CN106639322A - 一种利用电梯导轨的自升式混凝土布料塔及安装方法 - Google Patents

一种利用电梯导轨的自升式混凝土布料塔及安装方法 Download PDF

Info

Publication number
CN106639322A
CN106639322A CN201710037239.XA CN201710037239A CN106639322A CN 106639322 A CN106639322 A CN 106639322A CN 201710037239 A CN201710037239 A CN 201710037239A CN 106639322 A CN106639322 A CN 106639322A
Authority
CN
China
Prior art keywords
horizontal well
tower
distributing
cabinet frame
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710037239.XA
Other languages
English (en)
Other versions
CN106639322B (zh
Inventor
彭宝安
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Pingyi Economic Development Zone Investment Development Co ltd
Original Assignee
Jingmen Chuangjia Machinery Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jingmen Chuangjia Machinery Technology Co Ltd filed Critical Jingmen Chuangjia Machinery Technology Co Ltd
Priority to CN201710037239.XA priority Critical patent/CN106639322B/zh
Publication of CN106639322A publication Critical patent/CN106639322A/zh
Application granted granted Critical
Publication of CN106639322B publication Critical patent/CN106639322B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/02Conveying or working-up concrete or similar masses able to be heaped or cast

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Lift-Guide Devices, And Elevator Ropes And Cables (AREA)

Abstract

本发明一种利用电梯导轨的自升式混凝土布料塔及安装方法主要用于建筑工程领域高层建筑混凝土布料使用,它安装简单快捷,不需频繁地安装、拆除布料设备;本发明主要由液压系统、导轨、液压夹具、水平井字架、水平撑杆、塔架、混凝土输送管道、管道撑杆、管夹、轨道夹、塔架底座组成;其自升的工作过程是:在二层楼板B的楼面上安装一个水平井字架,用水平撑杆穿过塔架并将水平撑杆放在水平井字架上;拆除一层的水平井字架,再放松液压夹具,升起液压系统的活塞,逐渐将整个布料设备上升一个楼层的高度,同时用液压夹具将导轨夹紧,用水平井字架将塔架箍住夹紧,最后安装缺失的一段混凝土输送管道,爬升工作完成。

