out, the rationality and the performability of plan making are ensured, and the equipment of a manufacturer can be purposefully promoted to arrive according to a reminding window.
(8) Historical records of the data editing process can be checked, and responsibility tracing is achieved. Most data are filled in by adopting a pull-down menu with a limited range, so that the data can be conveniently input, and meanwhile, the data normalization can be ensured.
(9) Possesses basic database management function. Data can be imported and exported in batches according to a fixed template, documents such as EXCEL, WORD, PDF, pictures and the like can be imported, machine accounts such as relay protection fixed values, automatic point table management machine accounts, subsection project area diagrams and the like are established, and meanwhile systematic management of project data is achieved.
Taking the data management of the installation place of the breaker on one column of the intelligent power distribution network project as an example to calculate:
1. the total time consumption of work is shortened:
taking the filial sensation intelligent power distribution network engineering as an example, according to measurement and calculation, the installation site of a pole-mounted circuit breaker has about 15 types of equipment and materials, the cleaning of the complete equipment and material delivery data needs 3 hours for sorting and printing, the matching of test data needs 3 hours, and the matching of fixed value and point table and other data (the matching of fixed value fixed member and point table maker) needs 3 hours and 9 hours. After the system is used, the data is managed systematically and uniformly, and the total time of arranging the data, printing the data, collecting the data and packaging the data is 3 hours. Greatly shortening the data sorting time.
2. Labor cost expenditure is saved:
the data sorting work generally needs 2 data workers, 1 debugger, 1 constant value setter and 1 automatic point table maker. After the method is implemented, only 1 data worker is needed, the calculation is carried out according to the labor cost of 100 yuan per 3-hour working day, and after the method is implemented, the labor cost is saved by about 400 yuan due to the arrangement of the data of the installation place of the on-pole circuit breaker.