Description

一种利用电梯导轨的自升式混凝土布料塔及安装方法
技术领域
本发明主要用于建筑工程领域高层建筑混凝土布料使用。
背景技术
目前在建筑工程领域高层建筑混凝土布料设备安装在现浇混凝土楼面模板上,不但影响混凝土浇筑,还需频繁地安装拆除布料设备。
发明内容
本发明解决了上述问题,它将布料设备的塔身安装在电梯井道内,利用电梯导轨进行自升,不需频繁地安装拆除布料设备;本发明主要由液压系统(1)、导轨(2)、液压夹具(3)、水平井字架(4)、水平撑杆(5)、塔架(6)、混凝土输送管道(9)、管道撑杆(10)、管夹(11)、轨道夹(12)、塔架底座(13)组成;塔架底座(13)固定有液压系统(1),液压系统(1)的活塞固定有液压夹具(3),液压夹具(3)的夹头可以夹住导轨(2),导轨(2)与电梯井道(14)固定,塔架(6)的下端与塔架底座(13)固定,液压系统(1)的活塞伸出或者缩短可以将塔架(6)及塔架底座(13)上升或者下降,拼装式的水平井字架(4)可以将塔架(6)箍住夹紧,水平井字架(4)的梁与楼面临时固定,管道撑杆(10)的一端固定有管夹(11),管道撑杆(10)的另一端固定有轨道夹(12),管道撑杆(10)的一端通过管夹(11)与混凝土输送管道(9)临时固定,管道撑杆(10)的另一端通过轨道夹(12)与导轨(2)临时固定;本发明的主要工作原理及安装方法是:先施工一层楼板A(7)及一、二层的电梯井道,再安装一层和二层的电梯导轨(2),将电梯导轨(2)与电梯井道固定,再安装塔架(6)、塔架底座(13)及一层的水平井字架(4),此时液压夹具(3)的夹头已夹住导轨(2),水平井字架(4)已将塔架(6)箍住夹紧,水平井字架(4)的梁与一层楼板A(7)的楼面已经临时固定,再安装混凝土输送管道(9)及管道撑杆(10),将轨道夹(12)夹紧导轨(2),最后安装完布料设备的其他部分就可以对二层楼板B(8)的楼面进行混凝土布料作业了,当二层楼板B(8)的混凝土浇筑完成且混凝土达到一定强度后,需升起整个布料设备,其过程是:步骤一,首先脱开最下一节的混凝土输送管道(9),再在二层楼板B(8)的楼面上安装另一个水平井字架(4),将水平井字架(4)的梁与二层楼板B(8)的楼面临时固定,用水平撑杆(5)穿过塔架(6)并将水平撑杆(5)放在水平井字架(4)上;步骤二,拆除安装在一层的水平井字架(4),再放松液压夹具(3),此时整个布料设备的重量由水平撑杆(5)承担;步骤三,升起液压系统(1)的活塞,整个布料设备将沿着安装在二层的水平井字架(4)的内壁滑动上升一段距离,再将液压夹具(3)夹住导轨(2),抽出水平撑杆(5),将水平撑杆(5)穿过塔架(6)并将水平撑杆(5)放在水平井字架(4)上,再放松液压夹具(3),再升起液压系统(1)的活塞,逐渐将整个布料设备上升一个楼层的高度,同时用液压夹具(3)将导轨(2)夹紧,用安装在二层楼板B(8)上的水平井字架(4)将塔架(6)箍住夹紧,最后安装缺失的一段混凝土输送管道(9),并用管道撑杆(10)将混凝土输送管道(9)与导轨(2)固定,重复上述工作,完成整个高层建筑的混凝土布料工作;当需要拆除整个布料设备时,反向操作以上步骤,就可以由上至下逐段将整个布料设备拆除,最后导轨(2)作为电梯的永久部件留在电梯井道内。
附图说明
附图标记说明:1-液压系统,2-导轨,3-液压夹具,4-水平井字架,5-水平撑杆,6-塔架,7-楼板A,8-楼板B,9-混凝土输送管道,10-管道撑杆,11-管夹,12-轨道夹,13-塔架底座,14-电梯井道。
图1是本发明的立面剖面示意图。
图2是本发明的平面示意图。
图3是本发明步骤一的立面示意图。
图4是本发明步骤二的立面示意图。
图5是本发明步骤三的立面示意图。
具体实施方式
发明内容已详细说明了本发明的具体实施方式,这里不再重复。

Claims (2)

1.一种利用电梯导轨的自升式混凝土布料塔,其特征是:它主要由液压系统(1)、导轨(2)、液压夹具(3)、水平井字架(4)、水平撑杆(5)、塔架(6)、混凝土输送管道(9)、管道撑杆(10)、管夹(11)、轨道夹(12)、塔架底座(13)组成;塔架底座(13)固定有液压系统(1),液压系统(1)的活塞固定有液压夹具(3),液压夹具(3)的夹头可以夹住导轨(2),导轨(2)与电梯井道(14)固定,塔架(6)的下端与塔架底座(13)固定,液压系统(1)的活塞伸出或者缩短可以将塔架(6)及塔架底座(13)上升或者下降,拼装式的水平井字架(4)可以将塔架(6)箍住夹紧,水平井字架(4)的梁与楼面临时固定,管道撑杆(10)的一端固定有管夹(11),管道撑杆(10)的另一端固定有轨道夹(12),管道撑杆(10)的一端通过管夹(11)与混凝土输送管道(9)临时固定,管道撑杆(10)的另一端通过轨道夹(12)与导轨(2)临时固定。
2.根据权利要求1所述的一种利用电梯导轨的自升式混凝土布料塔,其主要安装方法是:先施工一层楼板A(7)及一、二层的电梯井道,再安装一层和二层的电梯导轨(2),将电梯导轨(2)与电梯井道固定,再安装塔架(6)、塔架底座(13)及一层的水平井字架(4),此时液压夹具(3)的夹头已夹住导轨(2),水平井字架(4)已将塔架(6)箍住夹紧,水平井字架(4)的梁与一层楼板A(7)的楼面已经临时固定,再安装混凝土输送管道(9)及管道撑杆(10),将轨道夹(12)夹紧导轨(2),最后安装完布料设备的其他部分就可以对二层楼板B(8)的楼面进行混凝土布料作业了,当二层楼板B(8)的混凝土浇筑完成且混凝土达到一定强度后,需升起整个布料设备,其过程是:步骤一,首先脱开最下一节的混凝土输送管道(9),再在二层楼板B(8)的楼面上安装另一个水平井字架(4),将水平井字架(4)的梁与二层楼板B(8)的楼面临时固定,用水平撑杆(5)穿过塔架(6)并将水平撑杆(5)放在水平井字架(4)上;步骤二,拆除安装在一层的水平井字架(4),再放松液压夹具(3),此时整个布料设备的重量由水平撑杆(5)承担;步骤三,升起液压系统(1)的活塞,整个布料设备将沿着安装在二层的水平井字架(4)的内壁滑动上升一段距离,再将液压夹具(3)夹住导轨(2),抽出水平撑杆(5),将水平撑杆(5)穿过塔架(6)并将水平撑杆(5)放在水平井字架(4)上,再放松液压夹具(3),再升起液压系统(1)的活塞,逐渐将整个布料设备上升一个楼层的高度,同时用液压夹具(3)将导轨(2)夹紧,用安装在二层楼板B(8)上的水平井字架(4)将塔架(6)箍住夹紧,最后安装缺失的一段混凝土输送管道(9),并用管道撑杆(10)将混凝土输送管道(9)与导轨(2)固定,重复上述工作,完成整个高层建筑的混凝土布料工作;当需要拆除整个布料设备时,反向操作以上步骤,就可以由上至下逐段将整个布料设备拆除,最后导轨(2)作为电梯的永久部件留在电梯井道内。
CN201710037239.XA 2017-01-19 2017-01-19 一种利用电梯导轨的自升式混凝土布料塔及安装方法 Active CN106639322B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710037239.XA CN106639322B (zh) 2017-01-19 2017-01-19 一种利用电梯导轨的自升式混凝土布料塔及安装方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710037239.XA CN106639322B (zh) 2017-01-19 2017-01-19 一种利用电梯导轨的自升式混凝土布料塔及安装方法

Publications (2)

Publication Number Publication Date
CN106639322A true CN106639322A (zh) 2017-05-10
CN106639322B CN106639322B (zh) 2019-01-15

Family

ID=58841636

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710037239.XA Active CN106639322B (zh) 2017-01-19 2017-01-19 一种利用电梯导轨的自升式混凝土布料塔及安装方法

Country Status (1)

Country Link
CN (1) CN106639322B (zh)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108868194A (zh) * 2018-07-30 2018-11-23 威海新特重工股份有限公司 一种烟囱拆除装置及烟囱拆除方法
CN113585291A (zh) * 2021-08-11 2021-11-02 中建八局发展建设有限公司 发泡混凝土肥槽回填应用的方法

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102005026120A1 (de) * 2005-06-07 2006-12-14 Hudelmaier, Götz Einrichtung zum Verteilen von Beton
CN202969938U (zh) * 2012-11-16 2013-06-05 三一汽车制造有限公司 支架和布料杆
CN203834914U (zh) * 2014-05-16 2014-09-17 中国建筑第四工程局有限公司 一种自动提升堆载平台
CN205077845U (zh) * 2015-09-08 2016-03-09 中国建筑第二工程局有限公司 建筑物核心筒井道液压智能爬升操作脚手架
CN205077885U (zh) * 2015-09-08 2016-03-09 中国建筑第二工程局有限公司 建筑物核心筒液压智能爬升防护平台
CN106013776A (zh) * 2016-07-01 2016-10-12 绍兴文理学院 一种液压自爬式电梯井定型化操作平台及施工方法

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102005026120A1 (de) * 2005-06-07 2006-12-14 Hudelmaier, Götz Einrichtung zum Verteilen von Beton
CN202969938U (zh) * 2012-11-16 2013-06-05 三一汽车制造有限公司 支架和布料杆
CN203834914U (zh) * 2014-05-16 2014-09-17 中国建筑第四工程局有限公司 一种自动提升堆载平台
CN205077845U (zh) * 2015-09-08 2016-03-09 中国建筑第二工程局有限公司 建筑物核心筒井道液压智能爬升操作脚手架
CN205077885U (zh) * 2015-09-08 2016-03-09 中国建筑第二工程局有限公司 建筑物核心筒液压智能爬升防护平台
CN106013776A (zh) * 2016-07-01 2016-10-12 绍兴文理学院 一种液压自爬式电梯井定型化操作平台及施工方法

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108868194A (zh) * 2018-07-30 2018-11-23 威海新特重工股份有限公司 一种烟囱拆除装置及烟囱拆除方法
CN108868194B (zh) * 2018-07-30 2023-12-22 威海新特重工股份有限公司 一种烟囱拆除装置及烟囱拆除方法
CN113585291A (zh) * 2021-08-11 2021-11-02 中建八局发展建设有限公司 发泡混凝土肥槽回填应用的方法

Also Published As

Publication number Publication date
CN106639322B (zh) 2019-01-15

Similar Documents

Publication Publication Date Title
CN105220769B (zh) 大面积螺栓球网架整体顶升施工方法
CN102080357B (zh) 钢管墩贝雷梁现浇支架整体落梁装置及方法
CN105088959B (zh) 一种钢桁梁节点自适应连续顶推系统
CN205348725U (zh) 一种大跨度、大幅度悬挑支撑结构
CN102677889A (zh) 钢柱筒架交替支撑整体爬升钢平台模架体系及施工方法
CN103643800A (zh) 屈曲约束支撑构件的提升安装体系及其施工方法
CN105672638B (zh) 一种带支撑滑移的脚手架及网架安装方法
CN106677542A (zh) 一种屋盖基座桁架结构的施工方法
CN113623482A (zh) 一种管道变形非开挖顶升修复装置及修复方法
CN106639322A (zh) 一种利用电梯导轨的自升式混凝土布料塔及安装方法
CN207211634U (zh) 一种分段式井道结构及集成式井道电梯
CN212222237U (zh) 一种新型管道安装台车
CN106744365B (zh) 一种利用电梯导轨的自升式塔吊
CN110318459A (zh) 大跨度钢结构连廊的水平累积滑移及垂直倒装提升安装方法
CN107335952B (zh) 一种钢板拼接焊缝底面陶瓷衬垫提升装置及其操作方法
CN207327167U (zh) 一种上覆硬土层地基打设塑料排水板的引孔装置
CN211314211U (zh) 盾构机顶升和下降装置
CN204225503U (zh) 大跨度钢桁架高空散装转换梁胎架
CN1987020B (zh) 附着爬升式高耸桅杆结构安装方法及施工装置
CN103850435A (zh) 框架楼房浇灌混凝土楼板托吊模架代替支撑模架的装置
CN207276133U (zh) 一种顶升装置
CN202689494U (zh) 一种电梯井模板支架
CN113523027B (zh) 一种基于非开挖管道弯曲变形修复系统及修复方法
CN207226943U (zh) 一种双横梁同步提升装置
CN206353102U (zh) 一种混凝土和钢筋混凝土排水管外压荷载试验装置

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20181122

Address after: 448000 No. 1, 1 1, Changning Avenue, Dongbao District, Jingmen, Hubei, Changning, China (1)

Applicant after: JINGMEN SI'AN MACHINERY EQUIPMENT CO.,LTD.

Address before: 448000 401 6 Hai Hui Road, Dongbao District, Jingmen, Hubei, 6

Applicant before: JINGMEN CHUANGJIA MACHINERY TECHNOLOGY Co.,Ltd.

TA01 Transfer of patent application right
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20221107

Address after: No. 207, East Second Floor, Administration Committee of Shandong Pingyi Economic Development Zone, West Section of Jinhua Road, Pingyi County Economic Development Zone, Linyi City, Shandong Province, 276000

Patentee after: Pingyi Economic Development Zone Investment Development Co.,Ltd.

Address before: 448000 No. 1, 1 1, Changning Avenue, Dongbao District, Jingmen, Hubei, Changning, China (1)

Patentee before: JINGMEN SI'AN MACHINERY EQUIPMENT CO.,LTD.

TR01 Transfer of patent right